CRONOGRAMA DE AVANCE DE OBRA VALORIZADO

"MEJORAMIENTO DE LA INFRAESTRUCTURA MUNICIPAL PARA LOS SERVICIOS ADMINISTRATIVOS DE LA MUNICIPALIDAD DISTRITAL DE NUEVO IMPERIAL - CANETE - LIMA" - 1ETAPA
DEPARTAMENTO: LIMA
PROVINCIA: CAETE PLAZO DE EJECUCION 180DC
DISTRITO: NUEVO IMPERIAL
FECHA: February 2017

TIEMPO 180 DIAS


ITEM DESCRIPCION UND METRADO PRECIO PARCIAL MES MES MES MES MES MES
1(30Dias) 2(30Dias) 3(30Dias) 4(30Dias) 5(30Dias) 6(30Dias)
01 OBRAS PROVISIONALES 10,619.88 3,169.98 1,269.98 1,269.98 1,269.98 1,269.98 2,369.98
01.01 CARTEL DE OBRA 3.60m x 2.40m und 1.00 800.00 800.00 800.00
01.02 ALMACEN Y GUARDIANIA mes 6.00 1,269.98 7,619.88 1,269.98 1,269.98 1,269.98 1,269.98 1,269.98 1,269.98
01.03 MOVILIZACIN Y DESMOVILIZACIN DE EQUIPOS Y und 1.00 2,200.00 2,200.00 1,100.00 1,100.00
HERRAMIENTAS
02 TRABAJOS PRELIMINARES 126,841.62 57,880.20 55,969.54 3,247.97 3,247.97 3,247.97 3,247.97
02.01 LIMPIEZA DE TERRENO MANUAL m2 933.23 2.32 2,165.09 360.85 360.85 360.85 360.85 360.85 360.85
02.02 DEMOLICION DE CONCRETO, ALBAILERIA, ETC m3 579.05 132.84 76,921.00 38,460.50 38,460.50

02.03 DESMONTAJE DE PUERTAS Y VENTANAS m2 175.45 10.89 1,910.65 1,910.65

02.04 ELIMINACION DE MATERIAL EXCEDENTE m3 792.25 30.63 24,266.62 12,133.31 12,133.31


02.05 TRAZOS, NIVELES Y REPLANTEO m2 933.23 4.56 4,255.53 2,127.76 2,127.76
02.06 SEGURIDAD Y SALUD 17,322.73 2,887.12 2,887.12 2,887.12 2,887.12 2,887.12 2,887.12
02.06.01 ELABORACION, IMPLEMENTACION Y GLB 1.00 7,000.00 7,000.00 1,166.67 1,166.67 1,166.67 1,166.67 1,166.67 1,166.67
ADMINISTRACION DEL PLAN DE SEGURIDAD Y SALUD
EN EL TRABAJO
02.06.02 EQUIPOS DE PROTECCION INDIVIDUAL. und 15.00 202.24 3,033.60 505.60 505.60 505.60 505.60 505.60 505.60
02.06.03 EQUIPOS DE PROTECCION COLECTIVA GLB 1.00 1,992.67 1,992.67 332.11 332.11 332.11 332.11 332.11 332.11
02.06.04 SEALIZACION TEMPORAL DE SEGURIDAD GLB 1.00 788.00 788.00 131.33 131.33 131.33 131.33 131.33 131.33

02.06.05 CAPACITACION EN SEGURIDAD Y SALUD mes 6.00 700.00 4,200.00 700.00 700.00 700.00 700.00 700.00 700.00

02.06.06 RECURSOS PARA RESPUESTA ANTE EMERGENCIAS GLB 1.00 308.46 308.46 51.41 51.41 51.41 51.41 51.41 51.41
EN SEGURIDAD Y SALUD DURANTE EL TRABAJO
03 ARQUITECTURA 691,373.79 0.00 245.63 103,392.31 100,875.01 267,201.71 219,659.14
03.01 REVOQUES Y ENLUCIDOS 52,256.46 0.00 0.00 17,418.82 17,418.82 17,418.82 0.00
03.01.01 TARRAJEO DE MUROS INTERIORES (MEZCLA, C:A m2 1,847.74 22.51 41,592.63 13,864.21 13,864.21 13,864.21
1:5, e=1.5cm)
03.01.02 TARRAJEO DE MUROS EXTERIORES (MEZCLA, C:A m2 182.94 25.72 4,705.22 1,568.41 1,568.41 1,568.41
1:5, e=1.5cm)
03.01.03 VESTIDURA DE DERRAMES (MEZCLA, C:A 1:5, m 451.41 13.20 5,958.61 1,986.20 1,986.20 1,986.20
e=1.5cm)
03.02 CIELORRASO 56,433.88 0.00 0.00 0.00 28,216.94 28,216.94 0.00
03.02.01 CIELORRASO (MEZCLA, C:A 1:5, e=1.5cm) m2 66.93 26.47 1,771.64 885.82 885.82
03.02.02 FALSO CIELORASO CON BALDOSAS ACUSTICAS. m2 758.25 72.09 54,662.24 27,331.12 27,331.12

03.03 ZOCALOS Y CONTRAZOCALOS 26,204.14 0.00 0.00 0.00 13,102.07 13,102.07 0.00
CRONOGRAMA DE AVANCE DE OBRA VALORIZADO

"MEJORAMIENTO DE LA INFRAESTRUCTURA MUNICIPAL PARA LOS SERVICIOS ADMINISTRATIVOS DE LA MUNICIPALIDAD DISTRITAL DE NUEVO IMPERIAL - CANETE - LIMA" - 1ETAPA
DEPARTAMENTO: LIMA
PROVINCIA: CAETE PLAZO DE EJECUCION 180DC
DISTRITO: NUEVO IMPERIAL
FECHA: February 2017

TIEMPO 180 DIAS


ITEM DESCRIPCION UND METRADO PRECIO PARCIAL MES MES MES MES MES MES
1(30Dias) 2(30Dias) 3(30Dias) 4(30Dias) 5(30Dias) 6(30Dias)
03.03.01 ZOCALO DE CERAMICO (0.30m x 0.20m) EN m2 219.60 70.70 15,525.72 7,762.86 7,762.86
INTERIORES H= 2.00m
03.03.02 CONTRAZOCALO DE CERAMICO (0.30m x 0.10m) EN m 602.28 17.73 10,678.42 5,339.21 5,339.21
INTERIORES H= 0.10m
03.04 PISOS Y PAVIMENTOS 107,098.47 0.00 0.00 64,961.29 42,137.18 0.00 0.00
03.04.01 FALSO PISO DE 4" CON MEZCLA 1:6 C-H m2 778.98 29.30 22,824.11 22,824.11

03.04.02 PISO PORCELANATO - ALTO TRANSITO m2 1,043.78 79.53 83,011.82 41,505.91 41,505.91

03.04.03 PISO DE CEMENTO PULIDO Y BRUADO E=2" m2 27.92 45.22 1,262.54 631.27 631.27
MEZ=1:4
03.05 PINTURA 18,536.56 0.00 0.00 0.00 0.00 9,268.28 9,268.28
03.05.01 PINTURA LATEX EN MUROS INTERIORES INC. m2 1,704.71 8.27 14,097.95 7,048.98 7,048.98
EMPASTADO
03.05.02 PINTURA LATEX EN MUROS EXTERIORES INC. m2 294.98 7.41 2,185.80 1,092.90 1,092.90
EMPASTADO
03.05.03 PINTURA LATEX EN VANOS INC. EMPASTADO m 451.41 3.80 1,715.36 857.68 857.68

03.05.04 PINTURA LATEX EN CIELO RASO INC EMPASTADO m2 66.93 8.03 537.45 268.72 268.72

03.06 CARPINTERIA DE MADERA 8,200.00 0.00 0.00 0.00 0.00 0.00 8,200.00
03.06.01 PUERTA DE MADERA CONTRAPLACADA - P-01 Unid. 1.00 400.00 400.00 400.00

03.06.02 PUERTA DE MADERA CONTRAPLACADA - P-02 Unid. 2.00 350.00 700.00 700.00

03.06.03 PUERTA DE MADERA CONTRAPLACADA - P-03 Unid. 1.00 300.00 300.00 300.00

03.06.04 PUERTA DE MADERA CONTRAPLACADA - P-04 Unid. 4.00 350.00 1,400.00 1,400.00

03.06.05 PUERTA DE MADERA CONTRAPLACADA - P-05 Unid. 3.00 300.00 900.00 900.00

03.06.06 PUERTA DE MADERA CONTRAPLACADA - P-06 Unid. 7.00 300.00 2,100.00 2,100.00

03.06.07 PUERTA DE MADERA CONTRAPLACADA - P-07 Unid. 5.00 250.00 1,250.00 1,250.00

03.06.08 PUERTA DE MADERA CONTRAPLACADA - P-11 Unid. 1.00 450.00 450.00 450.00

03.06.09 PUERTA DE MADERA CONTRAPLACADA - P-14 Unid. 2.00 350.00 700.00 700.00
CRONOGRAMA DE AVANCE DE OBRA VALORIZADO

"MEJORAMIENTO DE LA INFRAESTRUCTURA MUNICIPAL PARA LOS SERVICIOS ADMINISTRATIVOS DE LA MUNICIPALIDAD DISTRITAL DE NUEVO IMPERIAL - CANETE - LIMA" - 1ETAPA
DEPARTAMENTO: LIMA
PROVINCIA: CAETE PLAZO DE EJECUCION 180DC
DISTRITO: NUEVO IMPERIAL
FECHA: February 2017

TIEMPO 180 DIAS


ITEM DESCRIPCION UND METRADO PRECIO PARCIAL MES MES MES MES MES MES
1(30Dias) 2(30Dias) 3(30Dias) 4(30Dias) 5(30Dias) 6(30Dias)
03.07 CARPINTERIA METALICA Y HERRERIA 5,811.75 0.00 0.00 0.00 0.00 5,811.75 0.00
03.07.01 BARANDAS METALICAS =2" Inc. PINTURA E m 33.21 175.00 5,811.75 5,811.75
INSTALACION H=0.90m
03.08 VIDRIOS, CRISTALES Y SIMILARES 314,325.86 0.00 0.00 0.00 0.00 137,502.38 176,823.48
03.08.01 PUERTA DE VIDRIO DE UNA HOJA - P-12 (8mm) pza 9.00 914.87 8,233.83 8,233.83

03.08.02 PUERTA DE VIDRIO DE UNA HOJA CORREDIZA - P-13 pza 23.00 935.24 21,510.52 21,510.52
(E=8mm)
03.08.03 MAMPARA DE VIDRIO DE DOBLE HOJA BATIENTE - pza 1.00 1,857.14 1,857.14 1,857.14
M-01 (E=10mm)
03.08.04 MAMPARA DE VIDRIO DE DOBLE HOJA BATIENTE - pza 1.00 1,253.94 1,253.94 1,253.94
M-02 (E=10mm)
03.08.05 MAMPARA DE VIDRIO DE DOBLE HOJA BATIENTE - pza 1.00 1,291.64 1,291.64 1,291.64
M-03 (E=10mm)
03.08.06 MAMPARA DE VIDRIO DE DOBLE HOJA BATIENTE - pza 1.00 1,329.34 1,329.34 1,329.34
M-04 (E=10mm)
03.08.07 MAMPARA DE VIDRIO DE DOBLE HOJA BATIENTE - pza 1.00 1,348.19 1,348.19 1,348.19
M-05 (E=10mm)
03.08.08 MAMPARA DE VIDRIO DE DOBLE HOJA BATIENTE - pza 1.00 827.86 827.86 827.86
M-06 (E=10mm)
03.08.09 MAMPARA DE VIDRIO DE DOBLE HOJA BATIENTE - pza 1.00 1,668.64 1,668.64 1,668.64
M-07 (E=10mm)
03.08.10 SUMINISTRO Y COLOCACION DE VIDRIO CRISTAL m2 320.12 301.92 96,650.63 48,325.32 48,325.32
TEMPLADO DE 8mm EN DIVISIONES
03.08.11 SUMINISTRO Y COLOCACION DE VIDRIO CRISTAL m2 287.21 519.39 149,174.00 74,587.00 74,587.00
TEMPLADO DE 8mm EN MURO CORTINA
03.08.12 SUMINISTRO Y COLOCACION DE VIDRIO CRISTAL m2 144.98 201.27 29,180.12 14,590.06 14,590.06
TEMPLADO EN VENTANAS
03.09 DIVISIONES Y PUERTAS EN MELAMINE 4,913.35 0.00 0.00 0.00 0.00 4,913.35 0.00
03.09.01 MODULO DIVISORIO PARA SS.HH., H=1.80m en und 11.00 257.57 2,833.27 2,833.27
melamine e= 15mm
03.09.02 MURO DIVISORIO PARA URINARIOS en melamine e= und 6.00 88.31 529.86 529.86
15mm
03.09.03 MURO DIVISORIO PARA OFICINAS H=1.80m en und 5.00 156.18 780.90 780.90
melamine e= 15mm
03.09.04 MODULO DE OFICINA en melamine e= 18mm und 6.00 128.22 769.32 769.32

03.10 VARIOS 35,393.55 0.00 245.63 4,331.24 0.00 5,449.29 25,367.38


03.10.01 MESA DE CONCRETO REVEST. C/PORCELANATO und 4.00 245.12 980.48 980.48
P/LAVADERO TIPO OVALIN
CRONOGRAMA DE AVANCE DE OBRA VALORIZADO

"MEJORAMIENTO DE LA INFRAESTRUCTURA MUNICIPAL PARA LOS SERVICIOS ADMINISTRATIVOS DE LA MUNICIPALIDAD DISTRITAL DE NUEVO IMPERIAL - CANETE - LIMA" - 1ETAPA
DEPARTAMENTO: LIMA
PROVINCIA: CAETE PLAZO DE EJECUCION 180DC
DISTRITO: NUEVO IMPERIAL
FECHA: February 2017

TIEMPO 180 DIAS


ITEM DESCRIPCION UND METRADO PRECIO PARCIAL MES MES MES MES MES MES
1(30Dias) 2(30Dias) 3(30Dias) 4(30Dias) 5(30Dias) 6(30Dias)
03.10.02 ESPEJO (3.65 x 0.60m) pza 4.00 76.19 304.76 304.76
03.10.03 BARANDILLAS EN SS.HH. DE PERSONAS CON pza 2.00 248.11 496.22 496.22
DISCAPACIDAD
03.10.04 SARDINELES REVESTIDO CON TIPO PIEDRA m 8.64 153.90 1,329.70 1,329.70
TALAMOYE h= 0.50m
03.10.05 MESA DE CONCRETO REVEST. C/CERAMICO und 1.00 2,010.57 2,010.57 2,010.57
P/COCINA
03.10.06 SUMINISTRO E INSTALACION DE CORTASOL glb 1.00 6,500.00 6,500.00 6,500.00
METALICO
03.10.07 SUMINISTRO E INSTALACION DE CERRAMIENTO EN glb 1.00 15,000.00 15,000.00 15,000.00
DRYWALL, SUPERBOARD PINTADA
03.10.08 Fabricacion, Instalacion y Colocacion de Rtulos glb 1.00 3,500.00 3,500.00 3,500.00
corpreas en metacrilato.
03.10.09 SUMINISTRO E INSTALACION DE MADERA m2 19.84 234.29 4,648.31 4,648.31
LAMINADA MACHEMBRADA EN ESCENARIO
03.10.10 JUNTAS DE DILATACION 256.13 0.00 245.63 10.50 0.00 0.00 367.38
03.10.10.01 JUNTA ASFALTICA 1" m 3.43 3.06 10.50 10.50
03.10.10.02 JUNTA DE POLIESTIRENO EXPANDIDO E=25mm, m 15.40 15.95 245.63 245.63
CON ACABADO
03.10.11 SOL Y SOMBRA DE MADERA und 1.00 367.38 367.38 367.38
03.11 PUENTE INTEGRADOR 8,030.26 0.00 0.00 0.00 0.00 8,030.26 0.00
03.11.01 PISO PORCELANATO - ALTO TRANSITO m2 43.12 79.53 3,429.33 3,429.33
03.11.02 TARRAJEO DE MUROS INTERIORES (MEZCLA, C:A m2 27.14 22.51 610.92 610.92
1:5, e=1.5cm)
03.11.03 BARANDAS METALICAS =2" Inc. PINTURA E m 22.80 175.00 3,990.00 3,990.00
INSTALACION H=0.90m
03.12 ARQUITECTURA EXTERIOR 54,169.53 0.00 0.00 16,680.96 0.00 37,488.57 0.00
03.12.01 MURO DE FIBRA DE VIDRIO ( CONO TRUNCADO) m2 112.05 334.57 37,488.57 37,488.57
03.12.02 FUENTE DE AGUA 2,603.44 0.00 0.00 2,603.44 0.00 0.00 0.00
03.12.02.01 ENCHAPES EN PARAPETOS EXTERIORES CON m2 4.27 246.28 1,051.62 1,051.62
PIEDRA TIPO LAJA
03.12.02.02 ENCHAPE CON CERAMICO 30x30cm m2 20.82 72.32 1,505.70 1,505.70
03.12.02.03 TARRAJEO EN GARGOLA DE FUENTE DE AGUA m2 2.77 16.65 46.12 46.12
(MEZCLA, C:A 1:5, e=1.5cm)
03.12.03 GRADAS Y RAMPAS DE ACCESO 14,077.52 0.00 0.00 14,077.52 0.00 0.00 0.00
03.12.03.01 GRADAS, CONCRETO f 'c=175 kg/cm2, Incl. m3 10.11 305.33 3,086.89 3,086.89
FROTACHADO
CRONOGRAMA DE AVANCE DE OBRA VALORIZADO

"MEJORAMIENTO DE LA INFRAESTRUCTURA MUNICIPAL PARA LOS SERVICIOS ADMINISTRATIVOS DE LA MUNICIPALIDAD DISTRITAL DE NUEVO IMPERIAL - CANETE - LIMA" - 1ETAPA
DEPARTAMENTO: LIMA
PROVINCIA: CAETE PLAZO DE EJECUCION 180DC
DISTRITO: NUEVO IMPERIAL
FECHA: February 2017

TIEMPO 180 DIAS


ITEM DESCRIPCION UND METRADO PRECIO PARCIAL MES MES MES MES MES MES
1(30Dias) 2(30Dias) 3(30Dias) 4(30Dias) 5(30Dias) 6(30Dias)
03.12.03.02 RAMPAS, CONCRETO f 'c=175 kg/cm2, Incl. m3 4.02 305.33 1,227.43 1,227.43
TEXTURIZADO
03.12.03.03 PISO ENCHAPADO TIPO PIEDRA TALAMOYE m2 135.00 72.32 9,763.20 9,763.20

04 ESTRUCTURAS 822,101.50 0.00 196,040.11 351,819.49 178,732.19 95,509.71 0.00


04.01 MOVIMIENTO DE TIERRAS 24,418.33 0.00 6,922.15 12,743.99 4,752.20 0.00 0.00
04.01.01 EXCAVACION P/ZAPATAS m3 282.65 40.02 11,311.65 5,655.83 5,655.83
04.01.02 EXCAVACION MANUAL P/CIMIENTOS m3 72.32 35.02 2,532.65 1,266.32 1,266.32
04.01.03 RELLENO CON MATERIAL PROPIO m3 157.73 20.81 3,282.36 3,282.36
04.01.04 NIVELACION Y APISONADO PARA FALSO PISO m2 778.98 3.26 2,539.47 2,539.47

04.01.05 ELIMINACION DE MATERIAL EXCEDENTE m3 276.13 17.21 4,752.20 4,752.20


04.02 OBRAS DE CONCRETO SIMPLE 14,158.68 0.00 7,079.34 7,079.34 0.00 0.00 0.00
04.02.01 CONCRETO PARA CIMIENTO 175KG/CM2 + 30% PG m3 34.69 352.45 12,226.49 6,113.25 6,113.25
(T. MAX 10")
04.02.02 SOLADO DE CONCRETO E= 0.05 mts. (MEZCLA 1:10) m3 9.71 198.99 1,932.19 966.10 966.10

04.03 OBRAS DE CONCRETO ARMADO 767,666.89 0.00 166,181.03 331,996.16 173,979.99 95,509.71 0.00
04.03.01 ZAPATAS 107,679.63 0.00 53,839.82 53,839.82 0.00 0.00 0.00
04.03.01.01 CONCRETO PARA ZAPATAS f'c=210 kg/cm2 m3 128.44 363.73 46,717.48 23,358.74 23,358.74

04.03.01.02 ENCOFRADO Y DESENCOFRADO PARA ZAPATAS m2 261.05 62.49 16,313.01 8,156.51 8,156.51

04.03.01.03 ACERO DE REFUERZO F'Y=4200 kg/cm2 kg 8,823.94 5.06 44,649.14 22,324.57 22,324.57

04.03.02 VIGA DE CIMENTACION 4,385.08 0.00 2,192.54 2,192.54 0.00 0.00 0.00
04.03.02.01 CONCRETO f'c=210 kg/cm2 EN VIGA DE m3 2.91 386.22 1,123.90 561.95 561.95
CIMENTACION
04.03.02.02 ENCOFRADO Y DESENCOFRADO EN VIGAS DE m2 19.42 68.36 1,327.55 663.78 663.78
CIMENTACION
04.03.02.03 ACERO DE REFUERZO F'Y=4200 kg/cm2 kg 382.14 5.06 1,933.63 966.81 966.81

04.03.03 SOBRECIMIENTOS 37,430.67 0.00 18,715.33 18,715.33 0.00 0.00 0.00


04.03.03.01 CONCRETO f'c=210 kg/cm2 EN SOBRECIMIENTOS m3 21.53 386.22 8,315.32 4,157.66 4,157.66

04.03.03.02 ENCOFRADO Y DESENCOFRADO PARA m2 323.15 53.74 17,366.08 8,683.04 8,683.04


SOBRECIMIENTOS
CRONOGRAMA DE AVANCE DE OBRA VALORIZADO

"MEJORAMIENTO DE LA INFRAESTRUCTURA MUNICIPAL PARA LOS SERVICIOS ADMINISTRATIVOS DE LA MUNICIPALIDAD DISTRITAL DE NUEVO IMPERIAL - CANETE - LIMA" - 1ETAPA
DEPARTAMENTO: LIMA
PROVINCIA: CAETE PLAZO DE EJECUCION 180DC
DISTRITO: NUEVO IMPERIAL
FECHA: February 2017

TIEMPO 180 DIAS


ITEM DESCRIPCION UND METRADO PRECIO PARCIAL MES MES MES MES MES MES
1(30Dias) 2(30Dias) 3(30Dias) 4(30Dias) 5(30Dias) 6(30Dias)
04.03.03.03 ACERO DE REFUERZO F'Y=4200 kg/cm2 kg 2,321.99 5.06 11,749.27 5,874.63 5,874.63

04.03.04 COLUMNAS 88,782.83 0.00 44,391.42 44,391.42 0.00 0.00 0.00


04.03.04.01 CONCRETO EN COLUMNAS F'C=210 KG/CM2 m3 42.98 403.07 17,323.95 8,661.97 8,661.97

04.03.04.02 ENCOFRADO Y DESENCOFRADO EN COLUMNAS m2 452.21 65.48 29,610.71 14,805.36 14,805.36

04.03.04.03 ACERO DE REFUERZO F'Y=4200 kg/cm2 kg 8,270.39 5.06 41,848.17 20,924.09 20,924.09

04.03.05 COLUMNAS CIRCULARES 31,198.42 0.00 15,599.21 15,599.21 0.00 0.00 0.00
04.03.05.01 CONCRETO f'c = 210 Kg/cm2 COLUMNA CIRCULAR m3 17.18 403.07 6,924.74 3,462.37 3,462.37

04.03.05.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 114.65 88.59 10,156.84 5,078.42 5,078.42


COLUMNA CIRCULAR
04.03.05.03 ACERO DE REFUERZO F'Y=4200 kg/cm2 kg 2,789.89 5.06 14,116.84 7,058.42 7,058.42

04.03.06 COLUMNAS DE AMARRE 38,780.44 0.00 19,390.22 19,390.22 0.00 0.00 0.00
04.03.06.01 CONCRETO f'c = 210 Kg/cm2 COLUMNAS DE m3 13.81 403.07 5,566.40 2,783.20 2,783.20
AMARRE
04.03.06.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 282.35 65.48 18,488.28 9,244.14 9,244.14
COLUMNAS DE AMARRE
04.03.06.03 ACERO DE REFUERZO F'Y=4200 kg/cm2 kg 2,910.23 5.06 14,725.76 7,362.88 7,362.88

04.03.07 PLACAS DE CONCRETO f'c = 210 Kg/cm2 24,104.99 0.00 12,052.49 12,052.49 0.00 0.00 0.00
04.03.07.01 CONCRETO f'c = 210 Kg/cm2 EN PLACAS m3 11.73 446.19 5,233.81 2,616.90 2,616.90

04.03.07.02 ENCOFRADO Y DESENCOFRADO NORMAL EN m2 125.14 79.91 9,999.94 4,999.97 4,999.97


PLACAS
04.03.07.03 ACERO DE REFUERZO F'Y=4200 kg/cm2 kg 1,753.21 5.06 8,871.24 4,435.62 4,435.62

04.03.08 VIGAS 131,602.48 0.00 0.00 65,801.24 65,801.24 0.00 0.00


04.03.08.01 CONCRETO EN VIGAS f'c=210kg/cm2 m3 96.88 374.35 36,267.03 18,133.51 18,133.51
04.03.08.02 ENCOFRADO Y DESENCOFRADO EN VIGAS m2 860.56 68.43 58,888.12 29,444.06 29,444.06

04.03.08.03 ACERO DE REFUERZO F'Y=4200 kg/cm2 kg 7,203.03 5.06 36,447.33 18,223.67 18,223.67

04.03.09 ESCALERA 68,933.49 0.00 0.00 0.00 0.00 68,933.49 0.00


04.03.09.01 ESTRUCTURA METALICA ton 4.94 9,018.13 44,549.56 44,549.56
CRONOGRAMA DE AVANCE DE OBRA VALORIZADO

"MEJORAMIENTO DE LA INFRAESTRUCTURA MUNICIPAL PARA LOS SERVICIOS ADMINISTRATIVOS DE LA MUNICIPALIDAD DISTRITAL DE NUEVO IMPERIAL - CANETE - LIMA" - 1ETAPA
DEPARTAMENTO: LIMA
PROVINCIA: CAETE PLAZO DE EJECUCION 180DC
DISTRITO: NUEVO IMPERIAL
FECHA: February 2017

TIEMPO 180 DIAS


ITEM DESCRIPCION UND METRADO PRECIO PARCIAL MES MES MES MES MES MES
1(30Dias) 2(30Dias) 3(30Dias) 4(30Dias) 5(30Dias) 6(30Dias)
04.03.09.02 PELDAOS DE MADERA p2 687.84 35.45 24,383.93 24,383.93
04.03.10 LOSA ALIGERADA 161,406.68 0.00 0.00 80,703.34 80,703.34 0.00 0.00
04.03.10.01 CONCRETO EN LOSA ALIGERADA f'c=210kg/cm2 m3 115.72 359.63 41,616.38 20,808.19 20,808.19
04.03.10.02 ENCOFRADO Y DESENCOFRADO EN LOSA m2 900.31 64.80 58,340.09 29,170.04 29,170.04
ALIGERADA
04.03.10.03 ACERO DE REFUERZO F'Y=4200 kg/cm2 kg 7,607.25 5.06 38,492.69 19,246.34 19,246.34

04.03.10.04 LADRILLO HUECO DE ARCILLA 15X30X30 CM PARA und 6,616.00 3.47 22,957.52 11,478.76 11,478.76
TECHO ALIGERADO
04.03.11 ALBAILERIA 57,032.48 0.00 0.00 19,310.56 19,310.56 18,411.37 0.00
04.03.11.01 MURO DE SOGA, LADRILLO KK 18 H. CEMENTO- m2 898.70 61.46 55,234.10 18,411.37 18,411.37 18,411.37
ARENA
04.03.11.02 MURO DE CABEZA, LADRILLO KK 18 H. CEMENTO- m2 17.54 102.53 1,798.38 899.19 899.19
ARENA
04.03.12 PUENTE INTEGRADOR 16,329.71 0.00 0.00 0.00 8,164.86 8,164.86 0.00
04.03.12.01 CONCRETO EN LOSA MACIZA f'c=210kg/cm2 m3 7.54 371.55 2,801.49 1,400.75 1,400.75
04.03.12.02 ENCOFRADO Y DESENCOFRADO EN LOSA MACIZA m2 38.04 70.12 2,667.36 1,333.68 1,333.68

04.03.12.03 ACERO DE REFUERZO F'Y=4200 kg/cm2 kg 1,271.08 5.06 6,431.66 3,215.83 3,215.83

04.03.12.04 APOYO ELASTOMERICOS (200mm*200mm*70mm) und 8.00 100.06 800.48 400.24 400.24
04.03.12.05 JUNTA DE DILATACION (SELLO DE NEOPRENO) und 20.80 148.10 3,080.48 1,540.24 1,540.24
04.03.12.06 DISPOSITIVO DE CONTROL SISMICO und 8.00 68.53 548.24 274.12 274.12
04.04 FUENTE DE AGUA 4,795.07 0.00 4,795.07 0.00 0.00 0.00 0.00
04.04.01 EXCAVACION MANUAL P/FUENTE DE AGUA m3 9.65 35.02 337.94 337.94

04.04.02 CONCRETO EN FUENTE DE AGUA f'c=210kg/cm2 m3 4.39 446.91 1,961.93 1,961.93

04.04.03 ENCOFRADO Y DESENCOFRADO EN FUENTE DE m2 18.31 65.48 1,198.94 1,198.94


AGUA
04.04.04 ACERO DE REFUERZO F'Y=4200 kg/cm2 kg 186.08 5.06 941.56 941.56
04.04.05 ELIMINACION DE MATERIAL EXCEDENTE m3 11.58 30.63 354.70 354.70
04.05 CISTERNA 11,062.52 0.00 11,062.52 0.00 0.00 0.00 0.00
04.05.01 EXCAVACION MANUAL PARA CISTERNA m3 12.26 46.69 572.42 572.42

04.05.02 SOLADO DE CONCRETO E= 0.05 mts. (MEZCLA 1:10) m3 0.30 198.99 59.70 59.70
CRONOGRAMA DE AVANCE DE OBRA VALORIZADO

"MEJORAMIENTO DE LA INFRAESTRUCTURA MUNICIPAL PARA LOS SERVICIOS ADMINISTRATIVOS DE LA MUNICIPALIDAD DISTRITAL DE NUEVO IMPERIAL - CANETE - LIMA" - 1ETAPA
DEPARTAMENTO: LIMA
PROVINCIA: CAETE PLAZO DE EJECUCION 180DC
DISTRITO: NUEVO IMPERIAL
FECHA: February 2017

TIEMPO 180 DIAS


ITEM DESCRIPCION UND METRADO PRECIO PARCIAL MES MES MES MES MES MES
1(30Dias) 2(30Dias) 3(30Dias) 4(30Dias) 5(30Dias) 6(30Dias)
04.05.03 CONCRETO EN CISTERNA f'c=210kg/cm2 m3 5.19 446.19 2,315.73 2,315.73

04.05.04 ENCOFRADO Y DESENCOFRADO EN CISTERNA m2 40.03 65.48 2,621.16 2,621.16

04.05.05 ACERO DE REFUERZO F'Y=4200 kg/cm2 kg 855.76 5.06 4,330.15 4,330.15

04.05.06 ELIMINACION DE MATERIAL EXCEDENTE m3 14.71 30.63 450.57 450.57

04.05.07 TARRAJEO CON IMPERMEABILIZANTE (MEZCLA m2 22.52 26.43 595.20 595.20


C:A:1:4, e=1.50cm)
04.05.08 FABRICACION Y SUMINISTRO DE TAPA DE HIERRO m2 1.00 117.60 117.60 117.60

05 INSTALACIONES SANITARIAS 51,952.07 0.00 16,120.61 11,543.93 12,143.76 12,143.76 0.00


05.01 OBRAS PRELIMINARES 2,959.80 0.00 2,959.80 0.00 0.00 0.00 0.00
05.01.01 TRAZO Y REPLANTEO DE TUBERIA DE DESAGUE m 85.00 14.10 1,198.50 1,198.50

05.01.02 TRAZO Y REPLANTEO DE TUBERIA DE AGUA m 103.00 17.10 1,761.30 1,761.30

05.02 MOVIMIENTO DE TIERRAS 1,616.88 0.00 1,616.88 0.00 0.00 0.00 0.00
05.02.01 EXCAVACION DE ZANJA PARA TUBERIA m3 16.28 35.02 570.13 570.13

05.02.02 REFINE Y NIVELACION DE ZANJA PARA TUBERIA m2 43.07 7.00 301.49 301.49

05.02.03 RELLENO Y COMPACTACION DE ZANJAS MANUAL m3 10.62 17.58 186.70 186.70

05.02.04 ACARREO DE MATERIAL EXCEDENTE m3 16.28 14.01 228.08 228.08


05.02.05 ELIMINACION DE MATERIAL EXCEDENTE m3 6.80 48.60 330.48 330.48
05.03 SALIDAS DE DESAGUE 2,778.93 0.00 1,389.47 1,389.47 0.00 0.00 0.00
05.03.01 SALIDA DE PVC SAL PARA DESAGUE DE 2" pto 21.00 58.62 1,231.02 615.51 615.51
05.03.02 SALIDA DE PVC SAL PARA DESAGUE DE 4" pto 21.00 73.71 1,547.91 773.96 773.96
05.04 REDES DE DERIVACION 17,068.16 0.00 8,534.08 8,534.08 0.00 0.00 0.00
05.04.01 TUBERIA DE PVC SAL DE 2" m 170.00 25.32 4,304.40 2,152.20 2,152.20
05.04.02 TUBERIA DE PVC SAL DE 4" m 206.00 61.96 12,763.76 6,381.88 6,381.88
05.05 TEES 195.93 0.00 97.97 97.97 0.00 0.00 0.00
05.05.01 TEE PVC SAL 4" pza 21.00 9.33 195.93 97.97 97.97
05.06 YEES 103.53 0.00 51.77 51.77 0.00 0.00 0.00
05.07 YEE PVC DESAGUE SAL 4" x 2" und 21.00 4.93 103.53 51.77 51.77
CRONOGRAMA DE AVANCE DE OBRA VALORIZADO

"MEJORAMIENTO DE LA INFRAESTRUCTURA MUNICIPAL PARA LOS SERVICIOS ADMINISTRATIVOS DE LA MUNICIPALIDAD DISTRITAL DE NUEVO IMPERIAL - CANETE - LIMA" - 1ETAPA
DEPARTAMENTO: LIMA
PROVINCIA: CAETE PLAZO DE EJECUCION 180DC
DISTRITO: NUEVO IMPERIAL
FECHA: February 2017

TIEMPO 180 DIAS


ITEM DESCRIPCION UND METRADO PRECIO PARCIAL MES MES MES MES MES MES
1(30Dias) 2(30Dias) 3(30Dias) 4(30Dias) 5(30Dias) 6(30Dias)
05.08 CODOS 1,208.06 0.00 604.03 604.03 0.00 0.00 0.00
05.08.01 CODO PVC SAL 2" x 45 pza 8.00 3.13 25.04 12.52 12.52
05.08.02 CODO PVC SAL 4" x 45 pza 2.00 7.15 14.30 7.15 7.15
05.08.03 CODO PVC SAL 4" x 90 pza 8.00 6.32 50.56 25.28 25.28
05.08.04 CODO PVC SAL 2" x 90 pza 8.00 139.77 1,118.16 559.08 559.08
05.09 REGISTROS ROSCADOS DE BRONCE 156.36 0.00 78.18 78.18 0.00 0.00 0.00
05.09.01 REGISTRO DE BRONCE CROMADO ROSCADO DE 2" pza 4.00 39.09 156.36 78.18 78.18
05.10 SISTEMA DE AGUA FRIA 25,864.42 0.00 788.45 788.45 12,143.76 12,143.76 0.00
05.10.01 SALIDAS DE AGUA FRIA 721.28 0.00 360.64 360.64 0.00 0.00 0.00
05.10.01.01 SALIDA AGUA FRIA PVC 1/2" pto 16.00 45.08 721.28 360.64 360.64
05.10.02 REDES INTERIORES DE AGUA FRIA 298.81 0.00 149.40 149.40 0.00 0.00 0.00
05.10.02.01 TUBERIA DE PVC C-10, ENTERRADA EN PISO 1/2" m 31.52 9.48 298.81 149.40 149.40
05.10.03 LLAVES Y VALVULAS 213.63 0.00 106.82 106.82 0.00 0.00 0.00
05.10.03.01 VALVULA DE COMPUERTA DE BRONCE 1/2" pza 3.00 71.21 213.63 106.82 106.82
05.10.04 CODOS 166.90 0.00 83.45 83.45 0.00 0.00 0.00
05.10.04.01 CODO PVC SAL 1/2" x 90 pza 10.00 16.69 166.90 83.45 83.45
05.10.05 TEES 176.28 0.00 88.14 88.14 0.00 0.00 0.00
05.10.05.01 TEE PVC SAL 1/2" pza 12.00 14.69 176.28 88.14 88.14
05.10.06 APARATOS Y ACCESORIOS SANITARIOS 24,287.52 0.00 0.00 0.00 12,143.76 12,143.76 0.00
05.10.06.01 SUMINISTRO DE INODORO INCLUYE ACCESORIOS pza 18.00 429.21 7,725.78 3,862.89 3,862.89

05.10.06.02 SUMINISTRO OVALIN SONNET DE SOBREPONER und 17.00 578.93 9,841.81 4,920.91 4,920.91
COLOR BLANCO
05.10.06.03 SUMINISTRO URINARIO DE PARED CADET COLOR und 6.00 366.71 2,200.26 1,100.13 1,100.13
BLANCO I/ACC
05.10.06.04 INSTALACION DE APARATOS SANITARIOS pza 41.00 86.59 3,550.19 1,775.10 1,775.10

05.10.06.05 LAVADERO DE GRANITO SEGUN PLANO pza 3.00 250.60 751.80 375.90 375.90

05.10.06.06 SUMINISTRO E INSTALACION DE GRIFERIA PARA pza 3.00 72.56 217.68 108.84 108.84
LAVADERO INCLUYE ACCESORIOS
06 INSTALACIONES ELECTRICAS 65,863.10 0.00 2,830.05 12,405.08 9,608.97 0.00 41,019.00
06.01 SISTEMA DE ELECTRICIDAD 65,863.10 0.00 2,830.05 12,405.08 9,608.97 0.00 41,019.00
06.01.01 SALIDAS PARA ALUMBRADO 12,618.39 0.00 0.00 6,309.20 6,309.20 0.00 0.00
06.01.01.01 SALIDA DE TECHO C/CANALETA 20 MM + CABLE pto 111.00 102.19 11,343.09 5,671.55 5,671.55
TW DE 2.5MM2
CRONOGRAMA DE AVANCE DE OBRA VALORIZADO

"MEJORAMIENTO DE LA INFRAESTRUCTURA MUNICIPAL PARA LOS SERVICIOS ADMINISTRATIVOS DE LA MUNICIPALIDAD DISTRITAL DE NUEVO IMPERIAL - CANETE - LIMA" - 1ETAPA
DEPARTAMENTO: LIMA
PROVINCIA: CAETE PLAZO DE EJECUCION 180DC
DISTRITO: NUEVO IMPERIAL
FECHA: February 2017

TIEMPO 180 DIAS


ITEM DESCRIPCION UND METRADO PRECIO PARCIAL MES MES MES MES MES MES
1(30Dias) 2(30Dias) 3(30Dias) 4(30Dias) 5(30Dias) 6(30Dias)
06.01.01.02 SALIDA DE PARED PARA ALUMBRADO CON pto 22.00 43.98 967.56 483.78 483.78
TUBERIAS PVC-P DE 20MM+CABLE TW DE 2.5MM2
06.01.01.03 SALIDA DE TECHO PARA ALUMBRADO CON pto 6.00 51.29 307.74 153.87 153.87
TUBERIAS PVC-P DE 20MM+CABLE TW DE 2.5MM2
06.01.02 SALIDA PARA TOMACORRIENTES 3,568.94 0.00 657.37 1,784.47 1,127.10 0.00 0.00
06.01.02.01 SALIDA PARA PARED TOMACORRIENTE BIPOLAR pto 26.00 86.70 2,254.20 1,127.10 1,127.10
DOBLE 16 A C/TIERRA PVC SAP 20 MM
06.01.02.02 SALIDA PARA PISO TOMACORRIENTE BIPOLAR pto 14.00 93.91 1,314.74 657.37 657.37
DOBLE 16 A C/TIERRA PVC SAP 20 MM
06.01.03 SALIDA PARA INTERRUPTORES 2,667.44 0.00 889.15 889.15 889.15 0.00 0.00
06.01.03.01 INTERRUPTOR UNIPOLAR SIMPLE C/PVC SAP 20 pto 21.00 53.27 1,118.67 372.89 372.89 372.89
MM (TW 4 MM2)
06.01.03.02 INTERRUPTOR UNIPOLAR DOBLE C/PVC SAP 20 pto 21.00 53.44 1,122.24 374.08 374.08 374.08
MM (TW 4 MM2)
06.01.03.03 INTERRUPTOR UNIPOLAR TRIPLE C/PVC SAP 20 pto 3.00 72.19 216.57 72.19 72.19 72.19
MM (TW 4 MM2)
06.01.03.04 INTERRUPTOR UNIPOLAR SIMPLE C/CANALETA 20 pto 1.00 49.67 49.67 16.56 16.56 16.56
MM (TW 4 MM2)
06.01.03.05 INTERRUPTOR UNIPOLAR DOBLE C/CANALETA 20 pto 3.00 53.43 160.29 53.43 53.43 53.43
MM (TW 4 MM2)
06.01.04 CAJAS DE PASE 2,185.72 0.00 728.57 728.57 728.57 0.00 0.00
06.01.04.01 CAJA DE PASE OCTOGONAL DE FIERRO pto 4.00 11.83 47.32 15.77 15.77 15.77
GALVANIZADO
06.01.04.02 CAJA DE PASE 100x100x50MM DE FIERRO pto 45.00 47.52 2,138.40 712.80 712.80 712.80
GALVANIZADO
06.01.05 SALIDA PARA COMUNICACIONES DATA Y 1,664.87 0.00 554.96 554.96 554.96 0.00 0.00
06.01.05.01 SEALES
SALIDA PARA LUCES DE EMERGENCIAS pto 6.00 251.77 1,510.62 503.54 503.54 503.54
06.01.05.02 SALIDA PARA TELEVISION pto 2.00 30.85 61.70 20.57 20.57 20.57
06.01.05.03 SALIDA PARA INTERNET pto 3.00 30.85 92.55 30.85 30.85 30.85
06.01.06 TABLEROS ELECTRICOS 2,138.74 0.00 0.00 2,138.74 0.00 0.00 0.00
06.01.06.01 TABLEROS DISTRIBUCION CAJA METALICA CON 24 jgo 1.00 1,435.85 1,435.85 1,435.85
POLOS.
06.01.06.02 TABLERO DISTRIBUCION CAJA METALICA CON 12 und 1.00 702.89 702.89 702.89
POLOS
06.01.07 EQUIPOS DE ILUMINACION 34,225.14 0.00 0.00 0.00 0.00 0.00 34,225.14
06.01.07.01 ARTEFACTOS FLORECENTES 3/36 W SIMILAR A und 51.00 247.96 12,645.96 12,645.96
JOSFEL RAS-A
06.01.07.02 ARTEFACTOS FLORECENTES EMPOTRADOS 2X18 und 66.00 176.58 11,654.28 11,654.28
W MARCO DE ALUMINIO
06.01.07.03 BRAQUET REFLECTOR CON LAMPARAS 2X18 W und 22.00 161.22 3,546.84 3,546.84
AHORRADORASSIM.JOSFELRSO-2
CRONOGRAMA DE AVANCE DE OBRA VALORIZADO

"MEJORAMIENTO DE LA INFRAESTRUCTURA MUNICIPAL PARA LOS SERVICIOS ADMINISTRATIVOS DE LA MUNICIPALIDAD DISTRITAL DE NUEVO IMPERIAL - CANETE - LIMA" - 1ETAPA
DEPARTAMENTO: LIMA
PROVINCIA: CAETE PLAZO DE EJECUCION 180DC
DISTRITO: NUEVO IMPERIAL
FECHA: February 2017

TIEMPO 180 DIAS


ITEM DESCRIPCION UND METRADO PRECIO PARCIAL MES MES MES MES MES MES
1(30Dias) 2(30Dias) 3(30Dias) 4(30Dias) 5(30Dias) 6(30Dias)
06.01.07.04 ART. TIPO PLASTICO CUADRADO CON LAMPARA und 51.00 125.06 6,378.06 6,378.06
FLORECENTE DE 32 W
06.01.08 POZO A TIERRA 1,813.22 0.00 0.00 0.00 0.00 0.00 1,813.22
06.01.08.01 POZO PUESTA ATIERRA R=10 CHM5 und 2.00 906.61 1,813.22 1,813.22

06.01.09 SALIDA DE FUERZA 104.50 0.00 0.00 0.00 0.00 0.00 104.50
06.01.09.01 SALIDA PARA PARED PARA TOMACORRIENTE und 2.00 52.25 104.50 104.50
SIMPLE T/T CON TUBERIA PVC-P DE 20MM+CABLE TW
DE 4MM2
06.01.10 EQUIPAMIENTO DE BOMBEO 4,876.14 0.00 0.00 0.00 0.00 0.00 4,876.14
06.01.10.01 EQUIPO DE BOMBEO DE 0.5 HP und 2.00 2,201.98 4,403.96 4,403.96

06.01.10.02 SUMINISTRO E INSTALACION DE CONTROL DE NIVEL und 2.00 236.09 472.18 472.18
ELECTRICO

Costo Directo 1,768,751.97 61,050.18 272,475.93 483,678.77 305,877.88 379,373.13 266,296.09


GASTOS GENERALES (8%) 10.00% 176,875.20 6,105.02 27,247.59 48,367.88 30,587.79 37,937.31 26,629.61
UTILIDAD 5.00% 88,437.60 3,052.51 13,623.80 24,183.94 15,293.89 18,968.66 13,314.80
SUB TOTAL 2,034,064.77 70,207.71 313,347.32 556,230.59 351,759.56 436,279.10 306,240.50
IGV 18.00% 366,131.66 12,637.39 56,402.52 100,121.51 63,316.72 78,530.24 55,123.29
PRESUPUESTO TOTAL 2,400,196.43 82,845.09 369,749.84 656,352.09 415,076.28 514,809.34 361,363.79
PORCENTAJE DE AVANCE MENSUAL 3.45% 15.40% 27.35% 17.29% 21.45% 15.06%
PORCENTAJE DE AVANCE ACUMULADO 3.45% 18.86% 46.20% 63.50% 84.94% 100.00%
CRONOGRAMA DE DESEMBOLSOS

"MEJORAMIENTO DE LA INFRAESTRUCTURA MUNICIPAL PARA LOS SERVICIOS


Obra ADMINISTRATIVOS DE LA MUNICIPALIDAD DISTRITAL DE NUEVO IMPERIAL - CANETE -
LIMA" - 1ETAPA

Ubicacin CERCADO NUEVO IMPERIAL - CAETE - LIMA


Fecha February 2017
Plazo de Ejecucin 180.00 Dias = 6.00 Meses
Presupuesto Base S/. 2,400,196.43

Descripcin Mes Dias Porcentaje Parcial S/. Sub Total S/.

Adelanto en Efectivo 20.00% 480,039.29

Adelanto en Materiales 40.00% 960,078.57 1,440,117.86

Valorizacin N1 Primer Mes 30 3.45% 33,138.04 33,138.04

Valorizacin N2 Segundo Mes 30 15.40% 147,899.94 147,899.94

Valorizacin N3 Tercer Mes 30 27.35% 262,540.84 262,540.84

Valorizacin N4 Cuarto Mes 30 17.29% 166,030.51 166,030.51

Valorizacin N5 Quinto Mes 30 21.45% 205,923.73 205,923.73

Valorizacin N6 Sexto Mes 30 15.06% 144,545.52 144,545.52

SUB-TOTALES ( S/.) 180 100.00% 2,400,196.43

TOTAL S/. 2,400,196.43