You are on page 1of 47

Project No Unit Doc.

Type Serial no Rev Page


PC-0380 E11.3 0 1 of 47

LA MEG-1 PROJECT
MODULE FABRICATION WORK

PROJECT QUALITY PLAN

Inspection and Test Plan


For
Piping Work
This ITP shall applied for ASME B31.3 & B31.1 Metallic
Piping, not applied for Non-Metallic nor B31.4

Rev Date Revision Status Prepared by Approved by

Responsible Company Prepared by Checked by Aproved by


Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 2 of 47

LA MEG-1 PROJECT
MODULE FABRICATION WORK

PROJECT QUALITY PLAN

CONTENTS
1. ITP
ITP No.: 1007-0001 Inspection and Test Plan for Piping Work
1.1 Abbreviation:
I - Full Inspection by Subcontractor: The party is responsible for undertaking the Inspection / Test
and preparing inspection / test report.

V - Verification of record: It means an activity undertaken by the party to determine the suitability,
adequacy and effectiveness of an activity or inspection to achieve specified objectives.

H - Hold Point: RFI is required.


The party shall witness and sign for acceptance the inspection checking form.
The Subcontractor (or Contractor) is not allowed to proceed with the works until it has been
inspected by the responsible party in CONTRACTOR and COMPANY organization as stated within
requirements. Further following certification shall be submitted for review.

W - Witness Point: RFI is required. The Party shall optionally witness. It means a specifically
identified step during construction and testing at which the work should be inspected by
SUBCONTRACTOR, CONTRACTOR and COMPANY.
SUBCONTRACTOR / CONTRACTOR can proceed with inspection even if Party is absent. Party
shall request Contractor to submit particular inspection report that party requires to sign.

S - Surveillance: RFI is not required. The party shall spot witness during job execution.
Certification, if any, shall be spot reviewed.

S/C - SUBCONTRACTOR: Means the organization to which SECL has awarded the
contract for module fabrication/assembly works in accordance with applicable
procedures and specifications

1.2 Definition:
rd
3 : For Welder Performance Qualification Test, witness by an Independent third party is
required. For NDE services, inspection of welds (NDE) is carried out by an independent third
party.
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 3 of 47

LA MEG-1 PROJECT
MODULE FABRICATION WORK

PROJECT QUALITY PLAN

2. ATTACHMENT
2.1 Quality Control Report/Record
Form QCR No.: 1007-001: MATERIAL INSPECTION REPORT
Form QCR No.: 1007-002: DAILY ELECTRODE DRYING AND HOLDING RECORD
Form QCR No.: 1007-003: DAILY ELECTRODE ISSUANCE AND RETURN RECORD
Form QCR No.: 1007-004: DAILY WELDING VISUAL INSPECTION REPORT
Form QCR No.: 1007-005: INSPECTION SUMMARY REPORT FOR RADIOGRAPHIC
EXAMINATION
Form QCR No.: 1007-006: LIQUID PENETRANT EXAMINATION REPORT
Form QCR No.: 1007-007: MAGNETIC PARTICLE EXAMINATION REPORT

Form QCR No.: 1007-008: POSITIVE MATERIAL IDENTIFICATION REPORT


Form QCR No.: 1007-009: FERRITE CONTENT TESTING REPORT
Form QCR No.: 1007-010: POST WELD HEAT TREATMENT REPORT
Form QCR No.: 1007-011: HARDNESS TEST REPORT
Form QCR No.: 1007-012: DIMENSION AND CLEANING INSPECTION REPORT
Form QCR No.:1007-012A :DIMENTION AND CLEANING INSPECTION REPORT AT SITE
CONSTRUCTION
Form QCR No.: 1007-013: ORIFICE FLANGE GROUND FLUSH INSPECTION REPORT
Form QCR No.: 1007-014: PNEUMATIC TEST REPORT FOR REINFORCING PAD
Form QCR No.: 1007-015: PHASED ARRAY ULTRASONIC EXAMINATION REPORT
Form QCR No.: 1007-021: TORQUE / TENSIONING CONTROL RECORD

Form QCR No.: 1007-022: SUPPORT FABRICATION INSPECTION REPORT


Form QCR No.: 1007-023: INSPECTION REPORT FOR FINAL PAINTING WORK
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 4 of 47

LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN

Inspection Responsibility
Assignmment
Item No. Description of Activity Reference Document Acceptance Criteria Verifying Document* Remark
C
S/C OWN
CON QC
.
1 Material Inspection

1.1 Marking Inspection S-000-1360-0004V Para. 4.1.3 I W S

S-000-1670-000 1007-001
S-000-1360-0004V 4V_Table 1
1.2 Color Code Check I W S
Para.3

S-000-1670-000
S-000-16970-0007V 7V_Para.3.4
1.3 PMI Inspection, if not verified W I S
Para.3.3.2

2 Welding and NDE


S-000-1670-0006V
2.1 Welding Procedure Qualification WPS/PQR I R/W R
Para. 8 & 10
S-000-1670-0006V Welder
2.2 Welder Performance Qualification I R/W W R
Para. 8 Certificates
S-000-1670-0006V NDE
2.3 NDE Procedure R I R
Para 11 Procedure
NDT Personnel Qualification S-000-1670-0006V NDE Personnel
2.4 (Including PMI Operator) Certificates R I R
Para. 11.3.3
3 Pre-Fabrication
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 5 of 47

LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN

Inspection Responsibility
Assignmment
Item No. Description of Activity Reference Document Acceptance Criteria Verifying Document* Remark
C
S/C OWN
CON. QC

1 Material Inspection

S-000-1670-0006V 1007-002,
3.1 Welding Electrode Control I S S
Para. 8.4 1007-003

MT aft`er Thermal Cutting for low- S-000-1670-0006V ASME B31.3


3.2 alloy steel Para 5 Table 341.3.2 S I S

S-000-1670-0006V
3.3 Fit-up Check WPS 1007-004 I S S
Para. 7
S-000-1670-0006V Monitoring I
3.4 Welding Monitoring WPS S S
Para. 8.4 Sheet
S-000-1670-0006V ASME B31.3
Visual Inspection of Weld 1007-004
3.5 I W S
(Fit-up, Root pass, Cap pass) Table 8 Table 341.3.2
S-000-1670-000
S-000-1670-0006V
Intermediate Hydrogen Diffusion 6V 1007-004 I S S
3.6
Treatment for low alloy steel Para 8.4.11
Table 4
Radiographic Examination (Film S-000-1670-0006V
ASME B31.3
3.7 Review)
Para 11.4 & Table 8
Table 341.3.2
S-000-1630-0002V
for Normal, 1007-005 R I R
Para 11.0 Category M/D
and Severe
Subcontractors
Cyclic Service
Approved Procedure
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 6 of 47

LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 7 of 47

LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN

Verifying Inspection Mode


Item Reference Acceptance Document
Activity Remarks
No. Documents Criteria (QCR Form C
No.)
SUB EMP
CON 3rd
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 8 of 47

LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN

S-000-1670-0006V
Table 8
S-000-1630-0002V ASME B31.3
3.8 Dye Penetrant Examination 1007-006 S I S
Para 11.0 Table 341.3.2

Subcontractors
Approved Procedure
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 9 of 47

LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN

S-000-1670-0006V
Para 11.9 & Table 8
S-000-1630-0002V
ASME B31.3
3.9 Magnetic Particle Examination Para 11.0 1007-007 S I S
Table 341.3.2
Subcontractors
Approved Procedure
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 10 of 47

LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN

Positive Material Identification for S-000-1670-0007V S-000-1670-000


Welding Joint including adjacent Para 3.3.3 Table 2 6V 1007-008 W I S
3.10
Base Materials. Subcontractors
Approved Procedure Para. 3.4
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 11 of 47

LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN

S-000-1670-0006V
Para 11.7 Ferrite level
3.11 Ferrite Content Check 1007-009 W I S
Subcontractors 3% to 10 %
Approved Procedure
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 12 of 47

LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN

Verifying Inspection Mode


Item Reference Acceptance Document
Activity Remarks
No. Documents Criteria (QCR Form C
No.)
SUB OWN
CON 3rd
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 13 of 47

LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN

S-000-1670-0006V
S-000-1670-000
Para 9 6V
3.12 Post Weld Heat Treatment (PWHT) 1007-010 S I R
Subcontractors Table 5.1
Approved Procedure

S-000-1670-0006V ASME B31.3 (All NDE


3.13 NDE after PWHT S I S
Para 11.3.2 Table 341.3.2 Report)
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 14 of 47

LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN

S-000-1670-0006V
S-000-1670-000
Para 11.5 6V
3.14 Hardness Test 1007-011 S I R
Subcontractors Para. 11.5.5
Approved Procedure
CMS Log Sheet
3.15 Welding Log Sheet I I R
(1007-CMS)
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 15 of 47

LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN

S-000-1670-0006V S-000-1670-000
Dimension, Configuration and 6V
3.16 Para 4 1007-012 I W S/R
Flange Surface Check
Para. 4.4
ASME B31.3
Para. 4.6
Subcontractors
3.17 Pipe Internal Cleaning I W S
approved procedure No Debris 1007-012
S-000-1670-0006V
3.18 Orifice Flange Internal Check Ground Flush 1007-013 I W S
Para 4.5
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 16 of 47

LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN

Verifying Inspection Mode


Item Reference Acceptanc Document
Activity Remarks
No. Documents e Criteria (QCR Form C
No.)
SUB OWN
CON 3rd
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 17 of 47

LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN

ASME B31.3
Para. 328.5.4
3.19 Reinforcing Pad Leak Test No Leakage 1007-014 I W S
Subcontractors
approved procedure
Visual and Dimensional Inspection
3.20 AWS D1.1 As per DWG 1007-022 I W S
for Support
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 18 of 47

LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN

S-000-13A0-0001V
3.21 Painting Inspection 9000-202 &203 I W S
(Refer to ITP for Painting Work)
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 19 of 47

LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN

Service class: Report No.:


MATERIAL INSPECTION REPORT
Location: Date of inspection:

Item Material Heat No./


Description Quantity Unit Rating/SCH Cert. No. Color Code Remarks
No. Grade Tag No.
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 20 of 47

LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN

Company Sub-Contractor Contractor Employer

Name of Examiner/ Inspector


Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 21 of 47

LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN

Signature

Date
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 22 of 47

LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 23 of 47

LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN

QCR No.: 1007-002

Service class: DAILY ELECTRODE DRYING AND Record No.

Location: HOLDING RECORD Sub-contractor


Welding Material Drying Holding Material
Oven Controller
Lot Certificate Brand Finish Temp.
No. DATE No. Remark
Type Size No. No. Name Starting Time Temp. Time Starting Time (Signature)
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 24 of 47

LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN

Company Sub-contractor Contractor Employer

Name of Examiner/ Inspector


Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 25 of 47

LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN

Signature

Date
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 26 of 47

LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN

QCR No.: 1007-003


Service class: DAILY ELECTRODE ISSUANCE AND Record No.

Location: RETURN RECORD Sub-Contractor


WELDER Welding Material
Material Controller
No. Date Issue Weight Return Weight (Signature) Remark
I.D No. Name Type Size Lot No. Certificate No. Brand Name
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 27 of 47

LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 28 of 47

LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 29 of 47

LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN

Company Sub-contractor Contractor Employer


Name of Examiner/ Inspector
Signature
Date
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 30 of 47

LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN

QCR No.: 1007-004

DAILY WELDING VISUAL INSPECTION REPORT

Service class: Report No.:

Location: Weld Type: Loc.:


Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 31 of 47

LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN

Welder No. Visual Inspection


Mat. Mat.
Spool Joint Spec Heat Spec Heat Sch/
Root
No. Drawing / Line No. No. No. No.1 No.2 Size Thk WPS No.
No.1 No.2 1 2 Fit-up Pass Completed
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 32 of 47

LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 33 of 47

LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN

Legend: Welding Type: BW (Butt), FW (Fillet), SW (Socket Weld), TH (Threaded), FJ (Flange Joint), CW (Branch Welding), RP (Re inforcing Pad Joint)

Loc. (Location): S: Shop Welding, F: Field Welding

Company Sub-Contractor Contractor Employer

Name of Examiner/ Inspector

Signature
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 34 of 47

LA MEG-1 PROJECT
MODULE FABRICATION WORK
``
PROJECT QUALITY PLAN

Date
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 35 of 47

LA MEG-1 PROJECT
MODULE FABRICATION WORK

PROJECT QUALITY PLAN

QCR No.: 1007-005

INSPECTION SUMMARY REPORT FOR

RADIOGRAPHIC EXAMINATION

Service class: Report No.:

Location: Sub-Contractor:

Welder No. Total No. Result


No. ISO. DWG. No. Line Class Joint No. Remarks
of film
1st 2nd Accept Reject

Company NDE Sub-Contractor Contractor Employer

Name of Examiner/ Inspector

Signature

Date
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 36 of 47

LA MEG-1 PROJECT
MODULE FABRICATION WORK

PROJECT QUALITY PLAN

QCR No.: 1007-006

LIQUID PENETRANT EXAMINATION REPORT


Service class: Report No.:

Location: Sub-Contractor:

Stage of Prepared Edge After P.W.H.T Other

Examination As Welded After Pressure Test

Preparation Grinding Machining Other


Type Color Contract Other
Penetrant Application Brushing Other
o
Temperature C Penetrant time min.

Water Washable Penetrants

Removal Post Emulsifying Penetrant Developing Dry Developer

Solvent Removal Penetrants Wet Developer

Line Welder No. Result


No. ISO DRAWING No. Joint No. Remarks
Class 1st 2nd Accept Reject

Company NDE Sub-Contractor Contractor Employer

Name of Examiner/ Inspector

Signature

Date
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 37 of 47

LA MEG-1 PROJECT
MODULE FABRICATION WORK

PROJECT QUALITY PLAN

QCR No.: 1007-007

MAGNETIC PARTICLE EXAMINATION REPORT

Service class: Report No.:

Location: Sub-Contractor:

Stage of
Prepared Edge After P.W.H.T Other
Examination
As Welded After hydro Test

Preparation Grinding Marching Other

Instrument Type

Ref. Indicator

Mag. Space Yoke Brushing Other

Current AC DC AT
Time o
Sec Temperature C

Particle Dry Wet Black Brown Fluorescent

Density

Line Welder No. Result


No. ISO DRAWING No. Joint No. Remarks
Class 1st 2nd Accept Reject

Company NDT Sub-Contractor Contractor Employer

Name of Examiner/ Inspector

Signature

Date
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 38 of 47

LA MEG-1 PROJECT
MODULE FABRICATION WORK

PROJECT QUALITY PLAN

QCR No.: 1007-008

POSITIVE MATERIAL IDENTIFICATION REPORT


(For Site Made Weldments)

Service class: Report No.:

Location: Sub-Contractor:

Location:
Instrument Used:
Instrument Serial No.:
Material Type:
Isometric No.:

Weld Metal Base Metal #1 Base Metal #2 Insp. Accept/


Weld No. Date
PMI Result PMI Result PMI Result Initials Reject

Company PMI Sub-Contractor Contractor Employer

Name of Examiner/ Inspector

Signature

Date
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 39 of 47

LA MEG-1 PROJECT
MODULE FABRICATION WORK

PROJECT QUALITY PLAN

QCR No.: 1007-009

FERRITE CONTENT TESTING REPORT

Location: ................ Report No: .. Date:


Sub-Contractor: .... ...
Service class: ..... Page of .....

INSTRUMENT USED: APPLICABLE SPECIFICATION

INSTRUMENT SERIAL No:

Recorded Values Result


Item of Ferrite (%) (Cap
Spool No. Joint No. Material of weld metal) Average Remarks
No.
Accept Reject
1 2 3

Notes:

Company NDT Sub-Contractor Contractor Employer

Name of Examiner/
Inspector

Signature

Date
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 40 of 47

LA MEG-1 PROJECT
MODULE FABRICATION WORK

PROJECT QUALITY PLAN

QCR No.: 1007-010

POST WELD HEAT TREATMENT REPORT

Location: ................ Report No: .. Date:


Sub-Contractor: .... ...
Service class: ..... Page of .....

The temperature rise rate was unrestricted from ambient to:


Heating rate: .. Soaking temperature: .. Holding

time: . Cooling rate: ...

Spool Line Joint Result


No Drawing No. No. Class Material No. Size Thickness Accept Reject

Note: Attached chart report no.: Calibration


record:

Company PWHT Sub-Contractor Contractor Employer

Name of Examiner/ Inspector

Signature

Date
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 41 of 47

LA MEG-1 PROJECT
MODULE FABRICATION WORK

PROJECT QUALITY PLAN

QCR No.: 1007-011

HARDNESS TEST REPORT

Location: Report No: .. Date:


................ Sub- ...
Contractor: ....
Page of .....
Service class: ..
...
PORTION OF
ITEM WELD H.A.Z. BASE
EXAMINATION

MEASUREMEN
FURNACE HEATING: 10% of Each Lot Local: Each Welding Joint
T CONDITION

EQUIPMENT POLDI (BRINELL METHOD) TELEBRINELLER

Hardness (HB) Result


Spool Joint
No. DWG. No. No. No. Remarks
Weld Base Accept Reject

Company NDT Sub-Contractor Contractor Employer

Name of Examiner/
Inspector

Signature

Date
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 42 of 47

LA MEG-1 PROJECT
MODULE FABRICATION WORK

PROJECT QUALITY PLAN

QCR No.: 1007-012

DIMENSION AND CLEANING INSPECTION REPORT

Location: ................ Report No: .. Date:


Sub-Contractor: .... ...
Service class: ..... Page of .....

Flange Pipe
Dimension
Surface Cleaning Remarks
No. Drawing No. Spool No. Piece No. Check
Check Check

Acc. Rej. Acc. Rej. Acc. Rej.

Note: By ASME B31.3


Acc.: Accepted, Rej.: Rejected

Company Sub-Contractor Contractor Employer


Name of Examiner/ Inspector

Signature

Date
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 43 of 47

LA MEG-1 PROJECT
MODULE FABRICATION WORK

PROJECT QUALITY PLAN

QCR No.: 1007-014

PNEUMATIC TEST REPORT FOR REINFORCING PAD

Location: ................ Report No: .. Date:


Sub-Contractor: .... ...
Service class: ..... Page of .....

Result
No. ISO. DWG. No. Line No. Joint No. Remarks
Accept Reject

NOTES:

Company Sub-Contractor Contractor Employer

Name of Examiner/ Inspector

Signature

Date
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 44 of 47

LA MEG-1 PROJECT
MODULE FABRICATION WORK

PROJECT QUALITY PLAN

QCR No.: 1007-015

PHASED ARRAY ULTRASONIC EXAMINATION REPORT

Service class: Reference Code: Report No.:

Location: Standard Block: Sub-Contractor:

Procedure No.: Reference Block: Acceptance Code:

Couplant: Block Temp.: Weld Type:

Cable Type/Length: Test Temp.: Surface Condition:

Equipment Model: Calibration Date: Screen H. Linearity:

PAUT/TOFD Probe
Type PAUT PAUT TOFD TOFD

Probes Model

Serial No.

Wedge Model

Probe Aperture(mm)

Frequency (MHz)

Identification Interpretation (mm)


No. Welder
Dia Thk Result Remark
ISO No. Joint No. No. Location l D Type of Type of a a/l a/t
Flaw defect

Remark:

l : Length a/l : Aspect Ratio

D: Depth a/t : Flaw

a : Flaw of Height Type of Flaw : Surface or Subsurface

Company NDE Sub-Contractor Contractor Employer

Name of Examiner / Inspector

Signature

Date
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 45 of 47

LA MEG-1 PROJECT
MODULE FABRICATION WORK

PROJECT QUALITY PLAN

QCR No.: 1007-022

SUPPORT FABRICATION INSPECTION REPORT

Project No.: Report No.:

Subcontractor: Inspection Date:

Support
Support Dimension NDE
No. Drawing Size Q'ty Material Welding Result Remark
Type Check (if required)
No.

Company SUBCONTRACTOR CONTRACTOR EMPLOYER


Name

Signature

Date
Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 46 of 47

LA MEG-1 PROJECT
MODULE FABRICATION WORK

PROJECT QUALITY PLAN

FINAL INSPECTION REPORT FOR PAINTING WORK


QCR No. 1007-025

SYSTEM No.

AREA / UNIT EQUIPMENT / LINE / PKG No


DWG No.

CHECK ITEMS

Painting System No. :

Check Item Result Remark

1. Final Coated Colour

Final Inspection

2. Final Appearance

COMMENT:

SIGNATURE

SUBCONTRACTOR CONTRACTOR EMPLOYER

NAME: NAME: NAME:

DATE: DATE: DATE


Project No Unit Doc.Type Serial no Rev Page
PC-0380 E11.3 0 47 of 47

LA MEG-1 PROJECT
MODULE FABRICATION WORK

PROJECT QUALITY PLAN

You might also like