SUPPLY , COMMISSIONING AND ENGINEERING

OF PLC MARSHALING PANEL FOR PROJECT COOLER in light soda

A) MARSHALING PANEL HARDWARE BOM

1)INTERFACING MODULE FOR I/O TO CPU 313C WITH COMMUNICATION CABLE-01.


2) 32 CHANNEL DI MODULE 24 VDC 02 NO.
MLFB NO.:6ES7321-1BL00-0AA0
3) 16 CHANNEL DO MODULE -01 NO.
MLFB NO -322-1BH02-OAAO
6) 8 CHANNEL AI MODULE 02 NO.
MLFB NO.:6ES7331-1KF02-0AB0
7) 4 CHANNEL A0 MODULE 01 NO.
MLFB NO.:6ES7332-5HD01-0AB0
8) 40 PIN CONNECTOR REQUIRED NO.
MLFB NO.:6ES7392-1AM00-0AA0
9) 20 PIN CONNECTOR RQUIRED NO.
MLFB NO.:6ES7392-1AJ00-0AA0
10) MOUNTING RAIL 530 MM 01 NO.
MLFB NO.:6ES7390-1AF80-0AA0
11) SITOP POWER SUPPLY 24 VDC , 10 AMP 01 NO.
MLFB NO.:6EP1334-2AA01

(B) MARSHALING PANEL AND ACCESSORIES

PANEL
RITAL MAKE ENCLOSURE WALL MOUNTING 01 NO.
PANEL SIZE : SUITABLE HARDWARE BOM
AND FOLLOWING ACCESSORIES
MOC : 14 SWG CRC SHEET EPOXY PAINTED
SHADE MILKY CREAM. BOTTOM CABLE ENTRY
WITH DETACHABLE GLAND PLATE
COOLING FAN , VENTILATION GRILL , ILLUMINATION
AND UTILITY PLUG.
PROTECTION : DUST AND VERMIN PROOF

OTHER ACCESSORIES REQUIRED FOR GIVEN HARDWARE AND SOFTWARE.

OTHER ACCESSORIES

1) 24VDCX 8 RELAY BOARD FOR DO 02 NOS.


2) 110VACX 8 RELAY BOARD FOR DI 08 NOS.
3) ALTERNATE FUSE 110VAC TERMINALS AT MARSHALING
TERMINALS FOR DIGITAL INPUT AND OUTPUT.
4) REQUIRED MCB , TERMINALS & MOUNTING RAIL ,"
WIRING , ENGRAVING AND OTHER MISC
CONSUMABLES ITEMS
5)CURRENT TRANSDUCER WITH 4-20MA O/P AND 0 TO 1AMP I/P-10 NO
MAKE-ELSTER

( C ) SCADA SOFTWARE

1) WINCC RUN TIME LICENSE SOFTWARE TO BE UPGRATE FROM 128 TAG TO 2048 TAG 01 NO.

(D) ENGINEERING AND DEVELOPMENTS

1) COOLER PROJECT OPERATION CONTROL


SOFTWARE WITH ALL STANDARD PARAMETERS.
2) GRAPHICS,STATUS AND OPERATION PARAMETERS.
3) SYSTEM AND PROCESS ALARMS/FAULTS
4) OPERATION EVENTS HISTORY.

DOCUMENTS

- TEST AND WARRANTY CERTIFICATE.


ALL THE SUPPLIED HARD WARE.
- 03 SETS OF TECHNICAL MANUALS.
AND LAYOUT DRAWING WITH WIRING DETAIL

GENERAL TERMS
- ALL THE PROGRAM OF CPU AND SCADA
SHALL BE REMAIN OPEN TO CUSTOMER.
i.e. ANY SOFTWARE OR PROGRAM
SHALL NOT BE LOCKED BY ANY LEVEL
OF PASS WARD.
- PRIOR DRAWING AND SPECIFICATIONS
OF ALL THE ABOVE BOM APPROVAL
REQUIRED BEFORE RAISING PO.