Wall Finishes

Grand total Main Building Utility Building North guard house South Guard house
Sl.No. Description
Total UOM Start Finish Total Completed Remaining % completed Start Finish Total Completed Remaining % completed Start Finish Total Completed Remaining % completed Start Finish Total Completed Remaining % completed

1 Block work 4955 m2 8-Aug-17 3-Oct-17 4415 221 4194.25 5 26-Sep-17 3-Oct-17 497 497 0 25-Sep-17 30-Sep-17 22 22 0 26-Sep-17 3-Oct-17 21 21 0

2 Plastering 9918 m2 9-Sep-17 9-Oct-17 8671 8671 0 1-Oct-17 8-Oct-17 1105 1105 0 30-Sep-17 5-Oct-17 69 69 0 1-Oct-17 8-Oct-17 73 73 0

3 Wet area water proofing (Subcontract) 243 m 30-Sep-17 7-Oct-17 217 217 0 19-Oct-17 24-Oct-17 26 26 0

4 Primer 9056 m2 30-Sep-17 14-Oct-17 7976 7976 0 6-Oct-17 13-Oct-17 960 960 0 3-Oct-17 8-Oct-17 48 48 0 6-Oct-17 13-Oct-17 72 72 0

5 Stucco 9056 m2 5-Oct-17 24-Oct-17 7976 7976 0 11-Oct-17 26-Oct-17 960 960 0 8-Oct-17 13-Oct-17 48 48 0 11-Oct-17 26-Oct-17 72 72 0

4 1st coat paint 9056 m2 15-Oct-17 30-Oct-17 7976 7976 0 21-Oct-17 30-Oct-17 960 960 0 11-Oct-17 18-Oct-17 48 48 0 21-Oct-17 30-Oct-17 72 72 0

5 Corian wall cladding (Batimat) 2 m2 21-Oct-17 4-Nov-17 2 2 0

6 Corian tops (Batimat) 21 m 20-Oct-17 4-Nov-17 21 21 0

7 Stone cladding (Lithos design / Monaco) 17 m2 21-Oct-17 31-Oct-17 17 17 0

8 Wooden wall cladding (Chabros / Installer) 39 m2 11-Nov-17 16-Nov-17 39 39 0

9 Wallpaper (Subcontractor) 5.76 m2 4-Nov-17 9-Nov-17 5.76 5.76 0

10 Gypsum wall cladding 44 m2 20-Oct-17 28-Oct-17 44 44 0

11 Tiling (RAK) 1064 m2 12-Oct-17 7-Nov-17 912 912 0 22-Oct-17 1-Nov-17 138 138 0 14-Oct-17 16-Oct-17 14 14 0

12 Final coat paint 9056 m2 11-Oct-17 9-Nov-17 7976 7976 0 25-Oct-17 4-Nov-17 960 960 0 22-Oct-17 24-Oct-17 48 48 0 25-Oct-17 4-Nov-17 72 72 0
Floor Finishes
Grand total Main Building Utility Building North guard house South Guard house
Sl.No. Description
Total UOM Start Finish Total Completed Remaining % completed Start Finish Total Completed Remaining % completed Start Finish Total Completed Remaining % completed Start Finish Total Completed Remaining % completed

1 Screed 4168 m2 9-Sep-17 9-Oct-17 3928 3928 0 1-Oct-17 8-Oct-17 221 221 0 30-Sep-17 5-Oct-17 13 13 0 1-Oct-17 8-Oct-17 6 6 0

2 Wet area water proofing (Subcontract) 168 m2 5-Oct-17 11-Oct-17 154 154 0 19-Oct-17 24-Oct-17 14 14 0

3 Tiling (RAK) 712 m2 12-Oct-17 28-Oct-17 619 619 0 22-Oct-17 1-Nov-17 77 77 0 14-Oct-17 16-Oct-17 10 10 0 22-Oct-17 1-Nov-17 6 6 0

4 Tiling - Skirting (RAK) 206 m 14-Oct-17 28-Oct-17 128 128 0 22-Oct-17 1-Nov-17 57 57 0 14-Oct-17 16-Oct-17 12 12 0 22-Oct-17 1-Nov-17 9 9 0

4 Microtopping (Gambit) 362 m2 25-Oct-17 11-Nov-17 362 362 0

5 Linoleum (Thani Murshid) 243 m2 28-Oct-17 9-Nov-17 243 243 0

6 Vinyl (Thani Murshid) 550 m2 28-Oct-17 9-Nov-17 547 547 0 17-Oct-17 19-Oct-17 3 3 0

7 Vinyl - Skirting (Thani Murshid) 644 m 30-Oct-17 9-Nov-17 644 644 0

8 Carpet (Thani Murshid) 156 m2 8-Nov-17 14-Nov-17 156 156 0

9 Parquet (Chabros / Installer) 150 m2 1-Nov-17 12-Nov-17 150 150 0

10 Parquet - Tread & Raiser (Chabros / Installer) 28 m 1-Nov-17 12-Nov-17 28 28 0

11 Raised floor (Gulf computers) 53 m2 2-Nov-17 8-Nov-17 53 53 0

12 Entrance Floor mat (Thani Murshid) 5 m2 8-Nov-17 14-Nov-17 5 5 0

14 Epoxy (Gambit) 1721 m2 25-Oct-17 11-Nov-17 1721 1721 0


Ceiling Finishes
Grand total Main Building Utility Building North guard house South Guard house
Sl.No. Description
Total UOM Start Finish Total Completed Remaining % completed Start Finish Total Completed Remaining % completed Start Finish Total Completed Remaining % completed Start Finish Total Completed Remaining % completed

1 Surface preparation 1993 m2 12-Aug-17 25-Sep-17 1825 219 1606 12 10-Oct-17 12-Oct-17 157 157 0 25-Sep-17 27-Sep-17 11 11 0

3 Primer 3250 m2 26-Aug-17 28-Sep-17 3055 3055 0 13-Oct-17 16-Oct-17 184 184 0 28-Sep-17 29-Sep-17 11 11 0

4 Stucco 3250 m2 31-Aug-17 3-Oct-17 3055 3055 0 16-Oct-17 19-Oct-17 184 184 0 30-Sep-17 1-Oct-17 11 11 0

5 1st coat paint 3250 m2 10-Sep-17 13-Oct-17 3055 3055 0 20-Oct-17 21-Oct-17 184 184 0 2-Oct-17 4-Oct-17 11 11 0

6 Final coat paint 3250 m2 10-Oct-17 7-Nov-17 3055 3055 0 28-Oct-17 29-Oct-17 184 184 0 22-Oct-17 24-Oct-17 11 11 0

7 False ceiling framing (Al Kindi) 2134 m2 10-Oct-17 30-Oct-17 2049 2049 0 10-Oct-17 18-Oct-17 65 65 0 10-Oct-17 16-Oct-17 14 14 0 10-Oct-17 18-Oct-17 6 6 0

8 Accoustic ceiling Tiles (Al Kindi) 353 m2 30-Oct-17 7-Nov-17 312 312 0 15-Oct-17 25-Oct-17 38 38 0 15-Oct-17 22-Oct-17 3 3 0

9 Gypsum ceiling boards (Al Kindi) 1245 m2 17-Oct-17 4-Nov-17 1201 1201 0 15-Oct-17 25-Oct-17 27 27 0 15-Oct-17 22-Oct-17 11 11 0 15-Oct-17 25-Oct-17 6 6 0

10 Gypsum ceiling boards - Bulkhead (Al Kindi) 234 m 22-Oct-17 2-Nov-17 234 234 0

11 Aluminum baffle (Al Kindi) 481 m2 28-Oct-17 9-Nov-17 481 481 0

12 Stretched fabric (Al Kindi) 2 no 9-Nov-17 14-Nov-17 2 2 0

13 Cement board (Al Kindi) 55 m2 29-Oct-17 4-Nov-17 55 55 0


Joinery & fitouts
Grand total Main Building Utility Building North guard house South Guard house
Sl.No. Description
Total UOM Start Finish Total Completed Remaining % completed Start Finish Total Completed Remaining % completed Start Finish Total Completed Remaining % completed Start Finish Total Completed Remaining % completed

1 Fixing of subframes 100 no 2-Oct-17 12-Oct-17 84 84 0 29-Sep-17 4-Oct-17 14 14 0 30-Sep-17 5-Oct-17 1 1 0 29-Sep-17 4-Oct-17 1 1 0

2 Fixing of frames (HAG metal) 100 no 7-Oct-17 17-Oct-17 84 84 0 2-Oct-17 7-Oct-17 14 14 0 3-Oct-17 8-Oct-17 1 1 0 2-Oct-17 7-Oct-17 1 1 0

3 Fixing of wooden door panels (Vulcan) 39 no 10-Oct-17 20-Oct-17 39 39 0 0

4 Timber doors (Subcontractor) 6 no 4-Oct-17 10-Oct-17 5 5 0 5-Oct-17 10-Oct-17 1 1 0

4 Fixing of metal door panels (HAG metal) 52 no 10-Oct-17 20-Oct-17 42 42 0 4-Oct-17 10-Oct-17 9 9 0 4-Oct-17 10-Oct-17 1 1 0

5 Fixing of Rolling shutter (Dosteen) 2 no 20-Oct-17 25-Oct-17 2 2 0

6 Fixing of overhead colliding doors (Dosteen) 1 no 15-Oct-17 25-Oct-17 1 1 0

7 Aluminum Windows (Eurosystem) 20 no 23-Oct-17 7-Nov-17 15 15 0 24-Oct-17 27-Oct-17 3 3 0 16-Oct-17 21-Oct-17 1 1 0 24-Oct-17 27-Oct-17 1 1 0

8 Aluminum louver doors (Eurosystem) 5 no 23-Oct-17 7-Nov-17 2 2 0 2-Oct-17 10-Oct-17 3 3 0

9 Glazed partitions & doors (Eurosystem) 268 m2 7-Oct-17 22-Oct-17 244 244 0 18-Oct-17 23-Oct-17 24 24 0

10 Glazed doors (Eurosystem) 8 no 7-Oct-17 22-Oct-17 6 6 0 18-Oct-17 23-Oct-17 2 2 0

11 Fixing of Ironmongery (Provisional sum) 0 no 25-Oct-17 30-Oct-17 0 #DIV/0! 6-Oct-17 12-Oct-17 0 #DIV/0! 7-Oct-17 12-Oct-17 0 #DIV/0! 6-Oct-17 12-Oct-17 0 #DIV/0!

12 Fixing of mirrors (Noor al Huda) 9 no 9-Nov-17 11-Nov-17 8 8 0 22-Oct-17 23-Oct-17 1 1 0

13 Gypsum board partitions (Al Kindi) 97 m2 7-Oct-17 22-Oct-17 97 97 0

14 Cistern panelling (Batimat) 16 no 21-Oct-17 4-Nov-17 16 16 0

15 Installation of pantry cabinets (Subcontractor) 4 no 1-Nov-17 11-Nov-17 4 4 0

16 Installation of counter tops (Batimat) 7 no 21-Oct-17 4-Nov-17 7 7 0

17 Steel staircase (Opus / Extraco) 1 no 25-Oct-17 4-Nov-17 1 1 0

18 Balustrades (Eurosystem) 59 m 12-Oct-17 27-Oct-17 59 59 0

19 Handrails (Subcontractor) 29 m 15-Oct-17 30-Oct-17 29 29 0

20 Cat ladder 8 no 9-Nov-17 14-Nov-17 4 4 0 25-Oct-17 29-Oct-17 4 4 0

21 Fixed furniture (Subcontractor) 27 no 4-Nov-17 14-Nov-17 27 27 0

22 Blinds (Subcontractor) 8 no 9-Nov-17 14-Nov-17 8 8 0

23 Electronic blinds (Subcontractor) 1 no 12-Nov-17 14-Nov-17 1 1 0

24 Skylight Frames (Provisional sum) - Euro system 158 m2 15-Sep-17 21-Sep-17 158 158 0

25 Skylight Glass (Provisional sum) - Euro system 100 m2 18-Sep-17 24-Sep-17 100 100 0

26 Skylight PV panels (Provisional sum) - Value addition 58 m2 25-Sep-17 30-Sep-17 58 58 0

27 Lose furniture (Provisional sum) 0 no 4-Nov-17 14-Nov-17 0 #DIV/0!


External finishes
External
Sl.No. Description
Start Finish Total UOM Completed Remaining % completed

1 Excavation, Leveling, Road base & compaction 29-Jul-17 30-Aug-17 511 m 511 0

2 Blinding & Waterproofing 6-Aug-17 4-Sep-17 875 m2 875 0

3 Foundation Formwork 11-Aug-17 9-Sep-17 1328 m2 1328 0

4 Foundation concrete 16-Aug-17 14-Sep-17 511 m3 511 0

5 Precast panels for boundary walls (Gulf precast) 31-Aug-17 29-Sep-17 33 no 33 0

6 Sliding gate (Subcontractor) 19-Nov-17 24-Nov-17 2 no 2 0

7 Boom gate (Subcontractor) 19-Nov-17 24-Nov-17 2 no 2 0

6 Precast kerbs (Consent) 4-Sep-17 24-Sep-17 1728 m 1728 0

7 Grade slab 14-Sep-17 4-Oct-17 63 m2 63 0

8 Precast concrete paving (Consent) 19-Sep-17 9-Oct-17 5175 m2 5175 0

9 Precast concrete block paving (Consent) 19-Sep-17 9-Oct-17 87 m 87 0

10 Ceramic paving (Subcontractor) 19-Sep-17 9-Oct-17 314 m2 314 0

11 Cornwood paving (Green glades) 24-Sep-17 14-Oct-17 160 m2 160 0

12 Aluminum edge (Gloden fountain) 19-Sep-17 14-Oct-17 451 m 451 0

13 Stainless steel divider (Gloden fountain) 19-Sep-17 14-Oct-17 74 m 74 0

14 Handrail (Subcontractor) 15-Oct-17 21-Oct-17 63 m 63 0

12 Landscaping & root barrier (Gloden fountain) 29-Sep-17 8-Nov-17 100 % 100 0

13 Irrigation (Golden fountain) 29-Sep-17 8-Nov-17 100 % 100 0

14 Wadi gravel (Green glades) 8-Nov-17 13-Nov-17 334 m2 334 0

15 Gravel (Green glades) 8-Nov-17 13-Nov-17 1292 m2 1292 0

16 Natural rock boulders (Green glades) 8-Nov-17 13-Nov-17 100 % 100 0

17 Wheel stoppers (Consent) 10-Oct-17 18-Oct-17 94 no 94 0

18 Road marking (Subcontractor) 9-Nov-17 19-Nov-17 100 % 100 0

19 Parking shades (Al Hamrat) 14-Sep-17 19-Oct-17 18 no 18 0

20 Custom parking shades (Al Hamrat) 14-Sep-17 19-Oct-17 18 no 18 0

21 Solar parking shades - (Nominated) Value addition 14-Oct-17 3-Nov-17 53 no 53 0

22 Electric car charging stations (Provisional sum) - Green parking 8-Nov-17 14-Nov-17 2 no 2 0

23 Boom barriers (Subcontractor) 19-Nov-17 24-Nov-17 2 no 2 0

24 Backless seats 14-Nov-17 24-Nov-17 5 no 5 0

25 Chair & tables 14-Nov-17 24-Nov-17 6 no 6 0

26 Trash Bins 14-Nov-17 24-Nov-17 3 no 3 0

27 Signage (Subcontractor) 14-Nov-17 24-Nov-17 1 no 1 0


STRUCTURAL STEEL WORKS - GERMAN STEEL
Grand total South Elevation West Elevation - Grid A to G9 West Elevation - Grid H to N North Elevation East Elevation
Sl.No. Description
Total UOM Start Finish Total Completed Remaining % completed Start Finish Total Completed Remaining % completed Start Finish Total Completed Remaining % completed Start Finish Total Completed Remaining % completed Start Finish Total Completed Remaining % completed

1 Erection of structural steel members 1281 m2 3-Sep-17 7-Sep-17 86 86 0 9-Sep-17 17-Sep-17 344 344 0 18-Sep-17 29-Sep-17 312 312 0 30-Sep-17 5-Oct-17 261 261 0 6-Oct-17 10-Oct-17 278 278 0

2 Erection of scaffolding 100 % 8-Sep-17 10-Sep-17 100 100 0 18-Sep-17 22-Sep-17 100 100 0 30-Sep-17 3-Oct-17 100 100 0 6-Oct-17 7-Oct-17 100 100 0 11-Oct-17 12-Oct-17 100 100 0

3 Site weld & finishes 100 % 11-Sep-17 13-Sep-17 100 100 0 23-Sep-17 26-Sep-17 100 100 0 4-Oct-17 6-Oct-17 100 100 0 8-Oct-17 8-Oct-17 100 100 0 13-Oct-17 13-Oct-17 100 100 0

4 Installation of Catwalk 100 % 12-Sep-17 16-Sep-17 100 100 0 24-Sep-17 1-Oct-17 100 100 0 5-Oct-17 9-Oct-17 100 100 0 9-Oct-17 10-Oct-17 100 100 0 14-Oct-17 15-Oct-17 100 100 0

CURTAIN WALL WORKS - EURO SYSTEM


Grand total South Elevation West Elevation - Grid A to G9 West Elevation - Grid H to N North Elevation East Elevation
Sl.No. Description
Total UOM Start Finish Total Completed Remaining % completed Start Finish Total Completed Remaining % completed Start Finish Total Completed Remaining % completed Start Finish Total Completed Remaining % completed Start Finish Total Completed Remaining % completed

1 Bitumen paint 100 % 30-Sep-17 3-Oct-17 100 100 0 4-Oct-17 8-Oct-17 100 100 0 9-Oct-17 12-Oct-17 100 100 0 13-Oct-17 16-Oct-17 100 100 0 17-Oct-17 19-Oct-17 100 100 0

2 Thermal Insulation - Extruded boards 100 m2 1-Oct-17 4-Oct-17 100 100 0 5-Oct-17 11-Oct-17 100 100 0 10-Oct-17 18-Oct-17 100 100 0 14-Oct-17 17-Oct-17 100 100 0 18-Oct-17 21-Oct-17 100 100 0

3 Rock wool Insulation 332 m2 1-Oct-17 4-Oct-17 11 11 0 10-Oct-17 18-Oct-17 107 107 0 14-Oct-17 18-Oct-17 124 124 0 18-Oct-17 22-Oct-17 90 90 0

4 Installation of Mullions 670 m2 2-Oct-17 8-Oct-17 89 89 0 12-Oct-17 20-Oct-17 264 264 0 16-Oct-17 24-Oct-17 317 317 0

5 Installation of glass panels 670 m2 6-Oct-17 12-Oct-17 89 89 0 14-Oct-17 23-Oct-17 264 264 0 18-Oct-17 26-Oct-17 317 317 0

6 Finishing 100 % 8-Oct-17 14-Oct-17 100 100 0 6-Oct-17 13-Oct-17 100 100 0 16-Oct-17 25-Oct-17 100 100 0 19-Oct-17 27-Oct-17 100 100 0 19-Oct-17 23-Oct-17 100 100 0

PV PANEL WORKS - LILY SYSTEM / VALUE ADDITION / 5-STAR


Grand total South Elevation West Elevation - Grid A to G9 West Elevation - Grid H to N North Elevation East Elevation
Sl.No. Description
Total UOM Start Finish Total Completed Remaining % completed Start Finish Total Completed Remaining % completed Start Finish Total Completed Remaining % completed Start Finish Total Completed Remaining % completed Start Finish Total Completed Remaining % completed

1 Fixing of brackets 100 % 13-Sep-17 17-Sep-17 100 100 0 25-Sep-17 2-Oct-17 100 100 0 6-Oct-17 10-Oct-17 100 100 0 10-Oct-17 11-Oct-17 100 100 0 15-Oct-17 16-Oct-17 100 100 0

2 Fixing of panels - faade 536 nos 28-Sep-17 20-Sep-17 27 27 0 10-Oct-17 6-Oct-17 160 160 0 21-Oct-17 13-Oct-17 125 125 0 25-Oct-17 13-Oct-17 106 106 0 30-Oct-17 18-Oct-17 118 118 0

3 Fixing of panels - Canpoy 315 m2 23-Oct-17 15-Oct-17 278 278 0 27-Oct-17 29-Oct-17 37 37 0

4 Termination & finishes 100 % 30-Sep-17 22-Sep-17 100 100 0 12-Oct-17 8-Oct-17 100 100 0 25-Oct-17 17-Oct-17 100 100 0 28-Oct-17 31-Oct-17 100 100 0 31-Oct-17 20-Oct-17 100 100 0

FAADE LIGHTING WORKS - PROJECTS & SUPPLIES / GBH


Grand total South Elevation West Elevation - Grid A to G9 West Elevation - Grid H to N North Elevation East Elevation
Sl.No. Description
Total UOM Start Finish Total Completed Remaining % completed Start Finish Total Completed Remaining % completed Start Finish Total Completed Remaining % completed North Elevation Total Completed Remaining % completed Start Finish Total Completed Remaining % completed

1 Installation of lights 159 no 27-Sep-17 2-Oct-17 15 15 0 9-Oct-17 14-Oct-17 45 45 0 20-Oct-17 27-Oct-17 33 33 0 24-Oct-17 27-Oct-17 25 25 0 29-Oct-17 2-Nov-17 41 41 0

2 Wiring for lights 100 % 29-Sep-17 5-Oct-17 100 100 0 11-Oct-17 17-Oct-17 100 100 0 22-Oct-17 30-Oct-17 100 100 0 26-Oct-17 29-Oct-17 100 100 0 30-Oct-17 4-Nov-17 100 100 0

3 Termination and comissioning 100 % 6-Oct-17 10-Oct-17 100 100 0 14-Oct-17 19-Oct-17 100 100 0 27-Oct-17 30-Oct-17 100 100 0 28-Oct-17 31-Oct-17 100 100 0 5-Nov-17 7-Nov-17 100 100 0