Proximal - Trenching Cable for B

(AWI 1 to AWI 13)

NO WORK ITEMS DESCRIPTION

1 A. PREPARATION WORK
Land cleaning, forest (after tree cutting) include lrees less
1 1 than 15 cm dia and height below 2 m

2 CIVIL - CUT, EXCAVATE, AND TRENCHING SERVICE

Cut/excavate/trenching on sol, sand, dry - manual (without


2 1 Shoring)

2 2 Backlif (including compaction & Cleaning after excavation)

2 3 Supply material and install lean concrete

Supply material, fabricate le bar & formwork, pour & cute


2 4 concrete

2 5 Supply & Install Wairing tape (Clour Black + Yellow)


2 6 Supply & pour sand
3 B. TRENCING CABLE

INSTALL ONLY, ELECTRICAL/INSTRUMENT CABLE

3 1 Install Power cablle - above ground, underground, in wall

3 2 Install cable tray

Install Multimode Fiber Optic with amnour, ad size all core


3 3 number

3 4 Supply & Install Cable Marking post

Tota

Note : Harga tersebut sudah termasuk:


1. PPN 10%
2. Galian tanah biasa dan galian tanah keras harganya sama
3. Volume yang di tinggikan mengikuti actual di lapangan (jika ada perubahan harus tertulis)
4. Transportasi dan makan siang, PMCO, Flagman, PPE, MCU
5. Include Peralatan penunjang pekerjaan tersebut oleh subcont
6. Submit Eldding paling lambat tgl 2 Maret 2017 kepada team bidding Sarku Jakarta
7. Perusahaan Lokal Harus mempunyai SUJK agar potongan pembayaran hanya 2% apabila tidak di lampirkan SUJK
Proximal - Trenching Cable for Bidding
(AWI 1 to AWI 13)

BRIEF SPEC/REQUIRMENT/SCOPE SIZE/RANGE UNIT OF ESTIMATE UNIT


(DETAIL TO BE IN EXHIBIT A2) CLASS WORK QUANTITY RATE

As per Specification 02100, 02115 m2 405 12,000.00

CE

As per Specification 02220 m3 224.88 165,000.00

As per Specification 02220 m3 224.88 85,000.00

Ad per spec 03300 m3 5.5 950,000.00

Ad per spec 03300, Type I, steel reinforcing


max 125 Kg/m3 concrete (exceed the value K225 m3 N/A
may add supply & fanncate steel light - unit
rates), include admindure if required

m3 540.0 12,500.00
m3 61.31 265,000.00

See exhbil A 2.5.2 >75.01 mm2 meter 615.00 17,500.00

As per ELC 1000, Aluminum, completed 450 mm meter 70.00 35,000.00


with NEMA 20C cover

Material as per ITU-T G 652e, 9/125/250


Micrometer, anmour as per EC 502 Pireli, 1-4 core meter 615.00 16,500.00
Jembo, OCSI or equvalent

\ Ea 10.00 35,000.00

Total Bld Price (IDR)

ganya sama
lapangan (jika ada perubahan harus tertulis)
n, PPE, MCU
but oleh subcont
7 kepada team bidding Sarku Jakarta
r potongan pembayaran hanya 2% apabila tidak di lampirkan SUJK maka potongan sebesar 4%.
ESTIMATE
Remark
QUANTITY

4,860,000.00

37,105,200.00 Excavation sol

19,114,800.00

5,225,000.00 Cable ide

Pondation Support

6,750,000.00 Wainng tape


16,247,150.00 For sand back fill cable

10,762,500.00

2,450,000.00

10,147,500.00

350,000.00

113,012,150.00
Time Schedule -Proximal - Trenching Cable for Bidding
(AWI 1 to AWI 13)
ESTIMATE VALUE
NO WORK ITEMS DESCRIPTION MONT 1 MONT 2
QUANTITY %
1 A. PREPARATION WORK
Land cleaning, forest (after tree cutting) include lrees less
1 1 4,860,000.00 4.30 1.43 1.43 1.43
than 15 cm dia and height below 2 m

2 CIVIL - CUT, EXCAVATE, AND TRENCHING SERVICE

Cut/excavate/trenching on sol, sand, dry - manual (without


2 1 37,105,200.00 32.83 4.69 4.69 4.69 4.69
Shoring)

2 2 Backlif (including compaction & Cleaning after excavation) 19,114,800.00 16.91 2.42 2.42

2 3 Supply material and install lean concrete 5,225,000.00 4.62 0.66 0.66 0.66

Supply material, fabricate le bar & formwork, pour & cute


2 4 concrete

2 5 Supply & Install Wairing tape (Clour Black + Yellow) 6,750,000.00 5.97 0.85 0.85 0.85
2 6 Supply & pour sand 16,247,150.00 14.38 2.05 2.05 2.05

3 B. TRENCING CABLE

INSTALL ONLY, ELECTRICAL/INSTRUMENT CABLE

3 1 Install Power cablle - above ground, underground, in wall 10,762,500.00 9.52 1.36 1.36

3 2 Install cable tray 2,450,000.00 2.17


Install Multimode Fiber Optic with amnour, ad size all core
3 3 10,147,500.00 8.98 1.28
number

3 4 Supply & Install Cable Marking post 350,000.00 0.31


1.43 6.12 9.69 12.03 13.32
Total Bld Price (IDR) 113,012,150.00 100.00 1.43 7.56 17.25 29.28 42.60
g Cable for Bidding

MONT 2 MONT 3 Remark

4.69 4.69 4.69 Excavation sol

2.42 2.42 2.42 2.42 2.42

0.66 0.66 0.66 0.66 Cable ide

Pondation Support

0.85 0.85 0.85 0.85 Wainng tape


2.05 2.05 2.05 2.05 For sand back fill cable

1.36 1.36 1.36 1.36 1.36

0.36 0.36 0.36 0.36 0.36 0.36


1.28 1.28 1.28 1.28 1.28 1.28

0.05 0.05 0.05 0.05 0.05 0.05


13.68 13.73 13.73 9.04 5.47 1.70 0.05
56.28 70.01 83.74 92.78 98.25 99.95 100.00