You are on page 1of 97

Burtibang - Patihalne Road Project

Government of Nepal
Ministry of Physical Infrastructure and Transport
Department of Roads
BRIDGE PROJECT
Chakupat, Lalitpur.

Feasibility Study, Detailed Engineering Survey, Soil investigation, Hydrological Study and
Detailed Design of Bridges at Baglung District

District Labour Rate

Sn Description Unit Rate Remarks

1 Unskilled Labour M/d 550.00


2 Skilled Labour (Carpenter, masons) M/d 740.00
Skilled Labour (for blacktopping
3 M/d 740.00
works)
4 Supervisor / Fore man M/d 500.00
Length Man/Road Maintenance
5 M/d 450.00
Labour

District Market Construction Material Rate


Sn Description Unit Rate Remarks
1 Aggregate crushed
1.1 10mm Cum 2,600.00
1.2 20 mm Cum 2,600.00
1.3 40 mm Cum 2,600.00
Aggregate uncrushed ( River
2
single )
2.1 10mm Cum 1,750.00
2.2 20 mm Cum 1,750.00
2.3 40 mm Cum 1,750.00
3 Antistripping agent Additives Kg 323.50
4 Binding wire Kg 100.00
5 Bitumen 80 /100 Kg 92.60
6 Bolt Kg 180.00
7 Boulder / Rubble Cum 2,400.00
8 Brick No 17.00
9 Cement ( Indian ) Mt 16,000.00
10 Cement ( Nepali ) Mt 15,000.00
11 Diesel Lit 87.61
12 Enamel Paint Lit 400.00
13 Firewood Kg 10.00
14 Geotextile Sqm 86.00
15 GI Wire(heavy coated)
15.1 8 gauge Kg 101.00
15.2 10 gauge Kg 101.00

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

Sn Description Unit Rate Remarks


15.3 12 gauge Kg 101.00
Machine made double twisted
hexagonal mesh with size of 100 x
120mm including heavy coated GI
16 mesh wire of 3mm dia ,Selvege
wire of 3.9mm dia and lacing wire
of 2.4mm dia as per NS 163/169
Sqm 270.33 220.00, 268.00, 323.00
16.1 1.5 x 1 x 0.5 / 0 Box 1486.83 Rs. 1486.83 /Sft
16.2 2 x 1 x 0.5 / 1 Box 2027.50 Rs. 2027.50 /Sft
16.3 3 x 1 x 0.5 / 2 Box 2703.33 Rs. 2703.33 /Sft
16.4 4 x 1 x 0.5 / 3 Box 3649.50 Rs. 3649.50 /Sft
16.5 1.5 x 1 x 1 / 0 Box 2162.67 Rs. 2162.67 /Sft
16.6 2x1x1/1 Box 2973.67 Rs. 2973.67 /Sft
16.7 3x1x1/2 Box 4325.33 Rs. 4325.33 /Sft
16.8 4x1x1/3 Box 5677.00 Rs. 5677.00 /Sft
17 Gravel
17.1 ( 5 - 70 mm ) Cum 1,750.00
17.2 ( 5 - 40 mm ) Cum 1,750.00
17.3 ( 5 - 20 mm ) Cum 1,750.00
17.4 ( 5 - 08 mm ) Cum 1,750.00
18.1 HDPe Pipe ( 110 mm Dia ) Rm 345.45 (4kg/cm^2)
18.2 HDPe Pipe ( 200 mm Dia ) Rm 1,152.73 (4kg/cm^2)
19 Jute Kg 100.00
20 Kerosene Lit 66.37
21 Kukath for Form Work Cum 48,050.00
22 Nail Kg 105.00
23 Petrol Lit 87.61
24 Plywood ( Water Proof )
24.1 8 mm Sqm 968.40 Rs. 90.00 /Sft
24.2 12 mm Sqm 1,162.08 Rs. 108.00 /Sft
24.3 18 mm ( Board ) Sqm 1,345.00 Rs. 125.00 /Sft
25 Primer Lit 2,733.04
26 RCC Hume Pipe ( NP3 )
26.1 450 mm Rm 4,598.00 11495.00
26.2 600 mm Rm 6,534.00 16335.00
26.3 900 mm Rm 12,100.00 30250.00
26.4 1200 mm Rm 15,945.60 39864.00
27 RCC Hume Pipe Collar
27.1 450 mm No 1,149.50
27.2 600 mm No 1,633.50
27.3 900 mm No 3,025.00
27.4 1200 mm No 3,986.40
28 Road Marking Paint Lit 480.00
29 Salwood Cum 176,000.00
30 Sand Cum 2,600.00
31 Soil for Filling Cum 260.00 Without Transportation
32 Steel Reinforcement Mt 83,000.00
33 Stone Dust Cum 2,200.00
35 Steel Plate including fitting Kg 190.00
36 Steel Tube ( Iron Black Pipe ) Kg 135.00

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

Sn Description Unit Rate Remarks


37 Tarfelt Bundle 1,450.00 Rs. 1450.00 /Bundle (20 m2)
38 Water Lit 0.53

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

Sn Description Unit Rate Remarks


District Equipment Rate
S.N Description Unit Rate Remarks
1 Air compressor Per Hr 250.00
2 Asphalt Paver Per Hr 1,400.00
3 Asphalt Plant Per Hr 500.00
4 Backhoe Loader ( JCB ) Per Hr 1,000.00
5 Bitumen Distributor Per Hr 1,300.00
6 Bitumen Heater Per Hr 180.00
7 Boiler Per Hr 200.00
8 Cap Crane15t Per Hr 3,500.00
9 Concrete mixture Per Hr 500.00
10 Dozer Track Per Hr 2,000.00
11 Excavator Track Per Hr 1,800.00
12 Excavator + Breaker Per Hr 2,100.00
13 Flat bed truck Per Hr 450.00
14 Grader Motor Per Hr 1,600.00
15 Loader Wheel Per Hr 1,000.00
16 Truck Tipper Per Hr 450.00
17 Roller 3 wheel Per Hr 500.00
18 Roller Pneumatics Per Hr 1,200.00
19 Roller Vibrator Per Hr 700.00
20 Spreader Chips Per Hr 1,500.00
21 Vibrator with needle Per Hr 220.00
22 Water tanker Per Hr 550.00
23 Water Pump ( Upto 6" dia ) Per Hr 200.00

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

Government of Nepal
Ministry of Physical Infrastructure and Transport
Department of Roads
BRIDGE PROJECT
Chakupat, Lalitpur.

Feasibility Study, Detailed Engineering Survey, Soil investigation, Hydrological Study and Detailed Design of Bridges at Baglung District

Description of works: Collection of rubble of required size, hauling distance10m. and stacking. Unit: 1 m 3
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
8.01.01 a) Unskilled md 4.00 550.00 2200.00 ( 40 - 70 mm size)
8.01.01 b) Unskilled md 3.20 550.00 1760.00 ( 70 - 100 mm size)

Description of works: Collection and seiving gravel including stacking within 10m. Hauling distance. Unit: 1 m 3
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
8.01.02.a) Unskilled md 2.00 550.00 1100.00 ( 5 - 70 mm size)
8.01.02.b) Unskilled md 3.20 550.00 1760.00 ( 5 - 40 mm size)
8.01.02.c) Unskilled md 4.70 550.00 2585.00 ( 5 - 20 mm size)
8.01.02.d) Unskilled md 8.00 550.00 4400.00 ( 5 - 08 mm size)

Description of works: Collection of rubble of required size, hauling distance10m. and stacking. Unit: 1 m 3
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
8.01.03 Unskilled md 1.40 550.00 770.00

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

Description of works: Collection of rubble of required size, hauling distance10m. and stacking. Unit: 1 m 3

Description of works: Collection and seiving sand within 10m. hauling distance. Unit: 1 m 3
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
8.01.04.a) Unskilled md 4.00 550.00 2200.00 ( Quarry output less than 33%)
8.01.04.b) Unskilled md 3.00 550.00 1650.00 ( Quarry output 33 - 66 %)
8.01.04.c) Unskilled md 1.43 550.00 786.50 ( Quarry output more than 66%)

Description of works: Collection, quarring and seiving sand in hilly areas within 10m. hauling distance. Unit: 1 m 3
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
8.01.05 Unskilled md 1.50 550.00 825.00

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

Description of works: Collection of rubble of required size, hauling distance10m. and stacking. Unit: 1 m 3
Description of works: Washing broken stone, gravel and sand. Unit:
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
8.01.08 Unskilled md 1.50 550.00 825.00

Description of works: Washing rubble Unit: 1 m 3


Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
8.01.08 Unskilled md 0.40 550.00 220.00

Description of works: Breaking stones including Collection, seiving and stacking within 10m. Unit: 1 m 3
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
8.02.01.a) Unskilled md 6.00 550.00 3300.00 ( 70 - 100 mm size)
8.02.01.b) Unskilled md 8.00 550.00 4400.00 ( 40 - 70 mm size)
8.02.01.c) Unskilled md 12.00 550.00 6600.00 ( 20 - 40 mm size)
8.02.01.d) Unskilled md 18.00 550.00 9900.00 ( 10 - 20 mm size)
8.02.01.e) Unskilled md 25.00 550.00 13750.00 ( 5 - 10 mm size)

Description of works: Making blocks of required size out of stratified rocks including hammer dressing, hauling distance 10m. and stacking. Unit: 1 m 3
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
8.02.02 Unskilled md 5.88 550.00 3234.00

Description of works: Making rubbles of required size including breaking with distance 10m. and stacking. Unit: 1 m 3
Labour (A) Material (B) Equipment (C)
Norms No.

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

Description of works: Collection of rubble of required size, hauling distance10m. and stacking. Unit: 1 m 3
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
8.02.04 Unskilled md 5.50 550.00 3025.00

Description of works: Transportation of water by manpower including loading, hauling, unloading and stacking. Unit: 1000 lit
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
8.03.17(a) Unskilled md 0.47 550.00 258.50 a) First 10 m. with haul and unload 0.26 per lit
8.03.17(b) Unskilled md 0.12 550.00 66.00 b) Every additional 10m. upto 100m 0.07 per lit

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

Government of Nepal
Ministry of Physical Infrastructure and Transport
Department of Roads
BRIDGE PROJECT
Chakupat, Lalitpur.

Feasibility Study, Detailed Engineering Survey, Soil investigation, Hydrological Study and Detailed Design of Bridges at Baglung Distric

Description of works: Transportation of materials by truck, including loading, unloading and stacking by manpower lead upto 10m using 8 tonne capacity Truck.

Spec. Clause No. 800 Travel time (T) for truck to be used for this activity shall be determined as follows:
T=2x{d1/v1+d2/v2+d3/v3+..dn/vn}, where d1,d2,d3dn and v1,v2,v3..vn are the streches of distances to be travelled and corresponding average
streches. [ T = 2*(d1/v1+d2/v2+dn/vn) = ] (T=travel time for truck in
Description of works Unit Activity No d1 v1 d2 v2 d3 v3 d4 v4 . . dn
Excavated earthwork soil material m3 8.04.2.1.a T = 2 0.00 15.00 20.00 30.00
Excavated earthwork soil material for
8.04.2.1.b 2 0.00 15.00 20.00 30.00
disposal m3 T=
Sand, Stone dust (Local) m3 8.04.2.2 T= 2 0.00 15.00 20.00 0.00 30.00
Sand, Stone dust m3 8.04.2.3 T= 2 0.00 15.00 20.00 0.00 30.00
Crushed Aggregate m3 8.04.2.3 T= 2 0.00 15.00 20.00 0.00 30.00
Gravel, river shingle, broken stone,
8.04.2.3 2 0.00 15.00 20.00 0.00 30.00
aggregates, and bats (Local) m3 T=
Gravel, River shingle, aggregates(RCC) m4 8.04.2.4 T= 2 0.00 15.00 20.00 0.00 30.00
Boulder, Cobbles, quarry stone m 3 8.04.2.4 T= 2 0.00 15.00 20.00 30.00
Brick 1000 nos 8.04.2.6 T= 2 0.00 15.00 0.00 20.00 30.00
Cement (Nepali) t 8.04.2.7 T= 2 0.00 15.00 0.00 20.00 30.00
Cement (Indian) t 8.04.2.8 T= 2 0.00 15.00 0.00 20.00 30.00
Reinforcement Steel t 8.04.2.8 T= 2 0.00 15.00 0.00 20.00 30.00
Gabion wire / Gabion Box t 8.04.2.8 T= 2 0.00 15.00 0.00 20.00 0.00 30.00
Bitumen / Diesel / Kerosene 1000 lit 8.04.2.9 T= 2 0.00 15.00 0.00 20.00 30.00
Gi,Ci, Pipe and Fittings , Black pipe t 8.03.10 T= 2 0.00 15.00 0.00 20.00 30.00
Timber for temporary works m 3 8.04.2.11 T= 2 0.00 15.00 0.00 20.00 30.00

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

Timber for temporary works m3 8.04.2.11 T= 2 0.00 15.00 0.00 20.00 30.00
Fabricated Structural Timber m3 8.04.2.12 T= 2 0.00 15.00 0.00 20.00 0.00 30.00
Fabricated Structural Steel m3 8.04.2.13 T= 2 0.00 15.00 0.00 20.00 0.00 30.00
RCC hume pipe of 900mm dia m 8.04.2.16.a T= 2 0.00 15.00 0.00 20.00 0.00 30.00
RCC hume pipe of 750mm dia m 8.04.2.16.b T= 2 0.00 15.00 0.00 20.00 0.00 30.00
RCC hume pipe of 600mm dia m 8.04.2.16.c T= 2 0.00 15.00 0.00 20.00 0.00 30.00
RCC hume pipe of 450mm dia m 8.04.2.16.c T= 2 0.00 15.00 0.00 20.00 0.00 30.00
RCC hume pipe of 300mm dia m 8.04.2.16.c T= 2 0.00 15.00 0.00 20.00 0.00 30.00
Water 1000 lit 8.04.2.17 T= 2 0.00 15.00 0.00 20.00 30.00

Activity No: 8.04.02


Spec. Clause No. 800
Description of works: Transportation of materials by truck, including loading, unloading and stacking by manpower lead upto 10m using 8 tonne capacity Truck

Labour Materials Equipment


Description of works Unit
Type Unit Qty. Rate Amount Type Unit Quantity. Rate Amount Type Unit Quantity.
1)Excavated earthwork soil material Unskilled 0.00 550.00 0.00 Fuel lit 2 xT= 0.000 66.37 0.00 Truck hr 0.15 x (T+0.75)=
m3 md
disposal
Sub total of Labour + Materials + Equipments = 50.63 Contractor's overhead expenses 15% =

1)Excavated earthwork soil material Unskilled 0.00 550.00 0.00 Fuel lit 2.3xT= 0.000 66.37 0.00 Truck hr 0.18x(T+0.75)=
m3 md
disposal
Sub total of Labour + Materials + Equipments = 60.75 Contractor's overhead expenses 15% =

2) Sand/Stone dust (local) m3 Unskilled md 0.30 550.00 165.00 Fuel lit 1.7xT= 0.000 66.37 0.00 Truck hr 0.13x(T+0.75)=

Sub total of Labour + Materials + Equipments = 208.88 Contractor's overhead expenses 15% =
2a)Sand/stone dust m3 Unskilled md 0.30 550.00 165.00 Fuel lit 1.7xT= 0.000 66.37 0.00 Truck hr 0.13x(T+0.75)=

Sub total of Labour + Materials + Equipments = 208.88 Contractor's overhead expenses 15% =

3.a) Gravel, river shingle, broken stone, m3 Unskilled md 0.50 550.00 275.00 Fuel lit 2.1xT= 0.000 66.37 0.00 Truck hr 0.16x(T+0.75)=
aggregates, and bats (Local) Sub total of Labour + Materials + Equipments = 329.00 Contractor's overhead expenses 15% =

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

3.b) Gravel, river shingle, broken stone, Unskilled 0.50 550.00 275.00 Fuel lit 2.1xT= 0.000 66.37 0.00 Truck hr 0.16x(T+0.75)=
aggregates, and bats (RCC) m3 md
Sub total of Labour + Materials + Equipments = 329.00 Contractor's overhead expenses 15% =

4) Boulder, Cobbles, quarry stone m3 Unskilled md 0.50 550.00 275.00 Fuel lit 2.7xT 0.000 66.37 0.00 Truck hr 0.21x(T+0.75)=

Sub total of Labour + Materials + Equipments = 345.88 Contractor's overhead expenses 15% =

6) Brick 1000 Nos Unskilled md 0.60 550.00 330.00 Fuel lit 4xT 0.000 66.37 0.00 Truck hr 0.31x(T+0.75)=

Sub total of Labour + Materials + Equipments = 434.63 Contractor's overhead expenses 15% =
7) Cement t Unskilled md 0.40 550.00 220.00 Fuel lit 1.5xT 0.0000 66.37 0.00 Truck hr 0.12x(T+0.75)=

Sub total of Labour + Materials + Equipments = 260.50 Contractor's overhead expenses 15% =

8) Reinforcement Steel /Binding t Unskilled md 0.60 550.00 330.00 Fuel lit 1.5xT 0.0000 66.37 0.00 Truck hr 0.12x(T+0.75)=
Wire/Nails/Bolts Sub total of Labour + Materials + Equipments = 370.50 Contractor's overhead expenses 15% =

8a) Gabion wire / Gabion Box t Unskilled md 0.60 550.00 330.00 Fuel lit 1.5xT 0.0000 66.37 0.00 Truck hr 0.12x(T+0.75)=

Sub total of Labour + Materials + Equipments = 370.50 Contractor's overhead expenses 15% =

9) Bitumen 1000 lit Unskilled md 1.00 550.00 550.00 Fuel lit 2.6xT 0.000 66.37 0.00 Truck hr 0.2x(T+0.75)=

Sub total of Labour + Materials + Equipments = 617.50 Contractor's overhead expenses 15% =
10)Gi,Ci, Pipe and Fittings , Black pipe t Unskilled md 1.00 550.00 550.00 Fuel lit 1.5xT 0.000 66.37 0.00 Truck hr 0.12x(T+0.75)=

Sub total of Labour + Materials + Equipments = 590.50 Contractor's overhead expenses 15% =

11) Timber for temporary works m3 Unskilled md 0.30 550.00 165.00 Fuel lit 1.4xT 0.000 66.37 0.00 Truck hr 0.11x(T+0.75)=

Sub total of Labour + Materials + Equipments = 202.13 Contractor's overhead expenses 15% =
12) Fabricated structural timber m3 Unskilled md 0.50 550.00 275.00 Fuel lit 2xT 0.000 66.37 0.00 Truck hr 0.15x(T+1.25)=

Sub total of Labour + Materials + Equipments = 359.38 Contractor's overhead expenses 15% =
13) Fabricated structural steel t Unskilled md 4.00 550.00 2200.00 Fuel lit 1.5xT 0.000 66.37 0.00 Truck hr 0.12x(T+1.25)=

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

Skilled md 0.40 740.00 296.00


Sub total of Labour + Materials + Equipments = 2563.50 Contractor's overhead expenses 15% =
16) RCC Hume pipe
a) RCC hume pipe of 900mm m Skilled md 0.04 740.00 29.60 Fuel lit 0.78xT 0.000 66.37 0.00 Truck hr 0.06x(T+1.75)=

Unskilled md 0.40 550.00 220.00


Sub total of Labour + Materials + Equipments = 296.85 Contractor's overhead expenses 15% =

m Skilled md 0.03 740.00 22.20 Fuel lit 0.69xT 0.000 66.37 0.00 Truck hr 0.055x(T+1.75)=
b) RCC hume pipe of 750mm dia
Unskilled md 0.33 550.00 181.50
Sub total = 203.70 Sub total = 0.00
Sub total of Labour + Materials + Equipments = 247.01 Contractor's overhead expenses 15% =

c) RCC hume pipe of 600mm m Skilled md 0.02 740.00 14.80 Fuel lit 0.6xT 0.000 66.37 0.00 Truck hr 0.054x(T+1.75)=

Unskilled md 0.25 550.00 137.50


Sub total = 152.30 Sub total = 0.00
Sub total of Labour + Materials + Equipments = 194.83 Contractor's overhead expenses 15% =

d) RCC hume pipe of 450mm m Skilled md 0.02 550.00 11.00 Fuel lit 0.55xT 0.000 66.37 0.00 Truck hr 0.04x(T+1.75)=

Unskilled md 0.17 550.00 90.75


Sub total = 101.75 Sub total = 0.00
Sub total of Labour + Materials + Equipments = 133.25 Contractor's overhead expenses 15% =
d) RCC hume pipe of 300mm m Skilled md 0.01 740.00 7.40 Fuel lit 0.4xT 0.000 66.37 0.00 Truck hr 0.04x(T+1.75)=

Unskilled md 0.13 550.00 71.50


Sub total = 78.90 Sub total = 0.00
Sub total of Labour + Materials + Equipments = 110.40 Contractor's overhead expenses 15% =
17) Water 1000 lit Skilled md 0.01 740.00 7.40 Fuel lit 1.5xT 0.000 66.37 0.00 Truck hr 0.12x(T+0.75)=

Unskilled md 0.10 550.00 55.00 Pump 10cmdia hr 0.050


Sub total = 62.40 Sub total = 0.00

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

Sub total of Labour + Materials + Equipments = 102.90 Contractor's overhead expenses 15% =

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

Government of Nepal
Physical Infrastructure and Transport
Department of Roads
BRIDGE PROJECT
Chakupat, Lalitpur.

stigation, Hydrological Study and Detailed Design of Bridges at Baglung District

y manpower lead upto 10m using 8 tonne capacity Truck.

be determined as follows:
,d3dn and v1,v2,v3..vn are the streches of distances to be travelled and corresponding average speeds on these
] (T=travel time for truck in
vn Travel time T (hrs) Remarks
= 0.00 available within 2kms

= 0.00
= 0.00
= 0.00
= 0.00

= 0.00
= 0.00
= 0.00
0.00
= 0.00
= 0.00
= 0.00
= 0.00
= 0.00
= 0.00
= 0.00

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

= 0.00
= 0.00
= 0.00
= 0.00
= 0.00
= 0.00
= 0.00
= 0.00
= 0.00

F/Y: 070/71

Place:

Equipment
Remarks
Quantity. Rate Amount
0.113 450.00 50.63
Unit rate = 50.63

0.135 450.00 60.75


Unit rate = 60.75

0.098 450.00 43.88


Unit rate = 208.88
0.098 450.00 43.88
Unit rate = 208.88

0.120 450.00 54.00


Unit rate = 329.00

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

0.120 450.00 54.00


Unit rate = 329.00

0.158 450.00 70.88


Unit rate = 345.88

0.233 450.00 104.63


Unit rate = 434.63
0.090 450.00 40.50
Unit rate = 260.50

0.090 450.00 40.50


Unit rate = 370.50

0.090 450.00 40.50


Unit rate = 370.50

0.150 450.00 67.50


Unit rate = 617.50
0.090 450.00 40.50
Unit rate = 590.50

0.083 450.00 37.13


Unit rate = 202.13
0.188 450.00 84.38
Unit rate = 359.38
0.150 450.00 67.50

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

Unit rate = 2563.50

0.105 450.00 47.25

Unit rate = 296.85

0.096 450.00 43.31

Sub total = 43.31


Unit rate = 247.01

0.095 450.00 42.53

Sub total = 42.53


Unit rate = 194.83

0.070 450.00 31.50

Sub total = 31.50


Unit rate = 133.25
0.070 450.00 31.50

Sub total = 31.50


Unit rate = 110.40
0.090 450.00 40.50
1000.00 50.00
Sub total = 40.50

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

Unit rate = 0.10

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

Government of Nepal
Ministry of Physical Infrastructure and Transport
Department of Roads
BRIDGE PROJECT
Chakupat, Lalitpur.

Feasibility Study, Detailed Engineering Survey, Soil investigation, Hydrological Study and Detailed Design of Brid

District Labour, Collection Rate of Materials, Fuel and Equipment Hire Rate

Updated Rates
Royalty
District Rate Collection Transportation
Description Unit
(D) Rate (C) Rate ( Tp )
(R)
S.N.
A Labour
1 Unskilled Labour Md 550.00
2 Skilled Labour (Carpenter, masons) Md 740.00
Skilled Labour (for blacktopping works) Md 740.00
3
4 Supervisor M/d 500.00
5 Length Man M/d 450.00
B Material
1 Aggregate Crushed
1.1 10mm Cum 2,600.00 13,750.00 -
1.2 20 mm Cum 2,600.00 9,900.00 -
1.3 40 mm Cum 2,600.00 6,600.00 -
2 Aggregate uncrushed ( River Bed )
2.1 5-10mm Cum 1,750.00 4400.00 0.00
2.2 5-20mm Cum 1,750.00 2585.00 0.00
2.3 5-40mm Cum 1,750.00 1760.00 0.00
3 Antistripping agent Additives Kg 323.50
4 Binding wire Kg 100.00 0.00
5 Bitumen 80 /100 Kg 92.60 0.00
6 Bolt Kg 180.00 0.00
7 Boulder / Rubble Cum 2,400.00 770.00 0.00
8 Brick No 17.00 0.00
9 Cement ( Indian ) Mt 16,000.00 0.00
10 Cement ( Nepali ) Mt 15,000.00 0.00
11 Diesel Lit 87.61 0.00
12 Enamel Paint Lit 400.00
13 Firewood Kg 10.00
14 Geotextile Sqm 86.00
15 GI Wire(heavy coated)
15.1 7 and 8 gauge Kg 101.00 0.00
15.2 10 gauge Kg 101.00 0.00
15.3 12 gauge Kg 101.00 0.00

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

District Labour, Collection Rate of Materials, Fuel and Equipment Hire Rate

Updated Rates
Machine made double twisted
hexagonal mesh with size of 100 x
120mm including heavy coated GI
16 mesh wire of 3mm dia ,Selvege wire of
3.9mm dia and lacing wire of 2.4mm
dia as per NS 163/169
Sqm 270.33 0.00
17 Gravel Cum
17.1 ( 5 - 70 mm ) Cum 1,750.00 1100.00 0.00
18.1 HDPE Pipe - 100 mm dia Rm 345.45
18.2 HDPE Pipe - 200 mm dia Rm 1,152.73
19 Jute Kg 100.00
20 Kerosene Lit 66.37 0.00
21 Kukath for Form Work Cum 48,050.00
22 Nail Kg 105.00 0.00
23 Petrol Lit 87.61 0.00
24 Plywood ( Water Proof )
24.1 9 mm Sqm 968.40
24.2 12 mm Sqm 1,162.08
24.3 19 mm ( Board ) Sqm 1,345.00
25 Primer Lit 2,733.04
26 RCC Hume Pipe ( NP3 )
26.1 450 mm Rm 4,598.00 0.00
26.2 600 mm Rm 6,534.00 0.00
26.3 900 mm Rm 12,100.00 0.00
26.4 1200 mm Rm 15,945.60 0.00
27 RCC Hume Pipe Collar
27.1 450 mm Rm 1,149.50 -
27.2 600 mm No 1,633.50 -
27.3 900 mm No 3,025.00 -
28 Road Marking Paint Lit 480.00 -
29 Salwood Cum 176,000.00
30 Sand Cum
30.1 ( Quarry output less than 33%) 2,600.00 2200.00 0.00
30.2 ( Quarry output 33 - 66 %) 2,600.00 1650.00 0.00
30.3 ( Quarry output more than 66%) 2,600.00 786.50 0.00
30.4 Hilly Area 2,600.00 825.00 0.00
31 Soil for Filling excavated Earth Cum 260.00 0.00
32 Steel reinforcement Mt 83,000.00 0.00
33 Stone Dust Cum 2,200.00 0.00
35 Steel Plate including fitting Kg 190.00 0.00
36 Steel Tube ( Iron Black Pipe ) Kg 135.00 0.00
37 Tarfelt Sqm 1,450.00
38 Water Lit 0.53 0.00

Updated Equipment Rate

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

District Labour, Collection Rate of Materials, Fuel and Equipment Hire Rate

Updated Rates
S.N Description Unit Rate Remarks
1 Air compressor Per Hr 250.00
2 Asphalt Paver Per Hr 1,400.00
3 Asphalt Plant Per Hr 400.00
4 Backhoe Loader ( JCB ) Per Hr 1,000.00
5 Bitumen Distributor Per Hr 1,300.00
6 Bitumen Heater Per Hr 180.00
7 Boiler Per Hr 200.00
8 Cap Crane15t Per Hr 3,500.00
9 Concrete mixture Per Hr 500.00
10 Dozer Track Per Hr 1,800.00
11 Excavator Track Per Hr 1,800.00
12 Excavator + Breaker Per Hr 2,100.00
13 Flat bed truck Per Hr 450.00
14 Grader Motor Per Hr 1,600.00
15 Loader Wheel Per Hr 1,000.00
16 Truck Tipper Per Hr 450.00
17 Roller 3 wheel Per Hr 500.00
18 Roller Pneumatics Per Hr 1,200.00
19 Roller Vibrator Per Hr 700.00
20 Spreader Chips Per Hr 1,500.00
21 Vibrator with needle Per Hr 220.00
22 Water bowser Per Hr 550.00
23 Water Pump ( Upto 4" dia ) Per Hr 200.00

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

Government of Nepal
Physical Infrastructure and Transport
Department of Roads
BRIDGE PROJECT
Chakupat, Lalitpur.

stigation, Hydrological Study and Detailed Design of Bridges at Baglung District

e of Materials, Fuel and Equipment Hire Rate

Updated Rates
Total Rate
Remarks
( C + R + Tp)

550.00
740.00

740.00
500.00
450.00

2,600.00
2,600.00
2,600.00

1,750.00
1,750.00
1,750.00
323.50
100.00
92.60
180.00
2,400.00
17.00
16,000.00
15,000.00
87.61
400.00
10.00
86.00

101.00
101.00
101.00

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

e of Materials, Fuel and Equipment Hire Rate

Updated Rates

270.33 1Sqm = 5.5 Kg


-
1,750.00
345.45
1,152.73
100.00
66.37
48,050.00
105.00
87.61

968.40
1,162.08
1,345.00
2,733.04

4,598.00
6,534.00
12,100.00
15,945.60

1,149.50
1,633.50
3,025.00
480.00
176,000.00

2,600.00
2,600.00
2,600.00
2,600.00
260.00
83,000.00
2,200.00
190.00
135.00
1,450.00
0.53

Prepared By: Checked By : Recommended By : Approved By :


Khurkot-Ghurmi Sector Appendix - 3

Government of Nepal
Ministry of Physical Planning and Works
Department of Roads
Puspalal ( Mid -hill ) Highway Project
Babarmahal, Kathmandu.

Project : Detail Engineering Survey & Design of Khurkot-Ghurmi Sector

ANALYSIS OF RATE

Item no. 1 Clearing and grubbing of forest including uprooting, carrying and disposing of vegetation, gr
Trees and sapling less than 15 numbers per 100 sq.m
Unit-1 Sqm
Description Particular Quantity Unit Rate Amount Total
Labour Unskilled 0.03 M/D 315.00 9.45 9.45
Tools 3% of Labour 0.28
Actual Cost 9.73
Rate for Sqm 15% Contractors profit 1.46
NRs 11.19 Total Rate 11.19

Cutting of trees (the girth measured at a height of 1 m above ground level) including cuttting
Item no. 2 of trunks and branches, removing the roots, stacking serviceable materials and disposal of
unserviceable materials to 10m distance and back filling the depressions/pits
a. Above 300 to 600 mm girth
Unit-1 no.
Description Particular Quantity Unit Rate Amount Total
Labour Unskilled 0.92 M/D 315.00 289.80 289.80
Tools 3% of Labour 8.69
Actual Cost 298.49
Rate for no. 15% Contractors profit 44.77
NRs 343.27 Total Rate 343.27

b. Above 600 to 900 mm girth


Unit-1 No
Description Particular Quantity Unit Rate Amount Total
Labour Unskilled 3.50 M/D 315.00 1102.50 1102.50
Tools 3% of Labour 33.08
Actual Cost 1135.58
Rate for no. 15% Contractors profit 170.34
NRs 1305.91 Total Rate 1305.91

Road way excavation including disposal upto 10m and lift upto 1.5 m etc. all complete as per
Item no. 3
specification.
a. Hard soil/Gravel BMS
Unit-Cum
Description Particular Quantity Unit Rate Amount Total
Labour Unskilled 1.00 M/D 315.00 315.00 315.00
Tool & Plants 3% of Labour 9.45
Actual Cost 324.45
Rate per Cum 15% Contractors profit 48.67
NRs 373.12 Total Rate 373.12

Analysis of Rates-21
Khurkot-Ghurmi Sector Appendix - 3

Government of Nepal
Ministry of Physical Planning and Works
Department of Roads
Puspalal ( Mid -hill ) Highway Project
Babarmahal, Kathmandu.

Project : Detail Engineering Survey & Design of Khurkot-Ghurmi Sector

ANALYSIS OF RATE
b. Road way excavating and loading by excavator (capacity 0.8 cum) in Hard Soil / Gravel / BMS
Unit-Cum
Description Particular Quantity Unit Rate Amount Total
a)Skilled 0.0 M/D -
Labour b) Unskilled 0.0 M/D - -
c) Operator 0.0 M/D -
Material Diesel 0.1500 Lit 85.00 12.75 12.75
Equipment Hudraulic excavator 0.0125 Hr 1,400.00 17.50 17.50
Actual Cost 30.25
Rate per Cum 15% Contractors profit 4.54
NRs 34.79 Total Rate 34.79

c. Road way excavation with combination of Manual and Machined excavation


Hard soil/Gravel BMS
Unit- Cum
Description Particular Quantity Unit Rate Amount Total
Manual Excavation ( 20% ) 0.20 Cum 324.45 64.89 64.89
Machine Excavation ( 80% 0.80 Cum 30.25 24.20 24.20
Actual Cost 89.09
Rate per Cum 15% Contractors profit 13.36
NRs 102.45 Total Rate 102.45

Road way excavation including disposal upto 10m and lift upto 1.5 m etc. all complete as per
Item no. 4
specification.
a. Soft rock
Unit- Cum
Description Particular Quantity Unit Rate Amount Total
Labour Unskilled 2.75 M/D 320.00 880.00 880.00
Tool & Plants 3% of Labour 26.40
Actual Cost 906.40
Rate per Cum 15% Contractors profit & OH 135.96
NRs 1042.36 Total Rate 1042.36

b. Road way excavating and loading by excavator (capacity 0.8 cum) in Soft Rock
Unit- Cum
Description Particular Quantity Unit Rate Amount Total
a)Skilled 0.0 M/D -
Labour b) Unskilled 0.0 M/D - -
c) Operator 0.0 M/D -
Material Diesel 0.2064 Lit 85.00 17.54 17.54
Equipment Hydraulic excavator 0.0172 Hr 1,400.00 24.08 24.08
Actual Cost 41.62
Rate per Cum 15% Contractors profit & OH 6.24
NRs 47.87 Total Rate 47.87

Analysis of Rates-22
Khurkot-Ghurmi Sector Appendix - 3

Government of Nepal
Ministry of Physical Planning and Works
Department of Roads
Puspalal ( Mid -hill ) Highway Project
Babarmahal, Kathmandu.

Project : Detail Engineering Survey & Design of Khurkot-Ghurmi Sector

ANALYSIS OF RATE
c. Road way excavation with combination of Manual and Machined excavation
Soft Rock
Unit- Cum
Description Particular Quantity Unit Rate Amount Total
Manual Excavation ( 20% ) 0.20 Cum 906.40 181.28 181.28
Machined Excavation ( 80% 0.80 Cum 41.62 33.30 33.30
Actual Cost 214.58
Rate per Cum 15% Contractors profit & OH 32.19
NRs 246.77 Total Rate 246.77

Formation of embankment including compaction in layers not exceeding 150mm.


Item no. 5
Compacted depth, watering and haulage 10m. etc. all complete as per specification.
Unit-1 Cum
Description Particular Quantity Unit Rate Amount Total
a)Skilled 0.00 M/d 460.00 0.00
Labour
b)Unskilled 0.50 M/d 320.00 160.00 160.00
Suitable material 1.10 Cum 160.00 176.00
Material Fuel 0.08 litre 85.00 6.80
Water 100.00 litre 0.10 10.00 192.80
Equipment Roller 8-10t 0.017 Hr 2500.00 42.50 42.50
Tools & Plants 3% of labour cost 4.80
Actual Cost 400.10
Rate per Cum 15% Contractors profit & OH 60.02
NRs 460.12 Total Rate 460.12

Providing, laying, spreading, levelling and compaction of natural sand gravel sub-base
Item no. 6
grading as per table 12.1 of standard specification lead upto 10m

Unit-1 Cum
Description Particular Quantity Unit Rate Amount Total
a)Skilled 0.005 M/d 460.00 2.30
Labour
b)Unskilled 0.040 M/d 320.00 12.80 15.10
Sub base aggregate 1.28 Cum 600.00 768.00
Material
Diesel 0.792 litre 85.00 67.32 835.32
Grader 0.022 hr 2000.00 44.00
Vibrator roller 0.022 hr 2000.00 44.00
Equipment
Water bowser 0.038 hr 550.00 20.90
Loader 0.011 hr 1500.00 16.50 125.40
Actual Cost 975.82
Rate per Cum 15% Contractors profit & OH 146.37
NRs 1122.19 Total Rate 1122.19

Analysis of Rates-23
Khurkot-Ghurmi Sector Appendix - 3

Government of Nepal
Ministry of Physical Planning and Works
Department of Roads
Puspalal ( Mid -hill ) Highway Project
Babarmahal, Kathmandu.

Project : Detail Engineering Survey & Design of Khurkot-Ghurmi Sector

ANALYSIS OF RATE
Providing, laying, spreading, watering, levelling and compaction of of crusher run materials
Item no. 7
for base course lead upto 10m
Unit-1 Cum
Description Particular Quantity Unit Rate Amount Total
a)Skilled 0.005 M/d 460.00 2.30
Labour
b)Unskilled 0.020 M/d 320.00 6.40 8.70
Base aggregate 1.200 Cum 1200.00 1440.00
Material
Diesel 0.990 litre 85.00 84.15 1524.15
Grader 0.033 hr 2000.00 66.00
Vibrator roller 0.033 hr 2000.00 66.00
Equipment
Water bowser 0.033 hr 550.00 18.15
Loader 0.011 hr 1500.00 16.50 166.65
Actual Cost 1699.50
Rate per Cum 15% Contractors profit & OH 254.93
NRs 1954.43 Total Rate 1954.43

Providing and spraying bituminious Prime Coat MC30/MC70 including cleaning the road
Item no. 8
surface using wire, brushes, broom etc. before applying prime coat.

Unit: Lit
Description Particular Quantity Unit Rate Amount Total
Skilled 0.003 M/d 460.00 1.38
Labour
Unskilled 0.046 M/d 320.00 14.72 16.10
Bitumen 1.050 Lit 80.00 84.00
Materials
Kerosene 0.100 Lit 85.00 8.50 115.88
Diesel 0.275 Lit 85.00 23.38
Boiler 0.0025 hr 500.00 1.25
Equipment Sprayer 0.0025 hr 1000.00 2.50
Air compressor 0.0030 hr 500.00 1.50 5.25
Actual Cost 137.23
Rate per Lit 15% Contractors profit & OH 20.58
NRs 157.81 Total Rate 157.81

Analysis of Rates-24
Khurkot-Ghurmi Sector Appendix - 3

Government of Nepal
Ministry of Physical Planning and Works
Department of Roads
Puspalal ( Mid -hill ) Highway Project
Babarmahal, Kathmandu.

Project : Detail Engineering Survey & Design of Khurkot-Ghurmi Sector

ANALYSIS OF RATE
Item no. 9 Providing mixing and laying Asphalt Concrete with compaction
Unit: Cum
Description Particular Quantity Unit Rate Amount Total
Skilled 0.03 M/d 460.00 13.80
Labour Unskilled 0.13 M/d 320.00 41.60
Foreman 0.01 M/d 320.00 3.20 58.60
Bitumen 117.00 Lit 80.00 9360.00
Cement 0.022 t 12000.00 264.00
Materials
Diesel 10.45 Lit 85.00 888.25
Aggregates 1.20 Cum 1250.00 1500.00 12012.25
Asphalt mixing plant 0.0440 Hr 500.00 22.00
Wheel Loader 0.6600 Hr 1500.00 990.00
Asphalt Paver 0.2200 Hr 1400.00 308.00
Equipment
Steel tyred Roller 0.5500 Hr 500.00 275.00
Pneumatic Roller 0.5500 Hr 2500.00 1375.00
Tipper, Trucks 0.3200 Hr 450.00 144.00 3114.00
Actual Cost 15184.85
Rate per Cum 15% Contractors profit & OH 2277.73
NRs 17462.58 Total Rate 17462.58

Earth work excavation for trenches including shoring, struting, bracing, sheeting and
Item no. 10 disposal upto 10m and lift upto 1.5 m etc. all complete as per specification. ( For hard soil/
Gravels)
a. Manual Excavation
Unit- Cum
Description Particular Quantity Unit Rate Amount Total
Labour Unskilled 1.50 M/D 320.00 480.00 480.00
Tool & Plants 3% of Labour 14.40
Actual Cost 494.40
15% Contractors profit & OH 74.16
Rate per Cum Total Rate 568.56
NRs 568.56

b. Earthwork excavation for trenches with combination of Manual and Machined excavation
Unit- Cum
Description Particular Quantity Unit Rate Amount Total
Mannual Excavation ( 60% 0.60 Cum 494.40 296.64 296.64
Machined Excavation ( 40% 0.40 Cum 30.25 12.10 12.10
Actual Cost 308.74
Rate per Cum 15% Contractors profit & OH 46.31
NRs 355.05 Total Rate 355.05

Analysis of Rates-25
Khurkot-Ghurmi Sector Appendix - 3

Government of Nepal
Ministry of Physical Planning and Works
Department of Roads
Puspalal ( Mid -hill ) Highway Project
Babarmahal, Kathmandu.

Project : Detail Engineering Survey & Design of Khurkot-Ghurmi Sector

ANALYSIS OF RATE
Earth work excavation for trenches including shoring, struting, bracing, sheeting and
Item no. 11 disposal disposal upto 10m and lift upto 1.5 m etc. all complete as per specification. ( For
soft rocks)
a. Manual Excavation
Unit- Cum
Description Particular Quantity Unit Rate Amount Total
Labour Unskilled 3.00 M/D 320.00 960.00 960.00
Tool & Plants 3% of Labour 28.80
Actual Cost 988.80
Rate per Cum 15% Contractors profit & OH 148.32
NRs 1137.12 Total Rate 1137.12

b. Earthwork excavation for trenches with combination of Manual and Machined excavation
Soft Rock
Unit- Cum
Description Particular Quantity Unit Rate Amount Total
Mannual Excavation ( 70% 0.70 Cum 988.80 692.16 692.16
Machined Excavation ( 30% 0.30 Cum 30.25 9.08 9.08
Actual Cost 701.24
Rate per Cum 15% Contractors profit & OH 105.19
NRs 806.42 Total Rate 806.42

c. Earthwork excavation for trenches with combination of Manual and Machined excavation
All type of soil
Unit- Cum
Description Particular Quantity Unit Rate Amount Total
Hard Soil / Gravel /
Boulder Mixed ( 70% ) 0.70 Cum 308.74 216.12 216.12
Soft Rock ( 30 % ) 0.30 Cum 701.24 210.37 210.37
Actual Cost 426.49
Rate per Cum 15% Contractors profit & OH 63.97
NRs 490.46 Total Rate 490.46

Backfilling in layers in foundation pits, trenches etc. including compaction, watering etc.
Item no. 12
complete lead 10m. And depth of foundation upto 1.5m.
Unit-1Cum
Description Particular Quantity Unit Rate Amount Total
Labour Unskilled 1.14 M/D 320.00 364.80 364.80
Tools & Plants 3% of labour cost 10.94
Actual Cost 375.74
Rate per Cum 15% Contractors profit & OH 56.36
NRs 432.11 Total Rate 432.11

Analysis of Rates-26
Khurkot-Ghurmi Sector Appendix - 3

Government of Nepal
Ministry of Physical Planning and Works
Department of Roads
Puspalal ( Mid -hill ) Highway Project
Babarmahal, Kathmandu.

Project : Detail Engineering Survey & Design of Khurkot-Ghurmi Sector

ANALYSIS OF RATE
Item no. 13 Stone soling and leveling works including lead upto 30m
Unit-1 Cum
Description Particular Quantity Unit Rate Amount Total
a)Skilled 1.00 M/d 460.00 460.00
Labour
b)Unskilled 3.50 M/d 320.00 1120.00 1580.00
Stone 1.10 Cum 900.00 990.00
Material
Sand 0.71 Cum 650.00 461.50 1451.50
Tools & Plants 3% of labour cost 47.40
Actual Cost 3078.90
Rate per Cum 15% Contractors profit & OH 461.84
NRs 3540.74 Total Rate 3540.74

Providing and placing machine mixed non structural cement concrete in 1:2:4 ratio
Item no. 14 including compaction, curing, testing and lead 30m. etc. all complete as per specification
and drawing.
Unit-1 Cum
Description Particular Quantity Unit Rate Amount Total
Skilled 0.50 M/D 460.00 230.00
Labour
Unskilled 3.50 M/D 320.00 1120.00 1350.00
Cement 0.32 mt 12000.00 3840.00
Aggregate 20-40mm 0.52 Cum 1200.00 624.00
Aggregate 10 -20mm 0.33 Cum 1250.00 412.50
Material Sand 0.45 Cum 650.00 292.50
Petrol 0.10 Lit 116.00 11.60
Diesel 3.00 Lit 85.00 255.00
Water 192.00 Lit 0.10 19.20 5454.80
Mixer (0.28/ 0.20 m3 ) 0.60 hr 500.00 300.00
Equipment
Vibrator 0.25 hr 80.00 20.00 320.00
Quality Control 2.5 % of total 178.12
Actual Cost 7302.92
Rate per Cum 15% Contractors profit & OH 1095.44
NRs 8398.36 Total Rate 8398.36

Analysis of Rates-27
Khurkot-Ghurmi Sector Appendix - 3

Government of Nepal
Ministry of Physical Planning and Works
Department of Roads
Puspalal ( Mid -hill ) Highway Project
Babarmahal, Kathmandu.

Project : Detail Engineering Survey & Design of Khurkot-Ghurmi Sector

ANALYSIS OF RATE
Providing and placing machine mixed cement concrete , M20 for the abutment, pier, wall etc.
Item no. 15 including compaction, curing, testing and lead 30m. etc. all complete as per specification
and drawing.
Unit-1 Cum
Description Particular Quantity Unit Rate Amount Total
a) Skilled 0.90 M/D 460.00 414.00
Labour
b) Unskilled 9.00 M/D 320.00 2880.00 3294.00
Cement 0.32 mt 12000.00 3840.00
Aggregate 20-40mm 0.52 Cum 1200.00 624.00
Aggregate 10-20mm 0.22 Cum 1225.00 269.50
Aggregate 10mm & down 0.12 Cum 1250.00 150.00
Material
Coarse sand 0.45 Cum 650.00 292.50
Petrol 0.10 Lit 116.00 11.60
Diesel 3.00 Lit 85.00 255.00
Water 192.00 Lit 0.10 19.20 5461.80
Mixture 0.60 hr 500.00 300.00
Equipment
Vibrator 0.25 hr 80.00 20.00 320.00
Quality Control 2.5% of total 226.90
Actual Cost 9302.70
Rate per Cum 15% Contractors profit & OH 1395.40
NRs 10698.10 Total Rate 10698.10

Providing and placing machine mixed cement concrete, M25 for the super structure,
Item no. 16 deckslab, girder etc. including compaction, curing, testing and lead 30m. etc. all complete
as per specification and drawing.
Unit-1 Cum
Description Particular Quantity Unit Rate Amount Total
a)Skilled 0.80 M/D 460.00 368.00
Labour b) Unskilled 6.00 M/D 320.00 1920.00
c) Operator 0.20 M/D 460.00 92.00 2380.00
Cement 0.375 mt 12000.00 4500.00
Aggregate 20-40mm 0.58 Cum 1225.00 710.50
Aggregate 10-20mm 0.30 Cum 1250.00 375.00
Material Coarse sand 0.45 Cum 650.00 292.50
Petrol 0.10 Lit 116.00 11.60
Diesel 3.00 Lit 85.00 255.00
Water 225.00 Lit 0.10 22.50 6167.10
Mixture 0.60 hr 500.00 300.00
Equipment
Vibrator 0.25 hr 80.00 20.00 320.00
Quality Control 2.5% of total 221.68
Actual Cost 9088.78
Rate per Cum 15% Contractors profit & OH 1363.32
NRs 10452.09 Total Rate 10452.09

Analysis of Rates-28
Khurkot-Ghurmi Sector Appendix - 3

Government of Nepal
Ministry of Physical Planning and Works
Department of Roads
Puspalal ( Mid -hill ) Highway Project
Babarmahal, Kathmandu.

Project : Detail Engineering Survey & Design of Khurkot-Ghurmi Sector

ANALYSIS OF RATE
Providing , Preparing and Installing form work including necessary supports and removing
Item no. 17
after completion for foundation and footings.(Scrap value neglected)
( Assuming the plank shall be used eight times )
(Assuming the struts,ballies,etc. can be used for 12 times.)
Unit-10 Sqm
Description Particular Quantity Unit Rate Amount Total
a)Skilled 1.50 M/D 460.00 690.00
Labour
b) Unskilled 2.00 M/D 320.00 640.00 1330.00
Planks 38mm thick. 0.42 Cum 3750.00 1575.00
Materials struts, ballies, etc. 0.00 Cum 0.00 0.00
Nails,spikes,etc. 1.00 Kg 90.00 90.00 1665.00
Actual Cost 2995.00
Rate per Sqm 15% Contractors profit & OH 449.25
NRs 344.43 Total Rate 3444.25

Providing and laying Reinforcement including cutting, bending, binding, fixing in position
Item no. 18
and lead 30m. etc. all complete as per specification and drawing.
Unit- 1Mt
Description Particular Quantity Unit Rate Amount Total
a)Skilled 12.00 M/D 460.00 5520.00
Labour
b) Unskilled 12.00 M/D 320.00 3840.00 9360.00
Reinforcement 1.15 Mt 75000.00 86250.00
Materials
Binding Wire 10.00 Kg 95.00 950.00 87200.00
Actual Cost 96560.00
NRs Rate per Mt 15% Contractors profit & OH 14484.00
111044.00 Total Rate 111044.00

Providing and laying Random rubble stone masonry in cement mortar including scaffolding,
Item no. 19 curing, preparation of mortar etc. complete, masoned height 0-5m, lead 30m (Using
Concrete mixer) mortar 35% (cement :sand) 1:4
Unit-1 Cum
Description Particular Quantity Unit Rate Amount Total
a)Skilled 1.50 M/d 460.00 690.00
Labour
b)Unskilled 3.50 M/d 320.00 1120.00 1810.00
Stone 1.15 Cum 900.00 1035.00
Cement 0.155 Mt 12000.00 1860.00
Material Sand 0.45 Cum 650.00 292.50
water 100.00 litre 0.10 10.00
Diesel 1.00 litre 85.00 85.00 3282.50
Equipment Concrete Mixture 0.15 hr 500.00 75.00 75.00
Quality control 1.5% of total 77.51
Actual Cost 5245.01
Rate per Cum 15% Contractors profit & OH 786.75
NRs 6031.76 Total Rate 6031.76

Analysis of Rates-29
Khurkot-Ghurmi Sector Appendix - 3

Government of Nepal
Ministry of Physical Planning and Works
Department of Roads
Puspalal ( Mid -hill ) Highway Project
Babarmahal, Kathmandu.

Project : Detail Engineering Survey & Design of Khurkot-Ghurmi Sector

ANALYSIS OF RATE
Back filling behind abutment by sand and gravel spreading layers including sprinkling water
Item no. 20
and manual compaction with haulage 10m.
Unit-1 Cum
Description Particular Quantity Unit Rate Amount Total
a)Skilled 0.00 M/d 0.00 0.00
Labour
b)Unskilled 0.70 M/d 320.00 224.00 224.00
Sand 0.55 Cum 650.00 357.50
Material
Gravel 0.55 Cum 600.00 330.00 687.50
Tools & Plants 3% of labour cost 6.72
Actual Cost 918.22
Rate per Cum 15% Contractors profit & OH 137.73
NRs 1055.95 Total Rate 1055.95

Providing and laying RCC pipes with or without collars, jointed with stiff mixture of cement
Item no. 21
mortar in the proportion of 1:2 ( 1 cement : 2 fine sand ), lead upto 100m.
a. 600mm dia ( Int ) RCC Hume Pipe
Unit-Rm
Description Particular Quantity Unit Rate Amount Total
Skilled 0.281 M/D 460.00 129.26
Laour
Unskilled 1.094 M/D 320.00 350.08 479.34
RCC Hume Pipe ( 600 dia ) 1.00 Rm 4725.00 4725.00
Cement 0.0068 Mt 12000.00 81.76
Material
Sand 0.0090 Cum 650.00 5.85
Jute 0.219 Kg 100.00 21.90 4834.51
Tools & Plants 3 % of total 159.42
Actual Cost 5473.26
Rate per Rm 15% Contractors profit & OH 820.99
NRs 6294.25 Total Rate 6294.25

b. 900mm dia ( Int ) RCC Hume Pipe


Unit-Rm
Description Particular Quantity Unit Rate Amount Total
Skilled 0.344 M/D 460.00 158.24
Laour
Unskilled 1.562 M/D 320.00 499.84 658.08
RCC Hume Pipe ( 900 dia ) 1.000 Rm 8465.00 8465.00
Cement 0.0091 Mt 12000.00 108.74
Material
Sand 0.013 Cum 650.00 8.45
Jute 0.375 Kg 100.00 37.50 8619.69
Tools & Plants 3 % of total 278.33
Actual Cost 9556.11
Rate per Rm 15% Contractors profit & OH 1433.42
NRs 10989.52 Total Rate 10989.52

Analysis of Rates-30
Khurkot-Ghurmi Sector Appendix - 3

Government of Nepal
Ministry of Physical Planning and Works
Department of Roads
Puspalal ( Mid -hill ) Highway Project
Babarmahal, Kathmandu.

Project : Detail Engineering Survey & Design of Khurkot-Ghurmi Sector

ANALYSIS OF RATE
Item no. 22 Providing and laying two layers of Tarfelt
Unit-10 Sqm
Description Particular Quantity Unit Rate Amount Total
Skilled 2.300 M/D 460.00 1058.00
Laour
Unskilled 4.600 M/D 320.00 1472.00 2530.00
Tarfelt 22.000 Sqm 100.00 2200.00
Bitumin 25.000 Kg 80.00 2000.00
Material
Sand 0.310 Cum 650.00 201.50
Wood 80.000 Kg 4.30 344.00 4745.50
Actual Cost 7275.50
Rate per Sqm 15% Contractors profit & OH 1091.33
NRs 836.68 Total Rate 8366.83

Fabrication of Gabion boxes/mattresses with diapharagms including rolling, cutting and


weaving, assembling it, placing in position including stretching, forming compartments,
Item no. 23
tying the side and diaphargms with binding wire in each mesh, filling gabion box with stone
including dressing, beding, bonding and all transportation as per specification.
a. (3 x 1 x 1) box size
Unit- Box
Description Particular Quantity Unit Rate Amount Total
i) Gabion Box Weaving
Skilled 0.50 M/D 460.00 230.00
Unskilled 0.22 M/D 320.00 70.40
ii)Plancing in position and
tightening&
Labour
Unskilled 1.04 M/D 320.00 332.80
iii) Filling stone in gabion
box
Skilled 0.75 M/D 460.00 345.00
Unskilled 2.25 M/D 320.00 720.00 1698.20
GI wire ( 10 SWG ) 35.01 Kg 85.00 2975.85
Selvedge wire 4.51 Kg 85.00 383.35
Material
Binding Wire (12 SWG) 1.81 Kg 95.00 171.95
Boulder / stone 3.30 Cum 900.00 2970.00 6501.15
Actual Cost 8199.35
Rate per Cum 15% Contractors profit & OH 1229.90
NRs 3143.08 Total Rate 9429.25

Analysis of Rates-31
Khurkot-Ghurmi Sector Appendix - 3

Government of Nepal
Ministry of Physical Planning and Works
Department of Roads
Puspalal ( Mid -hill ) Highway Project
Babarmahal, Kathmandu.

Project : Detail Engineering Survey & Design of Khurkot-Ghurmi Sector

ANALYSIS OF RATE

b. (2 x 1 x 1) box size
Unit- Box
Description Particular Quantity Unit Rate Amount Total
i) Gabion Box Weaving

Skilled 0.34 M/D 460.00 156.40


Unskilled 0.15 M/D 320.00 48.00
ii)Plancing in position and
Labour tightening&
Unskilled 0.75 M/D 320.00 240.00
iii) Filling stone in gabion
box
Skilled 0.50 M/D 460.00 230.00
Unskilled 1.50 M/D 320.00 480.00 1154.40
GI wire ( 10 SWG ) 24.15 Kg 85.00 2052.75
selvedge wire 3.41 Kg 85.00 289.85
Materials
Binding Wire (12 SWG) 1.30 Kg 95.00 123.50
Boulder / stone 2.20 Cum 900.00 1980.00 4446.10
Actual Cost 5600.50
Rate per Cum 15% Contractors profit & OH 840.08
NRs 3220.2875 Total Rate 6440.58

c. (1.5 x 1 x 1) box size


Unit- Box
Description Particular Quantity Unit Rate Amount Total
i) Gabion Box Weaving
Skilled 0.28 M/D 460.00 128.80
Unskilled 0.12 M/D 320.00 38.40
ii)Plancing in position and
tightening&
Labour
Unskilled 0.68 M/D 320.00 217.60
iii) filling stone in gabion
box
Skilled 0.38 M/D 460.00 172.50
Unskilled 1.13 M/D 320.00 360.00 917.30
GI wire ( 10 SWG ) 19.75 Kg 85.00 1678.75
selvedge wire 3.11 Kg 85.00 264.35
Materials
Binding Wire (12 SWG) 0.68 Kg 95.00 64.60
Boulder / stone 1.65 Cum 900.00 1485.00 3492.70
Actual Cost 4410.00
Rate per Cum 15% Contractors profit & OH 661.50
NRs 3381 Total Rate 5071.50

Analysis of Rates-32
Khurkot-Ghurmi Sector Appendix - 3

Government of Nepal
Ministry of Physical Planning and Works
Department of Roads
Puspalal ( Mid -hill ) Highway Project
Babarmahal, Kathmandu.

Project : Detail Engineering Survey & Design of Khurkot-Ghurmi Sector

ANALYSIS OF RATE
Item no. 24 Providing , laying and fixing of Geotextile ( filter fabrics )
Unit- Sqm
Description Particular Quantity Unit Rate Amount Total
Skilled labour - M/d - -
Labour
Unskilled 0.017 M/d 320.00 5.44 5.44
Marerial Geotextile 1.20 Sqm 70.00 84.00 84.00
Actual Cost 89.44
Rate per Sqm 15% Contractors profit & OH 13.42
NRs 102.86 Total Rate 102.86

Item no. 25 Providing and painting of two coats of enamel painting with one coat primer
Unit- 100 Sqm
Description Particular Quantity Unit Rate Amount Total
Skilled labour 12.00 M/d 460.00 5520.00
Labour
Unskilled 8.00 M/d 320.00 2560.00 8080.00
Primer 8.00 Lit 230.00 1840.00
Marerial
Enamel paint 16.00 Lit 300.00 4800.00 6640.00
Actual Cost 14720.00
Rate per Sqm 15% Contractors profit & OH 2208.00
NRs 169.28 Total Rate 16928.00

Supplying and erecting traffic sign in place including 50mm dia. Steel tube, 2mm. thick steel
Item no. 26 plate, cement concrete, painting, writing and supporting steel angle nut and bolt etc.
complete.
a. 60cm. Dia. Circular, 60cm. equilateral traingle and 60cm.x 45cm. rectangular shaped sign (single
post).
Unit- 1 no.
Description Particular Quantity Unit Rate Amount Total
Skilled labour 0.033 M/d 460.00 15.18
Labour
Unskilled 0.088 M/d 320.00 28.16 43.34
Enamel paint 0.10 lit 300.00 30.00
M15/20 PCC 0.03 m3 7302.92 219.09
Marerial Steel plate 0.25 m2 1805.50 451.38
Formwork 0.36 m2 299.50 107.82
Steel tube 2.50 m 115.00 287.50 1095.78
Actual Cost 1139.12
Rate per no. 15% Contractors profit & OH 170.87
NRs 1309.99 Total Rate 1309.99

Analysis of Rates-33
Khurkot-Ghurmi Sector Appendix - 3

Government of Nepal
Ministry of Physical Planning and Works
Department of Roads
Puspalal ( Mid -hill ) Highway Project
Babarmahal, Kathmandu.

Project : Detail Engineering Survey & Design of Khurkot-Ghurmi Sector

ANALYSIS OF RATE
b. 1.2m.x 0.75m. Size bigger traffic sign with back support and two or more post.
Unit- 1 no.
Description Particular Quantity Unit Rate Amount Total
Skilled labour 0.085 M/d 460.00 39.10
Labour
Unskilled 0.30 M/d 320.00 96.00 135.10
Enamel paint 0.40 lit 300.00 120.00
M15/20 PCC 0.12 m3 7302.92 876.35
Marerial Steel plate 1.00 m2 1805.50 1805.50
Formwork 1.00 m2 299.50 299.50
Steel tube 5.00 m 115.00 575.00 3676.35
Actual Cost 3811.45
Rate per no. 15% Contractors profit & OH 571.72
NRs 4383.17 Total Rate 4383.17

Supplying and applying paint for Road marking including cleaning, watering, brooming etc.
Item no. 27
all complete ( 10cm wide strip ).
Unit- Rm
Description Particular Quantity Unit Rate Amount Total
Skilled labour 0.005 M/d 460.00 2.30
Labour
Unskilled 0.007 M/d 320.00 2.24 4.54
Marerial Road marking paint 0.070 lit 450.00 31.50 31.50
Actual Cost 36.04
Rate per Rm. 15% Contractors profit & OH 5.41
NRs 41.45 Total Rate 41.45

Providing and placing machine mixed cement concrete M20 for the foundation and footing
Item no. 28 etc. including compaction, curing, testing and lead 30m. etc. all complete as per
specification and drawing.
Unit-1 Cum
Description Particular Quantity Unit Rate Amount Total
a)Skilled 0.50 M/D 460.00 175.00
Labour
b) Unskilled 3.50 M/D 320.00 700.00 875.00
Cement 0.32 mt 12000.00 4000.00
Aggregate 20-40mm 0.52 Cum 1200.00 312.00

Aggregate 10-20mm 0.22 Cum 1225.00 132.00


Material
Aggregate 10mm & down 0.12 Cum 1250.00 72.00
Coarse sand 0.45 Cum 650.00 112.50
Petrol 0.10 Lit 116.00 7.80
Diesel 3.00 Lit 60.18 180.53
Water 192.00 Lit 0.10 180.53 4997.36
Mixture 0.60 hr 500.00 120.00
Equipment
Vibrator 0.25 hr 80.00 25.00 145.00
Quality Control 2.5% of total 150.43
Actual Cost 6167.79

Analysis of Rates-34
Khurkot-Ghurmi Sector Appendix - 3

Government of Nepal
Ministry of Physical Planning and Works
Department of Roads
Puspalal ( Mid -hill ) Highway Project
Babarmahal, Kathmandu.

Project : Detail Engineering Survey & Design of Khurkot-Ghurmi Sector

ANALYSIS OF RATE
Rate per Cum 15% Contractors profit & OH 925.17
NRs 7092.96 Total Rate 7092.96

Analysis of Rates-35
Khurkot-Ghurmi Sector Appendix - 3

Government of Nepal
Ministry of Physical Planning and Works
Department of Roads
Puspalal ( Mid -hill ) Highway Project
Babarmahal, Kathmandu.

Project : Detail Engineering Survey & Design of Khurkot-Ghurmi Sector

ANALYSIS OF RATE
Supplying and placing R.C.C. kilometer post including excavation, back filling, painting and
Item no. 29
writing etc. all complete as per specification.
a. Standard kilometer post (placed at each km.)
Unit- 1 no.
Description Particular Quantity Unit Rate Amount Total
Skilled labour 0.03 M/d 460.00 13.80
Labour
Unskilled 0.116 M/d 320.00 37.12 50.92
M20/20 RCC 0.06 m3 6167.79 370.07
M15/20 PCC 0.09 m3 7302.92 657.26
Marerial Formwork 0.50 m2 299.50 149.75
Enamel paint 0.12 lit 300.00 36.00
Reinforcement Bar 7.50 kg 96.56 724.20 1937.28
Actual Cost 1988.20
Rate per no. 15% Contractors profit & OH 298.23
NRs 2286.43 Total Rate 2286.43

b. Bigger kilometer post (placed at each 5 km.)


Unit- 1 no.
Description Particular Quantity Unit Rate Amount Total
Skilled labour 0.08 M/d 460.00 36.80
Labour
Unskilled 0.30 M/d 320.00 96.00 132.80
M20/20 RCC 0.17 m3 6167.79 1048.52
M15/20 PCC 0.23 m3 7302.92 1679.67
Marerial Formwork 1.30 m2 299.50 389.35
Enamel paint 0.40 lit 300.00 120.00
Reinforcement Bar 8.60 kg 96.56 830.42 4067.96
Actual Cost 4200.76
Rate per no. 15% Contractors profit & OH 630.11
NRs 4830.88 Total Rate 4830.88

Supplying and fixing in place R.C.C. delineator and guard post including excavation, back
Item no. 30
filling, painting and erection etc. all complete as per drawing.
Unit- 1 no.
Description Particular Quantity Unit Rate Amount Total
Skilled labour 0.021 M/d 460.00 9.66
Labour
Unskilled 0.055 M/d 320.00 17.60 27.26
M20/20 RCC 0.03 m3 6167.79 185.03
Formwork 0.54 m2 299.50 161.73
Marerial
Enamel paint 0.18 lit 300.00 54.00
Reinforcement Bar 2.82 lit 96.56 272.30 673.06
Actual Cost 700.32
Rate per no. 15% Contractors profit & OH 105.05
NRs 805.37 Total Rate 805.37

Analysis of Rates-36
Burtibang - Patihalne Road Project

Government of Nepal
Ministry of Physical Infrastructure and Transport
Department of Roads
BRIDGE PROJECT
Chakupat, Lalitpur.

Feasibility Study, Detailed Engineering Survey, Soil investigation, Hydrological Study and Detailed Design of Br

ANALYSIS OF RATE

Sp. No: 905 Earthwork excavating and loading by excavator (PC - 200 ) in Hard Soil / Gravel / BMS

Description Particular Quantity Unit Rate


a)Skilled 0.0 M/D
Labour b) Unskilled 0.00469 M/D 550.00
c) Operator 0.0 M/D
Material Diesel 0.1500 Lit 87.61
Lubricant ( 1% of Fuel )
Equipment Hudraulic excavator 0.0220 Hr 1,800.00
Actual Cost
Rate per Cum 15% Contractors profit &
NRs 63.76 Total Rate

Earthwork excavation for trenches with combination of Manual and Machined excavation ( Hard Soil
Sp. No: 905
Hard soil/Gravel BMS

Description Particular Quantity Unit Rate


Mannual Excavation ( 10% ) 0.10 Cum 849.75
Machined Excavation ( 90% ) 0.90 Cum 55.44
Actual Cost
Rate per Cum 15% Contractors profit &
NRS 155.10 Total Rate

Earth work excavation for trenches including shoring, struting, bracing, sheeting and disposal dispos
Sp. No: 905 ( c ) etc. all complete as per specification. ( For soft rocks)
Norms No: 9.02

Description Particular Quantity Unit Rate


Labour Unskilled 3.00 M/D 550.00
Tool & Plants 3% of Labour
Actual Cost
Rate per Cum 15% Contractors profit &

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

ANALYSIS OF RATE
NRS 1954.43 Total Rate

Sp. No: 905 Earthwork excavating and loading by excavator ( PC - 200 ) in Soft Rock

Description Particular Quantity Unit Rate


a)Skilled 0.0 M/D
Labour b) Unskilled 0.00469 M/D 550.00
c) Operator 0.0 M/D
Material Diesel 0.1500 Lit 87.61
Lubricant ( 1% of Fuel )
Equipment Excavator + Breaker 0.0220 Hr 2,100.00
Actual Cost
Rate per Cum 15% Contractors profit &
NRs 71.35 Total Rate

Sp. No: 905 Earthwork excavation for trenches with combination of Manual and Machined excavation ( Soft Rock
Soft Rock

Description Particular Quantity Unit Rate


Mannual Excavation ( 10% ) 0.10 Cum 1699.50
Machined Excavation ( 90% ) 0.90 Cum 62.04
Actual Cost
Rate per Cum 15% Contractors profit &
NRS 259.66 Total Rate

Earth work excavation for trenches including shoring, struting, bracing, sheeting and disposal dispos
Sp. No: 905
etc. all complete as per specification. ( For Hard Rock )
9.02.905.d ( I )

Description Particular Quantity Unit Rate


Labour Unskilled 16.00 M/D 550.00
Tool & Plants 3% of Labour
Actual Cost
Rate per Cum 15% Contractors profit &
NRS 10423.60 Total Rate

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

ANALYSIS OF RATE
Sp. No: 905 Earthwork excavating and loading by excavator ( PC - 200 ) in Hard Rock

Description Particular Quantity Unit Rate


a)Skilled 0.0 M/D
Labour b) Unskilled 0.00469 M/D 550.00
c) Operator 0.0 M/D
Material Diesel 0.1500 Lit 87.61
Lubricant ( 1% of Fuel )
Equipment Excavator + Breaker 0.0220 Hr 2,100.00
Actual Cost
Rate per Cum 15% Contractors profit &
NRs 71.35 Total Rate

Earthwork excavation for trenches with combination of Manual and Machined excavation ( Hard Roc
Sp. No: 905
Hard Rock

Description Particular Quantity Unit Rate


Mannual Excavation ( 10% ) 0.10 Cum 9064.00
Machined Excavation ( 90% ) 0.90 Cum 62.04
Actual Cost
Rate per Cum 15% Contractors profit &
NRS 1106.57 Total Rate

Earthwork excavation for trenches with combination of Manual and Machined excavation ( All Type o
Sp. No: 905
All type of soil

Description Particular Quantity Unit Rate

Boulder Mixed Soil ( 75 % ) 0.75 Cum 134.87


Soft Rock ( 25% ) 0.25 Cum 225.79
Hard Rock ( 0% ) 0.00 Cum 962.24

Actual Cost
Rate per Cum 15% Contractors profit &
NRS 181.24 Total Rate

Earthwork excavation for protection works with combination of Manual and Machined excavation ( Al
Sp. No: 905
All type of soil

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

ANALYSIS OF RATE

Description Particular Quantity Unit Rate

Boulder Mixed Soil ( 100% ) 1.00 Cum 134.87


Soft Rock ( 0% ) 0.00 Cum 0.00
Hard Rock ( 0% ) 0.00 Cum 0.00

Actual Cost
Rate per Cum 15% Contractors profit &
NRS 155.10 Total Rate

Providing and placing machine mixed cement concrete for the foundation and footing as a levelling c
Sp. No: 2000 compaction, curing, testing and lead 30m. etc. all complete as per specification and drawing.
Norms No: 20.01

Description Particular Quantity Unit Rate


Skilled 0.50 M/D 740.00
Laour
Unskilled 3.50 M/D 550.00
Cement 0.22 mt 15000.00
Aggregate 20-40mm 0.65 Cum 2600.00
Aggregate 10 -20mm 0.25 Cum 2600.00
Material Sand 0.48 Cum 2600.00
Petrol 0.10 Lit 87.61
Diesel 3.00 Lit 87.61
Water 132.00 Lit 0.53
Mixer (0.28/ 0.20 m3 ) 0.60 hr 500.00
Equipment
Vibrator 0.25 hr 220.00
Quality Control 2.5 % of total
Actual Cost
Rate per Cum 15% Contractors profit &
NRs 11645.52 Total Rate

Sp. No: 2000 Providing and placing machine mixed cement concrete M20/40 for the foundation and footing etc. inc
testing and lead 30m. etc. all complete as per specification and drawing.
Norms No: 20.01 (ii)

Description Particular Quantity Unit Rate


a)Skilled 0.50 M/D 740.00
Labour
b) Unskilled 3.50 M/D 550.00
Cement 0.32 mt 15000.00
Aggregate 20-40mm 0.52 Cum 2600.00
Aggregate 10-20mm 0.22 Cum 2600.00
Aggregate 10mm & down 0.12 Cum 2600.00
Material
Coarse sand 0.45 Cum 2600.00

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

Material
ANALYSIS OF RATE
Petrol 0.10 Lit 87.61
Diesel 3.00 Lit 87.61
Water 192.00 Lit 0.53
Mixture 0.60 hr 500.00
Equipment
Vibrator 0.25 hr 220.00
Quality Control 2.5% of total
Actual Cost
Rate per Cum 15% Contractors profit &
NRs 13236.60 Total Rate

Sp. No: 2000 Providing and placing machine mixed cement concrete, M35/20 for the super structure, deckslab, gir
Norms No: 20.04 curing, testing and lead 30m. etc. all complete as per specification and drawing.

Description Particular Quantity Unit Rate


a)Skilled 0.80 M/D 740.00
Labour
b) Unskilled 6.00 M/D 550.00
Cement 0.450 t 15000.00
Aggregate 10-20mm 0.57 Cum 2600.00
Aggregate 10mm & down 0.33 Cum 2600.00
Material Coarse sand 0.44 Cum 2600.00
Petrol 0.10 Lit 87.61
Diesel 3.00 Lit 87.61
Water 270.00 Lit 0.53
Mixture 0.60 hr 500.00
Equipment
Vibrator 0.25 hr 220.00
Quality Control 2.5% of total
Actual Cost
Rate per Cum 15% Contractors profit &

17130.04
NRs Total Rate

Providing and laying Reinforcement including cutting, bending, binding, fixing in position and lead 30
Sp. No: 2000 specification and drawing.
20.07 ( ii )

Description Particular Quantity Unit Rate


a)Skilled 12.00 M/D 740.00
Labour
b) Unskilled 12.00 M/D 550.00
Reinforcement 1.15 Mt 83000.00
Materials
Binding Wire 10.00 Kg 100.00
Actual Cost
NRs Rate per Mt 15% Contractors OH
128719.50 Total Rate

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

ANALYSIS OF RATE

Providing , Preparing and Installing form work including necessary supports and removing after comp
footing.
Sp. No: 1804,1805
18.01 ( a )
( Assuming the Planks shall be used 8 times )
( Assuming the Struts, Ballies shall be used 12 times )

Description Particular Quantity Unit Rate


a)Skilled 1.50 M/D 740.00
Labour
b) Unskilled 2.00 M/D 550.00
Planks 38mm thick. 0.053 Cum 48050.00
Materials Struts, Ballies, etc 0.02 Cum 48050.00
Nails,spikes,etc. 1.00 Kg 105.00
Actual Cost
Rate per Sqm 15% Contractors OH
NRs 639.21 Total Rate

Sp. No: 2000 Providing and placing machine mixed cement concrete M20/40 for stem , abutment etc. including co
lead 30m. etc. all complete as per specification and drawing.
Norms No: 20.02 (ii)

Description Particular Quantity Unit Rate


a)Skilled 0.90 M/D 740.00
Labour
b) Unskilled 9.00 M/D 550.00
Cement 0.32 mt 15000.00
Aggregate 20-40mm 0.52 Cum 2600.00
Aggregate 10-20mm 0.22 Cum 2600.00
Aggregate 10mm & down 0.12 Cum 2600.00
Material
Coarse sand 0.45 Cum 2600.00
Petrol 0.10 Lit 87.61
Diesel 3.00 Lit 87.61
Water 192.00 Lit 0.53
Mixture 0.60 hr 500.00
Equipment
Vibrator 0.25 hr 220.00
Quality Control 2.5% of total
Actual Cost
Rate per Cum 15% Contractors profit &
NRs 17151.23 Total Rate

Sp. No: 2000 Providing and placing machine mixed cement concrete M30/20 for the superstructure, deckslab, gird
including compaction, curing, testing and lead 30m. etc. all complete as per specification and drawin
Norms No: 20.03 (iii)

Description Particular Quantity Unit Rate


a)Skilled 0.80 M/D 740.00
Labour

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

ANALYSIS OF RATE
Labour
b) Unskilled 6.00 M/D 550.00
Cement 0.41 mt 15000.00
Aggregate 10-20mm 0.57 Cum 2600.00
Aggregate 10mm & down 0.33 Cum 2600.00
Material Coarse sand 0.44 Cum 2600.00
Petrol 0.10 Lit 87.61
Diesel 3.00 Lit 87.61
Water 192.00 Lit 0.53
Mixture 0.60 hr 500.00
Equipment
Vibrator 0.25 hr 220.00
Quality Control 2.5% of total
Actual Cost
Rate per Cum 15% Contractors profit &
NRs 16802.32 Total Rate

Sp. No: 908 Backfilling in layers in foundation pits, trenches etc. including compaction, watering etc.required depth
Norms No: 9.10 ( a )

Description Particular Quantity Unit Rate


Labour Unskilled 2.10 M/D 550.00
Tools & Plants 3% of labour cost
Actual Cost
Rate per Cum 15% Contractors profit &
NRs 1368.10 Total Rate

Sp. No: 905 Back filling by excavator from excavated all type of soil

Description Particular Quantity Unit Rate


a)Skilled 0.0 M/D
Labour b) Unskilled 0.00469 M/D 550.00
c) Operator 0.0 M/D
Material Diesel 0.1500 Lit 87.61
Lubricant ( 1% of Fuel )
Equipment Hudraulic excavator 0.0220 Hr 1800.00
Actual Cost
Rate per Cum 15% Contractors profit &
NRs 63.76 Total Rate

Back filling in layers in foundation by combination of machine and manual with compaction all comple
Sp. No: 908

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

ANALYSIS OF RATE
Norms No: 9.10 ( a )

Description Particular Quantity Unit Rate


Manual ( 10% ) 0.1 Cum 1189.65
Machine ( 90% ) 0.9 Cum 55.44
Material Diesel 0.1100 Lit 87.61
Equipment Roller 0.1100 Hr 500.00
Actual Cost
Rate per Cum 15% Contractors profit &
NRs 268.51 Total Rate

Weep hole Providing and laying of 110 mm dia HPD pipe for weep hole in abutment wall incuding ctting and fixin
HDP and instruction.

Description Particular Quantity Unit Rate

Material HDP pipe of 110 mm dia 1.10 Rm 345.45

Actual Cost
15% Contractors profit &
Rate per Cum Total Rate
NRS 436.99

Sp. No: 905 Road way excavation including disposal upto 10m and lift upto 1.5 m etc. all complete as per specific
Norms No: 9.01
Hard soil/Gravel BMS

Description Particular Quantity Unit Rate


Labour Unskilled 1.00 M/D 550.00
Tool & Plants 3% of Labour
Actual Cost
Rate per Cum 15% Contractors profit &
NRS 651.48 Total Rate

Sp. No: 905 Road way excavating and loading by excavator (PC - 200 ) in Hard Soil / Gravel / BMS

Description Particular Quantity Unit Rate


a)Skilled 0.0 M/D
Labour b) Unskilled 0.00469 M/D 550.00
c) Operator 0.0 M/D

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

ANALYSIS OF RATE
Material Diesel 0.1500 Lit 87.61
Lubricant ( 1% of Fuel )
Equipment Hudraulic excavator 0.0220 Hr 1,800.00
Actual Cost
Rate per Cum 15% Contractors profit &
NRs 63.76 Total Rate

Road way excavation with combination of Manual and Machined excavation


Sp. No: 905
Hard soil/Gravel BMS

Description Particular Quantity Unit Rate


Manual Excavation ( 10% ) 0.10 Cum 566.50
Machine Excavation ( 90% ) 0.90 Cum 55.44
Actual Cost
Rate per Cum 15% Contractors profit &
NRS 122.53 Total Rate

Road way excavation including disposal upto 10m and lift upto 1.5 m etc. all complete as per specific
Sp. No: 905

Soft rock

Description Particular Quantity Unit Rate


Labour Unskilled 2.75 M/D 550.00
Tool & Plants 3% of Labour
Actual Cost
Rate per Cum 15% Contractors profit &
NRS 1791.56 Total Rate

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

ANALYSIS OF RATE
Sp. No: 905 Road way excavating and loading by excavator ( PC - 200 ) in Soft Rock

Description Particular Quantity Unit Rate


a)Skilled 0.0 M/D
Labour b) Unskilled 0.00469 M/D 550.00
c) Operator 0.0 M/D
Material Diesel 0.1500 Lit 87.61
Lubricant ( 1% of Fuel )
Equipment Excavator + Breaker 0.0220 Hr 2,100.00
Actual Cost
Rate per Cum 15% Contractors profit &
NRs 71.35 Total Rate

Road way excavation with combination of Manual and Machined excavation


Sp. No: 905
Soft Rock

Description Particular Quantity Unit Rate


Manual Excavation ( 10% ) 0.10 Cum 1557.88
Machined Excavation ( 90% ) 0.90 Cum 62.04
Actual Cost
Rate per Cum 15% Contractors profit &
NRS 243.37 Total Rate

Road way excavation including disposal upto 10m and lift upto 1.5 m etc. all complete as per specific
Sp. No: 905

Hard rock

Description Particular Quantity Unit Rate


Labour Unskilled 12.00 M/D 550.00
Tool & Plants 3% of Labour
Actual Cost
Rate per Cum 15% Contractors profit &
NRS 7817.70 Total Rate

Sp. No: 905 Road way excavating and loading by excavator ( PC - 200 ) in Hard Rock

Description Particular Quantity Unit Rate


a)Skilled 0.0 M/D
Labour

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

ANALYSIS OF RATE
Labour b) Unskilled 0.00469 M/D 550.00
c) Operator 0.0 M/D
Material Diesel 0.1500 Lit 87.61
Lubricant ( 1% of Fuel )
Equipment Excavator + Breaker 0.0220 Hr 2,100.00
Actual Cost
Rate per Cum 15% Contractors profit &
NRs 71.35 Total Rate

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

ANALYSIS OF RATE
Road way excavation with combination of Manual and Machined excavation
Sp. No: 905
Hard Rock

Description Particular Quantity Unit Rate


Manual Excavation ( 10% ) 0.10 Cum 6798.00
Machined Excavation ( 90% ) 0.90 Cum 62.04
Actual Cost
Rate per Cum 15% Contractors profit &
NRS 845.98 Total Rate

Road way excavation with combination of Manual and Machined excavation in all type of Soil
Sp. No: 905
All Type

Description Particular Quantity Unit Rate


Boulder Mixed Soil ( 100% ) 1.00 Cum 106.55
Soft Rock ( 0% ) 0.00 Cum 211.63
Hard Rock ( 0% ) 0.00 Cum 735.64
Actual Cost
Rate per Cum 15% Contractors profit &
NRS 122.53 Total Rate

Disposal of excavated earth of all type of material including loading by machine and haulage as per in
Sp. No: 905
All type of soil

Description Particular Quantity Unit Rate


As per attached transportation
sheet 1.00 Cum 60.75
Actual Cost
Rate per Cum 15% Contractors profit &
NRS 69.86 Total Rate

Formation of embankment including compaction in layers not exceeding 150mm. Compacted depth, w
Sp. No: 905 all complete as per specification.
Norms No: 9.05.01

Description Particular Quantity Unit Rate


a)Skilled 0.002 M/d 740.00
Labour
b)Unskilled 0.008 M/d 550.00
Suitable material 1.10 Cum 260.00
Material Fuel 0.12 litre 87.61
Water 100.00 litre 0.53
Grader 0.005 Hr 1600.00
Equipment

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

ANALYSIS OF RATE
Equipment
Roller Vibrator 0.017 Hr 700.00
Tools & Plants 3% of labour cost
Actual Cost
Rate per Cum 15% Contractors profit &
NRs 431.79 Total Rate

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

ANALYSIS OF RATE

Subgrade construction and preparation of formation in cutting ( other than rock excavation ) including
Sp. No: 1003
Norms No: 10.01

Description Particular Quantity Unit Rate


a)Skilled 0.010 M/d 740.00
Labour
b)Unskilled 0.100 M/d 550.00
Material Diesel 0.122 Lit 87.61
Grader 0.010 Hr 1600.00
Equipment
Roller - 8-10t 0.017 Hr 500.00
Actual Cost
Rate per Cum 15% Contractors profit &
NRs 112.23 Total Rate

Rate of sub grade construction per square meter =


Average thickness of subgrade construction = 0.15m
Rate of sub grade construction per Sqm = 98.10/6.666 16.83 Rate per Sqm

Providing, laying, spreading, levelling and compaction of natural sand gravel sub-base grading as per
Sp. No: 1201 specification lead upto 10m
Norms No: 12.01

Description Particular Quantity Unit Rate


a)Skilled 0.005 M/d 740.00
Labour
b)Unskilled 0.040 M/d 550.00
Sub base aggregate 1.28 Cum 1750.00
Material
Diesel 0.792 litre 87.61
Grader 0.022 hr 1600.00
Vibrator roller 0.022 hr 700.00
Equipment
Water bowser 0.038 hr 550.00
Loader 0.011 hr 1000.00
Actual Cost
Rate per Cum 15% Contractors profit &
NRs 2780.23 Total Rate

Sp. No: 1202 Providing, laying, spreading, watering, levelling and compaction of of crusher run materials for base c
Norms No: 12.06

Description Particular Quantity Unit Rate


a)Skilled 0.005 M/d 740.00
Labour

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

ANALYSIS OF RATE
Labour
b)Unskilled 0.020 M/d 550.00
Base aggregate 1.200 Cum 2600.00
Material
Diesel 0.990 litre 87.61
Grader 0.033 hr 1600.00
Vibrator roller 0.033 hr 700.00
Equipment
Water bowser 0.033 hr 550.00
Loader 0.011 hr 1000.00
Actual Cost
Rate per Cum 15% Contractors profit &
NRs 3825.46 Total Rate

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

ANALYSIS OF RATE

Sp. No: 1301,1302 Providing and spraying bituminious Prime Coat / Tack Coat MC30/MC70 including cleaning the road
broom etc. before applying prime coat / Tack coat

Norms No: 13.03

Description Particular Quantity Unit Rate


Skilled 0.003 M/d 740.00
Labour
Unskilled 0.046 M/d 550.00
Bitumen 1.050 Lit 92.60
Materials
Kerosene 0.100 Lit 66.37
Diesel 0.275 Lit 87.61
Boiler 0.0025 hr 200.00
Equipment Sprayer 0.0025 hr 1300.00
Air compressor 0.0030 hr 250.00
Actual Cost
Rate per Lit 15% Contractors OH
NRs 183.98 Total Rate

Sp. No: 1307,1308


Providing mixing and laying Asphalt Concrete with compaction
Norms No: 13.10

Description Particular Quantity Unit Rate


Skilled 0.03 M/d 740.00
Labour Unskilled 0.13 M/d 550.00
Foreman 0.01 M/d 550.00
Bitumen 117.00 Lit 92.60
Cement 0.022 t 15000.00
Materials
Diesel 10.45 Lit 87.61
Aggregates 1.20 Cum 1750.00
Asphalt mixing plant 0.0440 Hr 400.00
Wheel Loader 0.6600 Hr 1000.00
Asphalt Paver 0.2200 Hr 1400.00
Equipment
Steel tyred Roller 0.5500 Hr 500.00
Pneumatic Roller 0.5500 Hr 1200.00
Tipper, Trucks 0.3200 Hr 450.00
Actual Cost
Rate per Cum 15% Contractors OH
NRs 18795.05 Total Rate

Sp. No: 905 Earth work excavation for trenches including shoring, struting, bracing, sheeting and disposal upto 10
Norms No: 9.02 complete as per specification. ( For hard soil/ Gravels)

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

ANALYSIS OF RATE

Description Particular Quantity Unit Rate


Labour Unskilled 1.50 M/D 550.00
Tool & Plants 3% of Labour
Actual Cost
15% Contractors profit &
Rate per Cum Total Rate
NRS 977.21

Earthwork excavation for trenches with combination of Manual and Machined excavation ( Hard Soil
Sp. No: 905
Hard soil/Gravel BMS

Description Particular Quantity Unit Rate


Mannual Excavation ( 10% ) 0.10 Cum 849.75
Machined Excavation ( 90% ) 0.90 Cum 55.44
Actual Cost
Rate per Cum 15% Contractors profit &
NRS 155.10 Total Rate

Earth work excavation for trenches including shoring, struting, bracing, sheeting and disposal dispos
Sp. No: 905 ( c ) etc. all complete as per specification. ( For soft rocks)
Norms No: 9.02

Description Particular Quantity Unit Rate


Labour Unskilled 3.00 M/D 550.00
Tool & Plants 3% of Labour
Actual Cost
Rate per Cum 15% Contractors profit &
NRS 1954.43 Total Rate

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

ANALYSIS OF RATE
Sp. No: 905 Earthwork excavation for trenches with combination of Manual and Machined excavation ( Soft Rock
Soft Rock

Description Particular Quantity Unit Rate


Mannual Excavation ( 10% ) 0.10 Cum 1699.50
Machined Excavation ( 90% ) 0.90 Cum 55.44
Actual Cost
Rate per Cum 15% Contractors profit &
NRS 252.83 Total Rate

Earth work excavation for trenches including shoring, struting, bracing, sheeting and disposal dispos
Sp. No: 905
etc. all complete as per specification. ( For Hard Rock )
9.02.905.d ( I )

Description Particular Quantity Unit Rate


Labour Unskilled 16.00 M/D 550.00
Tool & Plants 3% of Labour
Actual Cost
Rate per Cum 15% Contractors profit &
NRS 10423.60 Total Rate

Earthwork excavation for trenches with combination of Manual and Machined excavation ( Hard Roc
Sp. No: 905
Hard Rock

Description Particular Quantity Unit Rate


Mannual Excavation ( 10% ) 0.10 Cum 9064.00
Machined Excavation ( 90% ) 0.90 Cum 55.44
Actual Cost
Rate per Cum 15% Contractors profit &
NRS 1099.74 Total Rate

Earthwork excavation for trenches with combination of Manual and Machined excavation ( All Type o
Sp. No: 905
All type of soil

Description Particular Quantity Unit Rate

Boulder Mixed Soil ( 75 % ) 0.75 Cum 134.87


Soft Rock ( 18% ) 0.18 Cum 219.85

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

ANALYSIS OF RATE
Hard Rock ( 7% ) 0.07 Cum 956.30

Actual Cost
Rate per Cum 15% Contractors profit &
NRS 238.82 Total Rate

Backfilling in layers in foundation pits, trenches etc. including compaction, watering etc. complete lead
Sp. No: 908 upto 1.5m.
Norms No: 9.10 ( a )

Description Particular Quantity Unit Rate


Labour Unskilled 1.14 M/D 550.00
Tools & Plants 3% of labour cost
Actual Cost
Rate per Cum 15% Contractors profit &
NRs 742.68 Total Rate

Sp. No: 905 Back filling by excavator from excavated all type of soil

Description Particular Quantity Unit Rate


a)Skilled 0.0 M/D
Labour b) Unskilled 0.00469 M/D 550.00
c) Operator 0.0 M/D
Material Diesel 0.1500 Lit 87.61
Lubricant ( 1% of Fuel )
Equipment Hudraulic excavator 0.0220 Hr 1,800.00
Actual Cost
Rate per Cum 15% Contractors profit &
NRs 63.76 Total Rate

Back filling in layers in foundation by combination of machine and manual with compaction all comple
Sp. No: 908
Norms No: 9.10 ( a )

Description Particular Quantity Unit Rate


Manual ( 10% ) 0.1 Cum 645.81
Machine ( 90% ) 0.9 Cum 55.44
Material Diesel 0.1100 Lit 87.61
Equipment Roller 0.1100 Hr 700.00
Actual Cost
Rate per Cum 15% Contractors profit &

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

ANALYSIS OF RATE
NRs 231.27 Total Rate

Sp. No: 2401 Providing and laying Dry Stone Soling


Old Norms - 6(5)

Description Particular Quantity Unit Rate


a)Skilled 0.00 M/d 740.00
Labour
b)Unskilled 1.50 M/d 550.00
Material Stone 1.10 Cum 2400.00
Tools & Plants 3% of labour cost
Actual Cost
Rate per Cum 15% Contractors profit &
NRs 4013.21 Total Rate

Providing and placing machine mixed cement concrete for the foundation and footing etc. in M15 inc
Sp. No: 2000 testing and lead 30m. etc. all complete as per specification and drawing.
Norms No: 20.01

Description Particular Quantity Unit Rate


Skilled 0.50 M/D 740.00
Laour
Unskilled 3.50 M/D 550.00
Cement 0.26 mt 15000.00
Aggregate 20-40mm 0.53 Cum 1750.00
Aggregate 10 -20mm 0.24 Cum 1750.00
Aggregate 10 & down 0.11 Cum 1750.00
Material
Sand 0.46 Cum 2600.00
Petrol 0.10 Lit 87.61
Diesel 3.00 Lit 87.61
Water 156.00 Lit 0.53
Mixer (0.28/ 0.20 m3 ) 0.60 hr 500.00
Equipment
Vibrator 0.25 hr 220.00
Quality Control 2.5 % of total
Actual Cost
Rate per Cum 15% Contractors profit &
NRs 11086.31 Total Rate

Sp. No: 2000 Providing and placing machine mixed cement concrete M20 for the foundation and footing etc. includ
and lead 30m. etc. all complete as per specification and drawing.
Norms No: 20.01 (ii)

Description Particular Quantity Unit Rate


a)Skilled 0.50 M/D 740.00
Labour
b) Unskilled 3.50 M/D 550.00
Cement 0.32 mt 15000.00

Material

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

ANALYSIS OF RATE
Aggregate 20-40mm 0.52 Cum 1750.00
Aggregate 10-20mm 0.22 Cum 1750.00
Aggregate 10mm & down 0.12 Cum 1750.00
Material
Coarse sand 0.45 Cum 2600.00
Petrol 0.10 Lit 87.61
Diesel 3.00 Lit 87.61
Water 192.00 Lit 0.53
Mixture 0.60 hr 500.00
Equipment
Vibrator 0.25 hr 220.00
Quality Control 2.5% of total
Actual Cost
Rate per Cum 15% Contractors profit &
NRs 12073.10 Total Rate

Providing and placing machine mixed cement concrete , M20 for the abutment, pier, wall etc. includin
Sp. No: 2000 and lead 30m. etc. all complete as per specification and drawing.
Norms No: 20.02(ii)

Description Particular Quantity Unit Rate


a) Skilled 0.90 M/D 740.00
Labour
b) Unskilled 9.00 M/D 550.00
Cement 0.33 mt 15000.00
Aggregate 10-20mm 0.58 Cum 1750.00
Aggregate 10mm & down 0.30 Cum 1750.00
Material Coarse sand 0.44 Cum 2600.00
Petrol 0.10 Lit 87.61
Diesel 3.00 Lit 87.61
Water 198.00 Lit 0.53
Mixture 0.60 hr 500.00
Equipment
Vibrator 0.25 hr 220.00
Quality Control 2.5% of total
Actual Cost
Rate per Cum 15% Contractors profit &
NRs 16078.76 Total Rate

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

ANALYSIS OF RATE

Providing and placing machine mixed cement concrete, M25 for the super structure, deckslab, girder
Sp. No: 2000 curing, testing and lead 30m. etc. all complete as per specification and drawing.
Norms No: 20.03(ii)

Description Particular Quantity Unit Rate


a)Skilled 0.90 M/D 740.00
Labour
b) Unskilled 9.00 M/D 550.00
Cement 0.375 mt 15000.00
Aggregate 20-40mm 0.58 Cum 1750.00
Aggregate 10-20mm 0.30 Cum 1750.00
Material Coarse sand 0.45 Cum 2600.00
Petrol 0.10 Lit 87.61
Diesel 3.20 Lit 87.61
Water 225.00 Lit 0.53
Mixture 0.60 hr 500.00
Equipment
Vibrator 0.25 hr 220.00
Quality Control 2.5% of total
Actual Cost
Rate per Cum 15% Contractors profit &
NRs 16921.52 Total Rate

Providing , Preparing and Installing form work including necessary supports and removing after comp
Structures.(Scrap value neglected)
Sp. No: 1804,1805
18.01 ( a )
( Assuming the Planks shall be used 8 times )
( Assuming the Struts, Ballies shall be used 12 times )

Description Particular Quantity Unit Rate


a)Skilled 1.50 M/D 740.00
Labour
b) Unskilled 2.00 M/D 550.00
Planks 38mm thick. 0.05 Cum 48050.00
Materials Struts, Ballies, etc 0.02 Cum 48050.00
Nails,spikes,etc. 1.00 Kg 105.00
Actual Cost
Rate per Sqm 15% Contractors OH
NRs 639.21 Total Rate

Providing and laying Reinforcement including cutting, bending, binding, fixing in position and lead 30
Sp. No: 2000 specification and drawing.
20.07 ( ii )

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

ANALYSIS OF RATE

Description Particular Quantity Unit Rate


a)Skilled 12.00 M/D 740.00
Labour
b) Unskilled 12.00 M/D 550.00
Reinforcement 1.15 Mt 83000.00
Materials
Binding Wire 10.00 Kg 100.00
Actual Cost
NRs Rate per Mt 15% Contractors OH
128719.50 Total Rate

Sp. No: Providing and laying Random rubble stone masonry in cement mortar including scaffolding, curing, pr
2602,2603,2607 complete, masoned height 0-5m, lead 30m (Using Concrete mixer) (cement:sand) 1:3
26.03

Description Particular Quantity Unit Rate


RRM
Labour a)Skilled 1.5 M/d 740.00
b)Unskilled 3.50 M/d 550.00
Stone 1.15 Cum 2400.00
Cement 0.190 Mt 15000.00
Material Sand 0.40 Cum 2600.00
water 120.00 litre 0.53
Diesel 1.00 litre 87.61
Equipment Concrete Mixture 0.15 hr 500.00
Quality control 1.5% of total

Actual Cost
Rate per Cum 15% Contractors profit &
NRs 11397.89 Total Rate

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

ANALYSIS OF RATE

Sp. No: 2404,3110 Back filling with graded filter materials in layer behind abutment with necessary watering and compac
24.11

Description Particular Quantity Unit Rate


a)Skilled 0.00 M/d 0.00
Labour
b)Unskilled 0.80 M/d 550.00
Material Graded filter material 1.10 Cum 1750.00
Tools & Plants 3% of labour cost
Actual Cost
Rate per Cum 15% Contractors profit &
NRs 2734.93 Total Rate

18.08.02
Providing and assembling in position falsework for the construction of RCC superstrcture and removin
iii design & drawings as per specification. (Scrap value neglected)

( By using timber )
(Assumming height 6-9m)
(Assumming the timber shall be usid eight time)
Unit-10 Sqm of formworks
Description Particular Quantity Unit Rate

Labour
a)Skilled 40.00 M/D 740.00
b) Unskilled 50.00 M/D 550.00
timber 7.00 Cum 48050.00
Materials
Nails, spikes, etc 21.00 Kg 105.00
Actual Cost
Rate per Sqm 15% Contractors OH
NRs 45500.33 Total Rate

Providing and installing slab seal Expansion Joints including all necessaary axilliary and incidental
complete as per drawing and specification.
`19.02
Unit- m
Description Particular Quantity Unit Rate
Materials Expansion Joint 1.10 m 18719.00

Installation charge 12% of cost of Bearing including transportation


Actual Cost
Rate for Rm 15% Contractors profit &
NRs 26521.08 Total Rate

Providing and installing Elastomeric Bearing Pad including all necessary axilliary and incidental works
etc. complete as per drawing and specification.

Unit- 1 Set.

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

ANALYSIS OF RATE
Description Particular Quantity Unit Rate
Materials Bearing 1.00 no 47077.00
Installation Charge 12% of cost of Bearing including transportation
Actual Cost
Rate for 1 Set 15% Contractors profit &
NRs 60635.18 Total Rate

Providing and fitting of 100mm dia GI pipe for Drainage Spout including grating over pipe all comple
====
Unit- No
Description Particular Quantity Unit Rate
Plumber 0.09 M/d 740.00
Labour Helper 0.10 M/d 550.00
Unskilled 0.53 M/d 550.00
Pipe 1.50 Rm 1400.00
Material Red lead
Sundry's
NRs Grating 1.00 No LS
Actual Cost
Rate per No 15% Contractors profit &
3064.42 Total Rate

Providing, laying, spreading, watering, levelling and compaction of natural sand gravel subbase gradi
standard specification lead upto 10m (for manual works).
12.02

Unit- Cum
Description Particular Quantity Unit Rate
Skilled 0.01 M/d 460.00
Labour
Unskilled 1.05 M/d 320.00
Subbase agg. 1.28 Cum 600.00
Materials
Diesel 0.66 Lit 85.00
Equipment Road Roller 0.03 hr 2500.00
Actual Cost
Rate per Cum 15% Contractors OH
NRs 1423.01 Total Rate

Fabrication, Supply and placing in position of Machine made and Mechanically Selvedged Gabion b
mess type 100mmX120mm. with mesh wire 3mm dia, selvedge wire 3.9mm dia and lacing wire of 2
placing in position, tying the side and diaphargms with binding wire in each mesh all complete as per
Sp. No: 2401
24.02,01.a

(3 x 1 x 1) box size

Description Particular Quantity Unit Rate


Labour Unskilled 1.04 M/d 550.00
Machine Made Gabion Box 1.00 Box 3935.67
Material Binding Wire ( 11 swg ) 0.00 Kg
Binding Wire ( 12 swg ) 0.00 Kg
Prepared By: Checked By : Recommended By : ActualApproved
Cost By :
Rate per Cum 15% Contractors OH
NRs 1727.94 Total Rate
Burtibang - Patihalne Road Project

Government of Nepal
ysical Infrastructure and Transport
epartment of Roads
BRIDGE PROJECT
Chakupat, Lalitpur.

gation, Hydrological Study and Detailed Design of Bridges at Baglung District

ANALYSIS OF RATE

ator (PC - 200 ) in Hard Soil / Gravel / BMS

Unit-Cum
Amount Total
-
2.57 2.57
-
13.14 13.14
0.13
39.60 39.60
55.44
15% Contractors profit & OH 8.32
Total Rate 63.76

bination of Manual and Machined excavation ( Hard Soil / Gravel BMS )

Unit- Cum
Amount Total
84.98 84.98
49.90 49.90
134.87
15% Contractors profit & OH 20.23
Total Rate 155.10

g shoring, struting, bracing, sheeting and disposal disposal upto 10m and lift upto 1.5 m
soft rocks)

Unit- Cum
Amount Total
1,650.00 1650.00
49.50
1699.50
15% Contractors profit & OH 254.93

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

ANALYSIS OF RATE
Total Rate 1954.43

ator ( PC - 200 ) in Soft Rock

Unit- Cum
Amount Total
-
2.57 2.57
-
13.14 13.14
0.13
46.20 46.20
62.04
15% Contractors profit & OH 9.31
Total Rate 71.35

bination of Manual and Machined excavation ( Soft Rock )

Unit- Cum
Amount Total
169.95 169.95
55.84 55.84
225.79
15% Contractors profit & OH 33.87
259.66

g shoring, struting, bracing, sheeting and disposal disposal upto 10m and lift upto 1.5 m
Hard Rock )

Unit- Cum
Amount Total
8,800.00 8800.00
264.00
9064.00
15% Contractors profit & OH 1359.60
Total Rate 10423.60

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

ANALYSIS OF RATE
ator ( PC - 200 ) in Hard Rock

Unit-Cum
Amount Total
-
2.57 2.57
-
13.14 13.14
0.13
46.20 46.20
62.04
15% Contractors profit & OH 9.31
Total Rate 71.35

bination of Manual and Machined excavation ( Hard Rock )

Unit- Cum
Amount Total
906.40 906.40
55.84 55.84
962.24
15% Contractors profit & OH 144.34
1106.57

bination of Manual and Machined excavation ( All Type of Soil )

Unit- Cum
Amount Total

101.16 101.16
56.45 56.45
- 0.00

157.60
15% Contractors profit & OH 23.64
Total Rate 181.24

with combination of Manual and Machined excavation ( All Type of Soil )

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

ANALYSIS OF RATE
Unit- Cum
Amount Total

134.87 134.87
- 0.00
- 0.00

134.87
15% Contractors profit & OH 20.23
Total Rate 155.10

nt concrete for the foundation and footing as a levelling course etc. in M10/40 including
tc. all complete as per specification and drawing.

Unit-1 Cum
Amount Total
370.00
1,925.00 2295.00
3,300.00
1,690.00
650.00
1,248.00
8.76
262.83
69.96 7229.55
300.00
55.00 355.00
246.99
10126.54
15% Contractors profit & OH 1518.98
Total Rate 11645.52

nt concrete M20/40 for the foundation and footing etc. including compaction, curing,
per specification and drawing.

Unit-1 Cum
Amount Total
370.00
1,925.00 2295.00
4,800.00
1,352.00
572.00
312.00
1,170.00

8579.35

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

ANALYSIS OF RATE
8.76
262.83
101.76 8579.35
300.00
55.00 355.00
280.73
11510.08
15% Contractors profit & OH 1726.51
Total Rate 13236.60

nt concrete, M35/20 for the super structure, deckslab, girder etc. including compaction,
ete as per specification and drawing.

Unit-1 Cum
Amount Total
592.00
3,300.00 3892.00
6,750.00
1,482.00
858.00
1,144.00
8.76
262.83
143.10 10648.69
300.00
55.00 355.00
0.00
14895.69
15% Contractors profit & OH 2234.35

Total Rate 17130.04

ng cutting, bending, binding, fixing in position and lead 30m. etc. all complete as per

Unit- 1Mt
Amount Total
8,880.00
6,600.00 15480.00
95,450.00
1,000.00 96450.00
111930.00
15% Contractors OH 16789.50
Total Rate 128719.50

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

ANALYSIS OF RATE

rk including necessary supports and removing after completion for foundation and

Unit-10 Sqm
Amount Total
1,110.00
1,100.00 2210.00
2,522.63
720.75
105.00 3348.38
5558.38
15% Contractors OH 833.76
Total Rate 6392.13

nt concrete M20/40 for stem , abutment etc. including compaction, curing, testing and
tion and drawing.

Unit-1 Cum
Amount Total
666.00
4,950.00 5616.00
4,800.00
1,352.00
572.00
312.00
1,170.00
8.76
262.83
101.76 8579.35
300.00
55.00 355.00
363.76
14914.11
15% Contractors profit & OH 2237.12
Total Rate 17151.23

nt concrete M30/20 for the superstructure, deckslab, girder, abutement cap etc.
ad 30m. etc. all complete as per specification and drawing.

Unit-1 Cum
Amount Total
592.00
3892.00

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

ANALYSIS OF RATE
3,300.00 3892.00
6,150.00
1,482.00
858.00
1,144.00
8.76
262.83
101.76 10007.35
300.00
55.00 355.00
356.36
14610.71
15% Contractors profit & OH 2191.61
Total Rate 16802.32

hes etc. including compaction, watering etc.required depth and lead.

Unit-1Cum
Amount Total
1,155.00 1155.00
34.65
1189.65
15% Contractors profit & OH 178.45
Total Rate 1368.10

type of soil

Unit-Cum
Amount Total
-
2.57 2.57
-
13.14 13.14
0.13
39.60 39.60
55.44
15% Contractors profit & OH 8.32
Total Rate 63.76

nation of machine and manual with compaction all complete

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

ANALYSIS OF RATE

Unit-Cum
Amount Total
118.96
49.89 168.85
9.64 9.64
55.00 55.00
233.49
15% Contractors profit & OH 35.02
Total Rate 268.51

pe for weep hole in abutment wall incuding ctting and fixing all complete as per drawing

Unit- Rm
Amount Total

380.00 380.00

380.00
15% Contractors profit & OH 57.00
Total Rate 436.99

o 10m and lift upto 1.5 m etc. all complete as per specification.

Unit-Cum
Amount Total
550.00 550.00
16.50
566.50
15% Contractors profit & OH 84.98
Total Rate 651.48

ator (PC - 200 ) in Hard Soil / Gravel / BMS

Unit-Cum
Amount Total
-
2.57 2.57
-

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

ANALYSIS OF RATE
13.14 13.14
0.13
39.60 39.60
55.44
15% Contractors profit & OH 8.32
Total Rate 63.76

Manual and Machined excavation

Unit- Cum
Amount Total
56.65 56.65
49.90 49.90
106.55
15% Contractors profit & OH 15.98
Total Rate 122.53

o 10m and lift upto 1.5 m etc. all complete as per specification.

Unit- Cum
Amount Total
1,512.50 1512.50
45.38
1557.88
15% Contractors profit & OH 233.68
Total Rate 1791.56

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

ANALYSIS OF RATE
ator ( PC - 200 ) in Soft Rock

Unit- Cum
Amount Total
-
2.57 2.57
-
13.14 13.14
0.13
46.20 46.20
62.04
15% Contractors profit & OH 9.31
Total Rate 71.35

Manual and Machined excavation

Unit- Cum
Amount Total
155.79 155.79
55.84 55.84
211.63
15% Contractors profit & OH 31.74
Total Rate 243.37

o 10m and lift upto 1.5 m etc. all complete as per specification.

Unit- Cum
Amount Total
6,600.00 6600.00
198.00
6798.00
15% Contractors profit & OH 1019.70
Total Rate 7817.70

ator ( PC - 200 ) in Hard Rock

Unit-Cum
Amount Total
-

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

ANALYSIS OF RATE
2.57 2.57
-
13.14 13.14
0.13
46.20 46.20
62.04
15% Contractors profit & OH 9.31
Total Rate 71.35

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

ANALYSIS OF RATE
Manual and Machined excavation

Unit- Cum
Amount Total
679.80 679.80
55.84 55.84
735.64
15% Contractors profit & OH 110.35
Total Rate 845.98

Manual and Machined excavation in all type of Soil

Unit- Cum
Amount Total
106.55 106.55
- 0.00
- 0.00
106.55
15% Contractors profit & OH 15.98
Total Rate 122.53

aterial including loading by machine and haulage as per instruction of Engineer

Unit- Cum
Amount Total

60.75 60.75
60.75
15% Contractors profit & OH 9.11
Total Rate 69.86

ction in layers not exceeding 150mm. Compacted depth, watering and haulage 10m. etc.

Unit- Cum
Amount Total
1.48
4.40 5.88
286.00
10.51
53.00 349.51
8.00

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

ANALYSIS OF RATE
11.90 19.90
0.18
375.47
15% Contractors profit & OH 56.32
Total Rate 431.79

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

ANALYSIS OF RATE

rmation in cutting ( other than rock excavation ) including disposal of material.

Unit- Cum
Amount Total
7.40
55.00 62.40
10.69 10.69
16.00
8.50 24.50
97.59
15% Contractors profit & OH 14.64
Total Rate 112.23

ompaction of natural sand gravel sub-base grading as per table 12.1 of standard

Unit-Cum
Amount Total
3.70
22.00 25.70
2,240.00
69.39 2309.39
35.20
15.40
20.90
11.00 82.50
2417.59
15% Contractors profit & OH 362.64
Total Rate 2780.23

ing and compaction of of crusher run materials for base course lead upto 10m

Unit- Cum
Amount Total
3.70
14.70

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

ANALYSIS OF RATE
11.00 14.70
3,120.00
86.73 3206.73
52.80
23.10
18.15
11.00 105.05
3326.48
15% Contractors profit & OH 498.97
Total Rate 3825.46

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

ANALYSIS OF RATE

oat / Tack Coat MC30/MC70 including cleaning the road surface using wire, brushes,
coat

Unit: Lit
Amount Total
2.22
25.30 27.52
97.23
6.64
24.09 127.96
0.50
3.25
0.75 4.50
159.98
15% Contractors OH 24.00
Total Rate 183.98

e with compaction

Unit: Cum
Amount Total
22.20
71.50
5.50 99.20
10,834.20
330.00
915.52
2,100.00 14179.72
17.60
660.00
308.00
275.00
660.00
144.00 2064.60
16343.52
15% Contractors OH 2451.53
Total Rate 18795.05

g shoring, struting, bracing, sheeting and disposal upto 10m and lift upto 1.5 m etc. all
il/ Gravels)

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

ANALYSIS OF RATE
Unit- Cum
Amount Total
825.00 825.00
24.75
849.75
15% Contractors profit & OH 127.46
Total Rate 977.21

bination of Manual and Machined excavation ( Hard Soil / Gravel BMS )

Unit- Cum
Amount Total
84.98 84.98
49.90 49.90
134.87
15% Contractors profit & OH 20.23
Total Rate 155.10

g shoring, struting, bracing, sheeting and disposal disposal upto 10m and lift upto 1.5 m
soft rocks)

Unit- Cum
Amount Total
1,650.00 1650.00
49.50
1699.50
15% Contractors profit & OH 254.93
Total Rate 1954.43

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

ANALYSIS OF RATE
bination of Manual and Machined excavation ( Soft Rock )

Unit- Cum
Amount Total
169.95 169.95
49.90 49.90
219.85
15% Contractors profit & OH 32.98
252.83

g shoring, struting, bracing, sheeting and disposal disposal upto 10m and lift upto 1.5 m
Hard Rock )

Unit- Cum
Amount Total
8,800.00 8800.00
264.00
9064.00
15% Contractors profit & OH 1359.60
Total Rate 10423.60

bination of Manual and Machined excavation ( Hard Rock )

Unit- Cum
Amount Total
906.40 906.40
49.90 49.90
956.30
15% Contractors profit & OH 143.44
1099.74

bination of Manual and Machined excavation ( All Type of Soil )

Unit- Cum
Amount Total

101.16 101.16
39.57 39.57

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

ANALYSIS OF RATE
66.94 66.94

207.67
15% Contractors profit & OH 31.15
Total Rate 238.82

hes etc. including compaction, watering etc. complete lead 10m. And depth of foundation

Unit-1Cum
Amount Total
627.00 627.00
18.81
645.81
15% Contractors profit & OH 96.87
Total Rate 742.68

type of soil

Unit-Cum
Amount Total
-
2.57 2.57
-
13.14 13.14
0.13
39.60 39.60
55.44
15% Contractors profit & OH 8.32
Total Rate 63.76

nation of machine and manual with compaction all complete

Unit-Cum
Amount Total
64.58
49.89 114.47
9.64 9.64
77.00 77.00
201.11
15% Contractors profit & OH 30.17

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

ANALYSIS OF RATE
Total Rate 231.27

Unit-1 Cum
Amount Total
-
825.00 825.00
2,640.00 2640.00
24.75
3489.75
15% Contractors profit & OH 523.46
Total Rate 4013.21

nt concrete for the foundation and footing etc. in M15 including compaction, curing,
er specification and drawing.

Unit-1 Cum
Amount Total
370.00
1,925.00 2295.00
3,900.00
927.50
420.00
192.50
1,196.00
8.76
262.83
82.68 6990.27
300.00
55.00 355.00
0.00
9640.27
15% Contractors profit & OH 1446.04
Total Rate 11086.31

nt concrete M20 for the foundation and footing etc. including compaction, curing, testing
cification and drawing.

Unit-1 Cum
Amount Total
370.00
1,925.00 2295.00
4,800.00

Prepared By: Checked By : Recommended By : Approved By :


7848.35
Burtibang - Patihalne Road Project

ANALYSIS OF RATE
910.00
385.00
210.00
1,170.00
8.76
262.83
101.76 7848.35
300.00
55.00 355.00
0.00
10498.35
15% Contractors profit & OH 1574.75
Total Rate 12073.10

nt concrete , M20 for the abutment, pier, wall etc. including compaction, curing, testing
cification and drawing.

Unit-1 Cum
Amount Total
666.00
4,950.00 5616.00
4,950.00
1,015.00
525.00
1,144.00
8.76
262.83
104.94 8010.53
300.00
55.00 355.00
0.00
13981.53
15% Contractors profit & OH 2097.23
Total Rate 16078.76

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

ANALYSIS OF RATE

nt concrete, M25 for the super structure, deckslab, girder etc. including compaction,
ete as per specification and drawing.

Unit-1 Cum
Amount Total
666.00
4,950.00 5616.00
5,625.00
1,015.00
525.00
1,170.00
8.76
280.35
119.25 8743.36
300.00
55.00 355.00
0.00
14714.36
15% Contractors profit & OH 2207.15
Total Rate 16921.52

rk including necessary supports and removing after completion for Slab & Beam

Unit-10 Sqm
Amount Total
1,110.00
1,100.00 2210.00
2,522.63
720.75
105.00 3348.38
5558.38
15% Contractors OH 833.76
Total Rate 6392.13

ng cutting, bending, binding, fixing in position and lead 30m. etc. all complete as per

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

ANALYSIS OF RATE
Unit- 1Mt
Amount Total
8,880.00
6,600.00 15480.00
95,450.00
1,000.00 96450.00
111930.00
15% Contractors OH 16789.50
Total Rate 128719.50

masonry in cement mortar including scaffolding, curing, preparation of mortar etc.


(Using Concrete mixer) (cement:sand) 1:3

Unit-1 Cum
Amount Total

1110
1,925.00 3035.00
2,760.00
2,850.00
1,040.00
63.60
87.61 6801.21
75.00 75.00
0.00

9911.21
15% Contractors profit & OH 1486.68
Total Rate 11397.89

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

ANALYSIS OF RATE

er behind abutment with necessary watering and compaction, lead 30m, lift 1.5m

Unit-1 Cum
Amount Total
-
440.00 440.00
1,925.00 1925.00
13.20
2378.20
15% Contractors profit & OH 356.73
Total Rate 2734.93

ork for the construction of RCC superstrcture and removing after completion including
ap value neglected)

Amount Total

29,600.00
27,500.00
336,350.00
2,205.00 338,555.00
395655.00
15% Contractors OH 59348.25
Total Rate 455003.25

n Joints including all necessaary axilliary and incidental works etc.

Unit- m
Amount Total
20,590.90 20,590.90

12% of cost of Bearing including transportation 2,470.91


23,061.81
15% Contractors profit & OH 3,459.27
26,521.08

Pad including all necessary axilliary and incidental works


ion.

Unit- 1 Set.

Prepared By: Checked By : Recommended By : Approved By :


Burtibang - Patihalne Road Project

ANALYSIS OF RATE
Amount Total
47,077.00 47,077.00
12% of cost of Bearing including transportation 5,649.24
52,726.24
15% Contractors profit & OH 7,908.94
60,635.18

for Drainage Spout including grating over pipe all complete

Unit- No
Amount Total
64.75
55.00
293.33 413.08
2,100.00
41.31
10.33
100.00 2,251.64
2,664.72
15% Contractors profit & OH 399.70
3,064.42

ing and compaction of natural sand gravel subbase grading as per table 12.1 of
anual works).

Unit- Cum
Amount Total
2.30
336.00 338.30
768.00
56.10 824.10
75.00 75.00
1237.40
15% Contractors OH 185.61
Total Rate 1423.01

of Machine made and Mechanically Selvedged Gabion boxes/mattresses, of hexagonal


3mm dia, selvedge wire 3.9mm dia and lacing wire of 2.4mm dia including stretching,
rgms with binding wire in each mesh all complete as per specification.

Unit- Box
Amount Total
572.00 572.00
3,935.67
-
- 3,935.67
Prepared By: Checked By : Recommended
4,507.67By : Approved By :
15% Contractors OH 676.15
Total Rate 5,183.82
Sakhardi Khola Bridge, Palpa Final Report

Government of Nepal
Ministry of Physical Infrastructure and Transport
Department of Roads
BRIDGE PROJECT
Chakupat, Lalitpur.

Feasibility Study, Detailed Engineering Survey, Soil investigation, Hydrological Study and Detailed Design
District

Summary of Rates
Item
Description of Items Unit
No.
1 General
Providing and establishing Site Office with furniture and computer facilities
1.1 LS
as per specification and instruction of Engineer.

Insurances for the loss of damage to works, plants, material, equipment,


1.2 property and personnel injury or death all complete as per specification and PS
instruction of Engineer.

Preparation of Progress Report including photographs as per specification


1.3 Month
and instruction of Engineer.

2 FOUNDATION / SUBSTRUCTURE / ABUTMENT / FOUNDATION

Earthwork in excavation for foundation of structure in all type of soil including


shoring, struting, bracing, dewatering and disposal with necessary haulage
2.1 and lift, all complete, as per drawing, specification and instruction of Engineer. Cum

Providing and placing machine mixed cement concrete M10/40 for Levelling
course, including compaction, curing, testing and necessary lead, all
2.2 complete, as per drawing, specification and instruction of Engineer. Cum

Providing and placing machine mixed cement concrete M20/40 for


Foundation & Footings, including compaction, curing, testing and necessary
2.3 lead, all complete, as per drawing, specification and instruction of Engineer. Cum

Providing and laying Reinforcement bar for RCC works including cutting,
2.4 bending, binding, fixing in position and necessary lead, all complete, as per Mt
drawing, specification and instruction of Engineer.

Providing, preparing and installing Formwork for concrete works including


2.5 removing after completion, all complete as per drawing, specification and Sqm
instruction of Engineer.
Sakhardi Khola Bridge, Palpa Final Report

Item
Providing and laying Random Description of Items
rubble Stone masonry in 1:3 cement sand Unit
No.
mortar including scaffolding, curing, preparation of mortar etc. complete,
2.6 masoned height 0-5m, required lead (Using Concrete mixer) all complete as Cum
per specification and instruction of Engineer.

SUBSTRUCTURE
Providing and placing machine mixed cement concrete M20/40 for Stem,
Abutment, including compaction, curing, testing and necessary lead, all
2.7 complete, as per drawing, specification and instruction of Engineer. Cum

Providing and placing machine mixed cement concrete M30/20 in Abutment


Cap, including compaction, curing, testing and necessary lead, all complete,
2.8 as per drawing, specification and instruction of Engineer. Cum

Providing and laying Reinforcement bar for RCC works including cutting,
2.9 bending, binding, fixing in position and necessary lead, all complete, as per Mt
drawing, specification and instruction of Engineer.

Providing, preparing and installing Formwork for concrete works including


2.10 removing after completion, all complete as per drawing, specification and Sqm
instruction of Engineer.

Providing and filling with graded pervious Filter Material behind abutment in
2.11 layer with necessary watering and compaction, all complete as per drawing, Cum
specification and instruction of Engineer.

Providing suitable back fill material and Back filling in layers behind the
2.12 abutment including compaction and watering etc. all complete, as per drawing, Cum
specification and instruction of Engineer.

Providing and making of Weep Holes with 110mm HDPe pipe in position as
2.13 Rm
per drawing, specification and instruction of Engineer.

3 SUPERSTRUCTURE
Providing and placing machine mixed cement concrete M35/20 for deck
slab,precast slab, parapet, post, kerb etc, including compaction, curing,
3.1 testing and necessary lead, all complete, as per drawing, specification and Cum
instruction of Engineer.

Providing and laying Reinforcement bars, HYSD, TMT, minimum 0.2% prof
stress 500 MPA (FE 500) for RCC works including cutting, bending, binding,
3.2 fixing in position and necessary lead, all complete, as per drawing, Mt
specification and instruction of Engineer.

Providing, preparing and installing Formwork for concrete works including


3.3 removing after completion, all complete as per drawing, specification and Sqm
instruction of Engineer.
Sakhardi Khola Bridge, Palpa Final Report

Item
No. Providing and assembling Description
in position ofFalse
Items work (staging) for the Unit
construction of RCC superstructure and removing after completion including
3.4 design and drawing, all complete as per specification and instruction of Sqm
Engineer.

Providing and fixing of Expansion joints (Slab Seat Type) including


3.5 necessary assesories, all complete, as per drawing, specification and Rm
instruction of Engineer.

Providing and fixing of Neoprene Bearings as per drawing, specification and


3.6 No
instruction of Engineer

Providing, making and laying of Asphalt Concrete for Wearing Course with
3.7 compaction, all complete, as per drawing, specification ( SS/SP 1307,1308 ) Cum
and instruction of Engineer.

Providing and fixing of 75 mm dia Ralling pipe all complete, as per drawing,
3.8 Rm
specification and instruction of Engineer.

Providing and fixing of Drainage Sprouts all complete, as per drawing,


3.9 No
specification and instruction of Engineer.

Providing and fixing of 110 mm dia Service duct all complete, as per drawing,
3.10 Rm
specification and instruction of Engineer.

4 APPROACH ROAD
Road way excavation in all type of soil including necessary haulage ,
4.1 disposal and lift all complete, as per specification (SS/SP-905) and instruction Cum
of Engineer

Formation of Embankment including, compaction in layers not exceeding


4.2 150mm. Compacted depth, watering and haulage, etc. all complete, as per Cum
specification (SS/SP-909) and instruction of Engineer

Preparation of sub-grade for rehabilitation or other similar works ( filling or


4.3 cutting depth of 10 to 20 cm ) in common soil, all complete as per specification Sqm
(SS/SP-1003) and instruction of Engineer.

Providing , laying , spreading, levelling and compaction of natuaral sand gravel


Subbase grading as per table 12.1 of standard specification and lead, all
4.4 complete as per the specification (SS/SP-1201) and instruction of Engineer. Cum

Providing , laying , spreading, levelling and compaction of crusher run


4.5 materials for Base course, all complete, as per specification (SS/SP-1202) Cum
and instruction of Engineer.
Sakhardi Khola Bridge, Palpa Final Report

Item
Description
Providing and spraying bituminious PrimeofCoat
Items
MC30/MC70 including Unit
No.
cleaning the road surface using wire brushes, broom etc. before applying coat,
4.6 Lit
all complete as per specification (SS / SP 1301, 1302 ) and instruction of
Engineer.

Providing, making and laying of Asphalt Concrete with compaction, all


4.7 complete, as per drawing, specification (SS/SP 1307, 1308) and instruction of Cum
Engineer.

Supplying and erecting traffic sign in place including 50mm dia Steel tube
2mm thick steel plate, cement concrete, painting, writing and supporting steel
4.8 angle nut and bolt etc. all complete, as per drawing, specification and Ls
instruction of Engineer.

4.9 Bio engineering works LS

5 PROTECTION WORK
Earthwork in excavation for foundation of structure in all types of soil
including shoring, struting, bracing, dewatering and disposal with necessary
5.1 haulage and lift, all complete, as per drawing, specification and instruction of Cum
Engineer.

Providing suitable back fill material and Back filling in layers behind the
5.2 Gabion Wall including compaction and watering etc. all complete, as per Cum
drawing, specification and instruction of Engineer.

Fabrication of Gabion boxes/mattresses with diapharagms including rolling,


cutting and weaving, assembling it, placing in position including stretching,
5.3 forming compartments, tying the side and diaphargms with binding wire in Cum
each mesh, filling gabion box with stone including dressing, beding, bonding
and all transportation as per specification.
Sakhardi Khola Bridge, Palpa Final Report

Government of Nepal
try of Physical Infrastructure and Transport
Department of Roads
BRIDGE PROJECT
Chakupat, Lalitpur.

y, Soil investigation, Hydrological Study and Detailed Design of Bridges at Palpa


District

Summary of Rates
Rate Remarks

200,000.00

3,000.00

181.24

11,645.52

13,236.60

128,719.50

639.21
Sakhardi Khola Bridge, Palpa Final Report

Rate Remarks

11,397.89

17,151.23

16,802.32

128,719.50

639.21

2,734.93

268.51

436.99

17,130.04

128,719.50

639.21
Sakhardi Khola Bridge, Palpa Final Report

Rate Remarks

45,500.33

26,521.08

60,635.18

18,795.05

1,391.50

3,064.42

397.27

122.53

431.79

16.83

2,780.23

3,825.46
Sakhardi Khola Bridge, Palpa Final Report

Rate Remarks

183.98

18,795.05

10,000.00

3,422.35

155.10

268.51

5,521.31

You might also like