Professional Documents
Culture Documents
Date: 10-Sep-2017
The support of the world bank to MoE is multidimensional and one to the
important part is its support to the infrastructure part, construction of building
for educational facilities i.e. schools, teacher training centers, administration
building, hostels and etc.
Under EQUIP Phase I,II from 2004 to 2012, a total of 1347 community
contracts were planned out of which for 415 community contracts Buildings are
completed but there related contracted components ( water well, latrines, and
furnitures) remained incomplete.
Initially in 2012, the number of schools with incomplete components were 926
Project ,however the ministry of education through government financing and
off budget donor contribution has managed to provide incomplete components
to 511 schools and for the balance 415 schools , the incomplete components are
still to be provided. It worth mentioning that amongst 415 schools, 309 are girls
and 106 are boys schools. The issue of providing incomplete components and
finding funding source were brought up to the notice of H.E the president of
Afghanistan where the president has ordered a thorough technical investigation
and assigned a committee comprised of Policy Coordination Unit of the
presidents office, the Ministry of Education along with representatives of the
Ministries of Public Works, Urban Development, Ministry of Rural
Rehabilitation and Ministry of Economy to review the existing status of the 415
incomplete CC School projects , the required budget for completion and the
reasons for their incompletion. The committee found the reasons for
incompletion as bellow:
a. Design Problem:
The committee has identified that the civil works quantities were under
estimated and there has been discrepancies in bill of quantities and drawing.
Moreover the site specific Designs were not adopted and the terrain conditions
were not assessed properly resulting in more excavation and extra work in
construction activities. Since it was lump sum contract with fix celling, the
community were not paid for the additional work performed. Hence the
community could only complete the building with the available money and the
contracted components remained incomplete.
The committee assessed the variation in terms of extra work by re-calculating
the quantities from the drawings to figure out the difference between
Contracted BoQ and Drawings and physically surveying the site and reported
the actual work performed versus contracted quantities.
The unit cost were not derived from Site Specific Construction Material Rates,
No rate analysis has been performed and the transportation cost to the site were
not considered. In fact the same contract amount were paid to the communities
across Afghanistan irrespective of considering geographical and climatic
conditions. In EQUIP I (2004-2008), a lump sum amount of 32000 USD has
been paid to the communities across Afghanistan and in EQUIP II (2008-2012) ,
a lump sum amount of 64000 USD has been paid to communities.
e. Missing items:
The boundary walls and electricity system was not part of the contract with
community and they were missed from the original contract, however the
provision of these components are important for the schools hence it is
suggested to include these items along with incomplete items. The estimated
price for missing items amounts to 1,616,430 USD.
The MoE-ISD Engineers conducted survey of each school and identified the
incomplete items and prepare the site plan on the basis of which the design
drawing and price estimates were prepared for completion of these items.
Outmost care were taken to consider site specific design and construction
material rates. The committee has reviewed and approved the technical
documents which were again cross checked by World Bank civil work
consultant.
c. Completion period:
Option 1:
Option 2:
The incomplete items under the same packages and Lots will be provided by
contractors, however the funds will be transferred to provinces and the
provincial procurement department will carry out the National competitive
bidding method for selecting the contractor.
Project
Monitoring plan
Central/Provincial
report analyzed by
Regional Managers/
instructions provided to Technical committee
Contractor and Senior
Engineers
report submitted to
database and relevant
departments
The leadership of Ministry of Education values the partnership with the international
development partners and requests for providing financial support of a total amount of
6,773,970 USD to cover the difference indicated in the reasons of incompletion in order
to create safe access and learning environment for the school children of Afghanistan.
As one can gather from the reasons which left 415 schools incomplete and which is
continuously causing an anti-social environment for the school going children of
Afghanistan and is ultimately impairing the project objectives of the Education Quality
Improvement we request all the stakeholders to join hands and let the schools be
completed first and thereafter go for the causes which were responsible for such a huge
negligence. we request the international development partners to come forward, as one
time special favor, and make sure that their funded schools are put in proper usable
condition to serve the ultimate goal of the project.