EJERCICIO N 1

4
7
1 13
3 23 21
2
6
5 5
19 19

0 1 5
0 0 0 0 9 14

3 8
3 5 21 21

HOLGURAS DE PERT
TIEMPO OPTIMISTA TIEMPO PESIMISTA HOLG.
CODIGO DESCRIPCION SIMBOLO DURACION
to t+ ACTIVIDAD CONDICION
i j tij to i to j t+ i t+ j
0-1 0 0 0 0 0 0 Critica
1-2 5 0 5 0 5 0 Critica
1-3 3 0 3 0 5 2 no critica
2-4 8 5 13 5 13 0 Critica
2-5 4 5 9 5 14 5 no critica
3-5 4 3 9 5 14 7 no critica
4-6 6 13 19 13 19 0 Critica
5-6 5 9 19 14 19 5 no critica
5-8 3 9 21 14 21 9 no critica
6-7 4 19 23 19 21 -2 no critica
6-8 2 19 21 19 21 0 Critica

TIEMPOS FLOTANTES DEL CPM


TIEMPO OPTIMISTA TIEMPO PESIMISTA FLOTANTE
CODIGO DESCRIPCION SIMBOLO DURACION FLOTANTE FLOTANTE INDEPENDIE CONDICION
to t+ TOTAL LIBRE
NTE
i j tij to i to j t+ i t+ j
0-1 0 0 0 0 0 0 0 0 Critica
1-2 5 0 5 0 5 0 0 0 Critica
1-3 3 0 3 0 5 2 0 0 no Critica
2-4 8 5 13 5 13 0 0 0 Critica
2-5 4 5 9 5 14 5 0 0 no Critica
3-5 4 3 9 5 14 7 2 0 no Critica
4-6 6 13 19 13 19 0 0 0 Critica
5-6 5 9 19 14 19 5 5 0 no Critica
5-8 3 9 21 14 21 9 9 4 no Critica
6-7 4 19 23 19 0 -23 0 0 no Critica
6-8 2 19 21 19 21 0 0 0 Critica