CODE OF INSTRUCTIONPT-MB/0/E/IOI/03/8A SHIFT MANAGER :

SYSTEM 380V CB KKS CODE SUPERVISOR :

OPERATION ACTIVITY: OPERATOR :

380V Single Load CB Shutdown & Isolation SITE INSPECTION BY :

START Year Month Day Hr Min

END Year Month Day Hr Min

NORMAL EXECUTE
STEP PREVIOUSLY OPERATION RISK ASSESSMENT CONTROL STATUS CONFIRMATIO

1 Confirm all relevant Permit-To-Works have been completed,cancelled and cleared. Yes

2 All working parties have been evacuated from the workplace Yes

Ensure all operational personnel are wearing suitable PPE, such as gloves, safety helmet,
3 Yes
safety shoes, insulated gloves, earmuffs/plugs etc.

4 Ensure all operators are in good mental state and no drinking phenomenon. Yes

No water accumulation nor humid condition in operational area for the prevention of electric
5 Yes
short circuit

6 To provide a safe and comfortable workplace all tools and materials must be properly placed Yes

EXECUTE
STEP PROCEDURE CONFIRMATIO
Check relevant load(motor/pump/fan) already shutdown, and the CB (power breaker) of the load is in
1 "OFF" position

2 Switch the "local/remote" selector to "local" position

3 Switch main power handle to "DISCONNECTED" position

4 Switch mechanical interlock handle to "MOVEABLE" position

5 Rack-out the 380V CB

6 Lock the CB mechanical interlock handle in "DISCONNECTED" position

Verify again the above mentioned steps and ensure each step is correct, Report to supervisor that the
7 operation has completed.

END OF PROCEDURE

REMARK
EXECUTE
CONFIRMATION

EXECUTE
CONFIRMATION
PT.MB-IOI
CODE OF INSTRUCTIONPT-MB/0/E/IOI/03/9A SHIFT MANAGER :

SYSTEM 380V CB KKS CODE SUPERVISOR :

OPERATION ACTIVITY: OPERATOR :

380V Single Load CB De-isolation & Operation SITE INSPECTION BY :

START Year Month Day Hr Min

END Year Month Day Hr Min

NORMAL EXECUTE
STEP PREVIOUSLY OPERATION RISK ASSESSMENT CONTROL STATUS CONFIRMATIO

1 Confirm all relevant Permit-To-Works have been completed,cancelled and cleared. Yes

2 All working parties have been evacuated from the workplace Yes

Ensure all operational personnel are wearing suitable PPE, such as gloves, safety helmet,
3 Yes
safety shoes, insulated gloves, earmuffs/plugs etc.

4 Ensure all operators are in good mental state and no drinking phenomenon. Yes

No water accumulation nor humid condition in operational area for the prevention of electric
5 Yes
short circuit

6 To provide a safe and comfortable workplace all tools and materials must be properly placed Yes

EXECUTE
STEP PROCEDURE CONFIRMATIO
Ensure that relevant PTWs have been cancelled, the site of load equipment and switch cabinet should be
1 clean and tidy, no sundries , and satisfy power supply requirements

2 Check that 380V CB main power handle in "DISCONNECTED" position

3 Check that "remote/loacal" selector in "loacal" position

4 Unlock the CB mechanical interlock handle from "DISCONNECT" position

5 Switch the CB mechanical interlock handle to "MOVEABLE" position

6 Racking the 380V CB cabinet into working positon

7 Switch the CB mechanical interlock handle to "CONNECTED" position

8 Switch the CB main power handle to "CONNECTED" position

9 Check the singal of cabinet correctly

Verify again the above mentioned steps and ensure each step is correct, Report to supervisor that the
10 operation has completed.

END OF PROCEDURE

REMARK
REMARK
EXECUTE
CONFIRMATION

EXECUTE
CONFIRMATION
PT.MB-IOI
CODE OF INSTRUCTIONPT-MB/0/E/IOI/03/8B SHIFT MANAGER :

SYSTEM 380V MCC KKS CODE SUPERVISOR :

OPERATION ACTIVITY: OPERATOR :

380V MCC with ATS Shutdown & Isolation SITE INSPECTION BY :

START Year Month Day Hr Min

END Year Month Day Hr Min


NORMAL EXECUTE
STEP PREVIOUSLY OPERATION RISK ASSESSMENT CONTROL
STATUS CONFIRMATIO
1 Confirm all relevant Permit-To-Works have been completed,cancelled and cleared. Yes

2 All working parties have been evacuated from the workplace Yes

Ensure all operational personnel are wearing suitable PPE, such as gloves, safety helmet,
3 Yes
safety shoes, insulated gloves, earmuffs/plugs etc.

4 Ensure all operators are in good mental state and no drinking phenomenon. Yes
No water accumulation nor humid condition in operational area for the prevention of electric
5 Yes
short circuit

6 To provide a safe and comfortable workplace all tools and materials must be properly placed Yes
EXECUTE
STEP PROCEDURE CONFIRMATIO
Check all loads(motor/pump/fan) on the MCC already shutdown , and load power breakers are in "OFF"
1 position or out of switchborad
2 Check signal of ATS equipment correctly

3 Exit function of ATS auto switching

4 Open MCC working incoming CB from DCS

5 Check no voltage indcation on the MCC

6 Open MCC backup incoming CB from DCS

7 Switch "remote/local" selector of MCC working incoming CB to "local" positon

8 Racking the MCC working incoming CB to "repair" position

9 Switch "remote/local" selector of MCC backup incoming CB to "local" positon

10 Racking the MCC backup incoming CB to "repair" position

11 Open the isolation switch of ATS

12 Check and ensure no voltage on the MCC busbar by electroscope

13 Install a group earthing connection on the MCC busbar (require by maintenance)

Verify again the above mentioned steps and ensure each step is correct, Report to supervisor that the
14 operation has completed.

END OF PROCEDURE

REMARK
REMARK
EXECUTE
CONFIRMATION

EXECUTE
CONFIRMATION
PT.MB-IOI
CODE OF INSTRUCTIONPT-MB/0/E/IOI/03/9B SHIFT MANAGER :

SYSTEM 380V MCC KKS CODE SUPERVISOR :

OPERATION ACTIVITY: OPERATOR :

380V MCC with ATS De-isolation & Operation SITE INSPECTION BY :

START Year Month Day Hr Min

END Year Month Day Hr Min

NORMAL EXECUTE
STEP PREVIOUSLY OPERATION RISK ASSESSMENT CONTROL STATUS CONFIRMATIO

1 Confirm all relevant Permit-To-Works have been completed,cancelled and cleared. Yes

2 All working parties have been evacuated from the workplace Yes
Ensure all operational personnel are wearing suitable PPE, such as gloves, safety helmet,
3 Yes
safety shoes, insulated gloves, earmuffs/plugs etc.
4 Ensure all operators are in good mental state and no drinking phenomenon. Yes
No water accumulation nor humid condition in operational area for the prevention of electric
5 short circuit Yes

6 To provide a safe and comfortable workplace all tools and materials must be properly placed Yes

EXECUTE
STEP PROCEDURE CONFIRMATIO
Ensure that related PTWs have been cancelled, the switchborad should be clean and tidy, no sundries ,
1 and satisfy power supply requirements
2 Check that all loads CB on MCC are in "OFF" position

3 Remove the earthing connection from MCC busbar (if applied)

4 Close the isolation switch of ATS

5 Check that MCC woking incoming CB is in "OFF" postion

6 Racking the MCC working incoming CB to "working" position

7 Switch "remote/local" selector of MCC working incoming CB to "remote" positon

8 Check that MCC backup incoming CB is in "OFF" postion

9 Racking the MCC backup incoming CB to "working" position

10 Switch "remote/local" selector of MCC backup incoming CB to "remote" positon

11 Close the MCC working incoming CB

12 Check that MCC busbar operations normal with no-load, and ATS equipment signal correctly

13 Close the MCC backup incoming CB

14 Put the function of ATS auot switching in service

Verify again the above mentioned steps and ensure each step is correct, Report to supervisor that the
15
operation has completed.

END OF PROCEDURE