Professional Documents
Culture Documents
LA MEG-1 PROJECT
MODULE FABRICATION WORK
LA MEG-1 PROJECT
MODULE FABRICATION WORK
CONTENTS
1. ITP
ITP No.: 1007-0001 Inspection and Test Plan for Piping Work
1.1 Abbreviation:
I - Full Inspection by Subcontractor: The party is responsible for undertaking the Inspection / Test
and preparing inspection / test report.
V - Verification of record: It means an activity undertaken by the party to determine the suitability,
adequacy and effectiveness of an activity or inspection to achieve specified objectives.
W - Witness Point: RFI is required. The Party shall optionally witness. It means a specifically
identified step during construction and testing at which the work should be inspected by
SUBCONTRACTOR, CONTRACTOR and COMPANY.
SUBCONTRACTOR / CONTRACTOR can proceed with inspection even if Party is absent. Party
shall request Contractor to submit particular inspection report that party requires to sign.
S - Surveillance: RFI is not required. The party shall spot witness during job execution.
Certification, if any, shall be spot reviewed.
S/C - SUBCONTRACTOR: Means the organization to which SECL has awarded the
contract for module fabrication/assembly works in accordance with applicable
procedures and specifications
1.2 Definition:
rd
3 : For Welder Performance Qualification Test, witness by an Independent third party is
required. For NDE services, inspection of welds (NDE) is carried out by an independent third
party.
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 3 of 47
LA MEG-1 PROJECT
MODULE FABRICATION WORK
2. ATTACHMENT
2.1 Quality Control Report/Record
Form QCR No.: 1007-001: MATERIAL INSPECTION REPORT
Form QCR No.: 1007-002: DAILY ELECTRODE DRYING AND HOLDING RECORD
Form QCR No.: 1007-003: DAILY ELECTRODE ISSUANCE AND RETURN RECORD
Form QCR No.: 1007-004: DAILY WELDING VISUAL INSPECTION REPORT
Form QCR No.: 1007-005: INSPECTION SUMMARY REPORT FOR RADIOGRAPHIC
EXAMINATION
Form QCR No.: 1007-006: LIQUID PENETRANT EXAMINATION REPORT
Form QCR No.: 1007-007: MAGNETIC PARTICLE EXAMINATION REPORT
LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN
Inspection Responsibility
Assignmment
Item No. Description of Activity Reference Document Acceptance Criteria Verifying Document* Remark
C
S/C OWN
CON QC
.
1 Material Inspection
S-000-1670-000 1007-001
S-000-1360-0004V 4V_Table 1
1.2 Color Code Check I W S
Para.3
S-000-1670-000
S-000-16970-0007V 7V_Para.3.4
1.3 PMI Inspection, if not verified W I S
Para.3.3.2
LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN
Inspection Responsibility
Assignmment
Item No. Description of Activity Reference Document Acceptance Criteria Verifying Document* Remark
C
S/C OWN
CON. QC
1 Material Inspection
S-000-1670-0006V 1007-002,
3.1 Welding Electrode Control I S S
Para. 8.4 1007-003
S-000-1670-0006V
3.3 Fit-up Check WPS 1007-004 I S S
Para. 7
S-000-1670-0006V Monitoring I
3.4 Welding Monitoring WPS S S
Para. 8.4 Sheet
S-000-1670-0006V ASME B31.3
Visual Inspection of Weld 1007-004
3.5 I W S
(Fit-up, Root pass, Cap pass) Table 8 Table 341.3.2
S-000-1670-000
S-000-1670-0006V
Intermediate Hydrogen Diffusion 6V 1007-004 I S S
3.6
Treatment for low alloy steel Para 8.4.11
Table 4
Radiographic Examination (Film S-000-1670-0006V
ASME B31.3
3.7 Review)
Para 11.4 & Table 8
Table 341.3.2
S-000-1630-0002V
for Normal, 1007-005 R I R
Para 11.0 Category M/D
and Severe
Subcontractors
Cyclic Service
Approved Procedure
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 6 of 47
LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 7 of 47
LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN
LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN
S-000-1670-0006V
Table 8
S-000-1630-0002V ASME B31.3
3.8 Dye Penetrant Examination 1007-006 S I S
Para 11.0 Table 341.3.2
Subcontractors
Approved Procedure
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 9 of 47
LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN
S-000-1670-0006V
Para 11.9 & Table 8
S-000-1630-0002V
ASME B31.3
3.9 Magnetic Particle Examination Para 11.0 1007-007 S I S
Table 341.3.2
Subcontractors
Approved Procedure
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 10 of 47
LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN
LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN
S-000-1670-0006V
Para 11.7 Ferrite level
3.11 Ferrite Content Check 1007-009 W I S
Subcontractors 3% to 10 %
Approved Procedure
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 12 of 47
LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN
LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN
S-000-1670-0006V
S-000-1670-000
Para 9 6V
3.12 Post Weld Heat Treatment (PWHT) 1007-010 S I R
Subcontractors Table 5.1
Approved Procedure
LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN
S-000-1670-0006V
S-000-1670-000
Para 11.5 6V
3.14 Hardness Test 1007-011 S I R
Subcontractors Para. 11.5.5
Approved Procedure
CMS Log Sheet
3.15 Welding Log Sheet I I R
(1007-CMS)
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 15 of 47
LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN
S-000-1670-0006V S-000-1670-000
Dimension, Configuration and 6V
3.16 Para 4 1007-012 I W S/R
Flange Surface Check
Para. 4.4
ASME B31.3
Para. 4.6
Subcontractors
3.17 Pipe Internal Cleaning I W S
approved procedure No Debris 1007-012
S-000-1670-0006V
3.18 Orifice Flange Internal Check Ground Flush 1007-013 I W S
Para 4.5
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 16 of 47
LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN
LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN
ASME B31.3
Para. 328.5.4
3.19 Reinforcing Pad Leak Test No Leakage 1007-014 I W S
Subcontractors
approved procedure
Visual and Dimensional Inspection
3.20 AWS D1.1 As per DWG 1007-022 I W S
for Support
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 18 of 47
LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN
S-000-13A0-0001V
3.21 Painting Inspection 9000-202 &203 I W S
(Refer to ITP for Painting Work)
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 19 of 47
LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN
LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN
LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN
Signature
Date
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 22 of 47
LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 23 of 47
LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN
LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN
LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN
Signature
Date
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 26 of 47
LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN
LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 28 of 47
LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 29 of 47
LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN
LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN
LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN
LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 33 of 47
LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN
Legend: Welding Type: BW (Butt), FW (Fillet), SW (Socket Weld), TH (Threaded), FJ (Flange Joint), CW (Branch Welding), RP (Re inforcing Pad Joint)
Signature
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 34 of 47
LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN
Date
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 35 of 47
LA MEG-1 PROJECT
MODULE FABRICATION WORK
RADIOGRAPHIC EXAMINATION
Location: Sub-Contractor:
Signature
Date
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 36 of 47
LA MEG-1 PROJECT
MODULE FABRICATION WORK
Location: Sub-Contractor:
Signature
Date
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 37 of 47
LA MEG-1 PROJECT
MODULE FABRICATION WORK
Location: Sub-Contractor:
Stage of
Prepared Edge After P.W.H.T Other
Examination
As Welded After hydro Test
Instrument Type
Ref. Indicator
Current AC DC AT
Time o
Sec Temperature C
Density
Signature
Date
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 38 of 47
LA MEG-1 PROJECT
MODULE FABRICATION WORK
Location: Sub-Contractor:
Location:
Instrument Used:
Instrument Serial No.:
Material Type:
Isometric No.:
Signature
Date
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 39 of 47
LA MEG-1 PROJECT
MODULE FABRICATION WORK
Notes:
Name of Examiner/
Inspector
Signature
Date
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 40 of 47
LA MEG-1 PROJECT
MODULE FABRICATION WORK
Signature
Date
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 41 of 47
LA MEG-1 PROJECT
MODULE FABRICATION WORK
MEASUREMEN
FURNACE HEATING: 10% of Each Lot Local: Each Welding Joint
T CONDITION
Name of Examiner/
Inspector
Signature
Date
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 42 of 47
LA MEG-1 PROJECT
MODULE FABRICATION WORK
Flange Pipe
Dimension
Surface Cleaning Remarks
No. Drawing No. Spool No. Piece No. Check
Check Check
Signature
Date
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 43 of 47
LA MEG-1 PROJECT
MODULE FABRICATION WORK
Result
No. ISO. DWG. No. Line No. Joint No. Remarks
Accept Reject
NOTES:
Signature
Date
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 44 of 47
LA MEG-1 PROJECT
MODULE FABRICATION WORK
PAUT/TOFD Probe
Type PAUT PAUT TOFD TOFD
Probes Model
Serial No.
Wedge Model
Probe Aperture(mm)
Frequency (MHz)
Remark:
Signature
Date
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 45 of 47
LA MEG-1 PROJECT
MODULE FABRICATION WORK
Support
Support Dimension NDE
No. Drawing Size Q'ty Material Welding Result Remark
Type Check (if required)
No.
Signature
Date
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 46 of 47
LA MEG-1 PROJECT
MODULE FABRICATION WORK
SYSTEM No.
CHECK ITEMS
Final Inspection
2. Final Appearance
COMMENT:
SIGNATURE
LA MEG-1 PROJECT
MODULE FABRICATION WORK