You are on page 1of 7

Crusher Working

Sr.No Items Unit qty For 1 brass


1 Crusher Unit hr 0.0389
2 750 kv DG hr 0.0389
3 Blastig unit hr 2.8111
4 breaker hr 0.1192
5 Excavator hr 0.1192
6 Loader hr 0.1192
7 Tipper hr 0.1619
8 Stone Tn 6.4655
9 Crusher oprator hr 0.0149
10 Supervisor day 0.0149
11 Unskilled workers day 0.1937
12 diesel for tipper lit 1.0778

Rate / Cum
ITEM- Analysis for Metal transporction

Skilled Labour 450


Unskilled Labour 250
Supervisor 600
Poclain 1550 Per Hour Including Diesel & Driver
Tipper 400 Per Hour Including Driver
Diesel 63

OUT PUT IN CUM 600.00

Activity Unit Qty Rate


A Labour
1 Supervisor Day 1 600
2 Un Skilled Labours Day 2.0 250
3 Labour Expences

Total Cost A
B Machinery
1 Loder front end Loder Hour 11 990
3 Tipper 14 Cum Capacity Hour 768.75 400
4 Diesel Lit 1285.71 63

6 JCB Required at stock Yard Hour 2 260


7 Diesel for JCB Lit 14 63
8 Maintaines cost of all Machinery
Total Cost B

Total Cost A+B


Total Cost/Cum

BOQ Rate
Lead
30

iesel & Driver

Amount Remark

600
500

1100

10890
307500.00
81000.00

520.00
882.00
989.00
401781

402881.00
671.47
Name Of Project :- Vita Islampur , Peth , to kokrud
Project Length :- 120 km

Machinery Planing for Bituminum Plant and Crusher Plant.

A) Bituminum Plant Planing.

90 km
30km
0 km

60 km
B) Crusher Plant

2 C Plant (Bilashi gaon)


1 C Plant (Borgaon)
41 km

71 km
0km

Note :- Cover Length.


1) 1st Crusher Plant :- 41 km Quarry Lead -15 km + working lead 41 km
2) 2nd Crusher Plant :- 30 km Quarry Lead -10 km + working lead 49 km
3) 3rd Crusher Plant :- 49 km Quarry Lead - 5 km + working Lead 30 km
120 km

3 C Plant (Manjare gaon)


110 km

km-0 to 41 km
km- 41 to 90 km
Lead 30 km km - 90 to 120 km
Site Survey For :- Vita to Anuskura, & Top to Dhiganchi road & phaltan to Aundh project.

Sr.No Description of Item Date Expensess Remarks

1 Nasta 8/16/2017 365 Phaltan


2 Lunch 8/16/2017 950 Kolhapur
3 Lunch 8/16/2017 1362 Kolhapur
4 Tourist Hotel 8/16/2017 2599 Kolhapur
5 Lunch 8/17/2017 344 Aundh

A) Total Expensess for Site Survey :- 5620

B) Total isuue Amount 10500

C) Balance Amount in Rs. :- 4880


2000 1 2000
500 3 1500
100 12 1200
50 1 50
10 13 130
4880 5620 5620

5276
344