Professional Documents
Culture Documents
Answer Key
2. b. WBS
The WBS, along with the detailed scope statement and the WBS dic-
tionary, defines the projects scope baseline, which provides the basis
for any changes that may occur on the project. Formal change control
procedures should be used if the scope baseline requires change.
On the exam, recognize how the WBS is developed and the definitions
of a work package, a control account, and a planning package in case
one appears in the exam. [Planning]
PMI, PMBOK Guide, 2013, 131132
PMI PMP Examination Content Outline, 2015, Planning, 6, Task 2