You are on page 1of 1

Rate Amount

S. No Description Unit Quantity Remarks


Rs. Rs.
1 2 3 4 5 6 7

1 Excavation for Structures


Earthwork in excavation for structures as per drawing and
technical specifications Clause 305.1 including setting out,
construction of shoring and bracing, removal of stumps and
other deleterious material and disposal upto a lead of 50 m,
dressing of side

Note : Classifications of Earth Work Specification are as


per 302.2.1(a) of MORD and 301.2.1 of MORT&H
(I) Ordinary soil
(A) Manual Means
(i) Upto 3 m depth
Unit = cum
Taking output = 10 cum
a)Labour
Mate day -
Mazdoor (Unskilled) day 3.64 No. 268.75 978.25
b&c) Overheads & Contractors Profit 14.00% 978.25 136.96
Cost for 10 cum = a+b+c 1115.21
Rate per cum = (a+b+c)/10 111.52
Note : 1. Cost of dewatering may be added, where required, up to 5 per cent of labour cost. Assessment
for dewatering shall be made as per site conditions.
2. The cost of shoring and shuttering, where needed, may be added on cost of excavation for open
foundation.
3. The excavated earth if found suitable, can be used partly for backfilling in trenches & partly for road
work. Hence cost of disposal has not been added except for marshy soil. This note is common to all
cases of item 11.1 excluding 11.1 V
(B) Mechanical Means
i Upto 3 m depth
Unit = cum
Taking output = 240 cum
a)Labour
Mate day -
Mazdoor (Unskilled) day 8.32 268.75 2236.00
b) Machinery
Hydraulic Excavator 1 cum bucket capacity hour 6.00 2009.50 12057.00
c&d) Overheads & Contractors Profit 14.00% 14293.00 2001.02
Cost for 240 cum = a+b+c+d 16294.02
Rate per cum = (a+b+c+d)/240 67.89
Note : 1. Cost of dewatering upto 5% of a+b may be added, where required, up to 10 per cent of labour
cost. Assessment for dewatering shall be made as per site conditions.