1 PROYECTO CLINICA VETERINARIA, UZYT Y OFICINAS - LOTE 21 203 das lun 18/01/16 dom 07/08/16

2 INICIO 0 das lun 18/01/16 lun 18/01/16 18/01


3 SECTOR 1 203 das lun 18/01/16 dom 07/08/16

4 TRABAJOS PRELIMINARES 2 das lun 18/01/16 mar 19/01/16

5 MOVILIZACION DE EQUIPO Y HERRAMIENTAS 2 das lun 18/01/16 mar 19/01/16 2CC 18/01 19/01
6 OBRAS PROVISIONALES 9 das mar 19/01/16 mi 27/01/16

7 TRAZO Y REPLANTEO 3 das mar 19/01/16 jue 21/01/16 5FC-1 da 19/01 21/01
8 COLOCACION DE CERCO PERIMETRICO 3 das mar 19/01/16 jue 21/01/16 7CC 19/01 21/01
9 MONTAJE E INSTALACION DE OFICINA DE RESIDENTE DE OBRA 3 das jue 21/01/16 sb 23/01/16 8FC-1 da 21/01 23/01
10 MONTAJE DE OFICINA DE SUPERVISION Y SALA DE REUNIONES 2 das vie 22/01/16 dom 24/01/16 9CC 22/01 24/01
11 MONTAJE DE COMEDOR Y VESTUARIOS 2 das lun 25/01/16 mar 26/01/16 10FC-1 da 25/01 26/01
12 MONTAJE DE SS.HH. PERSONAL OBRERO 1 da mi 27/01/16 mi 27/01/16 11 27/01 27/01
13 ESTRUCTURAS 111 das lun 18/01/16 sb 07/05/16

14 MOVIMIENTO DE TIERRA 9 das lun 25/01/16 mar 02/02/16

15 TRAZO Y REPLANTEO DE ELEMENTOS DE CIMENTACION 3 das lun 25/01/16 mi 27/01/16 7FC+2 das 25/01 27/01
16 CORTE, EXCAVACION, ACARREO Y ELIMINACION LOCALIZADA 7 das mi 27/01/16 mar 02/02/16 15FC-1 da 27/01 02/02
17 CIMENTACION: ZAPATAS, VIGAS DE CIMENTACION, PLATEAS, LOSA 48 das lun 01/02/16 sb 19/03/16
DE PISO
18 SOLADO DE CIMENTACIN 5 das lun 01/02/16 vie 05/02/16 16FC-2 das 01/02 05/02
19 PERIODO DE DEFINICIN DE PLANOS Y COMPATIBILIDADES 12 das sb 06/02/16 mi 17/02/16 18 06/02 17/02
(PLANTA / CORTES)

20 REVISIN Y COMPATIBILIZACIN DE PLANOS ARQ vs ESTR POR AF 19 das jue 18/02/16 lun 07/03/16 19 18/02 07/03
SAC

21 ACERO EN ZAPATAS, VIGAS Y PLATEA DE CIMENTACIN 5 das lun 22/02/16 vie 26/02/16 19FC+4 das 22/02 26/02
22 ENCOFRADO 3 das mi 24/02/16 vie 26/02/16 21FC-3 das 24/02 26/02
23 REVISIN DE COMPATIBILIZACIONES REALIZADAS POR AF SAC Y 8 das mar 08/03/16 mar 15/03/16 20 08/03 15/03
APROBACIN DE PROYECTISTA ARQUITECTURA

24 MODIFICACIN ADECUACIN RED DE AGUA + INSTALACIN 8 das mar 08/03/16 mar 15/03/16 20 08/03 15/03
25 DEFINICIN Y APROBACIN DE ANCLAJES RESPUESTA A RFI 13 das mi 02/03/16 lun 14/03/16 20FC-6 das 02/03 14/03
26 REINSTALACIN DE ANCLAJES 3 das mar 15/03/16 jue 17/03/16 25 15/03 17/03
27 CULMINACIN DE ENCOFRADO DE LOSA POR AMPLIACIN, LUEGO 2 das mi 16/03/16 jue 17/03/16 23;24;25 16/03 17/03
DE APROBACIN DE PROYECTISTA

28 CONCRETO EN LOSA CIMENTACIN +CURADO 2 das vie 18/03/16 sb 19/03/16 27 18/03 19/03
29 LOSAS, MESAS DE LABORATORIO, BEVEDEROS 49 das dom 20/03/16sb 07/05/16

30 CAMBIO DE ORIENTACION DE POZA E INSTALACIONES 15 das dom 20/03/16dom 03/04/16 28 20/03 03/04
31 ESQUEMAS DE DETALLES PARA MESAS CON TOMACORRIENTES 27 das lun 04/04/16 sb 30/04/16 30 04/04 30/04
32 ACERO 4 das dom 01/05/16mi 04/05/16 31 01/05 04/05
33 ENCOFRADO 4 das mar 03/05/16 vie 06/05/16 32FC-2 das 03/05 06/05
34 CONCRETO 3 das jue 05/05/16 sb 07/05/16 33FC-2 das 05/05 07/05
35 CARPINTERIA METALICA 91 das lun 18/01/16 dom 17/04/16

Tarea Tarea crtica resumida Resumen inactivo Fecha lmite


Divisin Hito resumido Tarea manual Tarea crtica
Hito Progreso resumido Slo duracin Progreso
Proyecto: UCSUR COMPLETO
Fecha: lun 06/02/17 Resumen Tareas externas Informe de resumen manual Progreso manual
Resumen del proyecto Hito externo Resumen manual
Agrupar por sntesis Tarea inactiva Slo el comienzo
Tarea resumida Hito inactivo Slo fin

Pgina 1
Id ModoNombre de tarea Duracin
Comienzo Fin Predecesoras
de
tarea 26 oct '15 30 nov '15 04 ene '16 08 feb '16 14 mar '16 18 abr '16 23 may '16 27 jun '16 01 ago '16 05 sep '16
36 DIMENSIONAMIENTO, HABILITACION Y MONTAJE DE ELEMENTOS 22 das lun 18/01/16 lun 08/02/16
METALICOS ESTRUCTURALES
37 TRAZO DE ELEMENTOS 7 das lun 18/01/16 dom 24/01/16 2CC 18/01 24/01
38 CORTE DE ELEMENTOS 9 das lun 25/01/16 mar 02/02/16 37 25/01 02/02
39 ARMADO DE DESPIECE 8 das lun 01/02/16 lun 08/02/16 38FC-2 das 01/02 08/02
40 COLUMNAS PISO 1 52 das lun 08/02/16 mi 30/03/16

41 COLOCACION DE ANCLAJES EN ZAPATA - LOSA PISO 3 das lun 08/02/16 mi 10/02/16 39FC-2 das 08/02 10/02
42 MONTAJE DE COLUMNA METALICA 6 das lun 21/03/16 sb 26/03/16 28FC+1 da;41 21/03 26/03
43 ALINEAMIENTO DE COLUMNAS 6 das mi 23/03/16 lun 28/03/16 42CC+2 das 23/03 28/03
44 SOLDADURA DE TOPES Y FIJACION FINAL 6 das vie 25/03/16 mi 30/03/16 43CC+2 das 25/03 30/03
45 VIGAS Y VIGUETAS PISO 1 9 das sb 26/03/16 dom 03/04/16

46 MONTAJE DE VIGA METALICA V-1, V-2, V-3, V-4, V-5, VT1 7 das sb 26/03/16 vie 01/04/16 44CC+1 da 26/03 01/04
47 SOLDADURA DE VIGAS Y VIGUETAS 7 das dom 27/03/16sb 02/04/16 46CC+1 da 27/03 02/04
48 AJUSTE GENERAL DE VIGAS Y VIGUETAS 6 das mar 29/03/16 dom 03/04/16 47CC+2 das 29/03 03/04
49 COLOCACION DE ARRIOSTRES 6 das mar 29/03/16 dom 03/04/16 48FF 29/03 03/04
50 LOSA COLABORANTE DECK 17 das vie 01/04/16 dom 17/04/16

51 MONTAJE DE PLACAS COLABORANTES DECK 4 das vie 01/04/16 lun 04/04/16 49FC-3 das 01/04 04/04
52 FIJACION DE FRISOS PERIMETRALES 3 das dom 03/04/16mar 05/04/16 51CC+2 das 03/04 05/04
53 COLOCACION DE TOPES EN DECK, APUNTALAMIENTO 3 das dom 03/04/16mar 05/04/16 51CC+2 das 03/04 05/04
54 ACERO DE REFUERZO, INST. SANIT., II.E.. 3 das dom 03/04/16mar 05/04/16 51CC+2 das;124 03/04 05/04
55 INCONGRUENCIA ENTRE ARQUITECTURA Y ESTRUCTURAS 10 das mi 06/04/16 vie 15/04/16 54 06/04 15/04
VISTO EN CORTES. MAYOR ZONA DE TRABAJO

56 CONCRETO EN LOSA COLABORANTE 2 das sb 16/04/16 dom 17/04/16 54;53;52;55 16/04 17/04
57 ARQUITECTURA 68,5 das dom 27/03/16vie 03/06/16

58 CONTRAPISO 2 das dom 27/03/16mar 29/03/16

59 CONTRAPISO PULIDO / SEMIPULIDO e= 5 CM. 2 das dom 27/03/16mar 29/03/16 43FC-1,5 das 27/03 29/03
60 MUROS Y TABIQUES 51,5 das mar 29/03/16 jue 19/05/16

61 MURO LADRILLO KK CABEZA 3 das mar 29/03/16 vie 01/04/16 59 29/03 01/04
62 MURO LADRILLO KK SOGA 3 das vie 01/04/16 lun 04/04/16 61 01/04 04/04
63 TABIQUE DE DRYWALL STD 2 CARAS 8 das lun 18/04/16 lun 25/04/16 56;62 18/04 25/04
64 REUBICACIN DE SALA DE NECROPSIA 7 das mar 26/04/16 lun 02/05/16 63 26/04 02/05
65 MODIFICACIN POR NUEVOS MUROS Y TABIQUES DE DRYWALL EN 7 das mar 26/04/16 lun 02/05/16 63 26/04 02/05
QUIRFANO Y CONSULTORIO

66 INDEFINICIN DE MATERIAL DE FACHADA 5 das mar 03/05/16 sb 07/05/16 65 03/05 07/05


67 COLOCACIN DE DRYWALL EXTERIOR 10 das dom 08/05/16mar 17/05/16 66 08/05 17/05
68 CIELORRASO DE DRYWALL 5 das dom 15/05/16jue 19/05/16 67FC-3 das 15/05 19/05
69 REVOQUES ENLUCIDOS Y MOLDURAS 4 das vie 01/04/16 mar 05/04/16

70 TARRAJEO EN MUROS INTERIORES 2 das vie 01/04/16 dom 03/04/16 61 01/04 03/04
71 TARRAJEO EN MUROS EXTERIORES 2 das dom 03/04/16mar 05/04/16 70 03/04 05/04
72 PISOS Y PAVIMENTOS 8 das jue 19/05/16 jue 26/05/16

Tarea Tarea crtica resumida Resumen inactivo Fecha lmite


Divisin Hito resumido Tarea manual Tarea crtica
Hito Progreso resumido Slo duracin Progreso
Proyecto: UCSUR COMPLETO
Fecha: lun 06/02/17 Resumen Tareas externas Informe de resumen manual Progreso manual
Resumen del proyecto Hito externo Resumen manual
Agrupar por sntesis Tarea inactiva Slo el comienzo
Tarea resumida Hito inactivo Slo fin

Pgina 2
Id ModoNombre de tarea Duracin
Comienzo Fin Predecesoras
de
tarea 26 oct '15 30 nov '15 04 ene '16 08 feb '16 14 mar '16 18 abr '16 23 may '16 27 jun '16 01 ago '16 05 sep '16
73 PISO EN MUSEO,SALA DE REUNIONES,OFICINAS 8 das jue 19/05/16 jue 26/05/16 68FC-1 da;71;34 19/05 26/05
74 PISO EN PASADIZO 8 das jue 19/05/16 jue 26/05/16 68FC-1 da 19/05 26/05
75 PISO EN LABORATORIOS 8 das jue 19/05/16 jue 26/05/16 68FC-1 da 19/05 26/05
76 PISO EN AREA DE CULTIVOS 8 das jue 19/05/16 jue 26/05/16 68FC-1 da 19/05 26/05
77 PISO CERAMICO 30X30 EN BAOS 9 das sb 21/05/16 dom 29/05/16

78 ZOCALO 7 das sb 21/05/16 vie 27/05/16 76CC+2 das 21/05 27/05


79 ZOCALO DE CERAMICA EN BAOS (H=2.10MTS) 8 das sb 21/05/16 sb 28/05/16 76CC+2 das 21/05 28/05
80 CONTRAZOCALO CEMENTO PULIDO 5 das mi 25/05/16 dom 29/05/16 79FC-4 das 25/05 29/05
81 CARPINTERIA DE MADERA 9 das mi 25/05/16 jue 02/06/16

82 PUERTAS EN DEPOSITOS (0.80X2.10) 5 das mi 25/05/16 dom 29/05/16 73FC-2 das 25/05 29/05
83 PUERTAS EN SSHH (0.90X2.10) 6 das sb 28/05/16 jue 02/06/16 82FC-2 das 28/05 02/06
84 PUERTAS EN LABORATORIOS (1.60X2.40) 2 das mi 01/06/16 jue 02/06/16 83FC-2 das;86 01/06 02/06
85 PUERTAS EN PASADIZO (2.30X2.40) 3 das mi 25/05/16 vie 27/05/16 74FC-2 das 25/05 27/05
86 PUERTA EMERGENCIA (3.00X2.40) 3 das sb 28/05/16 lun 30/05/16 85 28/05 30/05
87 CARPINTERIA DE ALUMINIO 32 das mar 03/05/16 vie 03/06/16

88 VENTANAS 10 das mar 10/05/16 jue 19/05/16

89 VENTANAS EN SSHH 6 das mar 10/05/16 dom 15/05/16 101CC+2 das 10/05 15/05
90 VENTANAS EN OFICINAS 7 das mi 11/05/16 mar 17/05/16 89CC+1 da 11/05 17/05
91 VENTANAS EN LABORATORIOS 8 das jue 12/05/16 jue 19/05/16 90CC+1 da 12/05 19/05
92 MAMPARAS 29 das mar 03/05/16 mar 31/05/16

93 CAMBIO DE ALTURA DE MAMPARAS Y VENTANAS CON 15 das mar 03/05/16 mar 17/05/16 66CC 03/05 17/05
RESPECTO A DINTELES Y FALSO CIELO

94 MAMPARAS EN OFICINAS Y LABORATORIOS 7 das mi 18/05/16 mar 24/05/16 93 18/05 24/05


95 MURO CORTINA 7 das mi 25/05/16 mar 31/05/16 94 25/05 31/05
96 ELEMENTOS METALICOS 10 das mi 25/05/16 vie 03/06/16

97 BARANDA EN ESCALERA 6 das mi 25/05/16 lun 30/05/16 95CC 25/05 30/05


98 REJILLA EN ESTACIONAMIENTOS 4 das mar 31/05/16 vie 03/06/16 97 31/05 03/06
99 REJILLA DE PISO EN LABORATORIOS 4 das mar 31/05/16 vie 03/06/16 98CC 31/05 03/06
100 PINTURA 26 das dom 08/05/16jue 02/06/16

101 PINTURA EN MUROS INTERIORES 1RA MANO 11 das dom 08/05/16mi 18/05/16 66 08/05 18/05
102 PINTURA EN MUROS INTERIORES 2DA MANO 9 das jue 19/05/16 vie 27/05/16 101 19/05 27/05
103 PINTURA EN MUROS EXTERIORES 1RA MANO 9 das jue 19/05/16 vie 27/05/16 101 19/05 27/05
104 PINTURA EN MUROS EXTERIORES 2DA MANO 7 das vie 27/05/16 jue 02/06/16 102FC-1 da;103FC-1 da 27/05 02/06
105 OBRAS EXTERIORES 61 das jue 18/02/16 lun 18/04/16

106 VIAS PEATONALES - EJES G - G'' / 1 - 2 61 das jue 18/02/16 lun 18/04/16

107 TRAZO Y REPLANTEO 3 das jue 18/02/16 sb 20/02/16 15 18/02 20/02


108 EXCAVACION DE RED MATRIZ DE AGUA Y DESAGUE 5 das dom 21/02/16jue 25/02/16 107 21/02 25/02
109 SUMINISTRO E INSTALACIN DE TUBERAS DE PPR REDEFINIDAS 10 das mi 16/03/16 vie 25/03/16 24 16/03 25/03
POR EL PROYECTISTA

110 EXCAVACION DE MEDIA TENSION ELECTRICA 5 das sb 26/03/16 mi 30/03/16 109 26/03 30/03

Tarea Tarea crtica resumida Resumen inactivo Fecha lmite


Divisin Hito resumido Tarea manual Tarea crtica
Hito Progreso resumido Slo duracin Progreso
Proyecto: UCSUR COMPLETO
Fecha: lun 06/02/17 Resumen Tareas externas Informe de resumen manual Progreso manual
Resumen del proyecto Hito externo Resumen manual
Agrupar por sntesis Tarea inactiva Slo el comienzo
Tarea resumida Hito inactivo Slo fin

Pgina 3
Id ModoNombre de tarea Duracin
Comienzo Fin Predecesoras
de
tarea 26 oct '15 30 nov '15 04 ene '16 08 feb '16 14 mar '16 18 abr '16 23 may '16 27 jun '16 01 ago '16 05 sep '16
111 SARDINELES: EXCAVACION, ACERO, ENCOFRADO Y CONCRETO 5 das jue 31/03/16 lun 04/04/16 110 31/03 04/04
112 RAMPAS DE CONCRETO: ACERO, ENCOFRADO Y CONCRETO 6 das mar 05/04/16 dom 10/04/16 111 05/04 10/04
113 CONFORMACION DE PLATAFORMADO CON ARENA GRUESA 6 das sb 09/04/16 jue 14/04/16 112FC-2 das 09/04 14/04
114 COLOCACION DE ADOQUINADO FIRT SEGN PLANO 5 das jue 14/04/16 lun 18/04/16 113FC-1 da 14/04 18/04
115 INSTALACIONES SANITARIAS 120 das vie 05/02/16 vie 03/06/16

116 RED SISTEMA DE AGUA FRIA 120 das vie 05/02/16 vie 03/06/16

117 REDES DE DESAGUE 53 das vie 05/02/16 lun 28/03/16

118 TUBERIA PVC C-10 DE 2 " , 4 " , 6" 3 das vie 05/02/16 dom 07/02/16 18FC-1 da 05/02 07/02
119 SUMINISTRO E INSTALACIN DE TUBERAS DE PPR 10 das mi 16/03/16 vie 25/03/16 118;24 16/03 25/03
REDEFINIDAS POR EL PROYECTISTA

120 PRUEBAS DE ESTANQUEIDAD 4 das vie 25/03/16 lun 28/03/16 119FC-1 da 25/03 28/03
121 REDES DE DISTRIBUCION 5 das jue 24/03/16 lun 28/03/16

122 TUBERIA PVC C-10 DE 1/2 " , 3/4 " , 11/4 " , 11/2 " , C/R EMPOTRADA4 das jue 24/03/16 dom 27/03/16 119FC-2 das 24/03 27/03
123 PRUEBAS DE PRESION 2 das dom 27/03/16lun 28/03/16 122FC-1 da 27/03 28/03
124 PRUEBAS DE LIMPIEZA DE TUBERIAS 2 das dom 27/03/16lun 28/03/16 122FC-1 da 27/03 28/03
125 EQUIPAMIENTO SANITARIO EN BATERIAS DE BAOS 62 das vie 01/04/16 mi 01/06/16

126 COLOCACION DE PANELES DIVISORIOS MODULARES 4 das jue 26/05/16 dom 29/05/16 79FC-3 das;129 26/05 29/05
127 COLOCACIN DE ACCESORIOS 3 das dom 29/05/16mar 31/05/16 126FC-1 da 29/05 31/05
128 COLOCACION DE VALVULAS, GRIFERIAS Y REGISTROS 2 das mar 31/05/16 mi 01/06/16 127FC-1 da 31/05 01/06
129 CAJAS DE REGISTRO 2 das sb 09/04/16 dom 10/04/16 130 09/04 10/04
130 CAJA DE REGISTRO DE 30 X 60 4 das mar 05/04/16 vie 08/04/16 131 05/04 08/04
131 CAJA DE REGISTRO DE 45 X 60 4 das vie 01/04/16 lun 04/04/16 110FC+1 da 01/04 04/04
132 VARIOS 7 das sb 28/05/16 vie 03/06/16

133 CONEXIN A LA RED DE DESAGUE EXISTENTE 4 das sb 28/05/16 mar 31/05/16 126FC-2 das 28/05 31/05
134 ACCESORIOS,LLAVES Y TUBERIAS PARA SISTEMA DE BOMBEO 5 das sb 28/05/16 mi 01/06/16 133CC 28/05 01/06
EN TANQUES
135 CAMARA DE BOMBEO PARA IMPULSION DE DESAGUE: 3 das mi 01/06/16 vie 03/06/16 134FC-1 da 01/06 03/06
CONEXIN PROVISIONAL RED EXISTENTE
136 INSTALACIONES ELECTRICAS 165 das jue 25/02/16 dom 07/08/16

137 SALIDAS ELCTRICAS: FUERZA E ILUMINACION 79 das jue 25/02/16 vie 13/05/16

138 SALIDAS DE FUERZA: NORMAL, ESTABILIZADAS, UNIPOLARES, 4 das jue 25/02/16 dom 28/02/16 21FC-2 das 25/02 28/02
BIPOLARES, AA.
139 SALIDAS DE ILUMINACIN: CENTROS, BRAQUETS, EMERGENCIA. 3 das jue 14/04/16 sb 16/04/16 56CC-2 das 14/04 16/04
140 COMPATIBILIZACIN DE PLANOS Y REFORZAMIENTO DE 20 das dom vie 06/05/16 139 17/04 06/05
TABIQUERAS EN FACHADA PARALIZABAN LAS INSTALACIONES 17/04/16

141 SALIDA DE INTERRUMPTORES UNIPOLARES, CONMUTACIN. 5 das lun 09/05/16 vie 13/05/16 140FC+2 das 09/05 13/05
142 TABLEROS ELECTRICOS 7 das sb 14/05/16 vie 20/05/16

143 SUMINISTRO E INSTAL. DE TABLERO TDG-1, TN1-TN3, TS1-TS3, 7 das sb 14/05/16 vie 20/05/16 141 14/05 20/05
TE1-TE3, TCO
144 ALIMENTADORES ELCTRICOS 5 das sb 21/05/16 mi 25/05/16

145 CONEXIN PROVISIONAL 5 das sb 21/05/16 mi 25/05/16 143 21/05 25/05


146 CABLES Y CONDUCTORES 9 das mar 10/05/16 mi 18/05/16

Tarea Tarea crtica resumida Resumen inactivo Fecha lmite


Divisin Hito resumido Tarea manual Tarea crtica
Hito Progreso resumido Slo duracin Progreso
Proyecto: UCSUR COMPLETO
Fecha: lun 06/02/17 Resumen Tareas externas Informe de resumen manual Progreso manual
Resumen del proyecto Hito externo Resumen manual
Agrupar por sntesis Tarea inactiva Slo el comienzo
Tarea resumida Hito inactivo Slo fin

Pgina 4
Id ModoNombre de tarea Duracin
Comienzo Fin Predecesoras
de
tarea 26 oct '15 30 nov '15 04 ene '16 08 feb '16 14 mar '16 18 abr '16 23 may '16 27 jun '16 01 ago '16 05 sep '16
147 CABLEADO DE 2-1x4mm2 + 1x2.5mm2 NH 80 - 20mm PVC SAP 9 das mar 10/05/16 mi 18/05/16 140FC+3 das 10/05 18/05
148 CAJAS DE PASE 6 das vie 11/03/16 mi 16/03/16

149 CAJA DE PASE OCTOGONAL 100x55 mm EN CIELO RASO 2 das vie 11/03/16 sb 12/03/16 138FC+11 das 11/03 12/03
150 CAJA DE PASE DE 550x550x100, 300x300x100 , 250x250x100, 4 das dom mi 16/03/16 149 13/03 16/03
200x200x100, 150x150x100 mm 13/03/16
151 BANDEJA ELECTRICA 7 das vie 13/05/16 jue 19/05/16

152 BANDEJA ELECTRICA 300x100 7 das vie 13/05/16 jue 19/05/16 147FC-6 das;150 13/05 19/05
153 TUBERA ELCTRICA TABIQUES Y FALSO CIELO 4 das sb 07/05/16 mar 10/05/16

154 TUBERIA CONDUIT EMT DE 15mm, 20mm,25mm 4 das sb 07/05/16 mar 10/05/16 149CC-3,5 das;140 07/05 10/05
155 PRUEBAS ELECTRICAS 3 das lun 16/05/16 mi 18/05/16

156 PRUEBA DE AISLAMIENTO A SISTEMAS ELECTRICOS 3 das lun 16/05/16 mi 18/05/16 152CC+3 das 16/05 18/05
157 APARATOS ELECTRICOS 12 das mi 27/07/16 dom 07/08/16

158 SUMINISTRO DE LUMINARIAS 5 das mi 27/07/16 dom 31/07/16 27/07 31/07


159 SUMINISTRO E INSTALACIN DE LUMINARIAS, BRAQUETS, 6 das lun 01/08/16 sb 06/08/16 147FC-1 da;158 01/08 06/08
EMERGENCIAS.
160 SUMINISTRO E INSTALACIN DE PLACAS TOMACORRIENTES E 6 das mar 02/08/16 dom 07/08/16 159CC+1 da 02/08 07/08
INTERRUPTORES.
161 SISTEMA DE PUESTA A TIERRA 8 das sb 05/03/16 dom 13/03/16

162 POZO PUESTA A TIERRA 8 das sb 05/03/16 dom 13/03/16 138FC+5,5 das 05/03 13/03
163 OTROS 4 das jue 19/05/16 dom 22/05/16

164 BANCO DE MEDIDOR 4 das jue 19/05/16 dom 22/05/16 145CC-2 das 19/05 22/05
165 ALARMA CONTRAINCENDIO 14 das mi 11/05/16 mar 24/05/16

166 SALIDA DE DESTECTOR DE TEMPERATURA, HUMO, MOVIMIENTO 2 das mi 11/05/16 jue 12/05/16 154 11/05 12/05
167 PANEL CENTRAL DE DETECCIN DE ALARMA, SIRENA 7 das mi 18/05/16 mar 24/05/16 169;170 18/05 24/05
168 CCTV 21,5 das vie 13/05/16 vie 03/06/16

169 TUBERIA PVC L DE 15mm, 25mm, 35mm, 50mm 5 das vie 13/05/16 mar 17/05/16 166 13/05 17/05
170 CAJA DE PASE DE 250x250x150 mm, 250X250X200mm, 5 das vie 13/05/16 mar 17/05/16 166 13/05 17/05
650X350X150mm
171 PANEL CONTROL DE COMUNICACIONES: CENTRAL DE DATA, 6 das sb 28/05/16 vie 03/06/16 167FC+3,5 28/05 03/06
CENTRAL TELEFONICA das;164
172 SECTOR 2 185 das lun 01/02/16 mi 03/08/16

173 ESTRUCTURAS 142 das lun 01/02/16 mar 21/06/16

174 MOVIMIENTO DE TIERRA UZYT Y OFICINAS 108 das lun 01/02/16 mi 18/05/16

175 PARALIZACIN EN UZYT POR TEMA DE RELLENO 40 das lun 01/02/16 vie 11/03/16 15FC+4 das 01/02 11/03
176 PROPUESTAS DE RELLENO Y PRESUPUESTOS 30 das sb 12/03/16 dom 10/04/16 175 12/03 10/04
177 DEFINICIN DE PROPUESTA 21 das lun 11/04/16 dom 01/05/16 176 11/04 01/05
178 RELLENO DE UZYT 10 das lun 02/05/16 mi 11/05/16 177 02/05 11/05
179 TRAZO Y REPLANTEO DE ELEMENTOS DE CIMENTACION 3 das jue 12/05/16 sb 14/05/16 178 12/05 14/05
180 CORTE, EXCAVACION, ACARREO Y ELIMINACION LOCALIZADA 5 das sb 14/05/16 mi 18/05/16 179FC-1 da 14/05 18/05
181 CIMENTACION: ZAPATAS, VIGAS DE CIMENTACION, PLATEAS, LOSA 11 das mar vie 27/05/16
DE PISO UZYT 17/05/16

182 SOLADO DE CIMENTACIN 5 das mar 17/05/16 sb 21/05/16 180FC-2 das 17/05 21/05
183 ACERO EN ZAPATAS, VIGAS Y PLATEA DE CIMENTACIN 4 das sb 21/05/16 mar 24/05/16 182FC-1 da 21/05 24/05

Tarea Tarea crtica resumida Resumen inactivo Fecha lmite


Divisin Hito resumido Tarea manual Tarea crtica
Hito Progreso resumido Slo duracin Progreso
Proyecto: UCSUR COMPLETO
Fecha: lun 06/02/17 Resumen Tareas externas Informe de resumen manual Progreso manual
Resumen del proyecto Hito externo Resumen manual
Agrupar por sntesis Tarea inactiva Slo el comienzo
Tarea resumida Hito inactivo Slo fin

Pgina 5
Id ModoNombre de tarea Duracin
Comienzo Fin Predecesoras
de
tarea 26 oct '15 30 nov '15 04 ene '16 08 feb '16 14 mar '16 18 abr '16 23 may '16 27 jun '16 01 ago '16 05 sep '16
184 ENCOFRADO 3 das lun 23/05/16 mi 25/05/16 183FC-2 das 23/05 25/05
185 CONCRETO EN LOSA CIMENTACIN +CURADO 2 das jue 26/05/16 vie 27/05/16 184 26/05 27/05
186 CIMENTACION: ZAPATAS, VIGAS DE CIMENTACION, PLATEAS, LOSA 45 das sb 06/02/16 lun 21/03/16
DE PISO CV

187 SOLADO DE CIMENTACIN 5 das sb 06/02/16 mi 10/02/16 18 06/02 10/02


188 ACERO EN ZAPATAS, VIGAS Y PLATEA DE CIMENTACIN 4 das mi 10/02/16 sb 13/02/16 187FC-1 da 10/02 13/02
189 ENCOFRADO 3 das vie 12/02/16 dom 14/02/16 188FC-2 das 12/02 14/02
190 PARALIZACION POR INDEFINICIONES IGUAL QUE EN SECTOR 1 34 das lun 15/02/16 sb 19/03/16 189 15/02 19/03
191 CONCRETO EN LOSA CIMENTACIN +CURADO 2 das dom 20/03/16lun 21/03/16 28;190 20/03 21/03
192 CARPINTERIA METALICA 92 das mar 22/03/16 mar 21/06/16

193 COLUMNAS UZYT Y OFICINAS PISO 1 17 das lun 23/05/16 mi 08/06/16

194 COLOCACION DE ANCLAJES EN ZAPATA - LOSA PISO 2 das lun 23/05/16 mar 24/05/16 183FF 23/05 24/05
195 MONTAJE DE COLUMNA METALICA 6 das lun 30/05/16 sb 04/06/16 185FC+2 das 30/05 04/06
196 ALINEAMIENTO DE COLUMNAS 6 das mi 01/06/16 lun 06/06/16 195CC+2 das 01/06 06/06
197 6 das vie 03/06/16 mi 08/06/16 196CC+2 das 03/06 08/06
198 VIGAS Y VIGUETAS UZYT Y OFICINAS 12 das lun 06/06/16 vie 17/06/16

199 MONTAJE DE VIGAS METALICAS 7 das lun 06/06/16 dom 12/06/16 197CC+3 das 06/06 12/06
200 SOLDADURA DE VIGAS Y VIGUETAS 7 das jue 09/06/16 mi 15/06/16 199CC+3 das 09/06 15/06
201 AJUSTE GENERAL DE VIGAS Y VIGUETAS 7 das sb 11/06/16 vie 17/06/16 200CC+2 das 11/06 17/06
202 COBERTURA EN ZONA DE UZYT 4 das sb 18/06/16 mar 21/06/16

203 COLOCACIN DE COBERTURA TIPO ONDULIT 4 das sb 18/06/16 mar 21/06/16 201 18/06 21/06
204 COLUMNAS CV PISO 1 15 das mar 22/03/16 mar 05/04/16

205 COLOCACION DE ANCLAJES EN ZAPATA - LOSA PISO 3 das mar 22/03/16 jue 24/03/16 191 22/03 24/03
206 MONTAJE DE COLUMNA METALICA 9 das jue 24/03/16 vie 01/04/16 191FC+2 das 24/03 01/04
207 ALINEAMIENTO DE COLUMNAS 9 das sb 26/03/16 dom 03/04/16 206CC+2 das 26/03 03/04
208 SOLDADURA DE TOPES Y FIJACION FINAL 9 das lun 28/03/16 mar 05/04/16 207CC+2 das 28/03 05/04
209 VIGAS Y VIGUETAS CV PISO 1 18 das mar 29/03/16 vie 15/04/16

210 MONTAJE DE VIGAS METALICAS 10 das mar 29/03/16 jue 07/04/16 208CC+1 da 29/03 07/04
211 SOLDADURA DE VIGAS Y VIGUETAS 10 das mi 30/03/16 vie 08/04/16 210CC+1 da 30/03 08/04
212 AJUSTE GENERAL DE VIGAS Y VIGUETAS 10 das vie 01/04/16 dom 10/04/16 211CC+2 das 01/04 10/04
213 COLOCACION Y SOLDADURA DE ARRIOSTRES 5 das lun 11/04/16 vie 15/04/16 212 11/04 15/04
214 LOSA COLABORANTE DECK PISO 1 S2 - CLINICA VET Y UZYT 14 das vie 15/04/16 jue 28/04/16

215 MONTAJE DE PLACAS COLABORANTES DECK 4 das vie 15/04/16 lun 18/04/16 213FC-1 da 15/04 18/04
216 COLOCACION DE TOPES EN DECK, APUNTALAMIENTO 2 das dom 17/04/16lun 18/04/16 215CC+2 das 17/04 18/04
217 FIJACION DE FRISOS PERIMETRALES 3 das dom 17/04/16mar 19/04/16 215CC+2 das 17/04 19/04
218 ACERO DE REFUERZO, INST. SANIT., II.EE 3 das mar 19/04/16 jue 21/04/16 217CC+2 das 19/04 21/04
219 INCONGRUENCIA ENTRE ARQUITECTURA Y ESTRCTURAS 5 das vie 22/04/16 mar 26/04/16 218 22/04 26/04
VISTO EN CORTES. MAYOR ZONA DE TRABAJO

220 CONCRETO EN LOSA COLABORANTE 2 das mi 27/04/16 jue 28/04/16 219 27/04 28/04
221 OTRAS ESTRUCTURAS METALICAS 26 das dom 17/04/16jue 12/05/16

Tarea Tarea crtica resumida Resumen inactivo Fecha lmite


Divisin Hito resumido Tarea manual Tarea crtica
Hito Progreso resumido Slo duracin Progreso
Proyecto: UCSUR COMPLETO
Fecha: lun 06/02/17 Resumen Tareas externas Informe de resumen manual Progreso manual
Resumen del proyecto Hito externo Resumen manual
Agrupar por sntesis Tarea inactiva Slo el comienzo
Tarea resumida Hito inactivo Slo fin

Pgina 6
Id ModoNombre de tarea Duracin
Comienzo Fin Predecesoras
de
tarea 26 oct '15 30 nov '15 04 ene '16 08 feb '16 14 mar '16 18 abr '16 23 may '16 27 jun '16 01 ago '16 05 sep '16
222 MONTAJE DE ESTRUCTURA PARA SOPORTE DE DRYWALL Y 5 das dom jue 21/04/16 212FC+6 das 17/04 21/04
VENTANAS 17/04/16

223 REFORZAMIENTO PARA SOPORTE DE FACHADA CON 10 das vie 22/04/16 dom 01/05/16 222 22/04 01/05
ESTRUCTURA METLICA

224 INCOMPATILIZACIN ARQUITECTURA DE ESCALERA - NO 4 das lun 02/05/16 jue 05/05/16 223 02/05 05/05
CUMPLE CON RNE

225 MONTAJE DE ESTRUCTURA DE ESCALERAS 3 das vie 06/05/16 dom 08/05/16 224 06/05 08/05
226 FIJACIN DE ESTRUCTURA Y PELDAOS 2 das lun 09/05/16 mar 10/05/16 225 09/05 10/05
227 CONCRETO EN PELDAOS DE ESCALERAS 2 das mi 11/05/16 jue 12/05/16 226 11/05 12/05
228 ARQUITECTURA OFICINAS 43 das mi 22/06/16 mi 03/08/16

229 CONTRAPISO OFICINAS 3 das mi 22/06/16 vie 24/06/16

230 CONTRAPISO PULIDO / SEMIPULIDO e= 5 CM. 3 das mi 22/06/16 vie 24/06/16 203 22/06 24/06
231 MUROS Y TABIQUES SECTOR 2 - CV Y UZYT 24 das sb 25/06/16 lun 18/07/16

232 MURO LADRILLO KK CABEZA 6 das sb 25/06/16 jue 30/06/16 230 25/06 30/06
233 MURO LADRILLO KK SOGA 6 das jue 30/06/16 mar 05/07/16 232FC-1 da 30/06 05/07
234 TABIQUES DE DRYWALL INTERIORES 5 das sb 09/07/16 mi 13/07/16 233FC+3 das 09/07 13/07
235 TABIQUES DE DRYWALL EXTERIORES 6 das mi 13/07/16 lun 18/07/16 234FC-1 da 13/07 18/07
236 REVOQUES ENLUCIDOS Y MOLDURAS 8 das mi 06/07/16 mi 13/07/16

237 TARRAJEO EN MUROS INTERIORES 4 das mi 06/07/16 sb 09/07/16 233 06/07 09/07
238 TARRAJEO EN MUROS EXTERIORES 4 das dom 10/07/16mi 13/07/16 237 10/07 13/07
239 PISO CERAMICO 30X30 EN BAOS 8 das mar 19/07/16 mar 26/07/16

240 PISO CERAMICO EN BAOS 4 das mar 19/07/16 vie 22/07/16 235;238 19/07 22/07
241 ZOCALO DE CERAMICA EN BAOS (H=2.10MTS) 4 das sb 23/07/16 mar 26/07/16 240 23/07 26/07
242 CARPINTERIA DE ALUMINIO 5 das mar 26/07/16 sb 30/07/16

243 VENTANAS 5 das mar 26/07/16 sb 30/07/16

244 VENTANAS EN SSHH 2 das mar 26/07/16 mi 27/07/16 241CC+3 das 26/07 27/07
245 VENTANAS EN OFICINAS 3 das jue 28/07/16 sb 30/07/16 244 28/07 30/07
246 PINTURA SECTOR 2 - OFICINAS Y UZYT 16 das mar 19/07/16 mi 03/08/16

247 PINTURA EN MUROS EXTERIORES 5 das mar 19/07/16 sb 23/07/16 235 19/07 23/07
248 PINTURA EN MUROS INTERIORES 5 das dom 24/07/16jue 28/07/16 247 24/07 28/07
249 PINTURA FINAL EN MUROS EXT E INT 6 das vie 29/07/16 mi 03/08/16 248 29/07 03/08
250 ARQUITECTURA CV 62 das lun 11/04/16 sb 11/06/16

251 CONTRAPISO 3 das lun 11/04/16 mi 13/04/16

252 CONTRAPISO PULIDO / SEMIPULIDO e= 5 CM. 3 das lun 11/04/16 mi 13/04/16 212 11/04 13/04
253 MUROS Y TABIQUES SECTOR 2 - CV Y UZYT 44 das jue 14/04/16 vie 27/05/16

254 MURO LADRILLO KK CABEZA 3 das jue 14/04/16 sb 16/04/16 252 14/04 16/04
255 MURO LADRILLO KK SOGA 3 das sb 16/04/16 lun 18/04/16 254CC+2 das 16/04 18/04
256 TABIQUES DE DRYWALL INTERIORES 4 das dom 24/04/16mi 27/04/16 222FC+2 das;262 24/04 27/04
257 INDEFINICIN DE MATERIAL DE FACHADA 6 das sb 07/05/16 jue 12/05/16 66FC-1 da 07/05 12/05
258 TABIQUES DE DRYWALL EXTERIORES 10 das vie 13/05/16 dom 22/05/16 257 13/05 22/05

Tarea Tarea crtica resumida Resumen inactivo Fecha lmite


Divisin Hito resumido Tarea manual Tarea crtica
Hito Progreso resumido Slo duracin Progreso
Proyecto: UCSUR COMPLETO
Fecha: lun 06/02/17 Resumen Tareas externas Informe de resumen manual Progreso manual
Resumen del proyecto Hito externo Resumen manual
Agrupar por sntesis Tarea inactiva Slo el comienzo
Tarea resumida Hito inactivo Slo fin

Pgina 7
Id ModoNombre de tarea Duracin
Comienzo Fin Predecesoras
de
tarea 26 oct '15 30 nov '15 04 ene '16 08 feb '16 14 mar '16 18 abr '16 23 may '16 27 jun '16 01 ago '16 05 sep '16
259 CIELORRASO DE DRYWALL 7 das sb 21/05/16 vie 27/05/16 258FC-2 das 21/05 27/05
260 REVOQUES ENLUCIDOS Y MOLDURAS 4 das lun 18/04/16 jue 21/04/16

261 TARRAJEO EN MUROS INTERIORES 4 das lun 18/04/16 jue 21/04/16 255CC+2 das 18/04 21/04
262 TARRAJEO EN MUROS EXTERIORES 4 das lun 18/04/16 jue 21/04/16 261FF 18/04 21/04
263 PISOS Y PAVIMENTOS 9 das lun 23/05/16 mar 31/05/16

264 PISO EN REA DE RECEPCIN 6 das lun 23/05/16 sb 28/05/16 259FC-5 das 23/05 28/05
265 PISO EN REA DE ECOGRAFIA 6 das mar 24/05/16 dom 29/05/16 264CC+1 da 24/05 29/05
266 PISO EN LABORATORIOS 6 das jue 26/05/16 mar 31/05/16 265CC+2 das 26/05 31/05
267 PISO EN AREA DE QUIROFANO 6 das jue 26/05/16 mar 31/05/16 265CC+2 das 26/05 31/05
268 PISO CERAMICO 30X30 EN BAOS 8 das sb 28/05/16 sb 04/06/16

269 PISO CERAMICO EN BAOS 6 das sb 28/05/16 jue 02/06/16 267CC+2 das 28/05 02/06
270 ZOCALO DE CERAMICA EN BAOS (H=2.10MTS) 6 das sb 28/05/16 jue 02/06/16 267CC+2 das 28/05 02/06
271 CONTRAZOCALO CEMENTO PULIDO 5 das mar 31/05/16 sb 04/06/16 270FC-3 das 31/05 04/06
272 CARPINTERIA DE MADERA 10 das sb 28/05/16 lun 06/06/16

273 PUERTAS EN DEPOSITOS Y ALMACENES 4 das sb 28/05/16 mar 31/05/16 264FC-1 da 28/05 31/05
274 PUERTAS EN LABORATORIOS (1.60X2.40) 4 das mar 31/05/16 vie 03/06/16 273FC-1 da 31/05 03/06
275 PUERTAS EN SSHH (0.90X2.10) 2 das vie 03/06/16 sb 04/06/16 274FC-1 da 03/06 04/06
276 PUERTA EMERGENCIA (3.00X2.40) 2 das dom 05/06/16lun 06/06/16 275 05/06 06/06
277 CARPINTERIA DE ALUMINIO 10 das mar 31/05/16 jue 09/06/16

278 VENTANAS 7 das mar 31/05/16 lun 06/06/16

279 VENTANAS EN SSHH 2 das mar 31/05/16 mi 01/06/16 286CC+2 das 31/05 01/06
280 VENTANAS EN OFICINAS 3 das jue 02/06/16 sb 04/06/16 279CC+2 das 02/06 04/06
281 VENTANAS EN LABORATORIOS 3 das sb 04/06/16 lun 06/06/16 280CC+2 das 04/06 06/06
282 MAMPARAS 3 das mar 07/06/16 jue 09/06/16

283 MAMPARAS EN OFICINAS Y LABORATORIOS 3 das mar 07/06/16 jue 09/06/16 281 07/06 09/06
284 PINTURA SECTOR 2 - CV 26 das mar 17/05/16 sb 11/06/16

285 PINTURA EN MUROS EXTERIORES 1RA MANO 12 das mar 17/05/16 sb 28/05/16 258CC+4 das 17/05 28/05
286 PINTURA EN MUROS INTERIORES 1RA MANO 8 das dom 29/05/16dom 05/06/16 285 29/05 05/06
287 PINTURA EN MUROS EXTERIORES 2DA MANO 8 das dom 29/05/16dom 05/06/16 285 29/05 05/06
288 PINTURA EN MUROS INTERIORES 2DA MANO 6 das lun 06/06/16 sb 11/06/16 287 06/06 11/06
289 INSTALACIONES SANITARIAS 149 das jue 11/02/16 vie 08/07/16

290 RED SISTEMA DE AGUA FRIA UZYT 114 das jue 11/02/16 vie 03/06/16

291 REDES DE DISTRIBUCIONES 3 das jue 11/02/16 sb 13/02/16

292 TUBERIAS PPR 1/2", 3/4",1", 1 1/2" 2 das jue 11/02/16 vie 12/02/16 188CC+1 da 11/02 12/02
293 LIMPIEZA Y PRUEBAS DE PRESION 1 da sb 13/02/16 sb 13/02/16 292 13/02 13/02
294 SALIDAS DE AGUA FRIA 3 das mi 18/05/16 vie 20/05/16

295 TUBERIAS PPR 1/2", 3/4",1", 1 1/2" 3 das mi 18/05/16 vie 20/05/16 258CC+5 das 18/05 20/05
296 VALVULAS 14 das sb 21/05/16 vie 03/06/16

297 COLOCACIN DE VALVULAS DE COMPUERTA 1/2", 3/4", 1", 1 1/2" 4 das sb 21/05/16 mar 24/05/16 295 21/05 24/05

Tarea Tarea crtica resumida Resumen inactivo Fecha lmite


Divisin Hito resumido Tarea manual Tarea crtica
Hito Progreso resumido Slo duracin Progreso
Proyecto: UCSUR COMPLETO
Fecha: lun 06/02/17 Resumen Tareas externas Informe de resumen manual Progreso manual
Resumen del proyecto Hito externo Resumen manual
Agrupar por sntesis Tarea inactiva Slo el comienzo
Tarea resumida Hito inactivo Slo fin

Pgina 8
Id ModoNombre de tarea Duracin
Comienzo Fin Predecesoras
de
tarea 26 oct '15 30 nov '15 04 ene '16 08 feb '16 14 mar '16 18 abr '16 23 may '16 27 jun '16 01 ago '16 05 sep '16
298 NUEVAS INSTALACIONES SANITARIAS DE AGUA CALIENTE EN 5 das lun 30/05/16 vie 03/06/16 297FC+5 das 30/05 03/06
PRIMER PISO

299 RED SISTEMA DE DEAGUE UZYT 148 das vie 12/02/16 vie 08/07/16

300 REDES DE DESAGUE - UZYT 3 das vie 12/02/16 dom 14/02/16

301 TUBERIA PVC C-10 DE 2 " , 4 " , 6" 2 das vie 12/02/16 sb 13/02/16 292CC+1 da 12/02 13/02
302 PRUEBAS DE ESTANQUEIDAD 1 da dom 14/02/16dom 14/02/16 301 14/02 14/02
303 SALIAS DE DESAGUE 4 das jue 26/05/16 dom 29/05/16

304 TUBERIA PVC C-10 DE 1/2 ",4" 4 das jue 26/05/16 dom 29/05/16 295;310 26/05 29/05
305 EQUIPAMIENTO SANITARIO EN BATERIAS DE BAOS 22 das mi 18/05/16 mi 08/06/16

306 COLOCACION DE PANELES DIVISORIOS MODULARES 4 das vie 03/06/16 lun 06/06/16 271CC+3 das;304 03/06 06/06
307 COLOCACIN DE ACCESORIOS 4 das dom 05/06/16mi 08/06/16 306CC+2 das 05/06 08/06
308 CAJAS DE REGISTRO 2 das mi 18/05/16 jue 19/05/16 342 18/05 19/05
309 CAJA DE REGISTRO DE 30 X 60 3 das vie 20/05/16 dom 22/05/16 308 20/05 22/05
310 CAJA DE REGISTRO DE 45 X 60 3 das lun 23/05/16 mi 25/05/16 309 23/05 25/05
311 VARIOS 6 das dom 03/07/16vie 08/07/16

312 ACCESORIOS,LLAVES Y TUBERIAS PARA SISTEMA DE BOMBEO 3 das dom mar 05/07/16 348FC+3 das 03/07 05/07
EN TANQUES 03/07/16

313 CAMARA DE BOMBEO PARA IMPULSION DE DESAGUE: 3 das mi 06/07/16 vie 08/07/16 312 06/07 08/07
CONEXIN PROVISIONAL RED EXISTENTE

314 INSTALACIONES ELECTRICAS 174 das jue 11/02/16 mar 02/08/16

315 SALIDAS ELCTRICAS: FUERZA E ILUMINACION 97 das jue 11/02/16 mar 17/05/16

316 SALIDAS DE FUERZA: NORMAL, ESTABILIZADAS, UNIPOLARES, 2 das jue 11/02/16 vie 12/02/16 188CC+1 da 11/02 12/02
BIPOLARES, AA.

317 SALIDA DE INTERRUMPTORES UNIPOLARES, CONMUTACIN. 3 das dom 15/05/16mar 17/05/16 258CC+2 das;316 15/05 17/05
318 TUBERA ELCTRICA TABIQUES Y FALSO CIELO 4 das mar 17/05/16 vie 20/05/16

319 TUBERIA CONDUIT EMT DE 15mm, 20mm,25mm 4 das mar 17/05/16 vie 20/05/16 317CC+2 das 17/05 20/05
320 CAJAS DE PASE 5 das jue 19/05/16 lun 23/05/16

321 CAJA DE PASE OCTOGONAL 100x55 mm EN CIELO RASO 4 das jue 19/05/16 dom 22/05/16 319CC+2 das 19/05 22/05
322 CAJA DE PASE DE 550x550x100, 300x300x100 , 250x250x100, 3 das sb 21/05/16 lun 23/05/16 321CC+2 das 21/05 23/05
200x200x100, 150x150x100 mm

323 BANDEJA ELECTRICA 3 das mar 24/05/16 jue 26/05/16

324 BANDEJA ELECTRICA 300x100 3 das mar 24/05/16 jue 26/05/16 322 24/05 26/05
325 CABLES Y CONDUCTORES 7 das vie 27/05/16 jue 02/06/16

326 CABLEADO DE 2-1x4mm2 + 1x2.5mm2 NH 80 - 20mm PVC SAP 7 das vie 27/05/16 jue 02/06/16 324 27/05 02/06
327 PRUEBAS ELECTRICAS 2 das vie 03/06/16 sb 04/06/16

328 PRUEBA DE AISLAMIENTO A SISTEMAS ELECTRICOS 2 das vie 03/06/16 sb 04/06/16 326 03/06 04/06
329 TABLEROS ELECTRICOS 5 das mar 31/05/16 sb 04/06/16

330 SUMINISTRO E INSTAL. DE TABLEROS 5 das mar 31/05/16 sb 04/06/16 326FC-3 das 31/05 04/06
331 APARATOS ELECTRICOS 59 das dom 05/06/16mar 02/08/16

332 SUMINISTRO DE LUMINARIAS 2 das sb 30/07/16 dom 31/07/16 158FF 30/07 31/07

Tarea Tarea crtica resumida Resumen inactivo Fecha lmite


Divisin Hito resumido Tarea manual Tarea crtica
Hito Progreso resumido Slo duracin Progreso
Proyecto: UCSUR COMPLETO
Fecha: lun 06/02/17 Resumen Tareas externas Informe de resumen manual Progreso manual
Resumen del proyecto Hito externo Resumen manual
Agrupar por sntesis Tarea inactiva Slo el comienzo
Tarea resumida Hito inactivo Slo fin

Pgina 9
Id ModoNombre de tarea Duracin
Comienzo Fin Predecesoras
de
tarea 26 oct '15 30 nov '15 04 ene '16 08 feb '16 14 mar '16 18 abr '16 23 may '16 27 jun '16 01 ago '16 05 sep '16
333 SUMINISTRO E INSTALACIN DE LUMINARIAS, BRAQUETS, 2 das lun 01/08/16 mar 02/08/16 328;332 01/08 02/08
EMERGENCIAS.

334 SUMINISTRO E INSTALACIN DE PLACAS TOMACORRIENTES E 2 das dom lun 06/06/16 328 05/06 06/06
INTERRUPTORES. 05/06/16

335 ALARMA CONTRAINCENDIO 5 das dom 05/06/16jue 09/06/16

336 SALIDA DE DESTECTOR DE TEMPERATURA, HUMO, MOVIMIENTO 5 das dom 05/06/16jue 09/06/16 328 05/06 09/06
337 PANEL CENTRAL DE DETECCIN DE ALARMA, SIRENA 5 das dom 05/06/16jue 09/06/16 328 05/06 09/06
338 CCTV 4 das mar 07/06/16 vie 10/06/16

339 PANEL CONTROL DE COMUNICACIONES: CENTRAL DE DATA, CENTRAL


4 das
TELEFONICA
mar 07/06/16 vie 10/06/16 337FC-3 das 07/06 10/06
340 OBRAS EXTERIORES 68 das dom 15/05/16jue 21/07/16

341 ACCESOS PEATONALES Y VEHICULARES 68 das dom 15/05/16jue 21/07/16

342 TRAZO Y REPLANTEO 3 das dom 15/05/16mar 17/05/16 179 15/05 17/05
343 EXCAVACION P/CISTERNA. CAMARA DE BOMBEO 2 das mi 18/05/16 jue 19/05/16 342 18/05 19/05
344 CONSULTAS PARA DEFINICION DE POZO SUMIDERO EN CISTERNA 15 das vie 20/05/16 vie 03/06/16 343 20/05 03/06
345 EXCAVACION Y RELLENO DE BAJA TENSION ELECTRICA - 5 das sb 04/06/16 mi 08/06/16 344 04/06 08/06
INSTALACION DE TUBERIAS Y DADOS DE CONCRETO ZONA UZYT

346 DEFINICION DE POZO SUMIDERO EN CISTERNA POR PROYECTISTA 15 das jue 09/06/16 jue 23/06/16 345 09/06 23/06
347 DEFINICION Y EJECUCIN DE PLAZA N1 POR PROYECTISTA 10 das mi 22/06/16 vie 01/07/16 346FC-2 das 22/06 01/07
348 CISTERNA -CAM BOMBEO: ACERO, ENCOFRADO Y CONCRETO 9 das mar 21/06/16 mi 29/06/16 346FC-3 das 21/06 29/06
349 EXCAVACION Y RELLENO DE RED MATRIZ DE AGUA Y DESAGUE 4 das lun 27/06/16 jue 30/06/16 348FC-3 das 27/06 30/06
350 SUMINSTRO E INSTALACIN DE G.E 3 das vie 01/07/16 dom 03/07/16 349 01/07 03/07
351 SUMINSTRO Y CABLEADO DE BAJA TENSION HASTA G.E 4 das vie 01/07/16 lun 04/07/16 349 01/07 04/07
352 CONFORMACION DE PLATAFORMADO CON AFIRMADO 8 das mar 05/07/16 mar 12/07/16 351 05/07 12/07
353 SARDINELES: EXCAVACION, ACERO, ENCOFRADO Y CONCRETO 7 das dom 10/07/16sb 16/07/16 352FC-3 das 10/07 16/07
354 COLOCACIN DE BASE ARENA Y ADOQUINADO PEATONAL Y 8 das jue 14/07/16 jue 21/07/16 353FC-3 das 14/07 21/07
VEHICULAR

355 SECTOR 3 98 das vie 29/04/16 jue 04/08/16

356 ESTRUCTURAS 66 das vie 29/04/16 dom 03/07/16

357 CARPINTERIA METALICA 66 das vie 29/04/16 dom 03/07/16

358 COLUMNAS CV PISO 2 9 das vie 29/04/16 sb 07/05/16

359 ALINEAMIENTO DE COLUMNAS 7 das vie 29/04/16 jue 05/05/16 207FC+10 das;220 29/04 05/05
360 SOLDADURA DE TOPES Y FIJACION FINAL 7 das dom 01/05/16sb 07/05/16 359CC+2 das 01/05 07/05
361 VIGAS Y VIGUETAS PISO 2 34 das dom 08/05/16vie 10/06/16

362 CAMBIO EN NIVEL DE TECHO EN PISO 2 15 das dom 08/05/16dom 22/05/16 360 08/05 22/05
363 MONTAJE DE VIGAS METALICAS 10 das lun 23/05/16 mi 01/06/16 362 23/05 01/06
364 SOLDADURA DE VIGAS Y VIGUETAS 10 das mi 25/05/16 vie 03/06/16 363CC+2 das 25/05 03/06
365 AJUSTE GENERAL DE VIGAS Y VIGUETAS 10 das vie 27/05/16 dom 05/06/16 364CC+2 das 27/05 05/06
366 COLOCACION Y SOLDADURA DE ARRIOSTRES 5 das lun 06/06/16 vie 10/06/16 365 06/06 10/06
367 LOSA COLABORANTE DECK PISO 2 S3 - CLINICA VET 12 das vie 10/06/16 mar 21/06/16

368 MONTAJE DE PLACAS COLABORANTES DECK 4 das vie 10/06/16 lun 13/06/16 366FC-1 da 10/06 13/06

Tarea Tarea crtica resumida Resumen inactivo Fecha lmite


Divisin Hito resumido Tarea manual Tarea crtica
Hito Progreso resumido Slo duracin Progreso
Proyecto: UCSUR COMPLETO
Fecha: lun 06/02/17 Resumen Tareas externas Informe de resumen manual Progreso manual
Resumen del proyecto Hito externo Resumen manual
Agrupar por sntesis Tarea inactiva Slo el comienzo
Tarea resumida Hito inactivo Slo fin

Pgina 10
Id ModoNombre de tarea Duracin
Comienzo Fin Predecesoras
de
tarea 26 oct '15 30 nov '15 04 ene '16 08 feb '16 14 mar '16 18 abr '16 23 may '16 27 jun '16 01 ago '16 05 sep '16
369 COLOCACION DE TOPES EN DECK, APUNTALAMIENTO 2 das dom 12/06/16lun 13/06/16 368CC+2 das 12/06 13/06
370 FIJACION DE FRISOS PERIMETRALES 3 das dom 12/06/16mar 14/06/16 368CC+2 das 12/06 14/06
371 ACERO DE REFUERZO, INST. SANIT., II.EE 3 das mar 14/06/16 jue 16/06/16 370CC+2 das 14/06 16/06
372 NUEVAS INSTALACIONES ELCTRICAS Y SANITARIAS EN TECHO 3 das vie 17/06/16 dom 19/06/16 371 17/06 19/06
373 CONCRETO EN LOSA COLABORANTE 2 das lun 20/06/16 mar 21/06/16 372 20/06 21/06
374 OTRAS ESTRUCTURAS METALICAS 27 das mar 07/06/16 dom 03/07/16

375 MONTAJE DE ESTRUCTURA PARA SOPORTE DE DRYWALL Y 5 das mar 07/06/16 sb 11/06/16 365FC+1 da 07/06 11/06
VENTANAS

376 REPLANTEO DE REFORZAMIENTO DE ESTRUCTURA PARA 10 das dom mar 21/06/16 375 12/06 21/06
SOPORTE DE DRYWALL EN FACHADA 12/06/16

377 INCOMPATIBILIZACIN ARQUITECTURA DE ESCALERA - NO 5 das mi 22/06/16 dom 26/06/16 376 22/06 26/06
CUMPLE CON RNE

378 MONTAJE DE ESTRUCTURA DE ESCALERAS PISO 2 3 das lun 27/06/16 mi 29/06/16 377 27/06 29/06
379 FIJACIN DE ESTRUCTURA Y PELDAOS 2 das jue 30/06/16 vie 01/07/16 378 30/06 01/07
380 CONCRETO EN PELDAOS DE ESCALERAS 2 das sb 02/07/16 dom 03/07/16 379 02/07 03/07
381 ARQUITECTURA 60 das lun 06/06/16 jue 04/08/16

382 CONTRAPISO 2 das lun 06/06/16 mar 07/06/16

383 CONTRAPISO PULIDO / SEMIPULIDO e= 5 CM. 2 das lun 06/06/16 mar 07/06/16 365 06/06 07/06
384 MUROS Y TABIQUES SECTOR 2 - CV Y UZYT 44 das mi 08/06/16 jue 21/07/16

385 MURO LADRILLO KK CABEZA 3 das mi 08/06/16 vie 10/06/16 383 08/06 10/06
386 MURO LADRILLO KK SOGA 3 das vie 10/06/16 dom 12/06/16 385CC+2 das 10/06 12/06
387 TABIQUES DE DRYWALL INTERIORES NIVEL 2 12 das mi 22/06/16 dom 03/07/16 375;373 22/06 03/07
388 TABIQUES DE DRYWALL EXTERIORES NIVEL 2 10 das sb 02/07/16 lun 11/07/16 387FC-2 das 02/07 11/07
389 MODIFICACIN DE MUROS Y TABIQUES DE DRYWALL EN CUARTO 5 das mar 12/07/16 sb 16/07/16 388 12/07 16/07
ELCTRICO

390 CIELORRASO DE DRYWALL NIVEL 2 7 das vie 15/07/16 jue 21/07/16 389FC-2 das 15/07 21/07
391 REVOQUES ENLUCIDOS Y MOLDURAS 8 das dom 12/06/16dom 19/06/16

392 TARRAJEO EN MUROS INTERIORES 4 das dom 12/06/16mi 15/06/16 386CC+2 das 12/06 15/06
393 TARRAJEO EN MUROS EXTERIORES 4 das jue 16/06/16 dom 19/06/16 392 16/06 19/06
394 PISOS Y PAVIMENTOS 9 das mar 19/07/16 mi 27/07/16

395 PISO EN REA DE LABORATORIOS 5 das mar 19/07/16 sb 23/07/16 390FC-3 das 19/07 23/07
396 PISO EN REA DE AULAS 7 das jue 21/07/16 mi 27/07/16 395CC+2 das 21/07 27/07
397 PISO DE VIDRIO 4 das dom 24/07/16mi 27/07/16 396CC+3 das 24/07 27/07
398 PISO CERAMICO 30X30 EN BAOS 9 das sb 23/07/16 dom 31/07/16

399 PISO CERAMICO EN BAOS 6 das sb 23/07/16 jue 28/07/16 396CC+2 das 23/07 28/07
400 ZOCALO DE CERAMICA EN BAOS (H=2.10MTS) 6 das sb 23/07/16 jue 28/07/16 396CC+2 das 23/07 28/07
401 CONTRAZOCALO CEMENTO PULIDO 5 das mi 27/07/16 dom 31/07/16 400FC-2 das 27/07 31/07
402 CARPINTERIA DE MADERA 7 das jue 28/07/16 mi 03/08/16

403 PUERTAS EN SSHH (0.90X2.10) 2 das jue 28/07/16 vie 29/07/16 399FC-1 da 28/07 29/07
404 PUERTAS EN LABORATORIOS (1.60X2.40) 4 das sb 30/07/16 mar 02/08/16 403CC+2 das 30/07 02/08

Tarea Tarea crtica resumida Resumen inactivo Fecha lmite


Divisin Hito resumido Tarea manual Tarea crtica
Hito Progreso resumido Slo duracin Progreso
Proyecto: UCSUR COMPLETO
Fecha: lun 06/02/17 Resumen Tareas externas Informe de resumen manual Progreso manual
Resumen del proyecto Hito externo Resumen manual
Agrupar por sntesis Tarea inactiva Slo el comienzo
Tarea resumida Hito inactivo Slo fin

Pgina 11
Id ModoNombre de tarea Duracin
Comienzo Fin Predecesoras
de
tarea 26 oct '15 30 nov '15 04 ene '16 08 feb '16 14 mar '16 18 abr '16 23 may '16 27 jun '16 01 ago '16 05 sep '16
405 PUERTAS EN AULAS 4 das dom 31/07/16mi 03/08/16 404CC+1 da 31/07 03/08
406 CARPINTERIA DE ALUMINIO 10 das mi 20/07/16 vie 29/07/16

407 VENTANAS 7 das mi 20/07/16 mar 26/07/16

408 VENTANAS EN SSHH 2 das mi 20/07/16 jue 21/07/16 415CC+2 das 20/07 21/07
409 VENTANAS EN OFICINAS 3 das vie 22/07/16 dom 24/07/16 408CC+2 das 22/07 24/07
410 VENTANAS EN LABORATORIOS 3 das dom 24/07/16mar 26/07/16 409CC+2 das 24/07 26/07
411 MAMPARAS 3 das mi 27/07/16 vie 29/07/16

412 MAMPARAS EN OFICINAS Y LABORATORIOS 3 das mi 27/07/16 vie 29/07/16 410 27/07 29/07
413 PINTURA SECTOR 2 - CV Y UZYT 30 das mi 06/07/16 jue 04/08/16

414 PINTURA EN MUROS EXTERIORES 1RA MANO 12 das mi 06/07/16 dom 17/07/16 388CC+4 das 06/07 17/07
415 PINTURA EN MUROS INTERIORES 1RA MANO 10 das lun 18/07/16 mi 27/07/16 414 18/07 27/07
416 PINTURA EN MUROS EXTERIORES 2DA MANO 10 das lun 18/07/16 mi 27/07/16 414 18/07 27/07
417 PINTURA EN MUROS INTERIORES 2DA MANO 8 das jue 28/07/16 jue 04/08/16 416 28/07 04/08
418 INSTALACIONES SANITARIAS 29 das jue 07/07/16 jue 04/08/16

419 RED SISTEMA DE AGUA FRIA CV 11 das jue 07/07/16 dom 17/07/16

420 SALIDAS DE AGUA FRIA 5 das jue 07/07/16 lun 11/07/16

421 TUBERIAS PPR 1/2", 3/4",1", 1 1/2" 5 das jue 07/07/16 lun 11/07/16 388CC+5 das 07/07 11/07
422 VALVULAS 6 das mar 12/07/16 dom 17/07/16

423 COLOCACIN DE VALVULAS DE COMPUERTA 1/2", 3/4", 1", 1 1/2" 6 das mar 12/07/16 dom 17/07/16 421 12/07 17/07
424 RED SISTEMA DE DEAGUE CV 24 das mar 12/07/16 jue 04/08/16

425 SALIAS DE DESAGUE 5 das mar 12/07/16 sb 16/07/16

426 TUBERIA PVC C-10 DE 1/2 ",4" 5 das mar 12/07/16 sb 16/07/16 421 12/07 16/07
427 EQUIPAMIENTO SANITARIO EN BATERIAS DE BAOS 6 das sb 30/07/16 jue 04/08/16

428 COLOCACION DE PANELES DIVISORIOS MODULARES 4 das sb 30/07/16 mar 02/08/16 401CC+3 das;426 30/07 02/08
429 COLOCACIN DE ACCESORIOS 4 das lun 01/08/16 jue 04/08/16 428CC+2 das 01/08 04/08
430 INSTALACIONES ELECTRICAS 59 das dom 05/06/16mar 02/08/16

431 SALIDAS ELCTRICAS: FUERZA E ILUMINACION 35 das dom 05/06/16sb 09/07/16

432 SALIDAS DE FUERZA: NORMAL, ESTABILIZADAS, UNIPOLARES, BIPOLARES,


2 das AA.
dom 05/06/16lun 06/06/16 383FC-3 das 05/06 06/06
433 SALIDA DE INTERRUMPTORES UNIPOLARES, CONMUTACIN. 3 das jue 07/07/16 sb 09/07/16 388CC+5 das 07/07 09/07
434 TUBERA ELCTRICA TABIQUES Y FALSO CIELO 4 das sb 09/07/16 mar 12/07/16

435 TUBERIA CONDUIT EMT DE 15mm, 20mm,25mm 4 das sb 09/07/16 mar 12/07/16 433CC+2 das 09/07 12/07
436 CAJAS DE PASE 5 das lun 11/07/16 vie 15/07/16

437 CAJA DE PASE OCTOGONAL 100x55 mm EN CIELO RASO 4 das lun 11/07/16 jue 14/07/16 435CC+2 das 11/07 14/07
438 CAJA DE PASE DE 550x550x100, 300x300x100 , 250x250x100, 200x200x100,
3 das 150x150x100
mi 13/07/16
mm vie 15/07/16 437CC+2 das 13/07 15/07
439 BANDEJA ELECTRICA 3 das sb 16/07/16 lun 18/07/16

440 BANDEJA ELECTRICA 300x100 3 das sb 16/07/16 lun 18/07/16 438 16/07 18/07
441 CABLES Y CONDUCTORES 7 das mar 19/07/16 lun 25/07/16

442 CABLEADO DE 2-1x4mm2 + 1x2.5mm2 NH 80 - 20mm PVC SAP 7 das mar 19/07/16 lun 25/07/16 440 19/07 25/07
443 PRUEBAS ELECTRICAS 2 das mar 26/07/16 mi 27/07/16

Tarea Tarea crtica resumida Resumen inactivo Fecha lmite


Divisin Hito resumido Tarea manual Tarea crtica
Hito Progreso resumido Slo duracin Progreso
Proyecto: UCSUR COMPLETO
Fecha: lun 06/02/17 Resumen Tareas externas Informe de resumen manual Progreso manual
Resumen del proyecto Hito externo Resumen manual
Agrupar por sntesis Tarea inactiva Slo el comienzo
Tarea resumida Hito inactivo Slo fin

Pgina 12
Id ModoNombre de tarea Duracin
Comienzo Fin Predecesoras
de
tarea 26 oct '15 30 nov '15 04 ene '16 08 feb '16 14 mar '16 18 abr '16 23 may '16 27 jun '16 01 ago '16 05 sep '16
444 PRUEBA DE AISLAMIENTO A SISTEMAS ELECTRICOS 2 das mar 26/07/16 mi 27/07/16 442 26/07 27/07
445 TABLEROS ELECTRICOS 5 das sb 23/07/16 mi 27/07/16

446 SUMINISTRO E INSTAL. DE TABLEROS 5 das sb 23/07/16 mi 27/07/16 442FC-3 das 23/07 27/07
447 APARATOS ELECTRICOS 6 das jue 28/07/16 mar 02/08/16

448 SUMINISTRO DE LUMINARIAS 2 das sb 30/07/16 dom 31/07/16 332FF 30/07 31/07
449 SUMINISTRO E INSTALACIN DE LUMINARIAS, BRAQUETS, 2 das lun 01/08/16 mar 02/08/16 448 01/08 02/08
EMERGENCIAS.

450 SUMINISTRO E INSTALACIN DE PLACAS TOMACORRIENTES E 2 das jue 28/07/16 vie 29/07/16 444 28/07 29/07
INTERRUPTORES.

451 ALARMA CONTRAINCENDIO 5 das jue 28/07/16 lun 01/08/16

452 SALIDA DE DESTECTOR DE TEMPERATURA, HUMO, MOVIMIENTO 5 das jue 28/07/16 lun 01/08/16 444 28/07 01/08
453 PANEL CENTRAL DE DETECCIN DE ALARMA, SIRENA 5 das jue 28/07/16 lun 01/08/16 444 28/07 01/08
454 CCTV 4 das sb 30/07/16 mar 02/08/16

455 PANEL CONTROL DE COMUNICACIONES: CENTRAL DE DATA, CENTRAL


4 das
TELEFONICA
sb 30/07/16 mar 02/08/16 453FC-3 das 30/07 02/08
456 OBRAS EXTERIORES 26 das lun 27/06/16 vie 22/07/16

457 ACCESOS PEATONALES Y VEHICULARES 26 das lun 27/06/16 vie 22/07/16

458 MONTAJE DE ESTRUCTURA DE ESCALERAS EXTERIOR 6 das lun 27/06/16 sb 02/07/16 373FC+5 das 27/06 02/07
459 FIJACIN DE ESTRUCTURA Y PELDAOS 3 das dom 03/07/16mar 05/07/16 458 03/07 05/07
460 CONCRETO EN PELDAOS DE ESCALERAS 3 das mi 06/07/16 vie 08/07/16 459 06/07 08/07
461 CONFORMACION DE PLATAFORMADO CON AFIRMADO 8 das sb 09/07/16 sb 16/07/16 460 09/07 16/07
462 COLOCACIN DE BASE ARENA Y ADOQUINADO PEATONAL Y 8 das vie 15/07/16 vie 22/07/16 461FC-2 das 15/07 22/07
VEHICULAR

463 FIN 0 das dom 07/08/16dom 07/08/16 417;160 07/08

Tarea Tarea crtica resumida Resumen inactivo Fecha lmite


Divisin Hito resumido Tarea manual Tarea crtica
Hito Progreso resumido Slo duracin Progreso
Proyecto: UCSUR COMPLETO
Fecha: lun 06/02/17 Resumen Tareas externas Informe de resumen manual Progreso manual
Resumen del proyecto Hito externo Resumen manual
Agrupar por sntesis Tarea inactiva Slo el comienzo
Tarea resumida Hito inactivo Slo fin

Pgina 13

You might also like