Annual Overhauling of 210MW KWU Turbine and Generator of Unit # 2 of 3X210 MW , ATPS Anpara

Duration
Activity Description
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35
1 Barring gear stopped/Work started
2 Removal of insulation and scafolding arrangement
3 Removal of pedestal cover,bearing top half and LP hood
4 Run-out checking, decoupling of LP/Gen and its alignment checking
Run-out checking of HP/IP and IP/LP coupling,decoupling and alignment
5
checking
6 Swing check, thrust float,bump check, roll check and horn drop checking
7 Replacement of pressure regulating pressure limit valve of JOP line
8 Cleaning, D.P.T. of LPT Inlet and Extraction bellow
9 DPT and UT of bearings
10 Matching of bearing torous
11 Alignment of HP/IP,IP/LP and its correction
12 Coupling Of HP/IP,IP/LP and roll check,bump check,float,swing check
13 Dismantling of MOP, clearance checking, setting and assembly
14 Servicing of MS and HRH strainer
15 Dismantling, cleaning, hydro test and assembly of hydrogen cooler.
Dismentaling of lub oil , seal oil pipe line & oil catchers of both side (T.E
16
& E.E).
17 Dismentaling of seal body of both side(T.E & E.E).
Re-visioning and assembly of TE & EE side Hydrogen seals and oil
18
catchers
19 Overhauling work of SEAL OIL SYSTEM
20 Alignment of LP/Gen and coupling
21 Assembly of inner oil catcher and seal body of both side (T.E & E.E)
22 Bearing box-up and yoke placement
23 Rotor 'o' position for C&I calibration
24 Pedestal cover box-up and oil flushing
25 seal charging & airtightness test
26 Barring gear and governing setting