You are on page 1of 21

0068_C34_fm Page 1 Monday, August 12, 2002 1:20 PM

34
Developing
an Earthquake
Mitigation Program

34.1 Introduction
34.2 Overview of an Earthquake Mitigation Program
34.3 Phase 0: Pre-Program Activities
34.4 Phase 1: Assessing the Problem
34.5 Phase 2: Developing the Program
34.6 Phase 3: Implementing the Program
Retaining Seismic Retrofit Design Professionals Funding the
Program Coordinating with Other Parts of the Organization
Perform Seismic Retrofit Dealing with Residual Risk
34.7 Maintaining the Program
Charles Scawthorn Defining Terms
Consulting Engineer References
Berkeley, CA Further Reading

When schemes are laid in advance, it is surprising how often the circumstances fit in with them.
Sir William Osler (18491919)

34.1 Introduction
Previous chapters of this volume have discussed the effects of earthquake and the potential resulting
damage. This chapter provides guidance on how to go about developing and implementing an earthquake
risk reduction program to reduce that potential damage that is, this chapter discusses developing an
earthquake mitigation program. An earthquake mitigation program has five basic aspects:
1. Pre-program activities
2. Assessing the risk
3. Developing the program
4. Implementing the program
5. Maintaining the program
The next section first provides an overview of these aspects, and is then followed by sections providing
a detailed discussion of each aspect.

2003 by CRC Press LLC


0068_C34_fm Page 2 Monday, August 12, 2002 1:20 PM

34-2 Earthquake Engineering Handbook

34.2 Overview of an Earthquake Mitigation Program


Earthquakes are a problem and, in the most general sense, solving a problem has three basic phases:
1. Phase 1: Understanding the problem
2. Phase 2: Finding a solution
3. Phase 3: Putting the solution into effect
Solving the earthquake problem that is, an earthquake mitigation program has these three basic
phases, plus two more phases. These two additional phases are required because earthquake mitigation
typically involves activities in large organizations over a prolonged period (years, if not decades), during
which personnel changes are not uncommon. Therefore, the two additional phases are (1) a phase zero,
which consists of actually getting a large organization to embark on an earthquake mitigation program,
and (2) phase 4: putting in place the organizational mechanisms such that the earthquake mitigation
program is maintained over the required period.
Regarding the latter phase, maintaining the earthquake mitigation program over the required period
is not actually sufficient; once the formal earthquake mitigation program has been completed, or during
its implementation, conditions are likely to change such that the earthquake mitigation program should
likewise change. Lastly, part of any comprehensive earthquake mitigation program is an emergency plan.
As discussed in Chapter 33, maintaining an emergency plan is integral to that plan. Therefore, in the
sense that the emergency plan is part of the earthquake implementation program, and that the program
needs to be alert to changing conditions in the organization that may increase earthquake risk, mainte-
nance of the earthquake mitigation program is an ongoing task which never ends. That is, once the
formal earthquake mitigation program has been completed, earthquake mitigation should be an ongoing
part of the organizations normal risk management activities. Therefore, developing an earthquake
mitigation program involves the following five phases:
1. Phase 0, pre-program activities, involving increasing awareness of the potential earthquake prob-
lem, and gaining authorization for an initial assessment of the problem.
2. Phase 1, assessing the risk, consisting of an initial review of life, property, and business or functional
exposures, and the threat that earthquakes may pose to them, in order to determine the current
seismic risk. That is, are earthquakes indeed a problem (i.e., does a problem exist?) and, if so,
what is the magnitude and nature of that problem?
3. Phase 2, developing the program, which consists of determining the organizations acceptable risk,
the options that exist for reducing the current risk to an acceptable level, the costs of doing that,
and how it should be accomplished.
4. Phase 3, implementing the program that is, actually taking the actions that reduce the risk.
5. Phase 4, maintaining the program so that the risk does not become unacceptable.
These phases are shown in Figure 34.1, and discussed in more detail in the next sections.

34.3 Phase 0: Pre-Program Activities


Pre-program activities may be very simple or very difficult, depending on geographic and organizational
factors, such as the organizations mode of decision-making. The fundamental driver is geographic
is there a potential for earthquakes in regions in which the organization operates? While earthquakes
have the potential to occur almost anywhere, there are regions such as parts of California, Japan, and
Mexico, in which they are clearly a problem. There are other regions in which the degree of earthquake
risk is less clear in the eastern United States, for example, where earthquakes have occurred, but their
frequency is relatively low. The region to be considered, by the way, is not only the region in which the
organization may be located, but also regions related to the organization, such as where the organizations
suppliers, or customers, are located. Chapters 1 and 4 of this volume should provide sufficient informa-
tion, in a global sense, to obtain a broad understanding as to whether earthquakes are a problem for a

2003 by CRC Press LLC


0068_C34_fm Page 3 Monday, August 12, 2002 1:20 PM

Developing an Earthquake Mitigation Program 34-3

Factors
- Seismic environment?
Pre-program - Organization / decision-making
- Responsibility / liability

Data
- Seismic hazard
Assess the Risk - Exposure
- life
- property
- business / function
- revenue
Y - data
Stop Acceptable? - market share
- reputation / image
- Vulnerability
N - Assessment

Mitigation Options
Develop the Program - Locational
- Redundancy / backup
- Move
- Structural
- Strengthen structures
- Brace equipment / furnishings
- Operational
Acceptable? - Emergency Plan
N - Backup data
- Transfer
- Insurance
Y - Contracts

Implement the Program

Maintain the Program

FIGURE 34.1 Earthquake mitigation program.

specific region. More detailed information can then be obtained from references cited in those chapters,
as well as from expert sources, such as the U.S. Geological Survey or various seismological observatories.
If earthquakes appear to have some potential for occurrence, the next issue is obtaining the authori-
zation for assessing the risk they may pose to the organization. Depending on the organization and its
decision-making, several arguments may be needed to authorize the expenditure involved in a seismic
risk assessment. These arguments typically fall into the following categories:
Ethical this is often the first argument to occur to a proponent of a seismic risk assessment. It
typically takes the form of, it is the organizations responsibility to assess its earthquakes risk, to
be sure it is protecting life and property. This argument may sometimes be sufficient, but often
it is not, and it fails not because decision-makers are unethical, but rather because the argument
is insubstantial in itself. That is, logically, for this argument to prevail, it is then true that it is the
organizations responsibility to assess ALL risks, to be sure. Organizations cannot be risk-free,
and decision-makers are painfully aware of the limited resources they have available to deal with
quite real, significant risks, whether those risks are hurricanes, worker safety, foreign exchange,
competition, or others. Therefore, the argument needs to be accompanied by sufficient facts and
initial analysis to substantiate that some ethical risk exists the proponent must do some
homework.

2003 by CRC Press LLC


0068_C34_fm Page 4 Monday, August 12, 2002 1:20 PM

34-4 Earthquake Engineering Handbook

Good business also known as enlightened self-interest, this is often the most effective argument.
A bit of homework, consisting of assembling some facts on (1) earthquake history of the region;
(2) how other organizations may have been affected in past earthquakes (see Chapter 1, this
volume) or even other disasters, such as hurricanes, floods, or fires; and (3) the approximate
exposure the organization has in the event of a structural collapse, loss of IT data, or other possible
event, can go a very long way toward convincing a CEO that it is worth looking into the matter
a bit further. Thus, the basis for a seismic risk assessment should be that it can be cost-effective,
reduce potential losses greatly should an earthquake occur, and possibly reduce current insurance
and other costs.
Liability In the United States and many other countries today, an ignorance-of-risk defense is
highly questionable, and this should be brought to the attention of decision-makers in a tactful
manner. Decision-makers are responsible for protecting the welfare of their organizations and the
public today, and are expected to understand the extent of this risk and to deal with it in a
responsible manner. Questions such as, Are you prepared? are valid, and not inappropriate
(Figure 34.2). After a disaster occurs, decision-makers are often held responsible for having made
the wrong decision, especially if losses are seen as unacceptably high and all stakeholders were not
involved in the decision process. Steps to understand the risk and share the information with the
affected stakeholders can help to minimize post-event backlash, even if no action to mitigate is
ultimately taken. Once disclosure is made, the stakeholders can either accept the risk or make it
known that the risk must be addressed. In either event, the decision-maker who actively addresses
earthquake risk and involves all stakeholders is better off than one who does not.
Feasible Part of any argument for a seismic risk assessment should be that mitigation is feasible.
Decision-makers may believe they need to greatly mitigate or even totally eliminate risks once
they are discovered, relating this to issues of potential liability. Therefore, some decision-makers
may prefer to adopt an ignorance is bliss approach to risk management, avoid having positive
knowledge of a risk, and believe they have limited potential liability as a result. They believe that
if an earthquake causes a building to collapse, it will be considered an act of God for which they
will have no liability, particularly if no prior positive identification of the risk was available.
Opposing this is that it is often possible to obtain incremental reduction in risk by performing
limited mitigation as part of other programs. For example, if an existing building is going to be
expanded, seismic upgrade of the building can probably be accomplished concurrently, at little
additional cost. Similarly, if a major asbestos reduction program is going to be pursued, it may
be possible at very little additional expenditure to perform concurrent seismic upgrades. Until the
extent of seismic risk is understood and priorities set for mitigating this risk, the opportunities
to embark on such incremental and cost-effective programs cannot be identified.
Making the above arguments is not sufficient in themselves. A decision-maker will also want to know
what the next steps are, if he or she wishes to proceed. We discuss this aspect next.

34.4 Phase 1: Assessing the Problem


Assessing seismic risk, or risk screening, is discussed in some detail in Chapter 2 of this volume. Basically,
the process is shown in Figure 34.3, and consists of the following steps:
Identifying the assets (people, property, functions) at risk
Establishing (i.e., quantifying) the seismic hazard
Developing performance objectives
Performing first a risk screening and then, for selected structures, a more detailed review
Identifying the assets at risk should be relatively straightforward most organizations facilities
department should have values, personnel counts, etc. readily available. More difficult is determining

2003 by CRC Press LLC


0068_C34_fm Page 5 Monday, August 12, 2002 1:20 PM

Developing an Earthquake Mitigation Program 34-5

FIGURE 34.2 The cover and following page from Guide for Decision-Makers, prepared by the California Seismic
Safety Commission, asks, Californias Next Earthquake are you prepared? and states, The public will want to
know what you did to prepare. (Courtesy California Seismic Safety Commission)

the value of business or functional operations in a particular facility, and this may take a team effort
involving operations, the finance department, and perhaps others. Often, this aspect results in some
surprises, where a specific facility is found to be more critical than previously believed, due to its housing
high-value goods or operations. A classic example often encountered by the author is an organizations
data center, in which the equipment may be worth millions, and yet the building housing the data center
has a book value only a fraction of the value of the equipment it houses. In this regard, the data itself
may be priceless (e.g., it would cost tens of millions to replace, and would result in hundreds of millions
in lost revenues if it could not be replaced), and therefore organizations have learned to back up the data
offsite, and its value is less an issue.
Developing performance objectives should normally be straightforward. A first priority is no loss of
life, which normally translates into no significant collapse hazard, and dangerous processes should be
able to safely shut down. Following in priority is normally preservation of value, which usually means
limited property loss, no loss of essential equipment, and restoration of operations onsite, or at a backup
site, within a period of time appropriate for the organization.
These two aspects, identifying assets at risk and performance objectives, can be qualitatively assessed
using a technique developed by Saaty [1980] termed the Analytic Hierarchy Process (AHP). At the core
of the AHP lies a method for converting subjective assessments of relative importance to a set of overall
scores or weights. It is a simple yet useful tool, and one of the more widely applied multi-criteria analysis
methods. The fundamental input to the AHP is the decision-makers answers to a series of questions of

2003 by CRC Press LLC


0068_C34_fm Page 6 Monday, August 12, 2002 1:20 PM

34-6 Earthquake Engineering Handbook

Occupants
Buildings
Identify Assets at Risk Other Structures
Equipment
Infrastructure
Establish
Develop Performance Objective Operations
Seismic
Profits
Hazard
Market Share
Reputation

Buildings/Structures Equipment

Risk Screening

Is it OK Is it OK
Yes per MLEER Yes
Stop per FEMA- Stop
154? 99-0008?

No No

Detailed Review

Is it OK Is it OK
Yes Yes
Stop per FEMA- per Equipment Stop
310? Assessment?

No No

ALTERNATIVES

FIGURE 34.3 Earthquake risk assessment. (Courtesy California Seismic Safety Commission)

the general form, How important is criterion A relative to criterion B? These are termed pairwise
comparisons. Questions of this type may be used to establish, within AHP, both weights for criteria and
performance scores for options on the different criteria. In AHP, a very simple series of weights, such as:
Much more = 5
About the same = 3
Much less = 1
are applied in a matrix, such that off-diagonal terms are the complement of one another (i.e., if row 1
column 2 is much more = 5, then row 2 column 1 is much less = 1). A simple example suffices.
Suppose a company has the following facilities: headquarters, factory 1, factory 2, warehouse, and R&D
laboratory, and wishes to determine the relative value of these facilities on the basis of the number of
personnel, the value of building and contents, and the revenues that can be assigned to each facility. This
is a multi-criteria analysis (the criteria are lives, property, and revenues) problem. The first task is to
determine the relative importance of the criteria. This is done as shown in Table 34.1. In this table, life
is assigned a relative value much more than property, that is, a value of 5 (and, therefore, property is
much less, 1). The relative weights of the three criteria are thus:
Life = 10
Property = 4
Revenue = 4
The same technique is then applied to each of the facilities, for the facilitys respective values of life,
property, and revenue. For example, as shown in Table 34.2, headquarters contains 100 personnel, while
factory 1 contains 600, so that headquarters personnel are much less than factory 1 personnel, and

2003 by CRC Press LLC


0068_C34_fm Page 7 Monday, August 12, 2002 1:20 PM

Developing an Earthquake Mitigation Program 34-7

TABLE 34.1 AHP Results for Relative Weighting of Three Criteria

Criteria

TY

E
PER

ENU
PRO
LIFE

REV
SUM

0
1 LIFE 5 5 10
2 PROPERTY 1 3 4
3 REVENUE 1 3 4
4 0
5 0
6 0
7 0

much less than factory 2 personnel, much more than warehouse personnel, and about the same
as the R&D laboratory personnel (in numbers of personnel). The sum of the headquarters row is thus
10, which is multiplied by the weight assigned to life (which was 10), so that the life-weighted product
for headquarters is 100, for factory 1 is 180, and so on. This process is continued, and the final result is
shown in Table 34.3, where factory 2 is seen to be the most important facility (highest criteria-weighted
sum) and so on, to the least important facility (headquarters1).
Although it is somewhat arbitrary, the AHP is a useful tool for obtaining a relative ranking of facilities
during the risk assessment process.
Quantifying the hazard and developing seismic vulnerabilities are technical aspects that require the
expertise of specialist earth scientists, structural engineers, and related experts. Most organizations
utilize specialist consultants for this aspect who employ methods detailed in other chapters of this
volume. The methods can be highly quantified, although at a screening level of analysis such methods
may not be justified. It may simply suffice for facilities to be identified as being on good or poor
soils, from a seismic perspective, and the structures as being similarly good or poor. In the latter
case, a structural engineers review in identifying a continuous lateral-force-resisting system (LFRS) is
a powerful discriminant.
The result of an earthquake risk assessment task is a statement of the potential damage and losses that
can result under current conditions. An example is shown in Figure 34.4, which shows the findings for
a hypothetical arena that was judged to be a high collapse hazard. The result of the screening is typically
qualitative.

34.5 Phase 2: Developing the Program


Having performed a risk screening, facilities may be usefully grouped into several categories, such as:
I. Probable high risk
II. Possible high risk
III. Probable low risk
with the benefit that the category III probable low risk facilities can be dropped from further consider-
ation. The category I and category II facilities should then be subjected to a more detailed analysis, the
product of which is not only a confirmation of their risk, but also the design of strengthening or

1 Authors note: a result that perhaps many employees already suspected.

2003 by CRC Press LLC


0068_C34_fm Page 8 Monday, August 12, 2002 1:20 PM

34-8 Earthquake Engineering Handbook

TABLE 34.2 AHP Relative Weights for Facilities, for Two Criteria

Name of Facility Criteria

e
hous
1

2
ry

ry

Cr tt 1
Facto

Facto

Ware

R&D
HQ
LIFE SUM

0
1 HQ 100 1 1 5 3 10 100
2 Factory 1 600 5 3 5 5 18 180
3 Factory 2 900 5 3 5 5 18 180
4 Warehouse 25 1 1 1 3 6 60
5 R&D 50 3 1 1 3 8 80
6 0 0
7 0 0

ouse
y1

y2

h
r

Cr tt 2
Facto

Facto

Ware

R&D
HQ

PROPERTY SUM

0
1 HQ 100 1 1 3 1 6 24
2 Factory 1 600 5 1 5 3 14 56
3 Factory 2 2000 5 5 5 5 20 80
4 Warehouse 200 3 1 1 3 8 32
5 R&D 400 5 3 1 3 12 48
6 0 0 0
7 0 0 0

development of other mitigation measures, including the estimation of costs for the mitigation measures.
Since this is not a final design, the estimate of costs for structural strengthening or other mitigation
measures is necessarily approximate, and is often termed a rough order of magnitude (ROM) estimate
of costs. An example of a Phase 2 more detailed analysis is shown in Figure 34.5, which shows results of
a structural analysis of a San Francisco Fire Department fire station performed under the authors
direction, including a schematic of the structural retrofit scheme and a ROM cost estimate. All facilities
falling into categories I and II should be the subject of similar analyses, for structural retrofitting or
alternative mitigation measures, as appropriate.
Based on analyses such as indicated in Figure 34.5, all category I and category II facilities can be ranked
according to their risk, mitigation costs, or other criteria. Table 34.4 shows an example of a hypothetical
seismic risk assessment performed for a municipality. Strengthening cost based on a Phase 2 structural
analysis is indicated for each facility. Additionally, the facilities are ranked by their benefit-cost ratio
(explained below), and the cumulative costs are indicated. The cumulative cost column indicates in what
order a limited budget is best spent. In this example, if the organization (i.e., the city) has only $20 million,
then it is best spent not on the Fine Art Museum, but on the North Police Station, Fire Station 2, and
the Aquarium.
This ranking is based on a benefit-cost ratio, developed on the basis of a set of rules created for
assessing the benefits resulting from assured seismic functionality of each facility. Benefit is the loss

2003 by CRC Press LLC


0068_C34_fm Page 9 Monday, August 12, 2002 1:20 PM

Developing an Earthquake Mitigation Program 34-9

TABLE 34.3 Criteria-Weighted Sums and Final Ranking for Each Facility

Cr tt 1

Cr tt 2

Cr tt 3

Cr tt 4

Cr tt 5

Cr tt 6

Cr tt 7
Name of Facility

TY

E
PER

ENU
PRO
LIFE

REV
SUM RANK

0
1 HQ 100 24 16 140 5
2 Factory 1 80 56 56 292 2
3 Factory 2 180 80 80 340 1
4 Warehouse 60 32 56 148 4
5 R&D 80 48 32 160 3
6 0 0 0 0 0
7 0 0 0 0 0

avoided by mitigation, derived by investing the cost of mitigation. If a large loss can be avoided via a
small investment, the benefit-cost ratio is high, and the investment is a good investment. If the required
investment is large and only a small loss is avoided, then the mitigation action is not cost-beneficial
that is, it is not worth it. These rules can be as simple as assessing the cost of loss of functionality of the
facility as the rent that would have to be paid to provide the same space, if that facility is lost. In the
case of a fire station, the benefit should be this rent, plus perhaps some allowance for the fire department
not being able to function in the earthquake disaster that is, some allowance for losses due to fires
which the fire department cannot respond to (and also, perhaps, some allowance for lost lives, although
the latter are difficult to quantify). In the case of an art museum, some allowance might also be made
for damage to the high-value contents the works of art. While some works of art may be priceless
(even though they are bought and sold), a good proxy for the allowance would be the insurance premium
for the contents.
Thus, for each facility, the benefit is determined on a consistent basis, and that benefit divided by the
cost of mitigation. The facilities are then ranked by this ratio, as shown in Table 34.4. Such a ranking is
meant as a guide for decision-makers and should not be rigidly adhered to common sense may indicate
that a particular facility, although ranked low, may actually be more important than indicated. The true
meaning of this overriding of the ranking process is of course that the criteria employed in the process
did not truly reflect the actual, usually intuitive, criteria of the decision-maker.
The final decision as to what facilities to mitigate will depend on available budget or other resources
and is, ultimately, the final expression of the organizations acceptable risk. That is, the organization
must balance what it wishes against what it can afford. The final program, arrived at iteratively, expresses
what it can afford, and the allocation of resources is the indication of the risks the organization is willing
to incur. This is an important point, in that it is emphasized that the organizations acceptable risk cannot
be decided a priori it is arrived at in a give-and-take, once the potential losses, and the costs of reducing
those losses to various degrees, are known. Much time and effort are wasted in organizations at the
beginning of a risk reduction program, trying to decide what is their level of acceptable risk. Leave this
decision until the facts are known. Trying to determine acceptable risk early in the process can adversely
affect, even prematurely terminate, an earthquake risk reduction program.

2003 by CRC Press LLC


0068_C34_fm Page 10 Monday, August 12, 2002 1:20 PM

34-10 Earthquake Engineering Handbook

FIGURE 34.4 Example result of a seismic risk assessment.

2003 by CRC Press LLC


0068_C34_fm Page 11 Monday, August 12, 2002 1:20 PM

Developing an Earthquake Mitigation Program 34-11

FIGURE 34.5 Example Phase 2 seismic risk analysis, with rough order of magnitude (ROM) cost estimate. (Courtesy
EQE International)

2003 by CRC Press LLC


0068_C34_fm Page 12 Monday, August 12, 2002 1:20 PM

34-12 Earthquake Engineering Handbook

TABLE 34.4 Example Result, Seismic Risk Assessment

Facility Strengthening Cost Cumulative Cost Highest

North Police Station $82,600 $82,600


Fire Station 2 $115,500 $198,100
Aquarium $6,047,300 $6,245,400
Natural History Museum $11,663,300 $17,908,700
Thompson Fine Art Museum $17,725,000 $35,633,700
Fire Station 17 $887,100 $36,520,800
Justice Center $6,960,300 $43,481,100 Benefit/Cost
Municipal Building $10,497,400 $53,978,500
Central library $4,178,800 $58,157,300
South Police Station $1,154,500 $59,311,800
Fire Department Headquarters $2,149,900 $61,461,700
Fire Station 29 $2,590,400 $64,052,100
Municipal Building Annex $4,239,600 $68,291,700
Fire Station 24 $1,204,900 $69,496,600
Downtown parking garage $1,018,700 $70,515,300
Jefferson Community Center $5,729,800 $76,245,100
Bayside library $1,428,400 $77,673,500
Lowest
Lincoln Community Center $6,276,200 $83,949,700

34.6 Phase 3: Implementing the Program


Implementing the program consists of several key steps, including:
Retaining seismic retrofit design professionals
Funding the program
Performing final design
Coordinating design and construction with other parts of the organization
We discuss each of the aspects in turn.

34.6.1 Retaining Seismic Retrofit Design Professionals


Retaining engineers experienced in seismic retrofit is an important aspect of the retrofit process. One of
the most important attributes to look for is experience and satisfactory performance on previous projects.
As outlined above, the seismic retrofit professional will typically go about the assessment and mitigation
in a three-phased approach, consisting of:
Initial investigation and screening
Detailed investigation and conceptual retrofit design and costing of alternatives
Final design and production of design documents and a bid package
Step two is perhaps the most crucial from the decision-making viewpoint, since this is where the alter-
natives are evaluated for cost and effectiveness.
In retaining an engineer, a clear and detailed scope of services should form the basis for the relationship.
The scope of services must of course be specific to the particular situation, but may consist of the following
tasks (services for all three phases are listed below).
34.6.1.1 Phase I: Initial Investigation and Screening
1. Review all available construction documents for the building, including structural and architectural
drawings and specifications for the original construction, as well as similar documents for any
significant modifications or upgrades. The purpose of this review shall be to determine the basic

2003 by CRC Press LLC


0068_C34_fm Page 13 Monday, August 12, 2002 1:20 PM

Developing an Earthquake Mitigation Program 34-13

structural load-carrying systems and to identify seismic performance issues related to configura-
tion and structural detailing.
2. Review available geotechnical reports for the site to determine a site class for use in developing
seismic hazards and to identify conditions that could lead to ground failure or other site instabil-
ities. Where site-specific soils data are not available, reference should be made to available gener-
alized geotechnical data, such as found on regional maps produced by the U.S. Geologic Survey
and the California Division of Mines and Geology. Reference should also be made to the seismic
safety element of local general plans.
3. Perform a seismic hazard for analysis for the site to identify the location of the site relative to
significant faults, and to estimate the probable intensity of ground acceleration as a function of
return period (or probability of exceedance).
4. Conduct a visual survey of the building to document the structures condition and to confirm
that available construction documents are representative of existing conditions. To the extent that
construction documents are unavailable, perform field investigation to develop sufficient infor-
mation to identify the vertical and lateral structural load-carrying systems, and to quantify their
strengths.
5. Perform a preliminary structural evaluation to quantify the probable performance of the building
structure to resist the effects of ground shaking having a 10% probability of exceedance in 50
years. (Note that either more or less probable levels of ground shaking may be specified, based on
the importance of individual facilities. For facilities located within a few miles of major active
faults, it may be more appropriate to specify that the evaluation be performed for a median estimate
of the ground shaking resulting from a characteristic earthquake on that fault.) The evaluation
should, as a minimum, conform to the requirements of FEMA-310 [Federal Emergency Manage-
ment Agency, 1998] for a tier 1 evaluation. Alternative evaluations that quantify the adequacy of
the seismic-force-resisting system considering strength, ductility, and configuration issues may be
used.
6. Develop an inventory of critical nonstructural components, including building utility equipment
(power supply, HVAC systems), operating equipment, ceilings, building fascia panels, elevators,
and fire protection systems. Identify the adequacy of installation of these nonstructural compo-
nents to resist damage.
7. Develop a preliminary opinion as to the probable performance of the facilities, in the event of the
designated earthquake ground motion (see item 5 above) using the performance levels contained
in FEMA-273 and FEMA-310 [Federal Emergency Management Agency, 1997, 1998].
8. Prepare a written report documenting the scope of study, the findings, and recommendations,
with written documentation of the evaluation process (FEMA-310 checklists, calculations, etc.)
included as appendices. If preliminary study indicates significant potential for earthquake-induced
ground failure and sufficient site-specific soils data are not available to conclusively assess this,
the report should include a recommendation for site-specific geotechnical investigation. If the
existing construction of the structure is not sufficiently well defined to permit quantification of
its structural characteristics, include recommendations for detailed field investigations to confirm
the construction.
34.6.1.2 Phase II: Detailed Investigation and Conceptual Retrofit Design
1. Review the phase I evaluation report and available construction documents for the facility to develop
an overall understanding of the buildings construction and its probable seismic performance.
2. Conduct a visual survey of the building to observe the building condition and note obvious
deviations from the available documentation. Observe potential opportunities for introduction
of seismic upgrade elements. Note sensitive areas of the building, such as historic spaces, traffic
corridors, etc. that may not be impacted by seismic upgrade measures.

2003 by CRC Press LLC


0068_C34_fm Page 14 Monday, August 12, 2002 1:20 PM

34-14 Earthquake Engineering Handbook

3. Meet with the facility manager to discuss alternative performance criteria and to select an appro-
priate criterion, or set of criteria. Also discuss restrictions on placement of retrofit elements, relative
to building appearance and functionality concerns.
4. If recommended in the phase I evaluation, perform field investigation of the building to confirm
the details of its construction and material strengths.
5. If recommended in the phase I evaluation, obtain site-specific geotechnical data to evaluate
potential ground failure and associated mitigation measures.
6. Perform structural engineering calculations to quantify seismic deficiencies in the building relative
to the selected performance levels. As a minimum, the criteria of FEMA-310 for a tier 2 evaluation
should be performed. Alternatively, the performance analysis procedures contained in the Cali-
fornia Building Code, Division IIIR, in FEMA-273, or in the California Seismic Safety Commis-
sions SSC-9601 may be used.
7. Review alternative potential methods for seismic upgrade for each specified performance criterion,
to a level sufficient to confirm feasibility and to select a recommended approach. Meet with the
facility manager to review the alternatives and to agree on the appropriateness of the recommended
approach.
8. Develop conceptual-level upgrade designs for each specified performance criteria. Supporting
calculations shall be performed to a sufficient level of detail to confirm that the overall size and
scope of the recommendations are appropriate. The level of detail should be sufficient to permit
an ROM cost estimate to be performed. Consideration should be given to collateral upgrades
triggered by the seismic work, including disabled access, fire/life safety, and other code upgrades.
9. Prepare conceptual-level sketches showing recommended upgrades for nonstructural components.
10. Prepare preliminary cost estimates for the recommended seismic upgrade work, for each perfor-
mance criterion, together with required collateral upgrades.
11. Prepare a report indicating the scope of the study, the findings with regard to building deficiency
and performance, and the recommendations for alternative levels of upgrade, as well as any
recommendations for additional investigation to be performed as part of final design. Include
schematic drawings documenting the upgrade recommendations and cost estimating worksheets
in an appendix.
34.6.1.3 Phase III: Construction Documents and Construction Support
1. Assemble a complete design team, including project management, structural engineering, archi-
tecture, mechanical and electrical engineering, and cost estimating, as required to support the
development of construction documents.
2. Review all available documentation for the building as well as previous evaluation reports and
supporting calculations in order to develop an understanding of the building deficiencies and
recommended upgrade approach.
3. Meet with the building official as necessary to confirm the design criteria and proposed approach,
as well as to confirm the extent of required collateral upgrades.
4. Develop construction documents, including drawings and specifications, together with supporting
calculations, to implement the recommended structural upgrades, together with all required
collateral upgrades. Submit copies of construction documents to client for review, at the 40% and
90% stages of completion. Final construction documents shall be suitable for obtaining building
permits, competitive construction bids, and for executing the work.
5. Prepare an estimate of probable construction cost at each stage of document submittal and for
the final construction documents.
6. Provide support to client in the development of bid packages for construction contracts.
7. Respond to comments from plan checkers and revise construction documents as necessary to
obtain approval.
8. Respond to bidder requests for clarification.

2003 by CRC Press LLC


0068_C34_fm Page 15 Monday, August 12, 2002 1:20 PM

Developing an Earthquake Mitigation Program 34-15

9. Provide support to client in evaluation of construction contract bids for completeness and con-
sistency with the requirements of the construction documents.
10. Attend periodic meetings at the construction site, during the construction period, to coordinate
construction progress.
11. Conduct periodic site visits to confirm that the work is generally being conducted in accordance
with the design requirements.
12. Review contractor submittals and shop drawings.
13. Respond to contractor Requests for Information and assist client in negotiation of contractor
change order requests.
14. Review special inspection and test reports.
15. Perform a walkthrough of the project site at 95% completion to develop a punchlist of items not
completed by contractor.

34.6.2 Funding the Program


Like all programs, earthquake risk management requires the investment of funds. The initial phases of
the program, in which the risk is assessed and mitigation options explored, typically entails relatively
modest cost. By spreading these tasks out over a period of one or two years, most organizations will be
able to accommodate these costs within their normal operating budgets. However, major programs of
capital improvement will typically require extraordinary sources of funding. The following sources should
generally be considered when planning programs of seismic mitigation:
General operating and maintenance funds. Not all seismic upgrade projects are particularly costly
and some seismic upgrades can be done at nominal cost. For example, most equipment items can
be anchored or braced for seismic resistance at a per-item cost of a few hundred dollars or less.
Many organizations will be able to cover significant seismic upgrade activities out of their general
operating and maintenance funds.
Bond issues. If an organization understands its existing earthquake risk and is convinced that this
is unacceptable, it may be willing to support additional bonded indebtedness as a means of raising
the necessary funds. This is a particularly appropriate mechanism for the public sector. For
example, the City of San Francisco obtained permission from its electorate to raise more than
$100 million for earthquake safety retrofits of fire stations and other municipal buildings. From
a strategic perspective, such bond measures are most successful in the period immediately follow-
ing a major earthquake somewhere in the world, when the publics attention is drawn to the issue
of earthquake risk.
Special use fees. In some cases, it may be possible to support the cost of seismic upgrade through
the establishment of special use fees. As an example, the State of California raised tolls on bridges
crossing San Francisco Bay as a means of funding seismic upgrades of these structures.
Hazard mitigation grants. Occasionally, special grants become available from the federal and/or
state government for partial funding of seismic mitigation work. These grants may be offered as
(1) seed money for demonstration projects, to encourage and attract other sources of funding; or
(2) in order to reduce risk of damage in future earthquakes and to help communities become
more self-sufficient. These grants are usually available only for public or nonprofit organizations
and often are restricted to, or give preference to, certain types of projects. For example, using
funding obtained under the Proposition 122 bond program, the State of California made limited
mitigation funding available to cities, counties, and similar agencies. Generally, projects to
strengthen emergency response facilities, such as fire stations, police stations, and city halls,
received priority over other types of projects. When mitigation grant programs are available,
communities must typically apply for funding in competition with others. In addition, it is usually
necessary for the enterprise to provide some co-funding of the project, often in the amount of 10
to 20% of total project costs.

2003 by CRC Press LLC


0068_C34_fm Page 16 Monday, August 12, 2002 1:20 PM

34-16 Earthquake Engineering Handbook

Tax preferences and credits. Certain tax credit and tax preference incentives are available for the
rehabilitation of facilities. Special facilities, such as qualified historic landmarks, are prime candi-
dates for other tax incentives. These incentives are typically applicable only to private, for-profit
enterprises. In order to qualify for these incentives, it is necessary to comply with certain historic
preservation standards and to be subjected to a review and approval process for the design.

34.6.3 Coordinating with Other Parts of the Organization


It is very important to include earthquake risk mitigation measures with other facets of an organizations
asset management program. Key issues related to this are the following:
Often, by performing seismic upgrade work concurrently with other planned projects, it is possible
to reduce the cost and disruption of the upgrade work. For example, a common requirement of
seismic upgrade programs for low-rise buildings with wood roof structures is to increase the
nailing of the plywood roof sheathing. This can only be done upon removal of the roofing. Clearly,
if such upgrade work is performed concurrently with routine replacement of the roofing system,
it will be far more economical.
If an existing facility is assessed as incapable of providing adequate seismic performance for its
current use, consider changing its mission to be more compatible with its seismic performance
category. For example, if a critical care wing of a hospital is judged incapable of immediate post-
earthquake occupancy, and there is simultaneous need to develop new outpatient care at the
facility, the best choice may be to build new critical care space and convert the existing space to
use for outpatient care.
Consideration should be given to the length of time a facility is expected to remain in service. If
a facility is scheduled for replacement or retirement in the near future, it makes little sense to
invest in upgrade of the facility.
Construction for seismic improvements to a facility will often trigger mandatory requirements to
perform other types of upgrades, such as disabled access improvements, hazardous material
abatement, and fire/life safety improvements. These collateral upgrade requirements can have
substantial impact on the implementation cost and, in some cases, the cost of collateral upgrades
is higher than the seismic construction cost. It is important to account for these impacts when
evaluating the cost of seismic mitigation.
Earthquake risk cannot be managed effectively in a vacuum. The decision-maker and the risk manager
must involve the facilities or asset manager in planning and implementing the mitigation program in
order to assure that collateral issues are addressed and all capital improvements are coordinated. It is
also important to ask professional consultants, who may be retained to assist in quantifying risk and
suggesting mitigation alternatives, to be mindful of these needs.

34.6.4 Perform Seismic Retrofit


Performing the seismic retrofit consists of the following steps:
1. Retaining a team of design professionals to develop construction documents, using the phased
approach described above. Result: a series of specifications for performing the desired upgrade
work and reliable estimates of probable construction cost.
2. Identifying funding sources for performing the work. Available funding sources were discussed in
the previous section, and include:
General operating and reserve funds
Grant programs operated by HUD (Housing and Urban Development), FEMA, and other
agencies
General obligation bonds

2003 by CRC Press LLC


0068_C34_fm Page 17 Monday, August 12, 2002 1:20 PM

Developing an Earthquake Mitigation Program 34-17

Result: sufficient funds to execute the required construction work.


3. Hiring retrofit contractors. This is an important aspect of the retrofit process. As with hiring a
contractor for any other purpose, one of the most important attributes to look for is experience
and satisfactory previous performance. Generally, public agencies will have to use a competitive
bid process for the selection of a contractor. It is recommended that a process of bidder prequal-
ification be performed, prior to requesting construction bids, to assure that bidders have adequate
resources and experience. Result: on-board contractor, ready to go.
4. Scheduling the work so as to minimize disruption, in coordination with tenants, managers, or
operators, is another important aspect. Note that construction scheduling can have a significant
impact on construction costs. Therefore, any scheduling requirements or constraints that will be
imposed on the contractor, such as limiting work to certain periods of time or requiring that work
in certain sections of a facility be staged, should be clearly included in the general conditions
section of the specifications used to solicit contractor bids. The selected contractor should be
requested to submit a detailed construction schedule, incorporating the client-specified milestones
and indicating the specific timing of work by different trades. Result: schedule for construction.
5. Construction. Result: retrofitted facilities.
6. Maintaining the retrofitted facility. Retain as-builts, specifications, and engineers maintenance
instructions in the retrofitted building or other archive. Use a plaque or other notice to ensure
that these materials are not lost or overlooked. Result: complete record of retrofit.

34.6.5 Dealing with Residual Risk


After the seismic upgrade work has been completed, the seismic risk associated with a facility will be
greatly reduced from original levels. However, some residual risk will remain. Prudent risk management
suggests that effective steps be taken to further minimize the residual risk, through the steps outlined
below.
34.6.5.1 Emergency Plan
Even relatively minor damage to a facility can result in extended interruption of service and loss of use,
if no-one knows what to do about assessing its condition, securing potentially hazardous contents and
utilities, and conducting repairs so that service can be restored. Emergency response plans that clearly
designate the persons responsible for each of these actions, and how they can be contacted in the event
of an emergency, can significantly reduce the amount of confusion and lost time when an earthquake
actually occurs.
In addition to basic information on who is responsible for specific actions when an emergency occurs,
emergency response plans should include information on the critical equipment and systems within the
building, the structural system, expected types and locations of damage, and checklists for specific post-
earthquake actions to be taken. For critical facilities, the emergency operations plan can also include
provision for alternative work spaces, in the event that damage is so severe that reoccupancy of the facility
within the short term is not feasible.
34.6.5.2 Risk Transfer
Earthquake insurance can be an effective method of guarding against the direct financial losses associated
with an earthquake and is commonly used in the private sector for this purpose. Earthquake insurance
is very effective in reimbursing a property owner for the direct costs related to repair of damage. It is
less effective with regard to reimbursement for business interruption costs, as often the quantification
of these costs is difficult and therefore subject to dispute. It is also important to note that most earthquake
insurance policies include significant deductibles and will not cover upgrades to the facility that may be
triggered by the building official as part of damage repair work. The cost of earthquake insurance is
highly variable and depends as much on the global financial markets and health of the insurance industry
as it does on the actual risk associated with a facility. In some years insurance can be obtained at a fraction

2003 by CRC Press LLC


0068_C34_fm Page 18 Friday, August 16, 2002 4:25 PM

34-18 Earthquake Engineering Handbook

of its real value, while in other years, it may cost several times its actual value or may not be available at
all. This is why it is prudent not to rely on earthquake insurance as the sole means of risk management.
Another aspect of risk transfer involves an organizations suppliers and customers. To the extent that
provisions for special circumstances in the event of an earthquake can be written into contracts, then
the earthquake risk has been transferred. For example, if obligations to purchase supplies or deliver
product can be relaxed in the event of an earthquake, then additional time is gained by the organization
during its crisis period. Keeping this aspect in mind during contract negotiations, as an ongoing aspect,
can pay handsome dividends in the event of an earthquake, at little or no cost.
34.6.5.3 Physical Redundancy and Geographic Dispersion
One of the most effective techniques for mitigation of earthquake risk is to disperse operations into
independent locations at different sites. Although the effects of earthquakes can be widely dispersed over
a region of many square miles, the most extreme earthquake effects are typically limited to a small fraction
of the affected region. If all of the physical facilities associated with an operation are concentrated at a
single site or location, there may be significant potential for damage to this physical facility to completely
interrupt operations for an extended period of time. However, if the physical facilities are dispersed to
multiple locations, it becomes much less likely that all of these facilities would be damaged to an extent
that would limit operations at all of the locations. Thus, dispersion can become an effective tool to
maintain at least partial operational capability following a major earthquake. To the extent that the
dispersed facilities provide redundant capacity, it may be possible to provide full operational capability
if some of the facilities become damaged.
34.6.5.4 Data Backup
Redundant storage of critical records and data can be a highly effective risk mitigation technique.
Following the 1989 Loma Prieta earthquake, the City of Oaklands Building Department found itself
displaced from City Hall, which had been severely damaged by the earthquake. The building department
stored microfilm copies of the original construction drawings for private buildings in archives maintained
within City Hall. The red-tagging of that building effectively made these records unavailable for many
months following the earthquake, hampering the efforts of the community to assess and repair damage
sustained by other buildings. Had a redundant set of microfilm records been maintained in another, off-
site, location, it is highly unlikely that access to both sets of data would have been lost.
Public agencies and private businesses can maintain their own off-site records storage or, alternatively,
they can rely on any of a number of providers of this service. This may be particularly important for
electronic records that are maintained on-line. There are a number of private data centers that provide
stand-by electronic records storage, as well as data processing capability.
34.6.5.5 Retain Structural Engineers and Contractors
Following the 1989 Loma Prieta earthquake, the City of San Franciscos Building Inspection Department
found itself overwhelmed by the demand to perform post-earthquake safety inspections of public and
private buildings in the city. Even with the assistance of many volunteer inspectors, it took a period of
months before all buildings were evaluated and their conditions determined. During this period of time,
building owners and tenants were often at a loss to know whether it was safe to reoccupy damaged
buildings, leading to extensive economic losses.
In order to avoid these problems in future earthquakes, the City of San Francisco later established the
voluntary Business Occupancy Resumption Earthquake Inspection Program (BOREIP). Under the
BOREIP, building owners can retain qualified structural engineers to perform post-earthquake inspec-
tions of their buildings in the event of a future earthquake. These engineers must develop a
post-earthquake inspection plan for the building and be certified by the city as deputy building inspectors
for the specific building. Under the program BOREIP inspectors are obligated to perform post-earthquake
inspections within 36 hours of the occurrence of an earthquake disaster. They then have the authority
to post buildings, as inspected, following an earthquake, on behalf of the city.

2003 by CRC Press LLC


0068_C34_fm Page 19 Monday, August 12, 2002 1:20 PM

Developing an Earthquake Mitigation Program 34-19

Building departments can develop similar programs to speed the post-earthquake recovery of their
communities. In addition, even in the absence of such programs, individual public and private building
owners and tenants can retain structural engineers to perform rapid post-earthquake assessments of
buildings, to advise as to whether the buildings are safe for occupancy and to develop repairs in the event
these are required. While these engineers would not have the power to officially post a building, they
can provide assurance as to the condition of its structure and appropriate recovery actions. It is often
beneficial to develop retainer agreements with engineers before the earthquake actually occurs. In the
days and weeks immediately following a major earthquake, structural engineers are extremely busy and
are unlikely to be available on short notice unless advance arrangements have been made.
It may also be beneficial to develop similar retainer agreements with general contractors, so that there
is assurance that in the event repairs are needed, construction capability to effect these repairs will be
available.

34.7 Maintaining the Program


In many ways, the actual earthquake mitigation program has been performed when the following actions
have been carried through to completion:
Facilities have been strengthened, or otherwise dealt with such that their risk is acceptable.
Emergency response and business continuity plans have been developed and exercised.
Residual risk has been insured, transferred, or accepted.
However, organizations are dynamic and facilities, operations, and personnel are constantly changing.
Thus, documentation of the steps taken, including the process and criteria, is an important step to
complete. As new facilities or operations are developed, the same or enhanced criteria can be applied to
them, thus retaining the overall balance of the earthquake mitigation program. As new personnel join
the organization, they can review the earthquake mitigation program documentation and maintain the
overall goals.
Finally, when (not if) the earthquake occurs, there are a number of important steps to be quickly
performed, including:
1. Assessing the extent of damage. The first thing that should be done following an earthquake is to
assess the extent of damage that has occurred. It is necessary to assess whether physical facilities
that are relied upon for operations are functional and safe, as well as to estimate the amount of
time they may be out of service. It is impossible to implement an effective response and recovery
program until these data are known. For many public agencies, the responsibility for post-earth-
quake damage assessment may extend beyond the need to assess the performance of the physical
facilities that the agency relies upon for operation, to include an assessment of the extent of damage
and loss that has occurred community-wide. For example, if housing in a community is severely
impacted, public agencies will be expected to provide for the temporary shelter and care of
displaced families. If a number of building collapses have occurred, public agencies will be expected
to assist in locating and extracting victims. In order to effectively respond to such needs, it is
necessary to be able to rapidly assess the likely extent of damage and loss. These assessments can
be made by performing rapid post-earthquake reconnaissance or, alternatively, by implementing
one of several disaster simulation software packages that permit rapid estimation of losses. Regard-
less of the method an agency or business elects to pursue, a current emergency response plan and
previously negotiated agreements with necessary engineering consultants and contractors can
speed this phase of the recovery effort.
2. Implementing emergency operations procedures. As soon as an assessment of damage is made, and
the extent of impairment of ability to provide service and the need for these services is ascertained,
recovery operations should commence. In the period immediately following the earthquake,
individual public agencies and private businesses will have to rely on their own resources. An

2003 by CRC Press LLC


0068_C34_fm Page 20 Monday, August 12, 2002 1:20 PM

34-20 Earthquake Engineering Handbook

effective emergency response plan can help to smooth the difficult immediate post-event recovery
period. Within days to weeks, outside assistance will begin to become available from such sources
as FEMA, the State of California Office of Emergency Services, the American Red Cross, and other
volunteer agencies. In extreme emergencies, military assistance may also be made available.
3. Restoring normal operations. Over a period of days to weeks and, in the worst disasters, perhaps a
period of years, normal operations will be restored. The length of time necessary for restoration
of normal operations will be directly dependent on the severity of the event, as well as the extent
to which risks were identified and mitigated, and emergency response plans developed prior to
the event. It many cases, what is deemed to be normal operations after the earthquake is not
the same condition that existed before the event. Earthquakes can have far-reaching economic and
social impacts that can completely change the character of a community and the long-term
profitability of individual businesses. For this reason, it is particularly important that public leaders
view earthquake risk reduction not only as their responsibility with regard to protection of public
facilities, but a responsibility that the entire community must share. One of the major benefits of
proactive risk mitigation on the part of a public agency is that it sets a leadership example for the
community at large.
4. Assessing the lessons learned. An important but often overlooked concluding step in the process is
a carefully conducted review of the loss and recovery experience. No matter how well prepared a
community or business is for an emergency, it will typically find that unanticipated problems
developed and that preparation could have been better. Although severe earthquakes are rare
events, it is possible for some communities in California, Japan, or other high seismicity regions
to experience major damaging events several times during a typical lifetime. The San Fernando
Valley, for example, experienced large-magnitude events in both 1971 and 1994, located within a
few miles of each other. A careful assessment of what went wrong and what went right in the
disaster can allow for better preparation for the next event, as well as serve as valuable learning
tools for other communities that have not yet been affected by earthquake disaster.

Defining Terms
Benefit The loss avoided by mitigation.
Benefit-cost ratio Ratio of avoided losses to cost required to avoid those losses. Both amounts should
be computed on the same basis. For example, if the mitigation cost is the current cost of
retrofitting, then the benefit should be computed in present value dollars.
Earthquake mitigation Actions taken to reduce the effects or unwanted consequences of earthquakes,
such as human casualties, structural damage, or business interruption. Actions can be taken
prior to an earthquake (e.g., strengthening a building) or after the earthquake (e.g., activating
a business continuity plan).
Exposure What is at risk that is the total value of assets that could conceivably be lost due to a
hazard such as earthquake. If 100 workers are employed in a company in or near one location,
that companys exposure at that location is 100 employees.
Lateral-force-resisting system (LFRS) The structural system in a building or structure that resists
lateral forces, arising, for example, from an earthquake. In order to resist an earthquake, a
structure must have a LFRS continuous to the foundation. Surprisingly, many pre-code struc-
tures may not have a demonstrable LFRS, and therefore are collapse hazards.
Risk management An integral activity of an organization, normally centralized in a risk management
department headed by the risk manager and associated with the chief financial function. Ideally,
risk managers monitor and manage all sources of risk to the organization aside from those
associated with the organizations central mission. For example, in a manufacturing company,
the risk manager will deal with property, life, and health risk, but not market or foreign exchange
risks or worker safety. In dealing with property risk, the risk manager will normally purchase

2003 by CRC Press LLC


0068_C34_fm Page 21 Monday, August 12, 2002 1:20 PM

Developing an Earthquake Mitigation Program 34-21

property insurance, but will also examine alternatives to insurance, such as strengthening a
building for earthquake so as to reduce the need for earthquake insurance.
Rough order of magnitude (ROM) estimate of costs ROM estimates are made at an early stage in
the design or development of a project. By ROM is not meant, in the mathematical sense,
variations on the order of powers of 10, but rather within a factor of 2. Therefore, if the ROM
cost estimate for strengthening a building is $1 million, it is anticipated that the final cost will
not be less than $500,000 and not more than $2 million. ROM estimates are refined in later
stages of the design or development process, such that final cost estimates are usually 20%
or less.

References
Federal Emergency Management Agency. 1997. NEHRP Guidelines for the Seismic Rehabilitation of
Buildings, FEMA 273, prepared by the Building Seismic Safety Council for the Federal Emergency
Management Agency, Washington, D.C.
Federal Emergency Management Agency. 1998. Handbook for the Seismic Evaluation of Buildings: A
Prestandard, FEMA 310, prepared by the American Society of Civil Engineers for the Federal
Emergency Management Agency, Washington, D.C.
Saaty, T. 1980. The Analytical Hierarchy Process, John Wiley & Sons, New York.

Further Reading
Earthquake Risk Management: A Toolkit for Decision-Makers, prepared by the California Seismic Safety
Commission and available via their Web site (www.seismic.ca.gov), is a useful compendium of methods
and tools for developing and implementing an earthquake mitigation program. The author was involved
in the development of the Toolkit and drew on it for this chapter, but it contains much additional material
and is highly recommended. Also recommended are two accompanying publications: A Guide for Deci-
sion-Makers and Earthquake Risk Management: Mitigation Success Stories, both also available via the
Commissions Web site.

2003 by CRC Press LLC

You might also like