Professional Documents
Culture Documents
PRODUK GoGeom
Member of Group:
Class TI-38-01
FRI-38-001
TELKOM UNIVERSITY
2017
1
PREFACE
Praise be to Allah the Almighty God.Over the abudance of grace and mercy,
FACILITY LAYOUT PLANNING GoGeom PRODUCT can be solved according to
the authors expectation. This report is written as a requirement to fulfill the course
FACILITY LAYOUT PLANNING Telkom University. This report also suported by
Data from observation made by the theories related to the Production Planning.
Authors
2
DAFTAR ISI
PREFACE ............................................................................................................................................ 2
3
I.3.9 Knowing the gant chart of material handling that the company used based on unit
load. 15
I.3.10 Knowing how to calculate the allowance that needed in each facility. .....................15
I.3.11 Knowing how to analyze and calculate production area requirement based on the
allowance and each dimenson of machine that used ...............................................15
I.3.12 Knowing how to determine the initial layout for production area ............................15
I.3.13 Knowing how to calculate the allowance that needed in each facility ......................15
I.3.14 Knowing how to analyze and calculate production area requirement based on the a .
llowance and each dimenson of machine that used ..................................................15
I.3.15 Knowing how to determine the initial layout for production area ............................15
I.3.16 Knowing how much the Cost of Material Handling ....................................................15
I.3.17 Knowing how the material flow by using Form To Chart (FTC) ..................................15
I.3.18 Knowing how create an efficient relationship between departments within factory
15
I.3.19 Knowing how to pinpoint the location of every department in accordance with the
linkage between the activities and the flow material ................................................15
I.3.20 Knowing how to calculate Flow Unit Distribution (UFD). ...........................................15
I.3.21 Knowing how to create initial layout with the additional area ..................................15
I.4 Benefits ...........................................................................................................................16
I.4.1 Can know how to determine facility plant for PT Z ........................................................16
I.4.2 Can know where is the appropriate facility plant for PT Z .............................................16
I.4.3 Can know the process flow of th product ......................................................................16
I.4.4 Can know the Bill of Material of the product that PT Z produced .................................16
I.4.5 Can know is the operational process chart of the product ............................................16
I.4.6 Can know the Precendence Diagram of the product .....................................................16
I.4.7 Can know the type and dimension of material handling used .......................................16
I.4.8 Can know the stacking of material handling that will used in company ........................16
I.4.9 Can know the gant chart of material handling that the company used based on unit
load 16
I.4.10 Can know how to calculate the allowance that needed in each facility ....................16
I.4.11 Can know how to analyze and calculate production area requirement based on the
allowance and each dimenson of machine that used. ...............................................16
I.4.12 Can know how to determine the initial layout for production area. .........................16
I.4.13 Can know how to calculate the allowance that needed in each facility ....................16
I.4.14 Can know how to analyze and calculate production area requirement based on the
allowance and each dimenson of machine that used. ...............................................16
I.4.15 Can know how to determine the initial layout for production area. .........................16
I.4.17 Can know how the material flow by using Form To Chart (FTC) ................................17
4
I.4.18 Can know how to create initial layout with the additional area ...............................17
I.4.19 Can know how to pinpoint the location of every department in accordance with the
linkage between the activities and the flow material ................................................................17
I.4.20 Can know how to calculate Flow Unit Distribution (UFD) ..........................................17
I.4.21 Can know how to create initial layout with the additional area ...............................17
Bab II THEORITICAL SUPPORT ...................................................................................................18
II.1 Location And Layout Facility Theory ...................................................................................18
II.2 Determining Facilities Location ..........................................................................................18
II.3 Alternative Methods In Determining Facility Location.......................................................19
II.4 Bill of Material ....................................................................................................................20
II.5 Operation Process Chart .....................................................................................................21
Operation Process Chart performs the process of raw material into a product which the
operation steps and inspection belongs. The information is including time spent, raw material, a
process needed, tool and equipment. Operation process map illustrates the operating steps and
checks experienced ingredients in the order-order from the beginning to the final product as a
whole as well as semi- finished parts (Sutalaksana 2005, P23). There are several benefits of
Operational Process Chart, such as: ...............................................................................................21
II.6 Precedence Diagram ...........................................................................................................23
II.7 Routing Sheet Definition ....................................................................................................24
II.8 Routing Sheet Purposes ......................................................................................................24
II.9 Routing Sheet Table ............................................................................................................25
II.10 Material Handling System Planning....................................................................................26
II.11 Material Handling Equipment ............................................................................................27
II.12 Unit Load.............................................................................................................................27
II.13 Allowance ...........................................................................................................................28
II.14 Plant Surface Area ..............................................................................................................29
II.15 Material Handling Cost .......................................................................................................30
II.16 Input and Output Material Handling Cost ..........................................................................31
II.17 Distance Measurements .....................................................................................................31
II.18 From To Chart .....................................................................................................................32
II.19 Activity Relationship Chart (ARC) .......................................................................................34
II.20 ARC Normalization ..............................................................................................................35
II.21 Unit Flow Distribution (UFD) ..............................................................................................35
II.22 Worksheet ..........................................................................................................................35
II.23 Area Allocation Diagram .....................................................................................................36
II.24 Template .............................................................................................................................37
Bab III data calculation and analysis ..........................................................................................38
III.3 Unit Load Calculation and Determination of Material System.......................................58
5
III.3.1 Dimension of Material Handling .............................................................................58
III.3.2 Analysis of determining Material Handling Equipment..........................................58
III.3.3 Analysis of Stacking Calculation .............................................................................59
III.3.4 Analysis of Unit Load ..............................................................................................61
III.4 Calculation of Allowance and Determinating Space Requirement for Plant Facility
Layout Requirements. ................................................................................................................62
III.4.1 Allowance Calculation............................................................................................62
III.4.2 Calculation of Material ...........................................................................................64
III.4.3 Analysis of Plant Surface Requirement .................................................................66
III.4.4 Determination of Material Hadling Cost ................................................................68
III.4.5 Analysis of Process Flow Using FTC ........................................................................73
III.5 Determination The Relation Between Activity and Determining Production Floor of
Department Layout.....................................................................................................................75
III.5.1 Determination The Relation Between Activity and Determining Production Floor
of Department Layout ............................................................................................................75
III.5.2 Determination of The Relation Between The Activity and Determination of
Production Department with Added Facility ........................................................................82
III.6 Designing Plant Facility Layout .......................................................................................85
Bab IV KESIMPULAN DAN SARAN ..............................................................................................90
Bab V DAFTAR PUSTAKA ...........................................................................................................96
6
DAFTAR GAMBAR
Picture 1 Formula of Cx ..................................................................................................................19
Picture 2 Formula of Cy ..................................................................................................................20
Picture 3 Example of OPC ...............................................................................................................22
Picture 4 The Exmaple of Precedence DIagram .............................................................................24
Picture 5 Routing Sheet Table ........................................................................................................25
Picture 6 Formula of Part of Routing Sheet ....................................................................................25
Picture 7 Material Handling Based on Material Flow Level............................................................27
b. Picture 8 Pallet ........................................................................................................................27
Picture 9 Skid ..................................................................................................................................28
Picture 10 Formula of Allowance ...................................................................................................28
Picture 11 Formula of Total Allowance Material ............................................................................28
Picture 12 Formula of Allowance Material Removal ......................................................................29
Picture 13 Table of Production Floor Area Needs ..........................................................................29
Picture 14 Euclidean Distance ........................................................................................................32
Picture 15 Rectiliniar Distance ........................................................................................................32
Picture 16 Formula of FTC Calculation ...........................................................................................33
Picture 17 Formula of FTC Inflow ...................................................................................................33
Picture 18 Fromula of FTC Outflow ................................................................................................33
Picture 19 Respondent of qualitative factor ..................................................................................38
Picture 20 Jatinangor Area .............................................................................................................39
Picture 21 Ciganitri Area .................................................................................................................39
Picture 22 Mengger Area ................................................................................................................39
Picture 23 The Competitor Distance from Jatinangor ....................................................................41
Picture 24 The Competitor Distance from Ciganitri .......................................................................42
Picture 25 The Competitor Distance from Mengger ......................................................................42
Picture 26 Supplier Distance of Balsa Wood from Jatinangor ........................................................43
Picture 27 Supplier Distance of Balsa Wood from Ciganitri ...........................................................43
Picture 28 Supplier Distance of Balsa Wood from Mengger ..........................................................43
Picture 29 Supplier Distance paint from Jatinangor .......................................................................44
Picture 30 Supplier Distance paint from Ciganitri ..........................................................................44
Picture 31 Supplier Distance paint from Mengger .........................................................................45
Picture 32 GoGeom Product ...........................................................................................................46
Picture 33 CNC Machine as Facility ................................................................................................48
Picture 34 Sanding Machine as Facility ..........................................................................................48
Picture 35 Spray Paint Table as Facility ..........................................................................................48
Picture 36 Spray Paint Table as Facility ..........................................................................................49
Picture 37 Assembly & Inspection Area .........................................................................................50
Picture 38 Operation Process Chart of GoGeom Production Process ............................................51
Picture 39 Bill of Material ...............................................................................................................52
Picture 40 Precdence Diagram for GoGeom Product .....................................................................53
Picture 41 CNC Machine as Facility ................................................................................................54
Picture 42 Sanding Machine as Facility ..........................................................................................54
Picture 43 Spray Paint Table as Facility ..........................................................................................55
Picture 44 Area as Facility...............................................................................................................56
Picture 45 Routing Sheet ................................................................................................................56
Picture 46 Routing Sheet ................................................................................................................57
7
Picture 47 Hand Truck as Material Handling ..................................................................................58
Picture 48 Unit Load .......................................................................................................................61
Picture 49 Gantt Chart for each Process ........................................................................................61
Picture 50 Calculate The Removal Material Allowance ..................................................................63
Picture 51 Formula to calculate Removal Material Allowance ......................................................63
Picture 52 Weight of Component ...................................................................................................65
Picture 53 Recapitulation of Allowance .........................................................................................66
Picture 54 Plant Surface Area Needed ...........................................................................................66
Picture 55 Formula of Tota Surface Area .......................................................................................66
Picture 56 Initial Layout Design ......................................................................................................67
Picture 57 Flow of part ...................................................................................................................67
Picture 58 Initial Layout ..................................................................................................................68
Picture 59 MHE Cost Calculation ....................................................................................................69
Picture 60 From To Chart................................................................................................................73
Picture 61 FTC Inflow ......................................................................................................................74
Picture 62 From To Chart Outflow..................................................................................................74
Picture 63 Relevance Motive Table ................................................................................................76
Picture 64 Relevance Degree Activities ..........................................................................................76
Picture 65 Unit Flow Distribution ...................................................................................................78
Picture 66 Normalization ................................................................................................................79
Picture 67 Unit Flow Diagram .........................................................................................................80
Picture 68 Worksheet .....................................................................................................................80
Picture 69 Area Allocation Diagram ...............................................................................................81
Picture 70 Area Allocation Diagram for Receive and Shipment .....................................................81
Picture 71 Initial Layout based on AAD ..........................................................................................82
Picture 72 ARC of additional facility ...............................................................................................83
Picture 73 Worksheet Production Floor .........................................................................................83
Picture 74 AAD Production Floor for Added Facility ......................................................................84
Picture 75 Initial Layout for added facility......................................................................................84
Picture 76 Initial Layout ..................................................................................................................85
Picture 77 Final Layout 2 Department ............................................................................................86
Picture 78Final Layout 3 Department .............................................................................................87
Picture 79 Final Layout 2 then 3 Department ...............................................................................88
Picture 80 Final Layout 3 then 2 Department ................................................................................89
Picture 81 Recapitulation of Allowance Operator, Material, and Material Removal. ...................92
Picture 82 The Production Area Requirement ...............................................................................92
Picture 83 From To Chart................................................................................................................94
Picture 84 From To Chart Inflow ....................................................................................................94
Picture 85 From To Chart Outflow..................................................................................................95
8
DAFTAR TABEL
9
BAB I PRELIMINARY
I.1 Background
The layout of the plant or facility layout can be defined as a procedure for setting
the plant facilities to support the production process (Wignjosoebroto,2009). Based on the
theory above, any industry or home industry requires the design of the facility because
without good design of the facility their production process can not be efficient and
effective. The design and layout facility design needs to bee made. Starting with finding
the proper location for the factory, layout design, and material handling design.
After determining the location of the facility, the next stage of facility layout design
is determine the flow of product. The flow of these products serves to determine the
production processes that occur in a company. With this product stream researchers can
tell how a facility can be designed at a later time and create a new design for the facility.
Is used to determine the course of the production process of the components can use the
pattern map production process. The results of the determination or identification is
usually presented in form what is called Routing Sheet. To be able to design the layout of
a factory, the next step should be known is the production time and the number of engine
requirements. Therefore, it must be known when the process for making the product.
With Routing Sheet can be known sequence of machines or equipment needed to make
the seat, so that it can be predicted needs of materials, machinery or equipment used.
Raw material handling system plays a very important in the planning of a factory.
In most manufacturing, people assume that it is better material moving or switching of the
person or machine. For some particular cases will sometimes be a better man or machine
(or both) are being displaced. Factory layout planning cannot ignore the significance of
the material displacement activity, and vice versa is not possible to apply effective
material transfer system without regard to the common problems encountered in the
planning layout. Transfer of substance or material is a very important activity in
production activities and is closely linked with planning the layout of production
facilities. This activity is an activity of "non-productive" because it does not give any
change to the material or material that is removed, there will be no change in the shape,
dimensions, and properties of the physical or chemical properties of the material are
10
changed. Resettlement activities / material will add to the cost (cost). Thus whenever
possible removal activity such materials be eliminated or at least the right to reduce the
cost of the removal of such material is a material transfer at distances as short as short as
the layout of the production facility or an existing department.
Material handling is the flow of material that must be planned so that the hair-
splitting material (material) will be transferred at the time and to the right location.
Material handling cost will easily be able to be calculated. Usually the material handling
cost will be proportional to the distance the material displacement and distance
measurements will be carried out with a simple layout of the production facility where it
can be described. Material handling costs are often heavily influenced by the design
layout itself. Because the material handling cost is proportional to the distance moved by
the material, then the selection of the type of layout itself is going to influence the amount
of material handling costs.
Material handling costs (MHC) the costs incurred for the transport of materials,
ranging from raw materials, semi-finished materials, to finished materials. Below are
some of the reasons why the material handling costs (MHC) becomes the criterion of
goals / success in determining the layout of the facility. Most of the total operating costs
resulting from material handling costs. Due to the influence of the material handling costs
to the total cost of production, it takes the form of an analysis of how mengefisiensi use
of material handling in order to minimize both the total production cost or total cost of
designing the layout and facilities.
The design layout of the facility has a procedure that analyzes the product and the
process by performing initial identification, technical aspects, management and
organization, analysis of the economic and financial aspects, as well as activity analysis
and layout planning. Initial identification was conducted to determine the data needed to
design the layout of the facility, one of which is the operation process map. The technical
aspects explain the amount of materials and machines used by routing techniques sheet
and multi-product process chart (MPPC). After the election material handling, material
handling equipment determination, determination of the area of the plant, and the
efficiency of material handling process MPPC done in order to explain how the flow of
the production process can be made efficiently and minimize backtracking. MPPC (Multi
Product Process Chart) is a diagram showing the sequence for each of the components to
be produced. Map MPPC could also be useful as a general overview relating to measures
11
workmanship of every product that is at a particular process in order to obtain
information about the common process of each product with the other. Based MPPC can
also be known backflow (backtracking) and a flow pattern that does not comply with the
order process (Lutfah Ariana, 2005).
The technique is used as a tool to analyze the relationships between the activities that are
Activity Relationship Chart. ARC Activity Relationship Chart or Map Employment
activity is the activity or activities between each section that describes important whether
or not the closeness of the room. In an organization there must be a factory bonded
relationships between an activity with other activities that are considered important and
always near for smooth activity. Therefore made a map of the relationship of activities,
which will be known how relationship happened and must be met in accordance with the
tasks and a supportive relationship.
12
I.2 Problem Identification
I.2.8 How is the stacking of material handling that will used in company ?
I.2.9 How is the gant chart of material handling that the company used based on
unit load?
I.2.11 How to analyze and calculate production area requirement based on the
allowance and each dimenson of machine that used ?
I.2.14 How to analyze and calculate production area requirement based on the
allowance and each dimenson of machine that used ?
13
I.3 Objectives
14
I.3.6 To know the Precendence Diagram of the product
I.3.8 Knowing the stacking of material handling that will used in company.
I.3.9 Knowing the gant chart of material handling that the company used based
on unit load.
I.3.10 Knowing how to calculate the allowance that needed in each facility.
I.3.11 Knowing how to analyze and calculate production area requirement based
on the allowance and each dimenson of machine that used .
I.3.12 Knowing how to determine the initial layout for production area
I.3.13 Knowing how to calculate the allowance that needed in each facility
I.3.14 Knowing how to analyze and calculate production area requirement based
on the allowance and each dimenson of machine that used
I.3.15 Knowing how to determine the initial layout for production area
I.3.17 Knowing how the material flow by using Form To Chart (FTC)
I.3.21 Knowing how to create initial layout with the additional area
15
I.4 Benefits
I.4.4 Can know the Bill of Material of the product that PT Z produced
I.4.7 Can know the type and dimension of material handling used
I.4.8 Can know the stacking of material handling that will used in company
I.4.9 Can know the gant chart of material handling that the company used based
on unit load
I.4.10 Can know how to calculate the allowance that needed in each facility
I.4.11 Can know how to analyze and calculate production area requirement based
on the allowance and each dimenson of machine that used.
I.4.12 Can know how to determine the initial layout for production area.
I.4.13 Can know how to calculate the allowance that needed in each facility
I.4.14 Can know how to analyze and calculate production area requirement based
on the allowance and each dimenson of machine that used.
I.4.15 Can know how to determine the initial layout for production area.
I.4.16 Can know how much the Cost of Material Handling
16
I.4.17 Can know how the material flow by using Form To Chart (FTC)
I.4.18 Can know how to create initial layout with the additional area
I.4.19 Can know how to pinpoint the location of every department in accordance
with the linkage between the activities and the flow material
I.4.21 Can know how to create initial layout with the additional area
17
BAB II THEORITICAL SUPPORT
Facility Location is the right location for the manufacturing facility, it will have
sufficient access to the customers, workers, transportation, etc. Facility location
determination is a bussiness critical strategic decision. There are severa factors, which
determine the location of facility among them competition, cost, and corresponding
associated effects.
Before we determining the facilities location, we should do the facility planning.
Facility Planning Goals :
Support vision and mission of organization.
Utility of worker, space, equipment, and energy.
Minimize invenstment.
Ease the maintenance.
Protect the workers and their satisfaction.
Factors that influencing facility location:
a. Customer Proximity
Facility locations are selected closer to the customer as to reduce transportation
cost and decrease time in reaching the customer.
b. Bussiness Area
Presence of other similar manufacturing units around makes business area
conducive for facility establishment.
c. Availability Of Skill Labor
Education, experience and skill of available labor are another important, which
determines facility location.
18
d. Free Trade Zone/Agreement
Free-trade zones promote the establishment of manufacturing facility by providing
incentives in custom duties and levies. On another hand free trade agreement is
among countries providing an incentive to establish business, in particular, country.
e. Suppliers
Continuous and quality supply of the raw materials is another critical factor in
determining the location of manufacturing facility.
f. Environmentasl Policy
In current globalized world pollution, control is very important, therefore
understanding of environmental policy for the facility location is another critical
factor.
a. Quantitive Method
In this method, assumed that production cost is not calculated. The example of
quantitative method is Center Of Gravity (COG).
Center Of Gravity (COG)
The Center of Gravity Method is an approach that seeks to compute
geographic coordinates for a potential single new facility that will minimize costs. Its
an approach where the main inputs that it considers are the following:
Markets
Volume of goods shipped
Shipping costs
This method is beneficial because its simple to compute, considersexisting
facilities and minimizes costs. Step-by-step of CoG:
a. Place all the customer locations on a coordinate system
b. Put the total demand in each customer locations
c. Define the X and Y coordinates by using Equation :
With formula:
Picture 1 Formula of Cx
19
Picture 2 Formula of Cy
With details:
Cx = X coordinate of center of gravity
Cy = Y coordinate of center of gravity
dix = X coordinate of i location
diy = Y coordinate of the i location
Vi = volume of goods moved to or from i location
b. Qualitative Method
In using this method, all the factors that influence the selection of plant location, be
it a major factor and not the main factor, given the vote in accordance with the
conditions of each alternative location.
Factor Rating
Operation Process Chart performs the process of raw material into a product
which the operation steps and inspection belongs. The information is including time
spent, raw material, a process needed, tool and equipment. Operation process map
illustrates the operating steps and checks experienced ingredients in the order-order from
the beginning to the final product as a whole as well as semi- finished parts (Sutalaksana
2005, P23). There are several benefits of Operational Process Chart, such as:
21
Picture 3 Example of OPC
When the object has changed physically and chemically, then the operation is
done; assembly or disassembly by another object; change into another operation,
transportation, inspection or storage. An operation might be done when information sent
or received, or planning and calculating. It also shows the worker works.
Inspection
22
Inspection is an activity when the object inspected in term of quality and quantity.
Storage
Double Activities
Shows activities which are done in the same time by operator in the same work
station, for
23
Picture 4 The Exmaple of Precedence DIagram
II.7 Routing Sheet Definition
Routing sheet is made to streamline and simplify the way how to produce a
product. The main purpose of routing sheet is to determine the number of machines or
production equipment that necessary to meet the desired production quantities. There are
other specific purposes of the routing sheet:
24
1. Find out the process flow (from preparation to packaging) suffered by the materials
for each type of component to determine the number of machine.
2. As a basic of determining factory layout.
3. As a tool for improve the ways of work is being done.
4. As a process time guidance of component for each machine.
Disciplining / familiarize operators to work regularly and quickly according to what
has been planned.
Explanation:
A : The name of operation for each process
B : Name of the machine that is used for each process
C : The time that is needed for machine to produce one product
D : The average product that can be produced by the machine in one day
E : The ability level or measurement the success of a machine to produce a product
F : The capacity of the actual machine for produce product in one day
G : The percentage of process failure and cannot be used anymore (broken) or residual
(scrap)
H : Products that produced per day
I : Number of products that are prepared after defect per day
J : The theoretical number of machines required to meet production
K : The number of machines required in accordance with existing conditions.
By Formula:
25
II.10 Material Handling System Planning
26
Picture 7 Material Handling Based on Material Flow Level
The principle - the principle of the transfer of materials is as follows (Apple, 1972, p.49):
1. Planning Principle
2. Standardization Principle
3. Work Principle
4. Ergonomic Principle
5. Unit Load Principle
6. Space Utilization Principle
7. System Principe
8. Automation Principle
9. Environmental Principle
10. Life Cycle Cost Principle
Load Unit explained that the material should be dealt with everything that is most
efficient. Unit load provides insights on the maximum number of units of products being
transported / carried technically, with the aim of reducing the amount of displacement is
unnecessary. A logical question is right for Unit Load Principle is "What is the right size for a
package or load?" There are some advantages by using Unit Load:
a. More material is being handled at the same time can reduce the number of trips
required thereby potentially reducing material handling costs, reduce unloading
time and reduce product damage.
b. Possible to use standard material handling equipment.
b. Picture 8 Pallet
27
c. Skid
Skid is a tool used to transport materials for the transportation of large volumes
can achieve. Skid usually made of metal and shaped like a pallet surface. Skid
usually used to lift an unnecessary burden pernumpukan.
Picture 9 Skid
II.13 Allowance
Allowance is the flexibility of the engine room and clearances required for the alley
traffic of materials and workers can work smoothly. The type of allowance is to be noted:
a. Allowance Operators, namely leeway is given as a space for the operator to operate
the machine as well as the traffic operator.
b. Allowance Material, namely tolerance given for temporary storage of materials
to be processed.
Below the formula to calculate the material allowance:
28
Picture 12 Formula of Allowance Material Removal
The calculation of the floor area of the plant area was conducted to estimate the
broad needs of the plant area. This area needs to be considered for all activities in the
plant which should pay attention to three kinds of areas, namely:
Area necessary for the operation of machinery or equipment of existing
production.
The area needed for the storage of raw materials (receiving) and an area for
storage of finished products (shipping).
Area required for service facilities, such as offices.
Raw material warehouse floor area (receiving) a floor area used to store raw
materials or the materials to be used in production. Activities of receipt of goods is the
beginning of a whole pattern of material flow, so the placement should adjacent to
transportation facilities that connect the plant with the outside environment.
While the finished product warehouse floor area (shipping) is a department related
to the finished product storage and loading into the means of transportation
available to and then delivered to the consumer.
Picture 13 Table of Production Floor Area Needs
Dimension
Length (m) Width (m)
N Facili Machi Tot
o ty ne Machi Employ Materi Materi Tota Machi Employ MateriMateri Tot al
ne ee al al l ne ee al al al
Amou Are
nt Lengt Allow Movem Allow Leng Widt Allow Movem Allow Wid a
h4 ance ent ance th8 h9 ance ent ance th13 14
1 2 3 5 6 7 10 11 12
Allow Allow
ance ance
Information:
Column 1: number of machines adapted to the process sequence operation
Column 2: the name of the facility or machine used Column 3: number of similar
machines needed
Column 4: the length of the machine used
Column 5: allowance or allowances given to employees
Column 6: allowance or concession given to the removal of material
Column 7: allowance or concession given to material Column 8: The total length of the
machine required Column 9: measure the width of the machine used
Column 10: allowance or concession granted to employees
Column 11: allowance or concession given to the removal of material
29
Column 12: allowance or concession given to material Column 13: total width of the
machine is required Column 14: The vast size machines use.
Material handling is expressed as the art and science that includes handling
(handling), displacement (moving), packaging (packaging), storage (storing) while
controlling (controlling) of materials or materials with all its forms. (Wignjosoebroto,
2003).
Material handling costs (OMH) the costs incurred for the transport of materials, ranging
from raw materials, semi-finished materials, to finished materials. Below are some of the
reasons why the material handling costs (OMH) becomes the criterion of goals / success
in determining the layout of the facility (Joko Susetyo, 2010).
The amount of material handling costs (OMH) depends on several factors directly
affecting, namely:
a. The type of conveyances
This type of conveyance determined by the load carried. For efficiency, as long
as can be handled by humans, the material can be transported by humans. If the
material is transported exceed the load can be transported by humans, can use tools.
However, please note that the costs of using tools more expensive than the cost of man
power.
b. The weight of objects being moved
Heavy material that must be removed will determine the use of a type of
transport means. The heavier the load, the greater the tools used payload power and
will certainly have a larger overhead anyway.
c. Distance moved
If you already know what means of transport to be used, the following factors that
influence the displacement distance. The farther the distance used then the costs
involved will be even greater.
According to Tompkins and White (2000), 20-50% of the total cost of
manufacturing operations derived from material handling costs (OMH) and the costs
associated with the layout. If the use of efficient material handling it will indirectly lead
to an increase in capacity and the reduction of production costs and bottlenecks in the
production process.
There are several ways to minimize material handling cost are as follows:
a. Reducing idle time.
b. Maximizing the use of equipment to obtain higher unit charge.
c. Minimize displacement and back and forth movements of material handling
to reduce operating costs.
30
d. Adjust the distance between the facilities as close as possible in order to transfer
the material to become more optimal.
e. Using the right equipment to reduce damage to the material and use the
appropriate unit loads.
f. Perform maintenance on the equipment to prevent big repair costs.
Where:
31
Picture 14 Euclidean Distance
b) Rectilinear Distance
Is the distance measured perpendicular to follow the path of the center point to the
point of facilities other amenities. The formula used in the distance measurement
rectilinier namely :
Where:
xy = x-coordinate at the center of facilitation
yi = the x-coordinate at the center of the facility j dij = distance between the
centers facilities i and j
32
Picture 16 Formula of FTC Calculation
There 2 kind of FTC, FTC Inflow and FTC Outflow. Here the formula:
Formula of FTC Inflow:
33
II.19 Activity Relationship Chart (ARC)
34
Table 3 Total Department in ARC Techniqie
Code Amount
A 5% from total combination
E 10% from total combination
I 15% from total combination
O 20% from total combination
U The remainder of the combination of all
departments
X 5% from ttal combination
Normalization ARC used to transform qualitative data into quantitative data form to
be taken into account in the proposed layout further. The value of this normalization derived
from estimates of the scales every grade that every problem has the same multiplier
Table 4 ARC Normalization
Code Value
A 1
E 0.8
I 0.6
O 0.4
U 0.2
X 0
By looking at the relationship between departments in the ARC, the letter grade (A,
E, I, O, U, X) will be transformed into quantitative form. The code number will be useful to
be input on Unit Flow Distribution (UFD).
UFD is a multiplication of FTC with ARC. Matrix flow distribution unit is the data
that will be included in the algorithm using software WinQSB CRAFT.
UFD = FTC (Cost x Frequency) x ARC Normalization
II.22 Worksheet
Activity relationship chart (ARC) is useful for planning analysis of the relationship
between the activities of each - each department. As a result the data obtained will then be
used for the determination of the location of each - each department, namely through the
Area Allocation Diagram (AAD). AAD is to give an explanation of the relationship between
35
the activities of the department with other departments, the first data obtained from ARC
entered into a worksheet (work sheet).
Area allocation diagram (AAD) is a global pattern in the form of depiction of the
conclusions of the ARC, where the ARC has been known to the conclusion level of interest
among the activities. Thus, the level of interest among these activities affect the degree of
proximity between the layout of the event. Information obtained from the AAD is the
utilization of the layout area and the position of the activities that have been arranged by
importance proximity. ARC and AAD is a kind of map that illustrates the relationship
between the activity as a result of certain reasons that must be met. Here is a basic
consideration in determining the AAD, ie:
1. Flow production, material, equipment
2. ARC, information flow
3. Points required
4. Worksheet
The purpose of the AAD, namely:
1. Designing a space efficient production in one integrated entity.
2. Adjust the placement of work stations that are efficient in the production floor with
attention close relationship that has been determined in the ARC.
3. Determining the relationship between the facility and the reason.
4. Translating the approximate area into an initial layout
5. Provide comprehensive estimate of total approaching actual conditions. Became the
basis for further planning.
While profits from the manufacture of AAD, namely:
1. Division systematic activity area.
2. Facilitate the layout process
3. Minimize the unused space.
Area allocation diagram consists of two types, namely:
a. That depiction AAD AAD Powrarm approach in the form of block diagram
coincide between activity facilities.
b. The AAD on approach Muther That depiction AAD with the relationship line that
indicates the level of correlation between one activity to another activity. Muther
approach similar to that suggested DE Villenuve and Hofman and Downs. They
all have developed similar flow diagrams, with activities which were connected
by lines or bands with a variety of different thicknesses. The width of the line
indicates the flow volume between activities, and helps planners to connect each
of the activities as appropriate in the early stages of planning the layout. In
Muther approach, there is a conventional process symbols and line numbers
between emblem shows the importance of proximity, namely:
A = 4 lines
E = 3 lines
I = 2 lines
36
O = 1 line
U = no line
X = wavy lines
II.24 Template
Template is a picture of plant layout will be made based on the results of previous
AAD workmanship. Template is a depiction of all activities of the plant and the linkages
activities. In making the template should be held accountable floor area of a predetermined
and given gang.Dengan the template, it can be seen:
1. The layout of the office
2. Location of service facilities such as canteen, roads, and others.
3. The layout of the production floor
4. The material flow from receiving to shipping
The template is flexible, making it possible to obtain many alternatives layout. Templates can
generally be made in three forms, namely:
1. BLOCK rectangular determined by the length and maximum width which is owned
by the object.
2. Countour is a form of projection or shelter top of the object.
3. CLEARANCE countour is a form of projection of the object to be equipped
4. Clearances parts of the object that can move.
37
BAB III DATA CALCULATION AND ANALYSIS
III.1 Determiing Facilities Location
III.1.1 The step of determining the location of the factory:
a) Based on the observation result, the writers can determine the X & Y
coordinate of plant location :
Coordinate
Y X
107,655074 -6,967566
The selected plant that suitable for PT Z is Ciganitri. Because based on the
factor rating approach Ciganitri get highest Wt value.
b) The space available in Ciganitri is around 30000 m2
c) Here below, the writers attach the substantion of observation result and survey
photo with respondents.
38
Picture 20 Jatinangor Area
39
III.1.2 Below is data that correlated with step in determining plat location by Factor
Rating:
a) Quantitative and Qualitative data with the reason, analysis and Wt value:
Type Of
No Factors Reasons
Data
Because UMR/ UMK is a component that influence
1
UMR/UMK Quantitative labor cost
Supplier
2 Distance Of Becausethe supplier distance of balsa wood can
Balsa Wood Quantitative influence the cost of transportatiom
Because price of land can influence the investation
3
Price Of Land Quantitative cost
Potential Potential market can not calculated because it is
4
Market Qualitative depends on the place
Based on how the people around the place, most of
5
HR Quality Qualitative them is skilled or not, worked or not.
Based on wether the place ever got the natural disaster
6 Disaster Risk Qualitative ,or other disaster
Supplier
Distance Of
7 Paint Quantitative Can be calculated by google maps to find the distance.
Table 7 Each Factor of Quantitative and Qualitative Data With The Analysis
Factors Wt Analysis
Competitor It is affect in company's selling product but is not as
Distance 0,1 important as the price land
Supplier Distance It is affect in purchasing cost that can give in big impact
Quantitative
After define the qualitative and quantitative data and the Wt value, we should
calculate the quantitative data from any trusted resources but, for qualitative data we
got the data from survey by 5 respondents each place. And here is the result of :
40
Quantitative Data by search in any-trusted resources:
Table 8 Quantitative Data
Quantitative Alternatives
Factors Mengger Ciganitri Jatinangor
Competitor
Distance 142 146 161
Supplier Distance
Of Balsa Wood 155 159 173
Price Of Land Rp4.500.000 Rp1.200.000 Rp1.500.000
Supplier Distance
Of Paint 8,4 16,3 30,7
b) Here data that correlated with each factor in each location that was decided:
1. Quantitative Factor
Competitor Distance: The competitor of PT Z is company that produce
educational toys that addressed in: Istana Koleksi Toys, Jalan Pejuang Raya No.2,
Pejuang, Medan Satria, Pejuang, Medan Satria, Kota Bks, Jawa Barat 17131,
Indonesia. And here the competitor distance for each plant (Mengger, Cigantri,
and Jatinangor)
41
Picture 24 The Competitor Distance from Ciganitri
There are 2 raw material of GoGeom product. And balsa wood is one of them.
The supplier of balsa wood that cooperate with PT Z adressed in: Kirana Boutique
Office, Jl. Boulevard Raya No. 1, Kelapa Gading, Klp. Gading Tim., Klp. Gading,
Kota Jkt Utara, Daerah Khusus Ibukota Jakarta 14240, Indonesia. And here the
supplier distance of balsa wood for each plant (Mengger, Cigantri, and Jatinangor).
42
Picture 26 Supplier Distance of Balsa Wood from Jatinangor
Price Of Land is the price of each plant location. Here the link for Jatinangor,
Ciganitri, and Mengger:
http://rumahdijual.com/bandung/1345996-tanah-murah- cocok-untuk-perumahan-
atau-cluster.html
43
dijual.com/bandung/1655051-dijual-tanah-pesawahan-datar- di-ciganitri-buahbatu-
bandung.html
http://rumahdijual.com/bandung/1365632-tanah-datar- dalam-komplek-bayypas-
soetta-m-toha-mengger.html
The second raw material that PT Z needed is paint. And here the Supplier
Distance that addressed in: Lanud Sulaiman Bandung, Jalan Hercules 2, Sulaiman,
Margahayu, Sulaiman, Margahayu, Bandung, Jawa Barat 40229, Indonesia.
44
Picture 31 Supplier Distance paint from Mengger
2. Qualitative Factor:
Potential Market, the data is done by survey that will be sent by hardcover.HR
Quality the data is done by survey that will be sent by hardcover.Risk Disaster the
data is done by survey that will be sent by hardcover.
In survey, the writer use scale between 10 100. Then, the writers sum the total
scale for each place and finally the writers get the score by devided it
c). The selected area as potential plant facilities are: Jatinangor, Ciganitri and Mengger.
And with qualitative and quantitative factor we can rank for the smallest value then
we can get the Wtd value. The area that has the highes Wtd score will be choosen as
potential plant facilities for PT Z.
45
From the weight rate in ech potential area, we choose Ciganitri as the best potential
plant facilities because Ciganitri has the highest weight rate
46
Table 11 Process Time of GoGeom Production
Process Name
Process Time
NO
Part Wall Part Roof Part Shape Pieces (Menit)
47
No Faclity Name + Picture Facility Size Efficiency
CNC MACHINE
CNC MACHINE
CNC MACHINE
Sanding Machine 1
Sanding Machine 2
Sanding Machine 2
48
No Faclity Name + Picture Facility Size Efficiency
49
No Faclity Name + Picture Facility Size Efficiency
Assembly Table
Packaging Area
50
Picture 38 Operation Process Chart of GoGeom Production Process
51
Table 13 Data of GoGeoms Bill of Material
Bill Of Material
Company : HAPPINESS FIRM Prepared By : FRI-38-001
Product : GoGeom Date : 16/04/2017
From the result of Bill Of Material, the writers conclude that there are 2 levels in
GoGeom product, which all of the product is make by the company ( PT Z ). By knowing the
lead time, the production division should be know when to do the purchasing and the
production that can fulfill the demand of the customer. And then, by BOM the writers know
about the quantity that production division should produce GoGeom product.
III.2.6 Data of Name and Facility Size Dimension and Its Analysis ( machine, table,
or area)
53
No Faclity Name + Picture Facility Size Efficiency
CNC MACHINE
CNC MACHINE
CNC MACHINE
Sanding Machine 1
Sanding Machine 2
Sanding Machine 2
54
No Faclity Name + Picture Facility Size Efficiency
55
No Faclity Name + Picture Facility Size Efficiency
Assembly Table
Packaging Area
So from the routing sheet calculation above, there are several input of the column
which is operation number, macine name, process time, theoritical machine capacity, machine
efficiency, actual machine capacity unit/day, deffect, amount requested, and prepared, and the
machine needs. The theoritycal machine capacity is got from work hour / process time . The
56
product requested is 34 and the total product prepared is 35. There is a difference between the
product requested and the product prepared to face if there will be fluctuation demand.
Theoritical Machine
Operation Process Time Actual Machine Total Actual Total Requested Total Prepared
No Faciliy Name: Machine Capacity Efficiency Defect (%) Machine Needed
Number (menit) Capacity (unit/day) Machine (unit/day) (unit/day)
(Unit/Day) (%) Theoretical (Unit) Actual (Unit) Lot Size Work Hour
A B C D E F G H I J K L M
Balsa Wood for Wall Shape
0-1 CNC Machine 1 12 160 100,0% 160 0,00% 0 151,0 151,0 0,94375 1 1 4
1 0-2 Sanding Machine 1 2 960 100% 960 0% 0 151,0 151,0 0,157291667 1 1 4
0-3 Spray Paint Table a1 2 960 97% 931,2 3% 0 146,0 151,0 0,162156357 1 1 4
0-4 Spray Paint Table b1 2 960 99% 950,4 1% 0 144,0 146,0 0,153619529 1 1 4
Balsa Wood for Roof Shape
O-5 CNC Machine 2 12 80 100,0% 80 0,0% 0 73,0 73,0 0,9125 1 1 2
2 O-6 Sanding Machine 2 2 480 100% 480 0% 0 76,0 76,0 0,1583 1 1 2
O-7 Spray Paint Table a2 2 480 97% 465,6 3% 0 73,0 76,0 0,1632 1 1 2
O-8 Spray Paint Table b2 2 480 99% 475,2 1% 0 72,0 73,0 0,1536 1 1 2
3 Balsa Wood for Shape Pieces 8
0-9 CNC Machine 1 12 160 100,0% 160 0,0% 0 151,0 151,0 0,9438 1 1 4
0-10 Sanding Machine 2 2 960 100% 960 0% 0 151,0 151,0 0,1573 1 1 4
0-11 Spray Paint Table a3 2 960 97% 931 3% 0 146,0 151,0 0,1622 1 1 4
0-12 Spray Paint Table b3 2 960 99% 950 1% 0 144,0 146,0 0,1536 1 1 4
Half Finish Good
4
0-13, I-1 Assembly Table 3 160 99% 158,4 1% 0 35,0 36,0 0,227272727 1 1 1
Finish Good
5
0-14 Packaging Area 5 96 99% 95,04 1% 0 34 35,0 0,368265993 1 1 1
Total 14
So from the routing sheet calculation above, there are several input of the
column which is operation number, macine name, process time, theoritical machine
capacity, machine efficiency, actual machine capacity unit/day, deffect, amount
requested, and prepared, and the machine needs. The theoritycal machine capacity is
got from work hour / process time . The actual machine capacity is got from the
calculation of theoritycal machine capacity multiplied by machine efficiency. The
requested unit/day is got from demand devided by workdays in a year. The amount
prepared added by the amount requested devided by the actual machine capacity.
Then the total actual machine needed is 14
57
III.3 Unit Load Calculation and Determination of Material System
Spesifikasi MH Equipment
In this case, the writer use industrial wagon with dimension 900 x 600 x 510 mm
III.3.2 Analysis of determining Material Handling Equipment
b. Input the dimension from each product part to the determine MHE table
Table 16 Dimension of Material Each Process
From
To Panjang (mm) Lebar (mm) Tinggi (mm)
REC-A 150 150 250
REC-A2 150 150 250
REC-A3 150 150 250
A-B 120 120 200
B-C 120 120 200
C-D 120 120 200
58
From
To Panjang (mm) Lebar (mm) Tinggi (mm)
D-E 100 30 200
A2-B2 130 30 160
B2-C2 120 20 150
C2-D2 120 20 150
D2-E2 100 30 100
A3-B3 60 30 60
B3-C3 50 20 50
C3-D3 50 20 50
D3-E3 50 20 50
E-F 60 30 200
F-SHI 55 25 200
59
60
Picture 48 Unit Load
The selected dimension combination signifiesabout the maximum stacking load in the MHE
that could be transported. Then, the selcted stacking will be used in detemine the MHE
needed in each process.
61
III.4 Calculation of Allowance and Determinating Space Requirement for Plant Facility
Layout Requirements.
From the table above the writers make some assumption about the
allowance operator is 1. It is because the standard oparotor reach in the
company is about 1 meters. That is why the writer make a assumption to use
allowance of operator is 1.
62
b) Analysis of Removal Material
Spesifikasi MH Equipment
From the picture above, the writer get the allowance of material removal
with formula :
Which use the dimension in meters. So, the writer get the result of
material removal allowance is 1. How about the material removal
allowance in each facility ? it will be explain in Table of Recapitulation
below
c) Analysis of Allowance Material
Berat Part
Part
(gr)
64
Berat Part
Part
(gr)
Half Finished Goods 3 500
Finished Goods 1000
Finished Goods 250
REC 250
SHI 250
https://indonesian.alibaba.com/product-detail/new-arrival-heavy-density-
balsa-wood-strip-60233012107.html
In each workstation teh raw material will be proceed based on the right size
and ofcourse it will change the weight. For weight in each part can be seen or
check in picture below:
Allowance (m)
Initial Nama Fasilitas Allowance
Allowance Allowance
Pemindahan
Operator Material
Material
A CNC Machine 1 1 2 4
B Granding Table 1 1 2 4
C Spray Paint Table a1 1 2 4
D Spray Paint Table b1 1 2 3
E CNC Machine 2 1 2 3
F Granding Table 1 1 2 3
A2 Spray Paint Table a2 1 2 3
B2 Spray Paint Table b2 1 2 3
C2 CNC Machine 3 1 2 1
D2 Granding Table 3 1 2 1
E2 Spray Paint Table a3 1 2 1
F2 Spray Paint Table b3 1 2 1
A3 Assembly Table 1 2 3
B3 Packaging Area 0 0 0
REC RECEIVING 0 0 0
SHI SHIPPING 0 0 0
65
Picture 53 Recapitulation of Allowance
In here, the writer will find the Total Production each day adn Total
weight for each facility. To find Total Production each day, the writer use
data form roting sheet about the prepared demand each day. Then to
calculate Total Weght by multiple between The weight of part and Total
Production each day
Dimensi
Panjang (m) Lebar (m)
Jumlah
Initial Fasilitas Allowance Allowance Luas Total
mesin Panjang Allowance Allowance Total Lebar Allowance Allowance Total
Pemindahan Pemindahan
Mesin Operator Material Panjang Mesin Operator Material Lebar
Material Material
A CNC Machine 1 1 3 1 2 4 10 1,7 1 2 4 9 90
B Granding Table 1 1 2,8 1 2 4 10 1,7 1 2 4 9 90
C Spray Paint Table a1 1 2 1 2 4 9 0,5 1 2 4 8 72
D Spray Paint Table b1 1 2 1 2 3 8 0,5 1 2 3 7 56
A1 CNC Machine 2 1 3 1 2 3 9 1,7 1 2 3 8 72
B2 Granding Table 1 1 2,8 1 2 3 9 1,7 1 2 3 8 72
C2 Spray Paint Table a2 1 2 1 2 3 8 0,5 1 2 3 7 56
D2 Spray Paint Table b2 1 2 1 2 3 8 0,5 1 2 3 7 56
A3 CNC Machine 3 1 3 1 2 1 7 1,7 1 2 1 6 42
B3 Granding Table 3 1 2,8 1 2 1 7 1,7 1 2 1 6 42
C3 Spray Paint Table a3 1 2 1 2 1 6 0,5 1 2 1 5 30
D3 Spray Paint Table b3 1 2 1 2 1 6 0,5 1 2 1 5 30
E Assembly Table 1 5 1 2 3 11 5 1 2 3 11 121
F Packaging Area 1 6 0 0 0 6 6 0 0 0 6 36
REC RECEIVING 1 8 0 0 0 8 5 0 0 0 5 40
SHI SHIPPING 1 8 0 0 0 8 5 0 0 0 5 40
Total Area 945
Form the picture above, there are many inputs such as Total Machine
used, The dimension of the facilitie (Length, and Width). The data can be
find in the previous modul. After input the data requirements, the writer
calculate the Total Surface Area by formula:
What is the function of finding the Total Surface Area ? ofcourse we can
determine the minimum area that we needed to create initial layout of our
production area that will create. In this case the Total Surface area needed is
847 m2 .
66
The writer decide to provide area 40 x 40 m2 to meet the minimum
surface area that have calculated before.
b) Initial Layout Design
Initial Fasilitas Jumlah mesin Total Panjang Total Lebar Luas Total
A CNC Machine 1 1 10 9 90
B Granding Table 1 1 10 9 90
C Spray Paint Table a1 1 9 8 72
D Spray Paint Table b1 1 8 7 56
A2 CNC Machine 2 1 9 8 72
B2 Granding Table 1 1 9 8 72
C2 Spray Paint Table a2 1 8 7 56
D2 Spray Paint Table b2 1 8 7 56
A3 CNC Machine 3 1 7 6 42
B3 Granding Table 3 1 7 6 42
C3 Spray Paint Table a3 1 6 5 30
D3 Spray Paint Table b3 1 6 5 30
E Assembly Table 1 11 11 121
F Packaging Area 1 6 6 36
REC RECEIVING 1 8 5 40
SHI SHIPPING 1 8 5 40
TOTAL AREA 945
First step to create initial lay-out is by recap the total area for each
facility. Second, determine the flow of product by colouring the diferent
colour for arrows in each process.
Third create the initial layout based on the requirement.
67
m2 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40
1
2
3 REC
A3 B3
4
5
6
7 C3
8 A
9
10 A2
11 B2
12
13
14
15 C2
D3
16
17 B
18
19 D2 ASSEMBLY
20
21
22 C
23 D
24
25
26
27
28
29
30 PACKAGING
31
32 SHI
33
34
35
36
Initial Fasilitas X Y
Total Berat
From Jarak (dari
Nama Part Material
to from to)
(Kg/hari)
Rectilinier Formula:
Where:
70
Table 22 Material Handling Cost Calculation
Jarak
Pergerakan
Material Tempuh Material
Material Biaya
Handling Material Handling Cost
Handling
Handling
Rp
HAND TRUCK REC-A 6 450 Rp 5.402
Rp
HAND TRUCK REC-A2 15 450 Rp 13.505
Rp
HAND TRUCK REC-A3 41,5 450 Rp 37.364
Rp
HAND TRUCK A-B 9 450 Rp 8.103
Rp
HAND TRUCK B-C 17 450 Rp 15.306
Rp
HAND TRUCK C-D 9 450 Rp 8.103
Rp
HAND TRUCK D-E 13 450 Rp 11.704
Rp
HAND TRUCK A2-B2 8,5 450 Rp 7.653
Rp
HAND TRUCK B2-C2 15,5 450 Rp 13.955
Rp
HAND TRUCK C2-D2 9,5 450 Rp 8.553
Rp
HAND TRUCK D2-E2 14,5 450 Rp 13.055
Rp
HAND TRUCK A3-B3 33 450 Rp 29.711
Rp
HAND TRUCK B3-C3 6,5 450 Rp 5.852
Rp
HAND TRUCK C3-D3 6 450 Rp 5.402
Rp
HAND TRUCK D3-E3 12 450 Rp 10.804
Rp
HAND TRUCK E-F 34,5 450 Rp 31.062
Rp
HAND TRUCK F-SHI 33,5 450 Rp 30.162
TOTAL Rp 255.698
From the picture above, the writer get the result of total material handling cost. First, the
writer should be calculate the MHEs cost per meters using the table of MHE calculation
above. Then, input the MHEs Distance. Then, the MHE cost will be calculted by formula:
71
The frequency table is calculted based on the selected unit load. Which mean in this case the
selected unit load is 17.
Table 23 Frequency of Material Removing
From to Frekuensi
REC-A 2
REC-A2 2
REC-A3 2
A-B 2
B-C 2
C-D 2
D-E 2
E-F 2
F-G 2
A2-B2 2
B2-C2 2
C2-D2 2
D2-E2 2
E2-F2 2
F2-G 2
A3-B3 2
B3-C3 2
C3-D3 2
D3-E3 2
E3-F3 2
F3-G 2
G-H 2
H-SHI 2
After that the writers can calculate the total MHE cost. In this case the Total MHE cost is Rp
255.698 ,-
72
III.4.5 Analysis of Process Flow Using FTC
TO REC
A B C D A2 B2 C2 D2 A3 B3 C3 D3 E F SHI Total
FROM
REC Rp 5.402 Rp 13.505 Rp 37.364 Rp 56.271
A Rp 8.103 Rp 8.103
B Rp 15.306 Rp 15.306
C Rp 8.103 Rp 8.103
D Rp 11.704 Rp 11.704
A2 Rp 7.653 Rp 7.653
B2 Rp 13.955 Rp 13.955
C2 Rp 8.553 Rp 8.553
D2 Rp 13.055 Rp 13.055
A3 Rp 29.711 Rp 29.711
B3 Rp 5.852 Rp 5.852
C3 Rp 5.402 Rp 5.402
D3 Rp 10.804 Rp 10.804
E Rp 31.062 Rp 31.062
F Rp 30.162 Rp 30.162
SHI Rp -
TOTAL Rp 5.402 Rp 8.103 Rp 15.306 Rp 8.103 Rp 13.505 Rp 7.653 Rp 13.955 Rp 8.553 Rp 37.364 Rp 29.711 Rp 5.852 Rp 5.402 Rp 35.564 Rp 31.062 Rp 30.162 Rp255.698
73
b) Analysis of FTC Inflow and Outflow Calculation
FTC BIAYA INFLOW
TO REC
A B C D A2 B2 C2 D2 A3 B3 C3 D3 E F SHI Total
FROM
REC Rp 1 Rp 1 Rp 1 Rp 3
A Rp 1 Rp 1
B Rp 1 Rp 1
C Rp 1 Rp 1
D Rp 0 Rp 0
A2 Rp 1 Rp 1
B2 Rp 1 Rp 1
C2 Rp 1 Rp 1
D2 Rp 0 Rp 0
A3 Rp 1 Rp 1
B3 Rp 1 Rp 1
C3 Rp 1 Rp 1
D3 Rp 0 Rp 0
E Rp 1 Rp 1
F Rp 1 Rp 1
SHI Rp -
TOTAL Rp 1 Rp 1 Rp 1 Rp 1 Rp 1 Rp 1 Rp 1 Rp 1 Rp 1 Rp 1 Rp 1 Rp 1 Rp 1 Rp 1 Rp 1 Rp15
74
III.5 Determination The Relation Between Activity and Determining
Production Floor of Department Layout
1 A CNC Machine 1
2 B Granding Table 1
3 C Spray Paint Table a1
4 D Spray Paint Table b1
5 A1 CNC Machine 2
6 B2 Granding Table 1
7 C2 Spray Paint Table a2
8 D2 Spray Paint Table b2
9 A3 CNC Machine 3
10 B3 Granding Table 3
11 C3 Spray Paint Table a3
12 D3 Spray Paint Table b3
13 E Assembly Table
14 F Packaging Area
15 REC RECEIVING
16 SHI SHIPPING
75
Relevance Motive Table
No Alasan
1 Urutan Aliran Kerja
2 Memakai Peralatan yang sama
3 Memudahkan pemindahan barang
4 Menggunakan raw material yang sama
5 Pentingnya berhubungan
6 Kemudahan Pengawasan
7 Noise, Dust, Vibration, Odor
Based on table above, those are some reason for allocating the
workstation or area. The function of the reason is to determinate
the relation between the facility.
A 5%
E 10%
I 15%
O 20%
X 5%
U Sisa
Kombinasi 120 A 6
E 12
I 18
O 24
U 54
X 6
Picture 64 Relevance Degree Activities
76
U for white it means is no important, the last one is X for brown
color means it is not expected for close each departments. For this
case, we need to combine the facilities, it use for we can
determine all of departments if they were close. So because we
have 13 departments, using excel formula (=COMBIN) we get the
combinations as much as 120 times. Then each symbol has
different percentage A for 5%, E for 10%, I for 15%, O for 20%,
X for 5%, and U is remain of total minus by all symbols.
77
position, orange E its mean that the activity between department
it very important to neighboring, for the green I its mean that the
activity between department it important to neighboring, for the
blue O its mean there is no line between department, for the
white U its mean there is no important thing in each department,
for the brown X its mean the department is unwanted to be side
by side position.
Table 25 Grade
Grade Value
A 1
E 0,8
I 0,6
O 0,4
U 0,2
78
Grade Value
X 0,0
Normalisasi
Dari/Ke 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Rec A B C D A2 B2 C2 D2 A3 B3 C3 D3 E F SHI
1 Rec 1 0,6 0,2 0,2 1 0,6 0,0 0,2 1 0,6 0,0 0,2 0,2 0,2 0,0
2 A 1 ##### 0,6 0,4 0,4 0,8 0,4 0,6 0,2 0,8 0,4 0,2 0,2 0,4 0,2 0,0
3 B 0,6 0,6 0,6 0,4 0,2 0,8 0,4 0,2 0,2 0,8 0,4 0,2 0,2 0,2 0,2
4 C 0,2 0,4 0,6 0,6 0,2 0,4 0,8 0,2 0,2 0,6 0,8 0,4 0,2 0,2 0,2
5 D 0,2 0,4 0,4 0,6 0,2 0,2 0,2 0,8 0,2 0,2 0,2 0,8 0,6 0,2 0,2
6 A2 1 0,8 0,2 0,2 0,2 0,6 0,4 0,4 0,8 0,4 0,2 0,2 0,4 0,2 0,0
7 B2 0,6 0,4 0,8 0,4 0,2 0,6 0,6 0,4 0,2 0,8 0,4 0,2 0,2 0,2 0,2
8 C2 0,0 0,6 0,4 0,8 0,2 0,4 0,6 0,6 0,2 0,2 0,8 0,4 0,2 0,2 0,2
9 D2 0,2 0,2 0,2 0,2 0,8 0,4 0,4 0,6 0,2 0,2 0,4 0,8 0,6 0,2 0,2
10 A3 1 0,8 0,2 0,2 0,2 0,8 0,2 0,2 0,2 0,6 0,4 0,4 0,4 0,2 0,2
11 B3 0,6 0,4 0,8 0,6 0,2 0,4 0,8 0,2 0,2 0,6 0,6 0,4 0,2 0,2 0,0
12 C3 0,0 0,2 0,4 0,8 0,2 0,2 0,4 0,8 0,4 0,4 0,6 0,6 0,6 0,6 0,2
13 D3 0,2 0,2 0,2 0,4 0,8 0,2 0,2 0,4 0,8 0,4 0,4 0,6 1 0,2 0,4
14 E 0,2 0,4 0,2 0,2 0,6 0,4 0,2 0,2 0,6 0,4 0,2 0,6 1 1 0,4
15 F 0,2 0,2 0,2 0,2 0,2 0,2 0,2 0,2 0,2 0,2 0,2 0,6 0,2 1 1
16 SHI 0,0 0,0 0,2 0,2 0,2 0,0 0,2 0,2 0,2 0,2 0,0 0,2 0,4 0,4 1
Picture 66 Normalization
79
REC A B C D A2 B2 C2 D2 A3 B3 C3 D3 E F SHI
Dari/Ke No TOTAL
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
REC 1 900,3433164 1588,84115 1132,24993 0 3621,43
A 2 540,20599 540,206
B 3 540,20599 540,206
C 4 540,20599 540,206
D 5 540,20599 540,206
A1 6 540,20599 540,206
B2 7 540,20599 540,206
C2 8 540,20599 540,206
D2 9 540,20599 540,206
A3 10 2742,58426 2742,58
B3 11 540,20599 540,206
C3 12 540,20599 540,206
D3 13 900,343316 900,343
E 14 900,343316 900,343
F 15 900,3433164 900,343
SHI 16 0
TOTAL 0 900,3433164 540,20599 540,20599 540,20599 1588,84115 540,20599 540,20599 540,20599 1132,24993 2742,58426 540,20599 540,20599 1980,7553 900,343316 900,3433164 14467,1
Picture 68 Worksheet
80
Based on the table above, Activity relationship chart
(ARC) is useful for planning analysis of the relationship
between the activity of each - each department. As a result the
data obtained will then be used for the determination of the
location of each - each department, namely through the Area
Allocation Diagram (AAD). AAD is to give an explanation of
the relationship between the activities of the department with
other departments, the first data obtained from ARC entered into
a worksheet (work sheet). So the next for output for worksheet
is AAD, is one of conventional technique
81
according to the degree of closeness (symbol A,I,E,O,U,X). The red one
is A, it mus absolutely close each other department, and for Green and
Orange is only follow after the Red one is done. In this AAD, the Orange
allocated by diagonal position. Receiving and Shipping is fixed location
because both of them are main department to run the production line, so
we can not move it temporary it must permanent. We only moving the
other departments according worksheet.
REC
A3 B3
A
C3
A2
B2
D3
B
C2
D2
ASSEMBLY
C
D
PACKAGING
SHI
By using AAD, the writers vreate new initial layout for PT Z. SO, the initial
layout is create based on AAD
82
b. Mushola
c. Rest Room 1
d. Rest Room 2
e. Toilet Man
f. Toilet Woman
g. Canteen
h. Production Floor
83
III.5.2.4 Analysis AAD Production Floor +Added Facility
84
III.6 Designing Plant Facility Layout
85
Picture 77 Final Layout 2 Department
86
Picture 78Final Layout 3 Department
87
Picture 79 Final Layout 2 then 3 Department
88
Picture 80 Final Layout 3 then 2 Department
89
BAB IV KESIMPULAN DAN SARAN
Pada bagian ini merupakan kesimpulan dari Final tubes. Kesimpulan ini harus
dapat menjawab seluruh rumusan masalah yang telah ditetapkan sebelumnya(dari
modul 1-6). Tambahan pada bagian ini adalah saran yang diberikan untuk pabrik
yang akan dibangun.
3. The routing sheet of the GoGeom product has been made above ( The writter
attach in excel ) there is no far difference between the theoretical number of
machines and the number actual machine needed. Why the writers use 0 value
in the column machine that already exist because PT Z since be start up.
90
Routing sheet use machine efficiency, defect, and work hour as a input to
process.
4. The total machine needed by the company (Happiness Firm) is 14.
5. The type and dimension of material handling used is industrial wagon with
dimension 700 x 600x 650 mm.
Spesifikasi MH Equipment
91
Allowance (m)
Initial Nama Fasilitas Allowance
Allowance Allowance
Pemindahan
Operator Material
Material
A CNC Machine 1 1 2 4
B Granding Table 1 1 2 4
C Spray Paint Table a1 1 2 4
D Spray Paint Table b1 1 2 3
E CNC Machine 2 1 2 3
F Granding Table 1 1 2 3
A2 Spray Paint Table a2 1 2 3
B2 Spray Paint Table b2 1 2 3
C2 CNC Machine 3 1 2 1
D2 Granding Table 3 1 2 1
E2 Spray Paint Table a3 1 2 1
F2 Spray Paint Table b3 1 2 1
A3 Assembly Table 1 2 3
B3 Packaging Area 0 0 0
REC RECEIVING 0 0 0
SHI SHIPPING 0 0 0
92
10. The total material handling cost is:
93
a. Flow To Chart
FTC techniques, we will know each flow material movement,
Analyzing the material displacement, Planning flow patterns,
Determining the location of activities, Measurement of the efficiency
of the flow pattern, Shows the dependence of the activity with other
activities, and Shows the quantitative relationship between the
activities and movements. The key point we consider and determine
the minimize cost of material handling.
TO REC
A B C D A2 B2 C2 D2 A3 B3 C3 D3 E F SHI Total
FROM
REC Rp 5.402 Rp 13.505 Rp 37.364 Rp 56.271
A Rp 8.103 Rp 8.103
B Rp 15.306 Rp 15.306
C Rp 8.103 Rp 8.103
D Rp 11.704 Rp 11.704
A2 Rp 7.653 Rp 7.653
B2 Rp 13.955 Rp 13.955
C2 Rp 8.553 Rp 8.553
D2 Rp 13.055 Rp 13.055
A3 Rp 29.711 Rp 29.711
B3 Rp 5.852 Rp 5.852
C3 Rp 5.402 Rp 5.402
D3 Rp 10.804 Rp 10.804
E Rp 31.062 Rp 31.062
F Rp 30.162 Rp 30.162
SHI Rp -
TOTAL Rp 5.402 Rp 8.103 Rp 15.306 Rp 8.103 Rp 13.505 Rp 7.653 Rp 13.955 Rp 8.553 Rp 37.364 Rp 29.711 Rp 5.852 Rp 5.402 Rp 35.564 Rp 31.062 Rp 30.162 Rp255.698
94
FTC BIAYA OUTFLOW
TO REC
A B C D A1 B2 C2 D2 A3 B3 C3 D3 E F SHI Total
FROM
REC Rp 0 Rp 0 Rp 1 Rp 1
A Rp 1 Rp 1
B Rp 1 Rp 1
C Rp 1 Rp 1
D Rp 1 Rp 1
A1 Rp 1 Rp 1
B2 Rp 1 Rp 1
C2 Rp 1 Rp 1
D2 Rp 1 Rp 1
A3 Rp 1 Rp 1
B3 Rp 1 Rp 1
C3 Rp 1 Rp 1
D3 Rp 1 Rp 1
E Rp 1 Rp 1
F Rp 1 Rp 1
SHI Rp -
TOTAL Rp 0 Rp 1 Rp 1 Rp 1 Rp 0 Rp 1 Rp 1 Rp 1 Rp 1 Rp 1 Rp 1 Rp 1 Rp 3 Rp 1 Rp 1 Rp15
12. By doing this progress big assignment, we could understand that Activity
Relationship Chart is the activity or activities between each - each section
that describes important whether or not the closeness of the room to
determine the location of each department in accordance with the linkage
between the activities and the flow of material, fist we have to analyze all
the facilities that exist on the factory, second determine the relevance
motive for each department. This relevance motive could be the reason to
approach it or disassociate it. Third, finding out the value of A, E, I, O, U,
X with the combinantion of the partners for all department. Fourth,
analyze the relationship between each departments according to relevance
motive. Fifth, sort the ARC table from Z to A, or from biggest to smallest.
95
BAB V DAFTAR PUSTAKA
Pada bagian ini berisi daftar pustaka atau referensi yang dipakai (dipilah jangan
sampai ada tulisan referensi yang double). Penulisan referensi harap diperhatikan.
96