Professional Documents
Culture Documents
Company name
Date
Project Title TTSP OFFICE BUILDING PACKAGE 1
Location WEST CEBU INDUSTRIAL PARK - SEZ, BUANOY, BALAMBAN, CEBU
BILL OF QUANTITIES/COST ESTIMATES
Owner THI-CEBU INC.
requirements lot
expenses. lot
1.7 Miscellaneous
2.2.4 Structural backfilling 88.80 cu.m. 150.00 150.00 13,320.00 13,320.00 26,640.00
2.2.5 Make to fill levels 575.00 m 130.00 150.00 74,750.00 86,250.00 161,000.00
1.3.1 Exterior water proofing cementitious 14.00 m 550.00 150.00 7,700.00 2,100.00 9,800.00
1.3.3 Membraine type water proofing on Common and Individual C.R 148.13 m 550.00 81,471.50 81,471.50
1.3.4 Cementitious water proofing on all canopy slab 92.04 m 550.00 50,622.00 50,622.00
3.1 Concrete
3.1.2 Footing tie beams - 3000 psi 52.73 cu.m. 2,500.00 750.00 131,814.00 39,544.20 171,358.20
3.1.4 Beams and girders - 3000 psi 161.78 cu.m. 2,500.00 750.00 404,442.00 121,332.60 525,774.60
3.1.6 Slab on grade - 2500 psi 63.25 cu.m. 2,500.00 750.00 158,125.00 47,437.50
3.1.7 Staircases - 3000 psi 9.34 cu.m. 2,500.00 750.00 23,343.75 7,003.13 30,346.88
3.2.1 Foundation
3.2.1.1 20 mm - Grade 60 kg
3.2.1.2 16 mm - Grade 40 kg
3.2.1.3 12 mm - Grade 40 kg
UNIT PRICE TOTAL
TOTAL LABOR
DESCRIPTION QUANTITY UNIT MATERIAL OVER-ALL TOTAL
MATERIAL LABOR COST
COST
BILL OF QUANTITIES/COST ESTIMATES
PRELIMINARIES &3.2.1.4
GENERAL10
REQUIREMENTS
mm - Grade 33 kg
3.2.1.5 Miscellaneous
3.2.2.1 16 mm - Grade 40 kg
3.2.2.2 10 mm - Grade 33 kg
3.2.3.1 20 mm - Grade 60 kg
3.2.3.2 16 mm - Grade 40 kg
3.2.3.3 10 mm - Grade 33 kg
3.2.4.1 20 mm - Grade 60 kg
3.2.4.2 16 mm - Grade 40 kg
3.2.4.3 10 mm - Grade 33
3.2.5.1 10 mm - Grade 33 kg
3.2.6.1 10 mm - Grade 33 kg
3.2.7 Staircases
3.2.7.1 kg
3.2.7.2 kg
3.2.7.3 kg
3.2.8.1 kg
3.2.8.2 kg
3.2.8.3 kg
3.2.9 Canopy
3.2.9.1 kg
3.2.9.2 kg
3.2.10.1 kg
3.2.10..2 kg
3.2.10.3 kg
3.3 Formworks
3.3.2 Columns m
3.3.6 Staircases m
3.3.7 Canopy m
3.4.1.6 20mm Dia x 6m Plain Bars (Gr. 60), Cross Bracing length
Cost per m
Submitted by:
Company name
Title or Position
Date
Project Title TENSHIN BUILDING
Location BALAMBAN, CEBU CITY
Owner THI-CEBU INC.
Subject BILL OF QUANTITIES/COST ESTIMATES
UNIT PRICE TOTAL MATERIAL TOTAL LABOR
DESCRIPTION QUANTITY UNIT OVER-ALL TOTAL
MATERIAL LABOR COST COST
1.0 ARCHITECTURAL WORKS
1.1 GENERAL REQUIREMENTS
1.1.1 Mobilization / Demobilization 1 lot 320,000.00
1.1.2 Temporary Facilities 1 lot 160,000.00
1.1.3 Preparation of As-Builts & Shop Drawings 1 lot 225,000.00
1.1.4 Project Meeting Representation 1 lot 120,000.00
1.1.5 Testing & Commissioning 1 lot 40,000.00
SUB - TOTAL FOR ITEM NO. 1.2 865,000.00
1.2 Metal Works
1.2.1 Service Ramp
1.2.1.1 2" Dia. B.I. Pipe Handrailings 2.00 l.m 754.80 226.44 1,509.60 72,195.87 73,705.47
1.2.1.2 40 mm Dia B.I. Pipe 2.00 l.m 754.80 226.44 1,509.60 21,994.12 23,503.72
1.2.2 Stairs
1.2.2.1 2" Dia. B.I. Pipe Handrailings 30.00 l.m 754.80 226.44 22,644.00 527,831.64 550,475.64
1.2.2.2 40 mm Dia B.I. Pipe 30.00 l.m 754.80 226.44 22,644.00 404,195.40 426,839.40
1.2.2.5 PVC Stair Nosing 57.08 l.m 190.00 57.00 10,844.82 3,534.00 14,378.82
SUB - TOTAL FOR ITEM NO. 1.3 1,088,903.04
1.3 Glass and Glazing
1.3.1 1.0 (w) x 1.23 (h) Sliding Window 120.50 set 6,840.00 2,052.00 824,220.00 247,266.00 1,071,486.00
1.3.2 0.60 (w) x 0.50 (h) Jalousie Window 1.00 set 1,022.05 306.62 1,022.05 306.62 1,328.67
1.3.3 CR Reflective mirror 44.00 sq.ft 1,620.00 486.00 71,280.00 21,384.00 92,664.00
SUB - TOTAL FOR ITEM NO. 1.4 1,165,478.67
1.4 Ceiling Assemblies&Panelling
1.4.1 Ceiling on all rooms (3.5 mm Hardiflex) 318.83 pc. 358.00 107.40 114,141.14 34,242.34 148,383.48
1.4.2 Hallway, Lobby, and Stairs (4.5mm Hardiflex) 97.13 pc. 440.00 132.00 42,737.20 12,821.16 55,558.36
SUB - TOTAL FOR ITEM NO. 1.5 203,941.84
1.5 Tile Works
1.5.1 .60x.60m Room Ceramic Tiles 2,595.00 pc. 185.00 55.50 480,075.00 144,022.50 624,097.50
1.5.2 .30x.30m Kitchen Countertop and Bathroom Wall Ceramic Tiles 2,331.00 pc. 95.00 28.50 221,445.00 66,433.50 287,878.50
1.5.3 .30x.30m Bathroom and Laundry Area Floor Ceramic Tiles 1,785.00 pc. 95.00 28.50 169,575.00 50,872.50 220,447.50
1.5.4 .60X.60m Hallway Ceramic Tiles 550.00 pc. 185.00 55.50 101,750.00 30,525.00 132,275.00
1.5.5 .60X.60m Kitchen Floor Ceramic tiles 139.00 pc. 185.00 55.50 25,715.00 7,714.50 33,429.50
1.5.6 .60x.60m Stair Tile 62.00 pc. 185.00 55.50 11,470.00 3,441.00 14,911.00
SUB - TOTAL FOR ITEM NO. 1.6 1,313,039.00
1.80 Doors Schedule
1.6.1 1.60(w) x 2.10 (h) 1/4" thk Clear Glass Double Swing Door 3.00 units 20,962.88 6,288.86 62,888.64 18,866.59 81,755.23
1.6.2 1.60(w) x 2.10 (h) Double Metal Swing Door with Viewing Glass 2.00 units 24,000.00 7,200.00 48,000.00 14,400.00 62,400.00
1.6.3 1.0 (w) x 2.10 (h) Metal Flush Door with Viewing Glass and Panic Hardware 4.00 units 12,000.00 3,600.00 48,000.00 14,400.00 62,400.00
1.6.4 0.70(w) x 2.10 (h) Standard Flush Door w/ Lawaan Jamb 44.00 units 6,500.00 1,950.00 286,000.00 85,800.00 371,800.00
1.6.5 0.60 (w) x 2.10 (h) ABS Flush Door with Louvers 44.00 units 1,625.00 487.50 71,500.00 21,450.00 92,950.00
1.6.6 0.80 (w) x 2.10 (h) Flush Door with Louvers 2.00 units 8,967.50 2,690.25 17,935.00 5,380.50 23,315.50
1.6.7 0.40 (w) x 1.65 (h) Metal Flush Door 24.00 units 7,865.09 2,359.53 188,762.16 56,628.65 245,390.81
SUB - TOTAL FOR ITEM NO. 1.8 940,011.54
1.80 Painting & Finishing Works
1.8.1 Interior painting works
1.8.1.1. Latex Putty (Full Putty) 255.00 gal 276.00 82.80 70,380.00 21,114.00 91,494.00
1.8.1.2. Flat Latex (White) 306.00 gal 608.00 182.40 186,048.00 55,814.40 241,862.40
1.8.1.3. Concrete Neutralizer 14.25 gal 229.00 68.70 3,263.25 978.98 4,242.23
1.8.2 Exterior painting works
1.8.2.1. Latex Putty (Full Puty) 52.00 gal 276.00 82.80 14,352.00 4,305.60 18,657.60
1.8.2.2. Flat Latex Semi-Gloss(White) 62.00 gal 608.00 182.40 37,696.00 11,308.80 49,004.80
1.8.2.3. Cocrete Neutralizer 3.00 gal 229.00 68.70 687.00 206.10 893.10
SUB - TOTAL FOR ITEM NO. 1.9 337,598.63
3.3 Formworks
3.3.1 Footing tie beam and wall footing287.5 m 350.00
3.3.2 Columns 0.0 m 350.00
3.3.3 Beams and girders 230.00 m 350.00
3.3.4 Suspended slabs 497.0 m 350.00
3.3.6 Staircases 189.80 m 350.00
3.3.7 Canopy 0.0 m 350.00
Company name
Title or Position
Date
UNIT PRICE TOTAL MATERIAL TOTAL LABOR
OVER-ALL TOTAL
LABOR COST COST
75,000.00 75,000.00
40,000.00 40,000.00
75,000.00 75,000.00
75,000.00 75,000.00
40,000.00 40,000.00
50,000.00 50,000.00
80,000.00 80,000.00
80,000.00 80,000.00
75,000.00 75,000.00
200,000.00 200,000.00
25,000.00 25,000.00
50,000.00 50,000.00
75,000.00 75,000.00
940,000.00
Stainless Ramp railings using 1 1/2" Dia. Tube top rail with 1 1/2" Dia.
1.1.1.1 2.00 units
Baluster post and 1pc. 1 1/2" Dia. Horizontal rail @ 6.3 Lm.
30,688.75 9,206.63 61,377.50 18,413.25 79,790.75
Stainless Ramp railings using 1 1/2" Dia. Tube top rail with 1 1/2" Dia.
1.1.1.2 2.00 units
Baluster post and 1pc. 1 1/2" Dia. Horizontal rail @ 2.0 Lm.
9,720.00 2,916.00 19,440.00 5,832.00 25,272.00
Stainless Ramp railings using 2" Dia. Tube top rail with 1 1/2" Dia. Baluster
1.1.1.3 1.00 units
post and 1pc. 2" Dia. Horizontal rail @ 16 Lm. 77,760.00 23,328.00 77,760.00 23,328.00 101,088.00
1.1.1.4 2" x 4"x 3mm. Thk. 6m. length Rectangular Tubing 230.00 l.m 2,086.00 625.80 479,780.00 143,934.00 623,714.00
1.1.2 Stairs
1.1.2.1 1 1/2" Dia. Stainless Steel Pipe Handrailings l.m
1.1.2.2 3/8" x 2" Flat Bar l.m 1,666.00
1.2.2.3 3/4" Dia B.I Pipe l.m 754.00
1.2.2.4 4" x 6" 1/2" Post Base Plate sqm 652.00
1.2.2.5 Aluminum step nosing l.m
1.1.3 PWD C.R
1.1.3.1 1 1/2" Dia. vert. Stainless Steel Pipe Grab Bar pcs
1.1.3.2 1 1/2" Dia. hor. Stainless Steel Pipe Grab Bar pcs
1.1.4 Aluminum Composite Cladding lot
1.1.5 1" Dia. Aluminum Tray Railing at Concessionaire area l.m
1.1.6 Pathwalk 50mm B.I. Pipe 9.00 l.m 2,600.00 780.00 23,400.00 7,020.00 30,420.00
SUB - TOTAL FOR ITEM NO. 1.1 860,284.75
1.2 Glass and Glazing
Exterior
W-3A: 4 Sided Curtain Wall using 1/4 Reflective Blue Tempered Glass with Standard
1.2.1 1 3/4 x 4 Tubular in Powder Coated Finished and Patch Fitting Door using 1/2 Blue 1.00 lot 0.00 0.00 0.00 0.00 1,408,734.67
Tempered Glass with Handle - Front Facing
W-3A: 4 Sided Curtain Wall using 1/4 Reflective Blue Tempered Glass with Standard
1.2.2 1 3/4 x 4 Tubular in Powder Coated Finished and Patch Fitting Door using 1/2 Blue 1.00 lot 0.00 0.00 0.00 0.00 5,177,425.07
Tempered Glass with Handle - Front Facing
W1: 2.80 (w) x 3.10 (h)- Awning Window with Fixed Glass using 1/4 Reflective Blue
1.2.3 Annealed Glass with Ordinary 1 3/4 x 4 Tubular and Snap-on Base & Cover in 56.00 sets 51,780.96 0.00 2,899,733.76 0.00 2,899,733.76
Powder Coated Finished without Screen
W2: 2.80 (w) x 2.50 (h)- Awning Window with Fixed Glass using 1/4 Reflective Blue
1.2.4 Annealed Glass with Ordinary 1 3/4 x 4 Tubular and Snap-on Base & Cover in 12.00 sets 37,117.25 0.00 445,407.00 0.00 445,407.00
Powder Coated Finished without Screen
W3: 1.40 (w) x 0.60 (h)- Awning Windows using 1/4 Reflective Blue Annealed Glass
1.2.5 with Ordinary 1 3/4 x 4 Tubular and Snap-on Base & Cover in Powder Coated 37.00 sets 6,638.44 0.00 245,622.28 0.00 245,622.28
Finished without Screen
W4: 6.00 (w) x 3.80 (h)- Awning Windows with Fixed Glass using 1/4 Reflective Blue
1.2.6 Annealed Glass with Ordinary 1 3/4 x 4 Tubular and Snap-on Base & Cover in 4.00 sets 145,414.66 0.00 581,658.64 0.00 581,658.64
Powder Coated Finished without Screen
W5: 9.25 (w) x 5.18 (h)- Awning Windows with Fixed Glass using 1/4 Reflective Blue
1.2.7 Annealed Glass with Ordinary 1 3/4 x 4 Tubular and Snap-on Base & Cover in 12.00 sets 254,854.20 0.00 3,058,250.40 0.00 3,058,250.40
Powder Coated Finished without Screen
Interior
1.2.8 W-1A: 5.7m x 3.05m FFFFF/Door/F Glass Assembly with Door Transom 3.00 unit 27,562.00 8,268.60 82,686.00 24,805.80 107,491.80
1.2.9 W-1B: 2.6m x 2.34m F/Door/Door/F Glass Assembly with Door Transom 3.00 unit 24,946.00 7,483.80 74,838.00 22,451.40 97,289.40
1.2.10 W-2A: 5.84m x 1.55/2.1m FF/Door/FF Glass Assembly with Door Transom 5.00 unit 23,764.00 7,129.20 118,820.00 35,646.00 154,466.00
1.2.11 W-2B: 5.76m x 1.55/2.1m FFFF/Door/F Glass Assembly with Door Transom 1.00 unit 26,286.00 7,885.80 26,286.00 7,885.80 34,171.80
1.2.12 W-2C: 9.18m x 1.55/2.1m FFFFFFF/Door/F Glass Assembly with Door Transom 3.00 unit 36,234.00 10,870.20 108,702.00 32,610.60 141,312.60
1.2.13 W-3C: 5.36m x 3.05m FFFF/Door/F Glass Assembly with Door Transom 1.00 unit 38,448.00 11,534.40 38,448.00 11,534.40 49,982.40
1.2.14 W-3D: 4.06m x 3.05m Door/Door/FF Glass Assembly with Door Transom 6.00 unit 31,564.00 9,469.20 189,384.00 56,815.20 246,199.20
1.2.15 C.R. Reflective Mirror m 0.00 0.00 0.00 0.00
SUB - TOTAL FOR ITEM NO. 1.2 14,647,745.02
1.3 Ceiling Assemblies & Panelling
1.3.1 1/2" Thk.Gypsum Board on Metal Furring 4,106.00 pcs 300.00 90.00 1,231,800.00 369,540.00 1,601,340.00
1.3.2 1" Tee Runner 4,302.00 length 30.00 9.00 129,060.00 38,718.00 167,778.00
1.3.3 1" x 1" Wall Angle 1,312.00 length 30.00 9.00 39,360.00 11,808.00 51,168.00
1.3.4 1/4" x 1 x 2" Metal Furring, 6m legnth 1,611.00 length 78.00 23.40 125,658.00 37,697.40 163,355.40
1.3.5 Blind Revits 75,768.00 pcs 0.65 0.20 49,249.20 14,774.76 64,023.96
1.3.6 Consumables 1.00 lot 20,000.00 6,000.00 20,000.00 6,000.00 26,000.00
SUB - TOTAL FOR ITEM NO. 1.3 2,073,665.36
1.4 Tile Works
Floor Tiles
1.4.1 .60 x .60m PR5 02 Portino Matt Tiles for Offices 21,819.00 pcs 185.00 55.50 4,036,515.00 1,210,954.50 5,247,469.50
1.4.2 .60 x .60m PR5 03 Portino Matt Tiles for Hallways 4,296.00 m 185.00 55.50 794,760.00 238,428.00 1,033,188.00
1.4.3 .30 X .60m PR5 04 Portino Matt Tiles for Sidings and Borders 2,180.00 pcs 95.00 28.50 207,100.00 62,130.00 269,230.00
DESCRIPTION QUANTITY UNIT UNIT PRICE
TOTAL MATERIAL TOTAL LABOR
OVER-ALL TOTAL
MATERIAL LABOR COST COST
1.4.4 .60 X .60m PR5 04 Portino Matt Tiles for Sidings and Borders 842.00 185.00 55.50 155,770.00 46,731.00
.60 X .60m PB5 02 RB Portino Matt Tiles for Canteen/ Multipurpose Hall and
1.4.5 3,063.00 pcs 185.00 55.50 566,655.00 169,996.50 736,651.50
Concessionaires
1.4.6 .60 x.60m PB5 04 RB Portino Matt Tiles for Entries, Ramps, and Stairs 790.00 pcs 185.00 55.50 146,150.00 43,845.00 189,995.00
#10 pebble washout with plastic trim 0.00 0.00 0.00 0.00
1.4.7 .60 x.60m PD5 03 RB Portino Matt Tiles for Female and PWD C.R. 1,149.00 pcs 185.00 55.50 212,565.00 63,769.50 276,334.50
1.4.8 .60 x.60m PD5 04 RB Portino Matt Tiles for Male C.R. 1,038.00 pcs 185.00 55.50 192,030.00 57,609.00 249,639.00
Wall Tiles 0.00 0.00 0.00 0.00
1.4.9 .60 x.60m PD5 01 Portino Matt Tiles for Female and PWD C.R. 2,353.00 pcs 185.00 55.50 435,305.00 130,591.50 565,896.50
1.4.10 .60 x.60m PD5 02 Portino Matt Tiles for Male C.R. 1,856.00 pcs 185.00 55.50 343,360.00 103,008.00 446,368.00
SUB - TOTAL FOR ITEM NO. 1.4 9,014,772.00
1.5 Common C.R and Kitchen
1.5.1 Female Wall Hang Partition Panel
17-L Type Toilet Partition Phenolic Board With all Stainless Accessories (22
1.5.1.1
series) 1.00 lot 389,232.00 116,769.60 389,232.00 116,769.60 506,001.60
17-L Type Toilet Partition Phenolic Board With all Nylon Accessories (OA
1.5.1.2
Series) 1.00 lot 314,058.00 94,217.40 314,058.00 94,217.40 408,275.40
1.5.2 Female Wall Hang Partition Panel
11-L Type; 12 Urinals Toilet Partition Phenolic Board With all Stainless
1.5.2.1
Accessories (22 series) 1.00 lot 352,906.00 105,871.80 352,906.00 105,871.80 458,777.80
11-L Type; 12 Urinals Toilet Partition Phenolic Board With all Stainless
1.5.2.2
Accessories (OA series) 1.00 lot 255,564.85 76,669.46 255,564.85 76,669.46 332,234.31
1.5.3 Female Granite CR Lavatory Counter Top
1.5.3.1 Top 9.59 Area 4,000.00 1,200.00 38,360.00 11,508.00 49,868.00
1.5.3.2 Installation Top 9.59 Area 1,800.00 540.00 17,262.00 5,178.60 22,440.60
1.5.3.3 4" Splashboard 11.39 Area 800.00 240.00 9,112.00 2,733.60 11,845.60
1.5.3.4 Installation SB 11.39 Area 500.00 150.00 5,695.00 1,708.50 7,403.50
1.5.3.5 Quarter Round 11.79 Area 400.00 120.00 4,716.00 1,414.80 6,130.80
1.5.3.6 Bullnose 10.24 Area 1,200.00 360.00 12,288.00 3,686.40 15,974.40
1.5.3.7 4" Fascia 10.24 Area 800.00 240.00 8,192.00 2,457.60 10,649.60
1.5.3.8 Installation Fascia 10.24 Area 500.00 150.00 5,120.00 1,536.00 6,656.00
1.5.3.9 Hole 8.00 Area 1,500.00 450.00 12,000.00 3,600.00 15,600.00
1.5.4 Male Granite CR Lavatory Counter Top
1.5.4.1 Top 21.50 Area 4,000.00 1,200.00 86,000.00 25,800.00 111,800.00
1.5.4.2 Installation Top 21.50 Area 1,800.00 540.00 38,700.00 11,610.00 50,310.00
1.5.4.3 4" Splashboard 23.30 Area 800.00 240.00 18,640.00 5,592.00 24,232.00
1.5.4.4 Installation SB 23.30 Area 500.00 150.00 11,650.00 3,495.00 15,145.00
1.5.4.5 Quarter Round 24.30 Area 400.00 120.00 9,720.00 2,916.00 12,636.00
1.5.4.6 Bullnose 21.50 Area 1,200.00 360.00 25,800.00 7,740.00 33,540.00
1.5.4.7 4" Fascia 21.50 Area 800.00 240.00 17,200.00 5,160.00 22,360.00
1.5.4.8 Installation Fascia 21.50 Area 500.00 150.00 10,750.00 3,225.00 13,975.00
1.5.4.9 Hole 18.00 Area 1,500.00 450.00 27,000.00 8,100.00 35,100.00
1.5.3 Concessionaire Granite Counters Top
1.5.4.1 Top 29.00 Area 4,000.00 1,200.00 116,000.00 34,800.00 150,800.00
1.5.4.2 Installation Top 29.00 Area 1,800.00 540.00 52,200.00 15,660.00 67,860.00
1.5.4.3 4" Splashboard 34.00 Area 800.00 240.00 27,200.00 8,160.00 35,360.00
1.5.4.4 Installation SB 34.00 Area 500.00 150.00 17,000.00 5,100.00 22,100.00
1.5.4.5 Quarter Round 35.00 Area 400.00 120.00 14,000.00 4,200.00 18,200.00
1.5.4.6 Bullnose 31.00 Area 1,200.00 360.00 37,200.00 11,160.00 48,360.00
1.5.4.7 4" Fascia 31.00 Area 800.00 240.00 24,800.00 7,440.00 32,240.00
1.5.4.8 Installation Fascia 31.00 Area 500.00 150.00 15,500.00 4,650.00 20,150.00
1.5.4.9 Hole 16.00 Area 1,500.00 450.00 24,000.00 7,200.00 31,200.00
SUB - TOTAL FOR ITEM NO. 1.5 2,597,225.61
1.6 Doors Schedule
1.6.1 1.8 (w) x 2.1 (h) Double Swing Frameless Glass Door 2.00 sets 26,093.77 7,828.13 52,187.54 15,656.26 67,843.80
1.6.2 0.9 (w) x 2.1 (h) Single Swing Single Frame Glass Door 13.00 sets 13,049.80 3,914.94 169,647.40 50,894.22 220,541.62
1.6.3 0.9 (w) x 2.1 (h) Single Swing Single Frame Metal Door w/ Fixed Full Louvers 40.00 sets 8,967.50 2,690.25 358,700.00 107,610.00 466,310.00
1.6.4 1.8 (w) x 2.1 (h) Double Swing Single Frame Glass Door 13.00 sets 26,093.77 7,828.13 339,219.01 101,765.70 440,984.71
0.9 (w) x 2.1 (h) Single Swing Single Frame Standard Flush Door w/ Lauaan Door
1.6.5 18.00 sets 6,500.00 1,950.00 117,000.00 35,100.00 152,100.00
Jamb
1.6.6 0.9 (w) x 2.1 (h) Single Swing Single Frame Plain Metal Fire Exit Door w/ Panic Device 8.00 sets 8,486.25 2,545.88 67,890.00 20,367.00 88,257.00
1.8 (w) x 2.1 (h) Opposing Swing Single Frame 2 Panel Plain Metal Door w/ Panic
1.6.7 7.00 sets 16,972.50 5,091.75 118,807.50 35,642.25 154,449.75
Device
SUB - TOTAL FOR ITEM NO. 1.6 1,590,486.89
1.7 Painting & Finishing Works
1.7.1 Interior Wall Painting (White)
1.7.2 Latex Putty (full putty) 362.00 gals 276.00 82.80 99,912.00 29,973.60 129,885.60
1.7.3 Flat Latex (White) 2 Coats 434.00 gals 650.00 195.00 282,100.00 84,630.00 366,730.00
1.7.5 Concrete Neutralizer 21.00 gals 229.00 68.70 4,809.00 1,442.70 6,251.70
1.7.2 Exterior Wall Painting (Blue)
1.7.2.1 Latex Putty (full putty) 22.00 gals 276.00 82.80 6,072.00 1,821.60 7,893.60
1.7.2.2 Flat Latex- Semi Gloss (Blue) 2 Coats 27.00 gals 650.00 195.00 17,550.00 5,265.00 22,815.00
1.7.2.4 Concrete Neutralizer 2.00 gals 229.00 68.70 458.00 137.40 595.40
1.7.3 Exterior Wall Painting (White)
1.7.3.1 Latex Putty (full putty) 73.00 gals 276.00 82.80 20,148.00 6,044.40 26,192.40
1.7.3.2 Flat Latex- Semi Gloss (White) 2 Coats 87.00 gals 650.00 195.00 56,550.00 16,965.00 73,515.00
DESCRIPTION QUANTITY UNIT UNIT PRICE
TOTAL MATERIAL TOTAL LABOR
OVER-ALL TOTAL
MATERIAL LABOR COST COST
1.7.3.4 Concrete Neutralizer 4.00 gals 229.00 68.70 916.00 274.80 1,190.80
SUB - TOTAL FOR ITEM NO. 1.7 635,069.50
1.8 Modular Office Furnitures
3.0 (w) x 1.8 ( l ) x 1.1 (h) 3/4" thk Melamine Board Office Cubicle Modular Unit
1.8.1 2,140.00 pcs 3,500.00 1,050.00 7,490,000.00 2,247,000.00 9,737,000.00
Assembly-2 Seater
1.47 (w) x 0.45 ( l ) x 1.20 (h) 3/4" thk Melamine Board Floor Standing Office Files
1.8.2 760.00 pcs 3,500.00 1,050.00 2,660,000.00 798,000.00 3,458,000.00
Cabinet/ Storage w/ Wood Moulding
1.8.3 Consumables (Bolts, Screws, Etc.) 1.00 lot 0.00 0.00 0.00 0.00 20,000.00
SUB - TOTAL FOR ITEM NO. 1.8 13,215,000.00
1.90 Plumbing Fixtures
1.9.1 Toto Brand Water Closet CW896J 121.00 units 22,640.00 6,792.00 2,739,440.00 821,832.00 3,561,272.00
Toto
Brand
1.9.2
Wall 14.00 set 27,370.00 8,211.00 383,180.00 114,954.00 498,134.00
1.9.3 Toto Brand Console Lavatory LW711RCB 31.00 units 16,380.00 4,914.00 507,780.00 152,334.00 660,114.00
1.9.4 Toto Brand Ego II Lavatory Faucet TX108LEBR 31.00 units 12,590.00 3,777.00 390,290.00 117,087.00 507,377.00
1.9.5 Toto Brand Semi-Recessed Ceramic Paper Holder S20V2 121.00 units 610.00 183.00 73,810.00 22,143.00 95,953.00
1.9.6 Kitchen Sink DBL BOWL 33x 18 x 7 13.00 units 2,399.00 719.70 31,187.00 9,356.10 40,543.10
1.9.7 Kitchen Sink Faucet 13.00 units 1,092.00 327.60 14,196.00 4,258.80 18,454.80
1.9.8 Drinking Fountains 6.00 units 99,000.00 29,700.00 594,000.00 178,200.00 772,200.00
SUB - TOTAL FOR ITEM NO. 1.9 6,154,047.90
1.11 Lighting Fixtures
1.11.1 Recessed Single Square Downlight 24" 22w 3000K 1500lm 32.00 pcs 3,800.00 1,140.00 121,600.00 36,480.00 158,080.00
1.11.2 Recessed Double Square Downlight 45" 2 x 22w 400k 3000lm 75.00 pc 5,800.00 1,740.00 435,000.00 130,500.00 565,500.00
1.11.3 Housing Bulb Type - Downlight 168.00 pcs 150.00 45.00 25,200.00 7,560.00 32,760.00
1.11.4 LED Bulb 3000k 9.5w 806lm 168.00 pcs 220.00 66.00 36,960.00 11,088.00 48,048.00
1.11.5 Signature Recessed Troffer 300 x 1215 x 80 1,186.00 pcs 1,300.00 390.00 1,541,800.00 462,540.00 2,004,340.00
1.11.6 GE LED T8 16w 220-240v 6500k 1600lm 2,372.00 pcs 450.00 135.00 1,067,400.00 320,220.00 1,387,620.00
1.11.7 CDN Recessed Linear Light Dimmable 110" 28w 2918 lm 18.00 pcs 8,566.00 2,569.80 154,188.00 46,256.40 200,444.40
1.11.8 Endo Glareless Downlight 33" 14.2w 3000k 911lm 10.00 pcs 5,800.00 1,740.00 58,000.00 17,400.00 75,400.00
1.11.8 Flexible Strip Lights 120" 14.4 3000k 900lm/m 90.00 m 5,800.00 1,740.00 522,000.00 156,600.00 678,600.00
1.11.8 Meanwell Driver 12v 8.00 pcs 1,200.00 360.00 9,600.00 2,880.00 12,480.00
SUB - TOTAL FOR ITEM NO. 1.11 4,472,192.40
1.12 DX Type Air Conditioning Units- Inverter
1.12.1 Ceiling Cassette Inverter Type 4.0HP 15 units 131,760.00 500.00 1,976,400.00 7,500.00 1,983,900.00
1.12.2 Ceiling Cassette Inverter Type 6.0HP 193 units 156,420.00 500.00 30,189,060.00 96,500.00 30,285,560.00
1.12.3 Ceiling Conceiled Inverter Type 5.0HP 2 units 143,820.00 500.00 287,640.00 1,000.00 288,640.00
SUB - TOTAL FOR ITEM NO. 1.12 32,558,100.00
1.13 Auxiliary Fixtures
1.13.1.1 CCTV IP camera, 3MP 17 units 15,000.00 4,500.00 255,000.00 76,500.00 331,500.00
1.13.1.2 WIFI device 15 units 10,000.00 3,000.00 150,000.00 45,000.00 195,000.00
1.13.1.4 Adrressable Smoke detector and Heat detectors 185.00 pcs 4,500.00 1,350.00 832,500.00 249,750.00 1,082,250.00
1.13.1.5 Ceiling Speaker with casing and multi-tap transformer, 5watts 200 sets 1,700.00 510.00 340,000.00 102,000.00 442,000.00
SUB - TOTAL FOR ITEM NO. 1.13 2,050,750.00
A. OVERHEAD & PROFIT (7%) 6,290,853.76
B. CONTINGENCIES (10%) 8,986,933.94
C. CONTRACTORS PROFIT (15% OF A+B) 2,291,668.16
D. VAT (12% OF A+B+C) 2,108,334.70
GRAND TOTAL 109,547,129.98
Cost per m 9,262.46
Submitted by: RAMON N. VIOS JR.
M Arch AS, M Arch UD, PIA, UAP, CCA
Company name
Date
Project Title TENSHIN DORMITORY
Location WEST CEBU INDUSTRIAL PARK - SEZ, BUANOY, BALAMBAN, CEBU
Owner THI-CEBU INC.
1.2.1 Window Type Inverter, 1.5HP 132 units 38,000.00 - 5,016,000.00 - 5,016,000.00
1.3.1 TEF-01 50 CFM Ceiling Cassette Fan @ 0.125 in. sp. 132 units 3,200.00 - 422,400.00 - 422,400.00
1.3.2 RH-1 300 CFM In-Line Centrifugal Fan @ 0.25 in. sp. 3 units 6,800.00 - 20,400.00 - 20,400.00
100mm dia. Without insulation 132 roll 2,300.00 345.00 303,600.00 45,540.00 349,140.00
Flat bar 1"x 3/16 35 length 120.00 18.00 4,200.00 630.00 4,830.00
Full Thread bar, 3/8" 80 length 126.00 18.90 10,080.00 1,512.00 11,592.00
Bolts, nuts & washers 3/8" 1,500 pcs 7.00 1.05 10,500.00 1,575.00 12,075.00
Expansion Shield 3/8" 800 pcs 13.00 1.95 10,400.00 1,560.00 11,960.00
Primer paint (Red Oxide) 3 liters 960.00 144.00 2,880.00 432.00 3,312.00
Title or Position
Principal Architect
Date 14-Aug-17
UNIT PRICE TOTAL TOTAL OVER-ALL
DESCRIPTION QUANTITY UNIT
MATERIAL LABOR MATERIAL COST LABOR COST TOTAL
MECHANICAL WORKS
UNIT PRICE TOTAL TOTAL OVER-ALL
DESCRIPTION QUANTITY UNIT
MATERIAL LABOR MATERIAL COST LABOR COST TOTAL
MECHANICAL WORKS
0
UNIT PRICE TOTAL TOTAL OVER-ALL
DESCRIPTION QUANTITY UNIT
MATERIAL LABOR MATERIAL COST LABOR COST TOTAL
MECHANICAL WORKS
0
TTSP OFFICE BUILDING PACKAGE 2
WEST CEBU INDUSTRIAL PARK - SEZ, BUANOY, BALAMBAN, CEBU
THI-CEBU INC.
General Requirements
2.1.1 Mobilization/Demobilization lot
2.1.2 Temfacil(including electricity & water lot
2.1.3 Bonds and Permit lot
SUB - TOTAL FOR ITEM NO. 2.1
Site Storm Sewer Earthworks -
2.2.1 Drainage Structure Excavation cu.m.
2.2.2 Gravel Surface Course cu.m.
2.2.3 Backfilling and Compaction cu.m.
SUB - TOTAL FOR ITEM NO. 2.2
Site Storm Sewer Civil Works
2.3.1 Reinforced Concrete Pipe: 525 mm (21") x 1000 mm pc
2.3.2 Reinforced Concrete Pipe: 600 mm (24") x 1000 mm pc
2.3.3 Reinforced Concrete Pipe: 750mm (30") x 1000 mm pc
2.3.4 Portland Cement: 40 kg (for joint grout) bag
2.3.5 Fine Aggregate: Sand (for joint grout) cu.m.
2.3.6 Reinforced Concrete Manhole: for 21" RCP pc
2.3.7 Reinforced Concrete Manhole: for 24" RCP pc
2.3.8 Reinforced Concrete Manhole: for 30" RCP pc
2.3.9 Reinforced Concrete Street Inlet / Catch Basin: for 21" RCP pc
SUB - TOTAL FOR ITEM NO. 2.3
Building Storm Drain Earthworks
2.4.1 Excavation cu.m.
2.4.2 Gravel Base Course cu.m.
2.4.3 Backfill and Fill cu.m.
SUB - TOTAL FOR ITEM NO. 2.4
Building Storm Drain Civil Works
2.5.1 Reinforced Concrete Pipe: 300 mm (12") x 1000 mm pc
2.5.2 Reinforced Concrete Pipe: 375 mm (15") x 1000 mm pc
2.5.3 Reinforced Concrete Pipe: 450 mm (18") x 1000 mm pc
2.5.4 Interior Catch Basin pc
2.5.5 Exterior Catch Basin pc
SUB - TOTAL FOR ITEM NO. 2.5
Plumbing Works (Sanitary Line)
2.6.1 Sanitary Line ( PVC PIPE )
6"dia. PVC Pipe length
4 " dia. PVC Pipe length
3 " dia. PVC Pipe length
2 " dia. PVC Pipe length
2.6.2 Plumbing /Sanitary Fittings
6"X90 dia. Elbow pcs
6" x 3" dia. Wye Reducer pcs
4" x 4" dia. Wye pcs.
4" x 2"dia.PVC Pipe Wye Reducer pcs.
4" x 90 deg. PVC Elbow pcs.
2" x 90 deg. PVC Elbow pcs.
4" dia. P-Trap W/ Oring pcs.
3" dia. P-Trap W/Oring pcs.
2" dia. P-Trap W/Oring pcs.
4" x 45 PVC Pipe Elbow pcs
4" dia. Clean-out Cover pcs
2" dia. Clean-out Cover pcs
3" dia. Clean-out Cover pcs
2" x 2" dia TEE pcs
3" x 2" dia. PVC Pipe red. pcs
PVC Solvent Cement pint
SUB - TOTAL FOR ITEM NO. 2.6
Storm Drainage
2.7.1 450mm HDPE pcs.
400mm HDPE pcs.
6"Dia. PVC Pipe S-1000 length
Catch Basin units
Grease Trap Interceptor unit
SUB - TOTAL FOR ITEM NO. 2.7
Plumbing Work (Water Supply Line) -
2.8.1 Water Meter pcs.
Meter Stop pcs.
64mm Gate Valve pcs.
50mm Gate Valve pcs.
38mm Gate Valves pcs
Angle Valves pcs
Flexible Hose pcs
2.8.2 PPR Pipe PN20
PPR Pipe PN20 64 mm dia. length
PPR Pipe PN20 50 mm dia. length
PPR Pipe PN20 38 mm dia. length
PPR Pipe PN20 32 mm dia. length
PPR Pipe PN20 25 mm dia. length
PPR Pipe PN20 20 mm dia. length
2.8.3 FITTINGS (PPR Pipe PN20)
64 mm dia. Tee pcs.
50 mm x 38 mm dia. Tee Reducer pcs.
50 mm x 32 mm dia. Tee Reducer pcs.
64 mm dia. Elbow pcs.
50 mm x 38 mm dia. Elbow pcs.
50 mm x 32 mm dia. Elbow Reducer pcs.
20 mm dia. Tee Connector pcs.
20 mm dia. 90 Elbow pcs.
25mm x 20 mm 90 Elbow Reducer pcs.
20mm Coupling pcs
25mm Coupling pcs
25mm Femal Adaptor pcs
20mm Female Adaptor pcs
20 mm dia. Threaded Female Elbow pcs.
End Cap pcs.
2.8.4 Consumables lot
SUB - TOTAL FOR ITEM NO. 2.8
Plumbing Equipments
2.9.1 Transfer Pump Duplex Type 10 Horse Power sets
2.9.2 Boster Pump CPS Type 2.50 Horse Power sets
SUB - TOTAL FOR ITEM NO. 2.9
A. OVERHEAD & PROFIT (7%)
B. CONTINGENCIES (10%)
C. CONTRACTORS PROFIT (15% OF A+B)
D. VAT (12% OF A+B+C)
GRAND TOTAL
Cost per m
Submitted by:
Company name
Title or Position
Date
Project Title DORMITORY BUILDING PACKAGE 2
Location WEST CEBU INDUSTRIAL PARK - SEZ, BUANOY, BALAMBAN, CEBU
Owner THI-CEBU INC.
1.2.7 Fire Hose Cabinet w/ complete accessories 9 unit 16,000.00 4,000.00 144,000.00 36,000.00 180,000.00
1.2.7.1 1 Cabinet
1.2.7.2 1 - Fire Hose 100 ft. x 1 1/2" dia.
1.2.7.3 1 - Nozzle 1 1/2"
1.2.7.4 1 - Hose rack
1.2.7.5 1 - Angle Valve 1 1/2" dia.
1.2.7.6 1 - set coupling
1.2.7.7 1 - 5 kg. capacity fire extinguisher dry chem
4 way - 4 x 65 x 100 mm Dia. (FDC) 1 unit 13,500.00 3,375.00 13,500.00 3,375.00 16,875.00
Company name
Title or Position
Date
TTSP OFFICE BUILDING PACKAGE 5
WEST CEBU INDUSTRIAL PARK - SEZ, BUANOY, BALAMBAN, CEBU
THI-CEBU INC.
VIOSarchitects
Principal Architect
14-Aug-17
Junction Box/Pull box, 600mmW x 200mmD x 600mmH 2 boxes 1,800.00 540.00 3,600.00 1,080.00
Tenshin 2
EMT 50 mm dia 0 lengths 595.00 178.50 0.00 0.00
EMT 40 mm dia 42 lengths 510.00 153.00 21,420.00 6,426.00
EMT 32 mm dia 18 lengths 390.00 117.00 7,020.00 2,106.00
EMT 25 mm dia 40 lengths 295.00 88.50 11,800.00 3,540.00
EMT 20 mm dia 94 lengths 215.00 64.50 20,210.00 6,063.00
Utility Box, 2.5" x 4" 45 boxes 45.00 13.50 2,025.00 607.50
Junction Box, 4" x 4" 45 boxes 55.00 16.50 2,475.00 742.50
Junction Box/Pull box, 600mmW x 200mmD x 600mmH 2 boxes 1,800.00 540.00 3,600.00 1,080.00
Tenshin 3
EMT 50 mm dia 0 lengths 595.00 178.50 0.00 0.00
EMT 40 mm dia 42 lengths 510.00 153.00 21,420.00 6,426.00
EMT 32 mm dia 18 lengths 390.00 117.00 7,020.00 2,106.00
EMT 25 mm dia 40 lengths 295.00 88.50 11,800.00 3,540.00
EMT 20 mm dia 94 lengths 215.00 64.50 20,210.00 6,063.00
Utility Box, 2.5" x 4" 45 boxes 45.00 13.50 2,025.00 607.50
Junction Box, 4" x 4" 45 boxes 55.00 16.50 2,475.00 742.50
Junction Box/Pull box, 600mmW x 200mmD x 600mmH 2 boxes 1,800.00 540.00 3,600.00 1,080.00
1.1.5 Miscellaneous
Tenshin 1
connectors, couplings, access/pull boxes, supports, 194 sets 75.00 22.50 14,550.00 4,365.00
brackets, clamps, restoration materials and consumables
Tenshin 2
connectors, couplings, access/pull boxes, supports, 194 sets 75.00 22.50 14,550.00 4,365.00
brackets, clamps, restoration materials and consumables
Tenshin 3
connectors, couplings, access/pull boxes, supports, 194 sets 75.00 22.50 14,550.00 4,365.00
brackets, clamps, restoration materials and consumables
1.1.6 Grounding and Bonding
Tenshin 1 1 lot 5,000.00 1,500.00 5,000.00 1,500.00
Tenshin 2 1 lot 5,000.00 1,500.00 5,000.00 1,500.00
Tenshin 3 1 lot 5,000.00 1,500.00 5,000.00 1,500.00
SUB - TOTAL FOR ITEM NO. 1.1
1.2 CABLE TV SYSTEM
0.00
27,846.00
9,126.00
15,340.00
26,273.00
2,632.50
3,217.50
4,680.00
0.00
27,846.00
9,126.00
15,340.00
26,273.00
2,632.50
3,217.50
4,680.00
18,915.00
18,915.00
18,915.00
6,500.00
6,500.00
6,500.00
1,438,650.00
0.00
2,535.00
7,605.00
845.00
23,458.50
2,535.00
7,605.00
845.00
23,458.50
2,535.00
7,605.00
845.00
23,458.50
36,064.60
811.20
36,064.60
811.20
36,064.60
811.20
22,431.50
11,271.00
29,913.00
17,257.50
0.00
2,632.50
3,217.50
7,020.00
22,431.50
11,271.00
29,913.00
17,257.50
15,340.00
26,273.00
0.00
2,632.50
3,217.50
7,020.00
22,431.50
11,271.00
29,913.00
17,257.50
0.00
2,632.50
3,217.50
7,020.00
14,625.00
14,625.00
14,625.00
6,500.00
6,500.00
6,500.00
558,561.90
30,000.00
0.00
21,600.00
108,000.00
18,000.00
30,000.00
0.00
21,600.00
108,000.00
18,000.00
30,000.00
0.00
21,600.00
108,000.00
18,000.00
0.00
7,300.80
7,300.80
7,300.80
0.00
0.00
1,014.00
0.00
15,093.00
351.00
429.00
3,120.00
0.00
0.00
1,014.00
0.00
15,093.00
351.00
429.00
3,120.00
15,340.00
26,273.00
0.00
0.00
1,014.00
0.00
15,093.00
351.00
429.00
3,120.00
5,460.00
5,460.00
5,460.00
6,500.00
6,500.00
6,500.00
650,603.40
180,000.00
313,200.00
5,400.00
26,400.00
32,400.00
54,000.00
18,000.00
180,000.00
313,200.00
5,400.00
26,400.00
32,400.00
54,000.00
18,000.00
180,000.00
313,200.00
5,400.00
26,400.00
32,400.00
54,000.00
18,000.00
0.00
38,937.60
38,937.60
38,937.60
0.00
0.00
1,014.00
0.00
38,850.50
702.00
4,147.00
3,120.00
0.00
0.00
1,014.00
15,340.00
26,273.00
0.00
38,850.50
702.00
4,147.00
3,120.00
0.00
0.00
1,014.00
0.00
38,850.50
702.00
4,147.00
3,120.00
13,747.50
13,747.50
13,747.50
6,500.00
6,500.00
6,500.00
2,209,255.80
115,200.00
7,800.00
42,000.00
112,200.00
0.00
16,192.80
16,192.80
16,192.80
0.00
1,326.00
0.00
0.00
32,142.50
3,217.50
3,932.50
3,120.00
0.00
1,326.00
0.00
0.00
32,142.50
3,217.50
3,932.50
3,120.00
0.00
1,326.00
0.00
0.00
32,142.50
3,217.50
3,932.50
3,120.00
11,407.50
15,340.00
26,273.00
11,407.50
11,407.50
6,500.00
6,500.00
6,500.00
510,716.40
59,150.00
59,150.00
10,140.00
20,670.00
3,650.40
10,140.00
6,890.00
3,650.40
10,140.00
6,890.00
3,650.40
0.00
210,600.00
237,276.00
17,550.00
12,636.00
13,806.00
11,700.00
39,546.00
2,925.00
2,106.00
2,301.00
31,200.00
105,456.00
7,800.00
5,616.00
6,136.00
327,600.00
54,600.00
145,600.00
130,000.00
19,500.00
1,459,775.20
482,069.89
688,671.27
175,611.17
161,562.28
8,394,627.31
VIOSarchitects + Cebu Environmental Planner
1126 Villa Raya., Lawaan III ,Talisay City, Cebu, Philippines, 6045
Tel#: 272-0916
E-mail address: viosacrhitect.concepts@yahoo.comm