You are on page 1of 37

INTERNAL AUDIT CHECKLIST

Wanfeng Aluminum Wheel


India

Department : HOT SHOP AUDIT REF.: IQA Date :


Time : NC

Score
Auditee : Auditor : Shift : Remarks

CL.NO. Checkpoints Confirmation Observations Major/Minor/OI


Document

7.5.1 Is there a documented procedure for HOT SHOP Departmental


Department Procedure

Are the Quality objective deployed in the HOT SHOP


6.2.1/6.2.2 Department Departmental
i.e. Same Objective as determined along with the quality objectives.
policy or supporting departmental objectives.

6.1.2.1 Is there a formal process available for risk analysis? Risk Analysis

6.1.2.1 Are there any risks and opportunities identified? Any


Risk Analysis
Mitigation actions for risks identified?

6.1.2 Status of Mitigation actions implementation and


Risk Analysis
effectiveness?

1.Is there job setup perform such as Initial run of a Job,


8.5.1.3 material change over or job change required a new setup?
2.Is there maintained documented information for setup Setup Approval
personal? request & Setup
Approval Report

8.5.1.4 is there Verification after machine shut down?

Are the process inspection & testing is being carried out as


8.6.1 per defined frequency in PQCS / OPS/Inspections Inspection Report
standards/WI

8.7.1.1 Is there any concession approved from designated


Deviation Record
authority?

1.Is there suspected status is classified & controlled as


8.7.1.3/8.7.1.4 non-confirming product Rework Instruction/
2.Is there documented information available for verification Rework Record
of compliances to original specification

8.5.2/8.5.2.1
Is the material and parts flow secured against mix-ups /
Traceability System
exchanges by mistake and traceability guaranteed.

Do you have trace ability system - batch codification if heat


8.5.2 treatment is done, production month/year labelling or Traceability System
marking for final product (any process)

Are the Production Equipment ( Machine / Jig / Fixture / Master List,


8.5.1.6 Die ) that effect quality , and identify critical spare needed Critical Spare Part
as per replacement for expendable supplies List

8.5.4
Are tools, equipment and inspection, measuring and test Equipment
equipment stored correctly. Handling

Abnormal conditions / unexpected change ( Contingency


Plan )
6.1.2.3 Abnormal Conditions / Unexpected change to satisfy Contingency Plan
customer requirements in event of an emergency such as
labour shortage ,utility intruptions,key equipment failure

6.1.2.3 Is Contingency Plan tested for suitability and reviewed


Contingency Plan
annualy with CFT including top management?

Are the products / components appropriately stored and


8.5.4
Material Handling
are the transport means / packaging equipment tuned to
System Product
the special properties of the product / components.

Is there special charecteristics define in all operational PFD/CP/PFMEA/O


8.3.3.3 document such as ( PFD /PFMEA/ Control Plan/Work PS/Inspections
Instructions ) are specified by special symbol standards

Are the appearance item identify and displayed at the


required location.
Control of Limit Sample includes following information
1.Date of production of the limit sample
master List of Limit
8.6.3
2.Control No.
Sample/Identificatio
3.Inspection Items ( Scratch, Roughness, unevenness
n Tag
etc. )
4.Applicable Part Name & Part No.
Effective Period
6.Significant field.

master List of Limit


8.6.3 Are Limit sample retain considering damage,deteorition
Sample/Identificatio
etc.
n Tag

Operator Instructions & Standards


1. Is the work instruction language understood by
8.5.1.2 responsible person Work Instructions
2. Is the accessible for use at the designated work area.
3. Is the legible work instructions.

Die
1.) Is there maintenance & repair facilities and personnel? Unloading/Breakdo
8.5.1.6 2). Is there storage of tooling system appropriate? wn Intimation/Tool,
3). Is the Tooling modification & change records available? Die, Fixture Service
4). Is the tool/Die Identification system available? report, Tool History
Card

8.6.3
Lux Level for
Required lighting facilities provided for visual inspection
Inspection

10.2.4 Poke Yoke


Audit of poke-yoke whether it is in working condition
Verification

8.2.3
Is the Process Qualification made for process Validation/
PQS/SPC
Process Capability carried out for special characteristics

1). Is there change point Identification requirement


available?
Technical
1). Is there verification & validation activity as per
8.5.6.1
Noticem,Validation
plan/customer requirement?
plan & Record,
2.)Is there validate change before Implementation?
Change point
3.) Is there evidences & retention record available for
verification & validation?

8.7.1.7
Is there Non-Confirming Product disposition system
Rejection Record
available/followed?

Control of Record
7.5.3/7.5.3.1 Is the record have following requirement Records
identification,storage,Protection,retrivel,retention and
disposal of records
Records Retention
7.5.3.2 Is the statutory ,regulatory and customer requirement Retention system
follow

7.2.2/7.2.1 Is the competence defined for the personnel performing


Skill Matrix
Production process & Revaluate as defined interval
Corrective Action
Is the Reviewing the nonconformities ( Including Customer
10.2 Customer Complaints ) Complaints/
Verification of Nonconformity Implementation C'Measure
Is the effectiveness of Corrective action review. Implementation

Score Guide lines :


MS/WFIM 09 FO 12, ISSUE 01 July 2017 Score Achieve 0 0 Major NC
1 Minor NC
Total Score 78 2 Opportunity for Improvement ( OI if Trend is improving )
3 Full fill the system Requirements
Score % 0.00

Auditee Signature : Auditor Signature :


INTERNAL AUDIT CHECKLIST
Wanfeng Aluminum Wheel
India

Department : CNC SHOP AUDIT REF.: IQA Date :


Time : NC

Score
Auditee : Auditor : Shift : Remarks

CL.NO. Checkpoints Confirmation Observations Major/Minor/OI


Document

7.5.1 Is there a documented procedure for CNC SHOP Departmental


Department Procedure

Are the Quality objective deployed in the CNC SHOP


6.2.1/6.2.2 Department Departmental
i.e. Same Objective as determined along with the quality objectives.
policy or supporting departmental objectives.

6.1.2.1 Is there a formal process available for risk analysis? Risk Analysis

6.1.2.1 Are there any risks and opportunities identified? Any


Risk Analysis
Mitigation actions for risks identified?

6.1.2 Status of Mitigation actions implementation and


Risk Analysis
effectiveness?

1.Is there job setup perform such as Initial run of a Job,


8.5.1.3 material change over or job change required a new setup?
2.Is there maintained documented information for setup Setup Approval
personal? request & Setup
Approval Report

8.5.1.4 is there Verification after machine shut down?

Are the process inspection & testing is being carried out as


8.6.1 per defined frequency in PQCS / OPS/Inspections Inspection Report
standards/WI

8.7.1.1
Is there any concession approved from designated
Deviation Record
authority?

1.Is there suspected status is classified & controlled as


8.7.1.3/8.7.1.4
non-confirming product Rework Instruction/
2.Is there documented information available for verification Rework Record
of compliances to original specification

8.5.2/8.5.2.1
Is the material and parts flow secured against mix-ups / Traceability
exchanges by mistake and traceability guaranteed. System

Do you have trace ability system - batch codification if heat


8.5.2
Traceability
treatment is done, production month/year labelling or
System
marking for final product (any process)

Are the Production Equipment ( Machine / Jig / Fixture / Master List,


8.5.1.6 Die ) that effect quality , and identify critical spare needed Critical Spare Part
as per replacement for expendable supplies List

8.5.4
Are tools, equipment and inspection, measuring and test Equipment
equipment stored correctly. Handling

Abnormal conditions / unexpected change ( Contingency


Plan )
6.1.2.3 Abnormal Conditions / Unexpected change to satisfy Contingency Plan
customer requirements in event of an emergency such as
labour shortage ,utility intruptions,key equipment failure

6.1.2.3 Is Contingency Plan tested for suitability and reviewed


Contingency Plan
annualy with CFT including top management?

Are the products / components appropriately stored and


8.5.4
Material Handling
are the transport means / packaging equipment tuned to
System Product
the special properties of the product / components.

Is there special charecteristics define in all operational PFD/CP/PFMEA/O


8.3.3.3 document such as ( PFD /PFMEA/ Control Plan/Work PS/Inspections
Instructions ) are specified by special symbol standards

Are the appearance item identify and displayed at the


required location.
Control of Limit Sample includes following information
1.Date of production of the limit sample
master List of Limit
8.6.3
2.Control No.
Sample/Identificati
3.Inspection Items ( Scratch, Roughness, unevenness
on Tag
etc. )
4.Applicable Part Name & Part No.
Effective Period
6.Significant field.

master List of Limit


8.6.3
Are Limit sample retain considering damage,deteorition
Sample/Identificati
etc.
on Tag

Operator Instructions & Standards


1. Is the work instruction language understood by
8.5.1.2 responsible person Work Instructions
2. Is the accessible for use at the designated work area.
3. Is the legible work instructions.

Die
1.) Is there maintenance & repair facilities and personnel? Unloading/Breakdo
8.5.1.6
2). Is there storage of tooling system appropriate? wn Intimation/Tool,
3). Is the Tooling modification & change records available? Die, Fixture
4). Is the tool/Die Identification system available? Service report, Tool
History Card

8.6.3
Lux Level for
Required lighting facilities provided for visual inspection
Inspection

10.2.4 Poke Yoke


Audit of poke-yoke whether it is in working condition
Verification

8.2.3 Is the Process Qualification made for process Validation/


PQS/SPC
Process Capability carried out for special characteristics

8.7.1.7 Is there Non-Confirming Product disposition system


Rejection Record
available/followed?

1.Is there any special characteristics identified for process


9.1.1.2/9.1.1.3
capability as per PFMEA/Control Plan? Processs Capabilty
2. Is there process capability carried out as per plan & Plan & Record
Analysed

1). Is there change point Identification requirement


available?
Technical
1). Is there verification & validation activity as per
8.5.6.1
Noticem,Validation
plan/customer requirement?
plan & Record,
2.)Is there validate change before Implementation?
Change point
3.) Is there evidences & retention record available for
verification & validation?

Control of Record
7.5.3/7.5.3.1 Is the record have following requirement
Records
identification,storage,Protection,retrivel,retention and
disposal of records
Records Retention
7.5.3.2 Is the statutory ,regulatory and customer requirement Retention system
follow

7.2.2/7.2.1
Is the competence defined for the personnel performing
Skill Matrix
Production process & Revaluate as defined interval
Corrective Action
Is the Reviewing the nonconformities ( Including Customer
10.2 Customer Complaints ) Complaints/
Verification of Nonconformity Implementation C'Measure
Is the effectiveness of Corrective action review. Implementation
MS/WFIM 09 FO
12, ISSUE 01 July Score Achieve 0 Score Guide lines :
2017 0 Major NC
Total Score 78 1 Minor NC
2 Opportunity for Improvement ( OI if Trend is improving )
3 Full fill the system Requirements
Score % 0.00

Auditee Signature : Auditor Signature :


INTERNAL AUDIT CHECKLIST
Wanfeng Aluminum Wheel
India

Department : PAINT SHOP AUDIT REF.: IQA Date :


Time : NC

Score
Auditee : Auditor : Shift : Remarks

CL.NO. Checkpoints Confirmation Observations Major/Minor/OI


Document

7.5.1 Is there a documented procedure for PAINT SHOP Departmental


Department Procedure

Are the Quality objective deployed in the PAINT SHOP


6.2.1/6.2.2 Department Departmental
i.e. Same Objective as determined along with the quality objectives.
policy or supporting departmental objectives.

6.1.2.1 Is there a formal process available for risk analysis? Risk Analysis

6.1.2.1 Are there any risks and opportunities identified? Any


Risk Analysis
Mitigation actions for risks identified?

6.1.2 Status of Mitigation actions implementation and


Risk Analysis
effectiveness?

1.Is there job setup perform such as Initial run of a Job,


8.5.1.3 material change over or job change required a new setup?
2.Is there maintained documented information for setup Setup Approval
personal? request & Setup
Approval Report

8.5.1.4 is there Verification after machine shut down?

Are the process inspection & testing is being carried out as


8.6.1 per defined frequency in PQCS / OPS/Inspections Inspection Report
standards/WI

8.7.1.1
Is there any concession approved from designated
Deviation Record
authority?

1.Is there suspected status is classified & controlled as


Rework
8.7.1.3/8.7.1.4
non-confirming product
Instruction/
2.Is there documented information available for verification
Rework Record
of compliances to original specification

8.5.2/8.5.2.1
Is the material and parts flow secured against mix-ups / Traceability
exchanges by mistake and traceability guaranteed. System

Do you have trace ability system - batch codification if heat


8.5.2
Traceability
treatment is done, production month/year labelling or
System
marking for final product (any process)

Are the Production Equipment ( Machine / Jig / Fixture / Master List,


8.5.1.6 Die ) that effect quality , and identify critical spare needed Critical Spare Part
as per replacement for expendable supplies List

8.5.4
Are tools, equipment and inspection, measuring and test Equipment
equipment stored correctly. Handling

Abnormal conditions / unexpected change ( Contingency


Plan )
6.1.2.3 Abnormal Conditions / Unexpected change to satisfy Contingency Plan
customer requirements in event of an emergency such as
labour shortage ,utility intruptions,key equipment failure

6.1.2.3 Is Contingency Plan tested for suitability and reviewed


Contingency Plan
annualy with CFT including top management?

Are the products / components appropriately stored and


8.5.4
Material Handling
are the transport means / packaging equipment tuned to
System Product
the special properties of the product / components.

Is there special charecteristics define in all operational PFD/CP/PFMEA/


8.3.3.3 document such as ( PFD /PFMEA/ Control Plan/Work OPS/Inspections
Instructions ) are specified by special symbol standards

Are the appearance item identify and displayed at the


required location.
Control of Limit Sample includes following information
1.Date of production of the limit sample master List of
8.6.3
2.Control No. Limit
3.Inspection Items ( Scratch, Roughness, unevenness Sample/Identificat
etc. ) ion Tag
4.Applicable Part Name & Part No.
Effective Period
6.Significant field.

master List of
8.6.3
Are Limit sample retain considering damage,deteorition Limit
etc. Sample/Identificat
ion Tag

Operator Instructions & Standards


1. Is the work instruction language understood by
8.5.1.2 responsible person Work Instructions
2. Is the accessible for use at the designated work area.
3. Is the legible work instructions.

Die
Unloading/Breakd
1.) Is there maintenance & repair facilities and personnel?
own
8.5.1.6
2). Is there storage of tooling system appropriate?
Intimation/Tool,
3). Is the Tooling modification & change records available?
Die, Fixture
4). Is the tool/Die Identification system available?
Service report,
Tool History Card

8.6.3
Lux Level for
Required lighting facilities provided for visual inspection
Inspection

10.2.4 Poke Yoke


Audit of poke-yoke whether it is in working condition
Verification

8.2.3 Is the Process Qualification made for process Validation/


PQS/SPC
Process Capability carried out for special characteristics

8.7.1.7 Is there Non-Confirming Product disposition system


Rejection Record
available/followed?

1). Is there change point Identification requirement


available?
Technical
1). Is there verification & validation activity as per
8.5.6.1 Noticem,Validatio
plan/customer requirement?
n plan & Record,
2.)Is there validate change before Implementation?
Change point
3.) Is there evidences & retention record available for
verification & validation?

Control of Record
7.5.3/7.5.3.1 Is the record have following requirement
Records
identification,storage,Protection,retrivel,retention and
disposal of records
Records Retention
7.5.3.2 Is the statutory ,regulatory and customer requirement Retention system
follow

7.2.2/7.2.1
Is the competence defined for the personnel performing
Skill Matrix
Production process & Revaluate as defined interval
Corrective Action
Is the Reviewing the nonconformities ( Including Customer
10.2 Customer Complaints ) Complaints/
Verification of Nonconformity Implementation C'Measure
Is the effectiveness of Corrective action review. Implementation
MS/WFIM 09 FO
12, ISSUE 01 July Score Achieve 0 Score Guide lines :
2017 0 Major NC
Total Score 78 1 Minor NC
2 Opportunity for Improvement ( OI if Trend is improving )
3 Full fill the system Requirements
Score % 0.00

Auditee Signature : Auditor Signature :


INTERNAL AUDIT CHE
Wanfeng Aluminum Wheel
India

Department : Store AUDIT REF.: IQA

Auditee : Auditor :

CL.NO. Checkpoints Confirmation Document

Is there a documented procedure for Store


8.5.4.1 Departmental Procedure
Department?

Are the Quality objective deployed in the Store


Department
6.2.1/6.2.2 Departmental objectives.
i.e. Same Objective as determined along with the
quality policy or supporting departmental objectives.

Is There a documented procedure for material


8.5.4.1 Departmental Procedure
receiving, identification & Storage

Are the raw materials/Parts identified, handled


8.5.4.1 ,packed and stored adequately to preserve the Preservation of product
nonconformity of product?

Are the Quality objective deployed in the HOT SHOP


Department
6.2.1/6.2.2 Departmental objectives.
i.e. Same Objective as determined along with the
quality policy or supporting departmental objectives.

6.1.2.1 Is there a formal process available for risk analysis? Risk Analysis

Are there any risks and opportunities identified? Any


6.1.2.1 Risk Analysis
Mitigation actions for risks identified?

Status of Mitigation actions implementation and


6.1.2 Risk Analysis
effectiveness?

Is the condition of materials/product laying in stocks


8.5.4.1 Daily Stock Assessment
assessed?

8.5.4.1 Is there FIFO system Implemented? FIFO System Followed

Is frequency of such assessment defined and what is


8.5.4.1 Inventory assessment
the basis taken for the same?

Do you take any action to prevent the dust


8.5.4.1 ,rust,moiture& rain etc. for stock & unfinished Action plan/ Work Instructions
products.

Is there Preservation, pacakging & labeling as per


8.5.4.1 Packing condition
requirement of customer?
8.5.1.7 Is system for inventory management defined? Inventory management

is there Min-Max inventory level defined Min-Max inventory level

How are the obsolete products/components/materials


lying in stores dealt? Are these considered and Incoming Rejection Material
8.5.4.1
controlled as per nonconforming materials disposition
( Disposal )?

Control of Record
Is the record have following requirement
7.5.3/7.5.3.1 Records
identification,storage,Protection,retrivel,retention and
disposal of records

Records Retention
7.5.3.2 Is the statutory ,regulatory and customer requirement Retention system
follow

Is the competence defined for the personnel


7.2.2/7.2.1 performing Production process & Re-evaluate as Skill Matrix
defined interval

MS/WFIM 09 FO 12, ISSUE 00 DEC 2015 Score Achieve

Total Score

Score %

Auditee Signature :
NTERNAL AUDIT CHECKLIST

Date :
Time : NC
Score

Shift : Remarks

Observations Major/Minor/OI
0 Score Guide lines :
0 Major NC
1 Minor NC
2 Opportunity for Improvement ( OI if Trend is improving )
3 Full fill the system Requirements
#DIV/0!

Auditor Signature :
INTERNAL AUDIT CHECKLIST
Wanfeng Aluminum Wheel
India

Department : HR AUDIT REF.: IQA Date :


Time : NC

Score
Auditee : Auditor : Shift Remarks

Confirmation Major/Min
CL.NO. Checkpoints Document Observations or/OI

Is there a documented procedure for training / competency Departmental


7.2/7.3/7.5 & motivation of employee
Procedure

Are the Quality objective deployed in the HR Department


6.2.1/6.2.2 i.e. Same Objective as determined along with the quality policy or Departmental
supporting departmental objectives. objectives.

6.1.1 Is there a formal process available for risk analysis? Risk Analysis

Are there any risks and opportunities identified? Any


6.1.2 Mitigation actions for risks identified? Risk Analysis

6.1.2 Status of Mitigation actions implementation and


effectiveness? Risk Analysis

7.2 Do you make the education plan for employee ( by class, Training Plan
speciality , external or contractual, beginners )?

Do you implement the education as planned and keep the


7.2 records?

Is education given to managers and supervisor?


Training Plan &
Records
Do you perform the practical training ( On job ) of Workers.

AUDITEE AUDITOR
Do you record the education history of each individual?

7.2.2 Do you make skill sheet ( Matrix ) of each individual? Skill Matrix

7.2.2 Is there Guidance available for operator training Training Manual

is there any selection criterion available for contractor / Recruitment


7.2.2 agency providing contractual labour Procedure

7.1 Are resource required for the process available Recruitment


Procedure

Abnormal conditions / unexpected change ( Contingency Plan


) Contingency
6.1.2.3 Abnormal Conditions / Unexpected change to satisfy Plan
customer requirements in event of an emergency such as
labour shortage ,utility intruptions,key equipment failure

6.1.2.3 Is Contingency Plan tested for suitability and reviewed Contingency


annualy with CFT including top management? Plan

7.2.1 is there any system to allow operations only by qualified Training


operator Methodology

7.2.1 Is internal training environmental material regulation carried Training Manual


out

Organization
5.3 is there roles & Responsibility defined for each employee. Chart

Are criteria determined to ensure that the HRD Process are Competency
6.2.2.1 effective ( No of Retraining required, gap between
competency required vs Actual ) Matrix

AUDITEE AUDITOR
Departmental
6.2.2.1 Are the method available for above criteria. Procedure
Departmental
6.2.2.1 Are performance indicator measure & analysed. Objective

Corrective &
6.1/ 10.2 Are corrective & Preventive action taken when criteria's are Preventive
not met. Action

Dose the organization have a process for motivating the


7.3.2 employees to achieve the quality objective and continuous Training
improvement ( Kaizen awards , attendance awards etc. ) Procedure

7.4 What are the inputs communicated to various department Communication


and how they are communicated. Matrix

Is there any process established at all levels for promoting


7.3.1 Quality Technological awareness throughout the organization Training
( Quality Circle, Visual aids ) Procedure

Continual
Are the area of continuous improvements identified for Improvement
6.2 improving effectiveness of QMS in HRD Department. Procedures

7.2.1 Is the competence defined for the personnel performing Skill Matrix
Production process & Re-evaluate as defined interval

MS/WFIM 09 FO 12, ISSUE 01 July 2017 Score Achieve Score Guide lines :
0 Major NC
Total Score 1 Minor NC
2 Opportunity for Improvement ( OI if Trend is improving )
3 Full fill the system Requirements
Score %

Auditee Signature : Auditor Signature :

AUDITEE AUDITOR
INTERNAL AUDIT CHECKLIST
Wanfeng Aluminum Wheel India
Department : Quality Control AUDIT REF.: IQA Date :
Time : NC

Score
Auditee : Auditor : Shift : G Remarks
CL.NO. Checkpoints Confirmation Document Observations Major/Minor/OI

8.5.1 Are the process inspection & testing is being carried out as per defined frequency in
Inspection Report
PQCS / OPS/Inspections standards/WI

is there setup approval done as per defined standards Setup approval report

8.7.1 Are rejects, rework, and adjustment parts, as well as internal residues strictly separated
Reject , Rework Record
and identified & Record Maintain

8.7.1 Is the material and parts flow secured against mix-ups / exchanges by mistake and
Identification & Traceability
traceability guaranteed.

8.5.1.6 Are tools, equipment and inspection, measuring and test equipment stored correctly. List of Tools & Equipments

Abnormal conditions / unexpected change ( Contingency Plan )


6.1.2.3 Abnormal Conditions / Unexpected change to satisfy customer requirements in event of Contingency Plan
an emergency such as labor shortage ,utility intruptions,key equipment failure

6.1.1 Is there a formal process available for risk analysis? Risk Analysis

6.1.2 Are there any risks and opportunities identified? Any Mitigation actions for risks identified? Risk Analysis

6.1.2 Status of Mitigation actions implementation and effectiveness? Risk Analysis

8.3.3.3 Are the special characteristics identified in the PFMEA , PQCS,Operations standards ,
OPS,Inspections standards
Inspections standards, etc.

6.2 Are the Quality Objectives deployed in the department? PI data

6.1.2.2/10.2 Are correction and Preventive actions taken in case the Criteria are not met? Action plan

Are the appearance item identify and displayed at the required location.
Control of Limit Sample includes following information
1.Date of production of the limit sample
8.6.3 2.Control No. master List of Limit
3.Inspection Items ( Scratch, Roughness, unevenness etc. ) Sample/Identification Tag
4.Applicable Part Name & Part No.
Effective Period
6.Significant field.

8.6.3 master List of Limit


Are Limit sample retain considering damage,deteorition etc.
Sample/Identification Tag

9.1.1.2 Is there understanding of statistical concepts variation ,stability , process capability& over
Training Record
adjustment?

8.6.2 Are Layout Inspections at specified frequency included in control plans being carried out? Layout Plan

8.6.2
Does the verification of effectiveness of layout inspection functional testing has done?
Layout Reports & Records
Records for the same are maintained?

7.1.5
Are the instruments / Gauges / Test Soft Wares used for testing / verification in quality
Calibration History Card/ Plan
calibrated or verified?

7.1.5
Is MSA carried out for such instruments, which are referred in Control Plans?
MSA Plan / MSA Report
What are improvement plans for enhancing Measurement Systems?

8.7.1.4
Reject , Rework Record / Defect
Do work instructions for re-inspection of re-work products for the type of defects exist?
Matrix,WI

8.7.1.1
Is there a system for taking concessions on Non-conforming Products from customer prior
Deviation Request
to further processing?

8.7.1.1 Do records of concessions mention Quantity or Expiration period by customer? Deviation Request

8.7.1.1 What type of Marking / Identification is provided to customer Concession Products? Identification & Traceability

Is there any customer complaints closed or not Customer Complainst

is there customer complaints tracking record available customer complaints tracking sheet

Is there customer return record available Customer return register

Is there customer return rejection analysis available Customer return analysis record

10.2
Is there a system for utilizing a process for Problem Solving, leading to root cause
8D/ CAPA Report
identification and elimination?

8.2.3
Is the Process Qualification made for process Validation/ Process Capability carried out
PQS/SPC
for special characteristics

8.7.1.7 Is there Non-Confirming Product disposition system available/followed? Rejection Record

is there inhouse daily shop wise rejection review record available Rejection Record/Analysis

Control of Record
7.5.3/7.5.3.1 Is the record have following requirement identification,storage,Protection,retrivel,retention Records
and disposal of records

7.5.3.2 Records Retention


Retention system
Is the statutory ,regulatory and customer requirement follow

7.2.2/7.2.1
Is the competence defined for the personnel performing Production process & Revaluate
Skill Matrix
as defined interval
Corrective Action
Is the Reviewing the nonconformities ( Including Customer Complaints )
10.2
Verification of Nonconformity Implementation Customer Complaints/ C'Measure
Is the effectiveness of Corrective action review. Implementation

MS/WFIM 09 FO 12, ISSUE 00 DEC 2015 Score Achieve 0 Score Guide lines :
Total Score 72 0 Major NC
1 Minor NC
Score % 0 2 Opportunity for Improvement ( OI if Trend is improving )
Auditee Signature : Auditor Signature :
3 Full fill the system Requirements
INTERNAL AUDIT CHECKLIST
Wanfeng Aluminum Wheel
India
Department : Recieving Quality AUDIT REF.: IQA Date :
Time : NC

Score
Auditee : Auditor : Shift : Remarks
Confirmation
CL.NO. Checkpoints Document Observations Major/Minor/OI

Is there a documented procedure for Quality Assurance of Received Departmental


8.6
material Procedure

Are the Quality objective deployed in the Quality Department for


Incoming Quality Departmental
6.2
i.e. Same Objective as determined along with the quality policy or Objective
supporting departmental objectives.

Are the Quality objective deployed in the HOT SHOP Department


Departmental
6.2.1/6.2.2 i.e. Same Objective as determined along with the quality policy or
objectives.
supporting departmental objectives.

6.1.2.1 Is there a formal process available for risk analysis? Risk Analysis

Are there any risks and opportunities identified? Any Mitigation actions
6.1.2.1 Risk Analysis
for risks identified?

6.1.2 Status of Mitigation actions implementation and effectiveness? Risk Analysis

Abnormal conditions / unexpected change ( Contingency Plan )


Abnormal Conditions / Unexpected change to satisfy customer
6.1.2.3 Contingency Plan
requirements in event of an emergency such as labour shortage ,utility
intruptions,key equipment failure

Is the acceptance criteria estabilished and implemented to ensure that


8.6.6 Incoming Standard
purchased product meet the specified product requirement

Are there any customer supplied inspection tool /gauge?


8.5.1.6 List of Gauges
if Yes,how these tools / gauges are identified for tool ownership?

Are all the inputs available for monitoring & Measurements of product (
8.4.2 Receving inspection standards , drawing ,sample plan, Gauge Standard/Drawings
,Instruments )

Are the instrument/ Gauges used for testing / verification in quality


7.1.5.2 Calibration Record
calibrated or varified?

Is there a documented procedure for Non conforming of Received


material ?
8.7.1.2
Are the responsibility and authorities for dealing with non-conforming NC Product
product defined in the procedure ? Handling
Procedure
Does the procedure address identification and control of non-
8.7.1
conforming product prevent unintended use or delivery?

Do the procedure address the way of disposition of the non conforming


8.7.1.7 Rework Record
product in form of rework, use as it ,alternate use?

Are records of nature of non conformities and concessions


8.7.1.1 Deviation Record
maintained?

Is there continually improve the suitability, adequacy and effectiveness Improvement


10.3
of the Quality Management system? Records

8.4.1.2 Is there any supplier evaluation plan? Supplier Audit Plan

Is there any system for measurements of supplier perormance


Supplier Performance rating
8.4.2.4 Supplier Rating
Best Supplier in a month
Worst Supplier in a month

Is there any rule or procedure defined for product / process/ plant Change point
change from supplier? Control Procedure

1). Is there change point Identification requirement available?


8.5.6.1 1). Is there verification & validation activity as per plan/customer Technical
requirement? Noticem,Validation
2.)Is there validate change before Implementation? plan & Record,
3.) Is there evidences & retention record available for verification & Change point
validation?

Control of Record
Is the record have following requirement
7.5.3/7.5.3.1 Records
identification,storage,Protection,retrivel,retention and disposal of
records

Records Retention
7.5.3.2 Retention system
Is the statutory ,regulatory and customer requirement follow

Is the competence defined for the personnel performing Quality


7.2.2/7.2.1 Skill Matrix
process & Re-evaluate as defined interval

Corrective Action
Customer
Is the Reviewing the nonconformities ( Including Customer
Complaints/
10.2 Complaints )
C'Measure
Verification of Nonconformity Implementation
Implementation
Is the effectiveness of Corrective action review.

MS/WFIM 09 FO 12, ISSUE 00 DEC 2015 Score Guide lines :


Score Achieve 0 Major NC
1 Minor NC
Total Score 2 Opportunity for Improvement ( OI if Trend is improving )
3 Full fill the system Requirements

Score %
Auditee Signature : Auditor Signature :
INTERNAL AUDIT CH
Wanfeng Aluminum Wheel
India

Department : R&D AUDIT REF.:

Auditee : Auditor :

CL.NO. Checkpoints Confirmation Document

Is there a documented procedure available for R&D


8.3.2.1 Department
Departmental Procedure

Are the Quality objective deployed in the R & D


Department
6.2.1/6.2.2 Departmental objectives.
i.e. Same Objective as determined along with the quality
policy or supporting departmental objectives.

6.1.2.1 Is there a formal process available for risk analysis? Risk Analysis

Are there any risks and opportunities identified? Any


6.1.2.1 Risk Analysis
Mitigation actions for risks identified?

Status of Mitigation actions implementation and


6.1.2 Risk Analysis
effectiveness?

1). Is there development plan/ timing plan available?


2). Is there development plan/ Timing Plan reviewed
Timing Plan/APQP
timely?

8.3.1.2 1). Is there manufacturing process risk analysis available


such as FMEA's, Process Flow, control plan & standard
FMEA, Process Flow,
work Instructions?
Control Plan & standard work
2). Is there review of manufacturing process risk analysis
instructions
such as FMEA's, process flow, control plan & standard
work instructions?

Manufacturing Feasibility
1).Is there special characteristic identified?
8.3.3.2 2). Is there targets for productivity, process capability, Feasibility Study
timing & cost available?
3). Is there past problems included?

1). Is there special Characteristics identified in drawings,


Drawing/FMEA/Control
FMEA, Control Plan & standard work/operator
Plan/Standard Work
8.3.3.3 Instructions?
Instruction/List of Special
2). Is special characteristics identified with specific
Characteristics
marking/Symbol?
1). Is there Validation plan available?
2). Is there validation records available?
3). Is there any abnormality or problem during validation Validation
8.3.4 activity? plan/Record/Action Taken
4). Is there action taken against problem found during
validation activity?

Is there measurement & analysis results available &


8.3.4.1 reviewed in MRM?
Records & MRM

Is there validation according to customer requirements Customer & regulatory


8.3.4.2 including regulatory requirements? requirements

Identification and traceability


8.5.2 Is the traceability system included in all Operational Traceability System
document

8.3.6 Is there any change point control system available? Change Point Control

1). Is there change point Identification requirement


available?
1). Is there verification & validation activity as per
8.5.6.1 Technical Noticem,Validation
plan/customer requirement?
plan & Record, Change point
2.)Is there validate change before Implementation?
3.) Is there evidences & retention record available for
verification & validation?

8.5.6.1.1 Is there any temporary change in process control? Document Issue Records

Is the Record available of issue Mass Production


8.5.1 Transition Declaration prior going to Mass Production
Mass Production Declaration

7.2.2/7.2.1 Is the competence defined for the personnel performing


Skill Matrix
Production process & Revaluate as defined interval

Control of Record
7.5.3/7.5.3.1 Is the record have following requirement Records
identification,storage,Protection,retrivel,retention and
disposal of records

Records Retention
7.5.3.2 Is the statutory ,regulatory and customer requirement Retention system
follow

Corrective Action
Is the Reviewing the nonconformities ( Including
Customer Complaints/
10.2 Customer Complaints )
C'Measure Implementation
Verification of Nonconformity Implementation
Is the effectiveness of Corrective action review.

MS/WFIM 09 FO 12, ISSUE 00 DEC 2015 Score Achieve


Total Score

Score %

Auditee Signature :
INTERNAL AUDIT CHECKLIST

Date :
Time : NC
Score

Shift : Remarks

Observations Major/Minor/OI
Score Guide lines :
0 Major NC
1 Minor NC
2 Opportunity for Improvement ( OI if Trend is improving )
3 Full fill the system Requirements
Score Guide lines :
0 Major NC
1 Minor NC
2 Opportunity for Improvement ( OI if Trend is improving )
3 Full fill the system Requirements
#DIV/0!

Auditor Signature :
INTERNAL AUDIT CHECKLIS
Wanfeng Aluminum
Wheel India

Department : Purchase AUDIT REF.: IQA Date :

Score
Auditee : Auditor : Shift :
CL.NO. Checkpoints Confirmation Document O

Are the process identified and established ?


8.4 i.e. Supplier ,Performance monitoring, Purchase -local, Purchase- Departmental Procedure
Imports, Supplier Development, etc.

Are the Quality objective deployed in the Purchase


6.2.1/6.2.2 department.
Departmental objectives
i.e. Same Objective as determined along with the
quality policy or supporting departmental objectives.

Supplier Selection
8.4.1.2 Dose they have a process for supplier selection Procedure

6.1.2.1 Is there a formal process available for risk analysis? Risk Analysis

6.1.2.1 Are there any risks and opportunities identified? Any


Risk Analysis
Mitigation actions for risks identified?

6.1.2 Status of Mitigation actions implementation and


Risk Analysis
effectiveness?

Abnormal conditions / unexpected change


( Contingency Plan )
6.1.2.3 Abnormal Conditions / Unexpected change to
Contingency Plan
satisfy customer requirements in event of an
emergency such as labour shortage ,utility
intruptions,key equipment failure

Is Contingency Plan tested for suitability and


6.1.2.3 reviewed annualy with CFT including top Contingency Plan
management?
are records maintained as a result of necessary actions
8.4.2.1 taken for improvement in supplier performance & its supplier performance
effectiveness ?

Is statutory and regulatory requirements implemented at


8.4.2.2 Declaration from Supplier
supplier end?

1)Is Approved Supplier List available? Approved Supplier List/ISO


8.4.2.3 2.) Is supplier compliance to ISO 9001 through Second Certificates
Party Audits.
Are the supplier selected on base of following
1). An assesment of the selected supplier's risk to product
confirmity Supplier Selection
8.4.1.2 2).relevant quality & delivery performance Procedure
3). An evaluation of the supplier's quality management
system

Are the frequancy of supplier visit/audits are defined to Supplier Selection


8.4.1.2 know their status of system development?are records Procedure
maintained?

Actions plan are prepared in joint discussion with your Supplier Selection
8.4.2.5 supplier for estabilishing / upgrading the system as per Procedure
IATF 16949:2016

Has customer prescribed any source to purchase Supplier Selection


8.4.1.3 products,materials ,tools or services under contractual Procedure
conditions?

Is supplier performance been monitored based on


following:
Delivery product confirmity to requirements Supplier Performance
8.4.2.4 Customer disruptions at the receiving plant Rating Procedure
Delivery schedule performance
Number of occurences of Premium Freight
Customer Notification on quality / Delivery Issues

Are they any outsource process identified in the


organization?
8.5.1.6 E.g Casting ,Machining,painting Job Responsibility
Note : Are any technical responsibility with in the
organization delegated for outsource process

are control of these outsource process identified in the Supplier QMS


8.5.1.6 QMS? Improvement Plan

Is there a system exist for process/plant change request Change management


8.5.6.1 from supplier?are the responsible person defined for System
approval of chage request?

Control of Record
7.5.3/7.5.3.1 Is the record have following requirement Records
identification,storage,Protection,retrivel,retention and
disposal of records

Records Retention
7.5.3.2 Is the statutory ,regulatory and customer requirement Retention system
follow

Corrective Action
Is the Reviewing the nonconformities ( Including Customer Complaints/
10.2 Customer Complaints ) C'Measure
Verification of Nonconformity Implementation Implementation
Is the effectiveness of Corrective action review.
Is the competency defined for the personnel performing Competency
purchase process ?
7.2.2/7.2.1
Are input for Purchase process identified in terms of Training Need
training needs? Identification

Score Achieve 0 Score Guide lines :


MS/WFIM 09 FO 12, ISSUE 00 DEC 2015 Total Score 0 Major NC
Score % #DIV/0! 1 Minor NC
2 Opportunity for Improv
Auditee Signature : 3 Full fill the system Requ
AUDIT CHECKLIST

Date :
Time : NC
Shift : Remarks

Observations Major/Minor/OI
Score Guide lines :
0 Major NC
1 Minor NC
2 Opportunity for Improvement ( OI if Trend is improving )
Auditor Signature :
3 Full fill the system Requirements
Wanfeng Aluminum
INTERNAL AUDIT CHECK
Wheel India
Department : Maintenance AUDIT REF.: IQA

Score
Auditee : Auditor :
CL.NO. Checkpoints Confirmation Document

Is there a documented procedure available for


8.5.1.5 Departmental Procedure
Maintenence Department

Are the Quality objective deployed in the Maint.


6.2.1/6.2.2 department. Departmental objectives
i.e. Same Objective as determined along with the
quality policy or supporting departmental objectives.

8.4.1.2 Dose they have a process for supplier selection Supplier Selection Procedure

6.1.2.1 Is there a formal process available for risk analysis? Risk Analysis

6.1.2.1 Are there any risks and opportunities identified? Any


Risk Analysis
Mitigation actions for risks identified?

6.1.2 Status of Mitigation actions implementation and


Risk Analysis
effectiveness?

Abnormal conditions / unexpected change


( Contingency Plan )
6.1.2.3 Abnormal Conditions / Unexpected change to satisfy
Contingency Plan
customer requirements in event of an emergency such
as labour shortage ,utility intruptions,key equipment
failure

6.1.2.3 Is Contingency Plan tested for suitability and reviewed


Contingency Plan
annualy with CFT including top management?

Is there Identification of process equipment necessary


8.5.1.5 List of Machines/Equipments
to produce confirming product

Is there avaialability of parts for the


8.5.1.5 List of critical parts
equipment/machines identified?

Preventive and predictive maintenance - plan and Preventive Maintenance Plan &
8.5.1.5
records PM Report

8.5.1.5/8. Is there provision for packaging & preservation of


Equipment Handling
5.4 equipment, tooling & gauges?
8.5.1.5 Maintaining history card for Machine Machine History card

Is there MTBF (Mean Time Between Failures) & MTTR


8.5.1.5 MTBF & MTTR
calculated as defined frequency

8.5.1.5 What action taken to prevent the breakdown Action plan

How machine is approved after Planned & unplanned Machine check sheet & Product
8.5.1.4
shut down period? approval

8.5.1.4 Is the Breakdown intimation record available BD Intimation Slip

Is there Maintenance logs for each piece of equipment


8.5.1.4 Maintenance log book
Maintained

Control of Record
7.5.3/7.5.3 Is the record have following requirement
.1 Records
identification,storage,Protection,retrivel,retention and
disposal of records

Records Retention
7.5.3.2 Is the statutory ,regulatory and customer requirement Retention system
follow

Corrective Action
Is the Reviewing the nonconformities ( Including
Customer Complaints/
10.2 Customer Complaints )
C'Measure Implementation
Verification of Nonconformity Implementation
Is the effectiveness of Corrective action review.

Is the competency defined for the personnel performing Competency


Maint. process ?
7.2.2/7.2.1
Are input for Maint. process identified in terms of training Training Need Identification
needs?

MS/WFIM 09 FO 12, ISSUE 00 DEC 2015 Score Achieve 0

48 Total Score 48

Score % 0

Auditee Signature :
L AUDIT CHECKLIST

Date :
Time : NC
Shift : Remarks

Observations Major/Minor/OI
Score Guide lines :
0 Major NC
1 Minor NC
2 Opportunity for Improvement ( OI if Trend is improving )
3 Full fill the system Requirements

Auditor Signature :
INTERNAL AUDIT CHECKLI
Wanfeng Aluminum
Wheel India

Department : Marketing AUDIT REF.: IQA

Score
Auditee : Auditor :

CL.NO. Checkpoints Confirmation Document

8.2 Is there a documented procedure available for


Departmental Procedure
Marketing Department

Are the Quality objective deployed in the Purchase


6.2.1/6.2.2 department. Departmental objectives
i.e. Same Objective as determined along with the
quality policy or supporting departmental objectives.

8.4.1.2 Dose they have a process for supplier selection Supplier Selection Procedure

6.1.2.1 Is there a formal process available for risk analysis? Risk Analysis

6.1.2.1 Are there any risks and opportunities identified? Any


Risk Analysis
Mitigation actions for risks identified?

6.1.2 Status of Mitigation actions implementation and


Risk Analysis
effectiveness?

Abnormal conditions / unexpected change


( Contingency Plan )
6.1.2.3 Abnormal Conditions / Unexpected change to satisfy
Contingency Plan
customer requirements in event of an emergency such
as labour shortage ,utility intruptions,key equipment
failure

6.1.2.3 Is Contingency Plan tested for suitability and reviewed


Contingency Plan
annualy with CFT including top management?
Is method of measurement of customer
satisfaction/Perception determined?
Customer Feedback
Customer Audit
Customer Survey
Feedback to obtaine product image in the market
8.2.1 Customer Satisfaction index
Handling customer complaints
Increase market share
Repeative order
Cost effective
Enhance met in product properties
Product development and inovation etc.

Is following consider in customer satisfaction,as a


minimum.
Delivered part Quality Performance
8.2.2.1 Customer Line Distruptions Customer Satisfaction index
Delivery Performance
Incident Premium fraight
Customer notification ( Including penalty etc ) on
Quality / Delivery issue

8.2.1 Are corrective action identified if the customer Corrective & Preventive action
requirement are not full filled?

Are the requirement reviewed and necessory input from


8.2.3 various departmrnt obatined prior to organization
commitment?

Are the record of above reviews and action arising due


to this review maintained?

Are the relavent document amended and


communicated to the relavent department in case of
amendment to the order?

Is the output from the marketing department


communicated to the relavent department

Control of Record
7.5.3/7.5.3 Is the record have following requirement
.1 Records
identification,storage,Protection,retrivel,retention and
disposal of records
Records Retention
7.5.3.2 Is the statutory ,regulatory and customer requirement Retention system
follow

Corrective Action
Is the Reviewing the nonconformities ( Including
Customer Complaints/
10.2 Customer Complaints )
C'Measure Implementation
Verification of Nonconformity Implementation
Is the effectiveness of Corrective action review.

Is the competency defined for the personnel performing Competency


MKT process ?
7.2.2/7.2.1
Are input for MKT process identified in terms of training Training Need Identification
needs?

MS/WFIM 09 FO 12, ISSUE 00 DEC 2015 Score Achieve 0


Total Score 39
Score % 0
Auditee Signature :
AUDIT CHECKLIST

Date :
Time : NC
Shift : Remarks

Major/Min
Observations or/OI
Score Guide lines :
0 Major NC
1 Minor NC
2 Opportunity for Improvement ( OI if Trend is improving )
Auditor Signature :
3 Full fill the system Requirements
INTERNAL AUDIT CHECKLIST
Wanfeng Aluminum
Wheel India
Department : Quality Control AUDIT REF.: IQA Date :
Time : NC

Score
Auditee : Auditor : Shift : G Remarks
CL.NO. Checkpoints Confirmation Document Observations Major/Minor/OI

Are the process inspection & testing is being carried out as per defined frequency in
8.5.1 PQCS / OPS/Inspections standards/WI Inspection Report

is there setup approval done as per defined standards Setup approval report

Are rejects, rework, and adjustment parts, as well as internal residues strictly
8.7.1 separated and identified & Record Maintain Reject , Rework Record

Is the material and parts flow secured against mix-ups / exchanges by mistake and
8.7.1 traceability guaranteed. Identification & Traceability

Are tools, equipment and inspection, measuring and test equipment stored
8.5.1.6 correctly. List of Tools & Equipments

Abnormal conditions / unexpected change ( Contingency Plan )


Abnormal Conditions / Unexpected change to satisfy customer requirements in
6.1.2.3 event of an emergency such as labor shortage ,utility intruptions,key equipment Contingency Plan
failure

6.1.1 Is there a formal process available for risk analysis? Risk Analysis

Are there any risks and opportunities identified? Any Mitigation actions for risks
6.1.2 identified? Risk Analysis

6.1.2 Status of Mitigation actions implementation and effectiveness? Risk Analysis

Are the special characteristics identified in the PFMEA , PQCS,Operations


8.3.3.3 standards , Inspections standards, etc. OPS,Inspections standards

6.2 Are the Quality Objectives deployed in the department? PI data

6.1.2.2/10. Are correction and Preventive actions taken in case the Criteria are not
2 met? Action plan

Are the appearance item identify and displayed at the required location.
Control of Limit Sample includes following information
1.Date of production of the limit sample
8.6.3 2.Control No. master List of Limit Sample/Identification
3.Inspection Items ( Scratch, Roughness, unevenness etc. ) Tag
4.Applicable Part Name & Part No.
Effective Period
6.Significant field.

master List of Limit Sample/Identification


8.6.3 Are Limit sample retain considering damage,deteorition etc. Tag

9.1.1.2 Is there understanding of statistical concepts variation ,stability , process Training Record
capability& over adjustment?

Are Layout Inspections at specified frequency included in control plans


8.6.2 being carried out? Layout Plan

Does the verification of effectiveness of layout inspection functional


8.6.2 testing has done? Records for the same are maintained? Layout Reports & Records

7.1.5 Are the instruments / Gauges / Test Soft Wares used for testing / Calibration History Card/ Plan
verification in quality calibrated or verified?

Is MSA carried out for such instruments, which are referred in Control
7.1.5 Plans? MSA Plan / MSA Report
What are improvement plans for enhancing Measurement Systems?

Do work instructions for re-inspection of re-work products for the type of Reject , Rework Record / Defect
8.7.1.4 defects exist? Matrix,WI

Is there a system for taking concessions on Non-conforming Products from


8.7.1.1 customer prior to further processing? Deviation Request

8.7.1.1 Do records of concessions mention Quantity or Expiration period by Deviation Request


customer?

8.7.1.1 What type of Marking / Identification is provided to customer Identification & Traceability
Concession Products?

Is there any customer complaints closed or not Customer Complainst

is there customer complaints tracking record available customer complaints tracking sheet

Is there customer return record available Customer return register

Is there customer return rejection analysis available Customer return analysis record

Verify identification of the stages (Production & Delivery) and frequency of


9.2.2.4 Product Audit? Product Audit Plan

9.2.2.3 Is Process Audit carried out at each Manufacturing Process? Verify Process Audit Plan
frequency and check List.

Is there a system for utilizing a process for Problem Solving, leading to root
10.2 cause identification and elimination? 8D/ CAPA Report

Is the competence defined for the personnel performing Quality process &
7.2.2 Skill Matrix
Re-evaluate as defined interval

MS/WFIM 09 FO 12, ISSUE 00 DEC 2015 Score Achieve 0 Score Guide lines :
Total Score 72 0 Major NC
Score % 0 1 Minor NC
2 Opportunity for Improvement ( OI if Trend is improving )
Auditee Signature : Auditor Signature :
3 Full fill the system Requirements

You might also like