Time estimate for completions

Sl. ESTIMATED
ACTIVITY
No TIME (Days)
Casing cleaning trip, Filtration of brine to required cleanliness level for Gravel pack
1 4
job& changeover of well volume to brine
2 RIH with Wireline to Set Up Bridge Plug (SLB) 1
3 TCP trip. Perforation( SLB) 2
Run in lower completion string with FIV, screens, Seal bore packer etc. Set packer.
Rigging up of Gravel pack pumping assembly and testing. Perform Gravel pack job.
4 4
Pull out Lower completion assembly & Rig down Gravel pumping assembly.(HLB
COMPLETIONS and HLB PE TEAM)
5 Carryout space out run and with Completion string (Single by single run in) 2
6 Retrieval of Bore protector from tree along with Jet Wash of Tubing hanger Profile 1
Rig up & R/I upper completion assembly till tubing hanger including Gauges, Chemical
7 Injection mandrels, GLVs & Safety valve. Terminate the cables/lines at the tubing 3
hanger
Make up THRT & SSTT with Tubing hanger. Test SSTT and R/I assembly with the
8 1.5
landing string
Make up Big bore Flow head to the landing string and land and lock tubing hanger to
9 0.5
the subsea tree.
10 Slick line job (sliding sleeve opening) 0.5
11 Change over tubing volume of brine to Diesel 1
12 Slick line job(Sliding sleeve closing) 0.5
13 Set the upper packer. Activate well, clean out and 2

TOTAL 23