1. The group of holes which are detonated on the first few delays are called [ ]
a) easers b) trimmers c) cut holes d) none
3. The diameter of the drum at sheve of the winding engine if installed should be at least
[ ]
a) 150 times the diameter of the rope b) 100 times the diameter of the rope
c) 120 times the diameter of the rope d) 110 times the diameter of the rope
7. What is the average length of wooden planks used for temporary supports used in shaft sinking
[ ]
a) 1.5m b) 3m c) 10m d) 15m
8. The rigid ventilation duct range terminates at least ____ above the shaft bottom to avoid its damage due
to blasting. [ ]
a) 5m b) 6m c) 4m d) 4.5m
10. Long-hole drilling with crater blasting is used for the construction of [ ]
a) winze b) shaft c) raise d) decline
Cont..2
Code No:117FF :2: Set No. 1
11. In areas of unstable overburden and water bearing, the initial excavation is carried out using the
_______________ method.
13. _____________ is more popular drilling pattern used in the rectangular shafts.
14. In practice shaft bottoms during sinking are usually full of water; therefore, __________ explosives are
used to charge the holes.
15. _________ is the arrangement that is made for the loading of blasted materials.
16. Which enables the scaffold ropes to act as the guide ropes for the smooth run of the kibble from shaft
top to the scaffold position in the shaft muck into conveyance for its disposal is _____________.
17. When the shaft depth increases and make of water is sufficient, it is always preferred, to have
intermediate pump chambers with sumps at an interval not exceeding _____mts.
19. The main shaft which is meant for the production hoisting should be located in the ___________ work-
load centre of the deposit.
-ooOoo-
Code No: 117FF Set No. 2
JAWAHARLAL NEHRU TECHNOLOGICAL UNIVERSITY HYDERABAD
IV B.Tech. I Sem., I Mid-Term Examinations, September-2017
MINE CONSTRUCTION ENGINEERING
Objective Exam
Name: ______________________________ Hall Ticket No. A
Answer All Questions. All Questions Carry Equal Marks. Time: 20 Min. Marks: 10.
4. What is the average length of wooden planks used for temporary supports used in shaft sinking
[ ]
a) 1.5m b) 3m c) 10m d) 15m
5. The rigid ventilation duct range terminates at least ____ above the shaft bottom to avoid its damage due
to blasting. [ ]
a) 5m b) 6m c) 4m d) 4.5m
8. The group of holes which are detonated on the first few delays are called [ ]
a) easers b) trimmers c) cut holes d) none
10. The diameter of the drum at sheve of the winding engine if installed should be at least
[ ]
a) 150 times the diameter of the rope b) 100 times the diameter of the rope
c) 120 times the diameter of the rope d) 110 times the diameter of the rope
Cont..2
Code No:117FF :2: Set No. 2
11. In practice shaft bottoms during sinking are usually full of water; therefore, __________ explosives are
used to charge the holes.
12. _________ is the arrangement that is made for the loading of blasted materials.
13. Which enables the scaffold ropes to act as the guide ropes for the smooth run of the kibble from shaft
top to the scaffold position in the shaft muck into conveyance for its disposal is _____________.
14. When the shaft depth increases and make of water is sufficient, it is always preferred, to have
intermediate pump chambers with sumps at an interval not exceeding _____mts.
16. The main shaft which is meant for the production hoisting should be located in the ___________ work-
load centre of the deposit.
18. In areas of unstable overburden and water bearing, the initial excavation is carried out using the
_______________ method.
20. _____________ is more popular drilling pattern used in the rectangular shafts.
-ooOoo-
Code No: 117FF Set No. 3
JAWAHARLAL NEHRU TECHNOLOGICAL UNIVERSITY HYDERABAD
IV B.Tech. I Sem., I Mid-Term Examinations, September-2017
MINE CONSTRUCTION ENGINEERING
Objective Exam
Name: ______________________________ Hall Ticket No. A
Answer All Questions. All Questions Carry Equal Marks. Time: 20 Min. Marks: 10.
2. What is the average length of wooden planks used for temporary supports used in shaft sinking
[ ]
a) 1.5m b) 3m c) 10m d) 15m
3. The rigid ventilation duct range terminates at least ____ above the shaft bottom to avoid its damage due
to blasting. [ ]
a) 5m b) 6m c) 4m d) 4.5m
6. The group of holes which are detonated on the first few delays are called [ ]
a) easers b) trimmers c) cut holes d) none
8. The diameter of the drum at sheve of the winding engine if installed should be at least
[ ]
a) 150 times the diameter of the rope b) 100 times the diameter of the rope
c) 120 times the diameter of the rope d) 110 times the diameter of the rope
Cont..2
Code No:117FF :2: Set No. 3
11. Which enables the scaffold ropes to act as the guide ropes for the smooth run of the kibble from shaft
top to the scaffold position in the shaft muck into conveyance for its disposal is _____________.
12. When the shaft depth increases and make of water is sufficient, it is always preferred, to have
intermediate pump chambers with sumps at an interval not exceeding _____mts.
14. The main shaft which is meant for the production hoisting should be located in the ___________ work-
load centre of the deposit.
16. In areas of unstable overburden and water bearing, the initial excavation is carried out using the
_______________ method.
18. _____________ is more popular drilling pattern used in the rectangular shafts.
19. In practice shaft bottoms during sinking are usually full of water; therefore, __________ explosives are
used to charge the holes.
20. _________ is the arrangement that is made for the loading of blasted materials.
-ooOoo-
Code No: 117FF Set No. 4
JAWAHARLAL NEHRU TECHNOLOGICAL UNIVERSITY HYDERABAD
IV B.Tech. I Sem., I Mid-Term Examinations, September-2017
MINE CONSTRUCTION ENGINEERING
Objective Exam
Name: ______________________________ Hall Ticket No. A
Answer All Questions. All Questions Carry Equal Marks. Time: 20 Min. Marks: 10.
1. The rigid ventilation duct range terminates at least ____ above the shaft bottom to avoid its damage due
to blasting. [ ]
a) 5m b) 6m c) 4m d) 4.5m
4. The group of holes which are detonated on the first few delays are called [ ]
a) easers b) trimmers c) cut holes d) none
6. The diameter of the drum at sheve of the winding engine if installed should be at least
[ ]
a) 150 times the diameter of the rope b) 100 times the diameter of the rope
c) 120 times the diameter of the rope d) 110 times the diameter of the rope
10. What is the average length of wooden planks used for temporary supports used in shaft sinking
[ ]
a) 1.5m b) 3m c) 10m d) 15m
Cont..2
Code No:117FF :2: Set No. 4
12. The main shaft which is meant for the production hoisting should be located in the ___________ work-
load centre of the deposit.
14. In areas of unstable overburden and water bearing, the initial excavation is carried out using the
_______________ method.
16. _____________ is more popular drilling pattern used in the rectangular shafts.
17. In practice shaft bottoms during sinking are usually full of water; therefore, __________ explosives are
used to charge the holes.
18. _________ is the arrangement that is made for the loading of blasted materials.
19. Which enables the scaffold ropes to act as the guide ropes for the smooth run of the kibble from shaft
top to the scaffold position in the shaft muck into conveyance for its disposal is _____________.
20. When the shaft depth increases and make of water is sufficient, it is always preferred, to have
intermediate pump chambers with sumps at an interval not exceeding _____mts.