August 7. 2009

PROJECT ACCOMPLISHMENT REPORT NO.4


For the Period Covering June 15 to July 15. 2009

Project : TRIPACK MANUFACTURING PLANT


Hon. Circle St., Sterling Industrial Estate, Iba, Meycauayan, Bulacan

Contractor : ILO Construction, Inc.

I. Project Accomplishment Computations

Contract Projected Actual Variance


Particular Remarks
% Wgt % % Wgt % % Wgt % % Wgt

I GENERAL REQUIREMENTS 2.77 50.00 1.385 56.20 2.0000 +6.20 +0.6500 Advanced

II EARTHWORKS
A. Layout and Staking 0.18 100.00 0.175 95.00 0.1665 -5.00 -0.0085 Delayed
` B. Excavation Works 0.57 100.00 0.570 90.00 0.5200 -5.00 -0.0200 Delayed
C. Backfill and Compaction 0.36 100.00 0.360 30.00 0.1100 -70.00 -0.0490 Delayed
D. Imported Fill 2.15 100.00 2.150 40.00 0.8600 -60.00 -1.2900 Delayed
E. Gravel Fill / Soil Poisoning 1.27 0 0 92.00 1.2700 92.00 +1.2700 Advanced
F. Dampproofing 0.22 0 0 0 0 0 0 -
III MAIN BUILDING
A. Structural / Civil Works
1. Column & Wall Footing 1.61 100.00 1.610 77.23 1.2400 -22.77 -0.3700 Delayed
2. Footing Tie Beam 1.78 100.00 1.780 88.46 1.5700 -11.54 --0.2100 Delayed
3. Columns 7.31 87.50 6.396 88.388 6.4600 +0.89 +0.0640 Advanced
4. Mid Beams Roof Beams 4.81 84.62 4.070 79.47 3.8200 -5.15 -0.2500 Delayed
5. Suspended Slabs & Canopies 0.67 100.00 0.607 90.00 0.6100 -10.00 -0.6100 Delayed
6. RC Wall & Stairs 0.52 76.47 0.397 75.00 0.3900 -1.47 -0.007 Delayed
7. Slab on Fill 6.21 0 0 0 0 0 0 -
B. Structural Steel Works 14.48 40.00 5.792 35.00 4.4200 -5.00 -1.372 Delayed
C. Tinsmithery Works 7.38 10.00 0.738 0 0 -10.00 -0.738 Delayed
D. Architectural Works
1. Masonry Works 9.64 66.66 6.426 59.80 5.4700 6.86 -0.956 Delayed
2. Floor Finishes 3.04 0 0 0 0 0 0 -
3. Wall Finishes 6.42 0 0 22.76 1.4600 +22.76 +1.460 Advanced
4. Ceiling Finishes 1.21 0 0 0.55 0.0100 +0.55 +0.010 Advanced
E. Doors and Windows 1.81 0 0 0 0 0 0 -
F. Miscellaneous Works 0.24 0 0 0 0 0 0 -
G. Metal Works 0.55 0 0 0 0 0 0 -
H. Waterproofing Works 0.64 0 0 0 0 0 0 -
I. Painting Worls 5.62 0 0 0 0 0 0
J. Electrical Works 0 30.43 0 0 0 0 0
K. Plumbing Works 5.94 26.32 1.56 0.50 0.0200 -25.82 -1.54 Delayed

IV OTHER UTILITIES

Kitchen,Canteen,Pump Room, 5.35 0 0 0 0 0 0 -


A.
Locker & Toilets
Guardhouse, Scrap Area & 3.35 0 0 0 0 0 0 -
B.
Garbage Room
C. Fence And Gate 0.91 0 0 0 0 0 0 -
D. Driveway 2.11 0 0 0 0 0 0 -
E. Cistern & Septic Tank 0.89 100 0.89 0 0 -100.00 -0.089 Delayed

Total 100.00 34.90 30.5765 -4.3235 Delayed

II. Project Duration

A. Construction Day 1 March 14, 2009

March 14, 2009Project Completion as per Contract

July 22, 2010


B. Project Contract Duration 224 calendar days
C. Total Number of Days Elapsed 123 calendar days
D. Total Remaining Number of Days 101 calendar days
E. % of Days Elapsed 54.91 %
F. Projected One day equivalent 0.4464 %
G. Actual One day equivalent 0.2486 %
H. No. of Days Delayed 9.685 Days

Prepared By:

Arch. Arnel L. Freo


Construction Manager

Noted:

Arch. Richard M. Garcia


Project Architect