You are on page 1of 1

FLETE RURAL

FLETE RURAL DE MATERIALES

Medidas Parcial
Costo Flete
DESCRIPCION Unid. Cant.
S/.
Origen Destino Dist. Prom Total S/.

AGREGADOS m3 677.70 S/. 40.000 Almacen Obra 2.0 km S/. 27,108.00


CEMENTO PORTLAND TIPO I (42.5 kg) bls 2,650.60 S/. 1.500 Almacen Obra 2.0 km S/. 3,975.90
ACERO CORRUGADO kg 16,788.22 S/. 0.100 Almacen Obra 2.0 km S/. 1,678.82
TUBERIA F G 2" u 24.00 S/. 1.000 Almacen Obra 2.0 km S/. 24.00
Flete por
S/. 32,786.72