Professional Documents
Culture Documents
PV System
BP 0403
Off-Grid PV Design
BP 0403
Off-Grid Design Example
Step 1: Determine the DC Load.
Refrigerator 60 24 1,440
Device A 12 8 96
BP 0403
Step 2: Determine the AC Load, Convert to DC
Pump 80 0.5 40
BP 0403
Step 8: Determine Number of Modules in Parallel
Total PV Array Current / (Module Operating Current) X
(Module Derate Factor)
76.6 Amps / (3.56 Amps/Module)(0.90) = 23.90 modules
Use 24 Modules
BP 0403
Step 13: Determine Number of Batteries in Parallel
Required Battery Capacity (Step 11) / Capacity of
Selected Battery
1,436 Amp-hrs / (220 Amp-hrs/Battery) = 6.5
Use 6 Batteries
+ + Parallel:
+ 6A Current is additive
3A 3A
12 V 12 V - 12 V
- -
BP 0403
Step 16: Determine the need for a Standby
Generator to reduce other Components
(number of Modules and Batteries). Several
iterations may be necessary to optimize costs.
Step 17: Complete Balance of System
a. Complete the design by specifying the:
Charge Controller
Inverter
Wire Sizes (Battery will have larger gage
due to higher currents)
Fuses and Disconnects
Standby Generator, if needed
Battery Charger, if needed
Manual Transfer Switch, if needed.
BP 0403
Step 17 (Cont.):
b. Determine mounting method:
Roof mount
Ground mount with racks
Ground mount with pole.
BP 0403
Solar Hybrid Operation
Case Study: RPS Kemar, Gerik
Solar Hybrid Station is located in RPS Kemar, Gerik, Perak and coordinate:
N 05 12.038 , E 101 23.765.
The site is accessible via speed boat ride from Jetty Banding or Jetty Trojen
Tasik Temenggor, Gerik which takes 1 hour journey to reach Jetty Kemar.
Design Configuration
Based on the load profile and to suite with client design requirement
which need 70% energy generates will come from Solar energy and
battery will only allow one (1) complete cycle charge and discharge
per day, the design configuration as follows:
Installed Plant
Installed Plant (cont.)
System performance Nov 12 Jan 13
Diesel
generation, 1%
Solar PV
generation, 99%