Analisa EI-791

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET : Peningkatan Jalan Desa Bunga Tanjung
.
PROP / KAB / KODYA : Bengkulu / Mukomuko
ITEM PEMBAYARAN NO. : 7.9.(1) PERKIRAAN VOL. PEK. : 240,00
JENIS PEKERJAAN : Pasangan Batu TOTAL HARGA (Rp.) : 178.103.391,43
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK : #DIV/0!

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja Biasa (L01) jam 6,4257 11.428,57 73.436,60


2. Tukang (L02) jam 1,6064 14.285,71 22.948,94
3. Mandor (L03) jam 0,8032 16.114,29 12.943,20

JUMLAH HARGA TENAGA 109.328,74

B. BAHAN

1. Batu Kali (M02) M3 1,1700 198.700,00 232.479,00


2. Semen (PC) (M12) Kg 141,0000 1.250,00 176.250,00
3. Pasir (M01) M3 0,4225 192.200,00 81.207,38

JUMLAH HARGA BAHAN 489.936,38

C. PERALATAN

1 Conc. Mixer (E06) jam 0,8032 92.712,14 74.467,58


2 Water Tanker (E23) jam 0,0014 285.534,02 401,35
1 Alat Bantu Ls 1,0000 500,00 500,00

JUMLAH HARGA PERALATAN 75.368,94

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 674.634,06


E. OVERHEAD & PROFIT 10,0 % x D 67.463,41
F. HARGA SATUAN PEKERJAAN ( D + E ) 742.097,46
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.