You are on page 1of 10

Geotechnical Engineering Proceedings of the Institution of Civil Engineers

Volume 165 Issue GE1 Geotechnical Engineering 165 February 2012 Issue GE1
Pages 312 http://dx.doi.org/10.1680/geng.2012.165.1.3
The design of temporary excavation support Paper 900096
to Eurocode 7 Received 17/12/2009 Accepted 20/01/2011
Keywords: codes of practice & standards/excavation/temporary works
Markham

ICE Publishing: All rights reserved

The design of temporary


excavation support to
Eurocode 7
Paul David Markham MSc, CEng, FICE
Director, RNP Associates Limited, Sutton Coldeld, UK

This paper examines how Eurocode 7 relates to the design of temporary excavation support. It is shown that total
stress design and the net available passive resistance method described in Ciria Report 104 can produce inconsistent
results, which must be carefully checked for sensitivity to the soil parameter values used. Many temporary
excavations are designed using moderately conservative soil parameter values and a limit equilibrium method of
analysis with a lumped factor of safety of 1.5. It is concluded that design in accordance with Eurocode 7 produces
higher propping forces than design using this approach, but that Eurocode 7 produces propping forces over 60%
lower than design in accordance with Ciria Report C580.

Notation Where frames or props are used, proprietary equipment available


cu undrained cohesion for hire will usually be used (Figure 1).
cu;d design value of undrained cohesion
ka active pressure coefficient The major differences between the design of temporary and
kac active pressure coefficient permanent excavation support include the following.
kp passive pressure coefficient
kpc passive pressure coefficient j Temporary works are required for a comparatively short time,
Psls value of the prop force derived from the SLS load case thus in fine-grained soils it can be appropriate to use total
ua pore water pressure on active side of wall stress parameters for the design rather than effective stress
up pore water pressure on passive side of wall parameters
F partial factor for an action j The design has to be undertaken based on the ground
G;dst partial factor for a permanent destabilising action investigation report for the permanent works. Often this
G;stb partial factor for a permanent stabilising action report has not been conceived or written for the design of
a active earth pressure temporary excavations; the necessary information for design
p passive earth pressure
va total vertical stress on the active side of the wall
vp total vertical stress on the passive side of the wall
 v9a effective vertical stress on the active side of the wall
 v9p effective vertical stress on the passive side of the wall

1. Introduction
Eurocode 7 (EC7) (BSI, 2004a) is now the sole national and
European standard for the design of geotechnical works and its
use is mandatory on publicly funded work. There are several
design guides to EC7 (Bond and Harris, 2008; Department for
Communities and Local Government, 2007; Frank et al., 2004),
which state the general manner in which EC7 is applied. This
paper will specifically refer to the design of routine excavation
support, usually carried out by a contractor as part of the
construction process, and is based on the authors experience of
the design and checking of temporary works schemes. These Figure 1. Typical small temporary excavation supported by trench
excavations are supported by the use of steel trench sheets or sheets and proprietary frames
steel sheet piles with or without support from frames or props.

3
Geotechnical Engineering The design of temporary excavation
Volume 165 Issue GE1 support to Eurocode 7
Markham

of such structures is absent and there is not time to conduct a usually treated as unfavourable throughout. However, towards the
supplementary site investigation. Where suitable site toe of the wall the soil on the retained side becomes favourable
investigation data are not available, then it would not be because it prevents rotation of the toe of the wall and reduces
possible to do a design in accordance with EC7. bending moment in the wall and reduces prop loads. It is not
j The excavation is in the upper layers of soil. The ground in clear where the soil changes from being unfavourable to favour-
this area often consists of fill, made ground, disturbed ground, able and using the principles of EC7 different partial factors
head or recent deposits that do not form coherent beds. should be applied to each of these actions, which would make the
Owing to a lack of suitable case histories, it is usually calculations unnecessarily complex. When favourable and unfa-
difficult to base the design on case histories from previous vourable actions come from the same source, EC7 allows the
excavations in similar material. same partial factor, F, to be applied to all those forces; this
j These temporary excavations are usually less than 6 m deep. reduces the complexity of the calculations and has become known
as the single source principle.
BS 8002:1994 (BSI, 1994) has not been widely adopted by
designers of sheet pile walls (Puller and Lee, 1996). Therefore, For retaining walls, in cohesionless soils, the active and passive
temporary works design of retaining walls uses a hybrid of earth pressures are calculated from the formulae
several methods. Gaba et al. (2003) recognised that there was a
multitude of guidance for designers and that this advice was often active pressure
contradictory, and therefore aimed to summarise both best prac-
tice and the alternative design methods in Ciria Report C580.  a k a  v9a ua
This was published before the publication of EC7 and is not
compatible with EC7 on some issues, such as factors of safety for
stability and strut design. passive pressure

 p k p  v9p up
2. Eurocode 7
2.1 Application of the partial factors
Eurocode 7 is a limit state and partial factor code which adopts Substituting the usual formula for effective stress and rearranging
the same philosophy as the other structural Eurocodes, with to separate the effects of earth and water pressure, the formulae
actions subject to different partial factors depending on whether become:
they are favourable (or stabilising) or unfavourable (or destabilis-
ing). For example, when treated as an action, earth pressure is  a k a  va ua 1  k a
subject to the partial factors G;fav 1.0 for a favourable action
or the partial factor G 1.35 for an unfavourable action. On a
propped wall (Figure 2) the soil on the retained side of the wall is and

Unfavourable permanent
geotechnical action, G 135
Actual earth pressure Earth pressure according
distribution (indicative) to active earth pressure theory
Actual earth pressure
distribution
Favourable permanent
geotechnical action, G 100
Surcharge, Q 0

Earth pressure according to


passive earth pressure theory

Figure 2. Propped retaining wall showing that it is not clear


where the earth pressure changes from being an unfavourable
action to a favourable action

4
Geotechnical Engineering The design of temporary excavation
Volume 165 Issue GE1 support to Eurocode 7
Markham

 p k p  vp up 1  k p traffic loading. BSI has also published NCCI for structures


subject to traffic loading in PD 6694-1 (BSI, 2011) which
says very little about embedded retaining walls and refers the
Since ka is generally less than 1.0, these formulae show that the reader to Ciria Report C580 (Gaba et al., 2003).
vertical total stress on the active side of the wall, va , and the
water pressure on the active side of the wall, ua , are both This leaves the engineer in a difficult position as illustrated by
unfavourable, since they increase the pressure on the active side an international workshop (Orr, 2005: p. 4) which was held to
of the wall. On the passive side of the wall, as the vertical total review ten geotechnical examples that had previously been
stress, vp , increases so the passive pressure increases, hence the distributed to members of the European Technical Committee 10
vertical total stress is favourable. However, since kp is greater (ETC10). The committee members prepared solutions to the
than 1.0, the term (1  kp ) is negative and water on the passive design examples and the solutions showed a considerable spread
side reduces the passive resistance; hence it is unfavourable. To in the range of results. It was concluded (Simpson, 2005) that
avoid applying different partial factors to the earth and water some of the spread was due to contributors applying additional
pressures it is simplest to use the single source principle. measures on top of the requirements of EC7, for example using
values of =9 lower than required or applying additional
2.2 Comparable experience penetration beyond that required by the equilibrium equations.
Eurocode 7 places considerable value on comparable experience, However, it is necessary to apply additional measures that are
which is defined in clause 1.5.2.2 as follows. not covered by EC7 to deal with the likes of passive softening,
arching, minimum effective fluid pressure, eccentricity of load
Documented or other clearly established information related to the on props or accidental load on props. Therefore, owing to the
ground being considered in design, involving the same types of soil lack of definitive NCCI, engineers will apply existing guidance
and rock and for which similar geotechnical behaviour is expected, in an inconsistent manner, which could result in unsafe or
and involving similar structures. Information gained locally is uneconomic designs (Simpson, 2005).
considered to be particularly relevant. (BSI, 2004a)

2.5 Selection of soil parameter values from test results


Historically, there has been little guidance to the designer on
Therefore, to use comparable experience, the soil and the scale of how parameter values should be selected (Simpson and Driscoll,
the structure must be similar. However, there is a shortage of case 1998) and engineers have always had to use engineering
histories for shallow excavations, which limits the circumstances judgement to obtain parameter values. The precise method of
in which comparable experience can be applied (Driscoll et al., doing this has not been well defined, but EC7 attempts to
2008). Consequently, an alternative method is required (Section 3). provide some guidance to the engineer on this subject by
suggesting that parameter values can be obtained using statistical
2.3 Deformation techniques. The guidance is to be welcomed, but in practice the
Eurocode 7 requires the engineer to assess deformation when this statistical techniques are difficult to apply and a large number of
could have an effect on neighbouring structures. Where there are test results is required to produce meaningful results. Geo-
sufficient geotechnical data available, sufficient time for the technical engineers, by definition, have put their time and effort
analysis and appropriate engineering expertise, then deformation into the study of geotechnics and few geotechnical engineers
can be calculated using the finite-element (FE) method of analy- will also have studied statistics to a sufficiently high level to be
sis. However, the data and time are not usually available for FE able to apply these statistical techniques (Simpson and Driscoll,
analysis for these routine excavation supports. Therefore, defor- 1998); consequently, the use of statistical methods is not
mation is best assessed on the basis of case history data such as appropriate on the majority of projects (Department for Commu-
the charts by Clough and ORourke (1990). nities and Local Government, 2007). The exception is on large
projects where there is an abundance of high-quality ground
2.4 Guidance investigation data and a team can be built up to include
Previous standards, such as CP2:1951 (Institution of Structural statisticians. This does not apply to the small, temporary
Engineers, 1951) and BS 8002:1994 (BSI, 1994), attempted to excavations under consideration. So, although these statistical
provide the designer with rules for design and the geo- methods cannot be used directly, they can be used to show the
technical information necessary to do the design. EC7 provides way in which engineering judgement should be heading (Dris-
only the rules for design to ensure safety and economy coll et al., 2008).
(Simpson and Driscoll, 1998) and allows the engineer consid-
erable scope regarding choice of method. Therefore, the 2.6 Accidental overdig
engineer is required to consult other references to non-contra- It is usual to make some allowance for accidental overdig in
dictory complementary information (NCCI) such as Ciria design. This is commonly 10% of the depth of excavation below
Report C580 (Gaba et al., 2003). The British Standards the bottom strut, up to a maximum of 0.5 m (see BS 8002:1994
Institution is also publishing NCCI for structures subject to (BSI, 1994) and BSC (1997)). Control of dig level during

5
Geotechnical Engineering The design of temporary excavation
Volume 165 Issue GE1 support to Eurocode 7
Markham

excavation of a cofferdam is very good. Overdig costs money to monitoring frequency must be stated and reflect the level of risk
excavate, more money to dispose of the arisings, and the overdig and mode of failure.
has to be replaced with expensive concrete, hence site manage-
ment has incentives to minimise overdig. Where 75 mm of 2.7 Design in fine-grained soils
blinding is specified, the target dig level can be 10 mm high so The indicative design working life of a temporary structure is
that there is never any overdig. stated in Eurocode: Basis of Structural Design, BS EN 1990:
2002 (BSI, 2002) as 10 years. This is only indicative and
EC7 allows the depth of accidental overdig to be determined by designers can use other values for the design life, but the designer
risk assessment, in which case the following factors should be has to be able to justify the adoption of a shorter design life. The
taken into consideration. significance to a temporary retaining wall is that a small
cofferdam can be installed, excavated and removed within a few
weeks or months. For the design of excavation support in London
j Total depth of excavation.
clay, undrained conditions are commonly assumed for durations
j Depth below bottom frame.
up to six months (Gaba et al., 2003). However, clause 9.6(3) of
j Is it possible to get a digger into the excavation to bottom
EC7 states that for silts and clays water pressures should
up? (Figure 3)
normally be assumed to act behind the wall. . .[corresponding] to
j Is the ground easy to trim to the required level, or is it likely
a water table at the surface of the retained material. This
to come out in irregular lumps (e.g. weak sandstone)?
produces the same water pressures as assuming a water-filled
j Will the excavator driver work from outside the cofferdam?
tension crack (Figure 4) for the full depth of the wall. Where
j Will the excavator driver be able to see where he is digging
water is not expected, EC7 does not contain any rule regarding
or will he rely on a banksman?
minimum effective fluid pressure (MEFP) of the retained soil, but
j Will there be experienced supervisors on site throughout the
the UK National Annex (BSI, 2004b) does refer to Ciria Report
construction period?
C580 (Gaba et al., 2003) as a source of NCCI, which does
j Can remedial action be taken in the event that distress to the
require MEFP.
cofferdam is noted?

Where there is experience of excavations in similar soil, mixed


Where risk assessment shows that it is not necessary to consider total and effective stress design is recommended in Ciria Report
accidental overdig in the design, then a sensitivity analysis should C580 (Gaba et al., 2003) in conjunction with pore water pressures
be undertaken to examine the effects of accidental overdig and care obtained from a flow net and passive softening. Where there is no
must be taken to ensure that the result of analysis is still reasonable. potential for recharge, either at excavation level or within the
Additionally, the requirement for supervision and construction soil, on the passive side of the wall, the recommended depth of
control measures must be specified in the geotechnical design passive softening is 0.5 m. Further recommendations are made in
report (Bond and Harris, 2008). Construction control measures Ciria Report C580 (Gaba et al., 2003) where there is potential for
would include a monitoring system with clear trigger levels. The recharge below formation, possibly by sand or silt layers. How-
ever, in this case, the appropriateness of design assuming
undrained conditions is questionable, which leads to the conclu-

Figure 3. Trimming formation in an excavation where there can


be good control of the dig level and little or no accidental overdig Figure 4. Tension crack adjacent to an excavation

6
Geotechnical Engineering The design of temporary excavation
Volume 165 Issue GE1 support to Eurocode 7
Markham

sion that the depth of passive softening should be taken as 0.5 m 2.10 Factors applied to water pressure
whenever the design is based on undrained parameters; alterna- Eurocode 7 is not definitive regarding the factors that should be
tively, undrained parameters should not be used. This should be applied to water pressure, and the engineer is left with consider-
used with the assumption that there is zero adhesion between the able scope regarding the factors to be used and the water levels to
pile and the soil so kac kpc 2.0. be used. This is discussed by Bond and Harris (2008) and they
show five different ways in which EC7 can be interpreted
2.8 Thermal effects regarding water levels and partial factors. Some of the interpreta-
Props are affected by temperature because the ground, on the tions make the calculations very difficult or lead to unrealistic
retained side, restrains the props against thermal expansion. situations and Bond and Harris (2008) go on to suggest the
This paper is concerned only with comparatively shallow sheet following approach, which is both realistic and reliable. When
pile walls and, for a frictional soil, passive resistance is earth pressures are factored, the same partial factor (G 1.35) is
proportional to depth. Therefore, for a frame near ground level, applied to the earth and water pressure, which is calculated using
supporting a sheet pile wall, there will not be much restraint to the highest normal water level (i.e. the characteristic value).
temperature effects, so prop loads should not be greatly affected Alternatively, when the factor G 1.0 is applied to the effective
by temperature. For example a 10 m long prop, with a 258 rise earth pressure, the same factor is applied to the water pressure
in temperature would lengthen by 3 mm (1.5 mm at each end). but the water pressure is calculated using the highest possible
This would result in the force in the prop being slightly higher water level. This level can be obtained by applying a margin to
than the active force, but still, probably, less than that due to the characteristic water level.
the earth pressure at rest. This leads to the conclusion that
temperature changes have little effect on prop loads supporting 3. Reliability of existing methods
flexible walls (Twine and Roscoe, 1999). However, using the The difficulty of obtaining accurate predictions of design effects
values suggested in Ciria Report C580 (Gaba et al., 2003), a using numerical methods is illustrated by the benchmarking of
10 m long, 305 mm 3 305 mm 3 97 kg/m universal column the software Plaxis (Schweiger, 2009). Several engineers used
propping a flexible wall in stiff soil would have a temperature Plaxis to analyse a strutted retaining wall where the constitutive
effect of 300 kN in addition to the prop force from the stability model, the soil parameters and the geometry were predefined.
analysis. The method described in Ciria Report C580 (Gaba et Users were then free to make decisions regarding the type of
al., 2003) was based on measurement of prop loads in strutted elements to use, the tolerance settings, groundwater modelling
excavations and the method does not take account of the depth and the extent of the grid. The range of calculated maximum
of the prop below ground level. For deeper props there will be displacement varied between 12 and 28 mm. The calculated
more restraint, but for shallow props supporting sheet pile walls bending moment ranged from 25 to 51 kN m and the calculated
there is less restraint from the ground and the method in Ciria strut force ranged between 84 and 124 kN/m. Where engineers
C580 could be conservative. have to make decisions regarding the software to use, the soil
parameter values, the constitutive model and the mesh, then there
2.9 Workload would be a greater range of calculated values. Software for FE
Eurocode 7 has been criticised for requiring additional work from analysis is complex, and incomplete understanding of the consti-
the engineer. However, for the relatively simple excavations under tutive model was at least partially responsible for the Nicoll
consideration, the amount of additional work is small in compari- Highway collapse (Karlsrud and Andresen, 2007). Schweiger
son to the overall amount of work required (Table 1). (2009) concluded that the results of a FE analysis need to be

Existing requirements based on Ciria Report C580 (Gaba et al., 2003) Requirement of EC7-2

Understand the requirements As existing


Assessment and selection of soil parameter values As existing
The assessment of the load in the support system at an overall factor of safety DA1-C1,
of unity
The assessment of the design wall depth at a factor of safety of 1.22.0 DA1-C2
depending on the method of analysis chosen
Where required, the serviceability load case As existing
Check sensitivity to accidental overdig and variation in soil parameter values As existing
Production of written calculations Production of geotechnical design report
Production of drawings As existing

Table 1. Comparison of the analysis required by EC7-1 and


existing requirements

7
Geotechnical Engineering The design of temporary excavation
Volume 165 Issue GE1 support to Eurocode 7
Markham

checked very carefully and that experience is necessary for 3.1 Problems with total stress design
obtaining reliable results from such an analysis. There are problems with the gross pressure method where, in a
total stress analysis, the factor of safety reduces as the pile length
These excavations are usually designed by the contractor as part increases. With the strength factor method, a related problem can
of the construction process using the site investigation report arise in which there is extreme sensitivity of the calculation
commissioned for the permanent works design. On most small when, on the retained side, the vertical effective stress at
schemes the only laboratory test results available are the results formation is about four times the undrained cohesion below
of index tests and quick undrained triaxial tests. Accurate values formation (assuming ka kp 1.0, kac kpc 2.0 and the same
of the stiffness parameters for numerical design are not generally soil on both sides of the wall) (Figure 5). This is because the
available and the engineer either has to use approximate input active pressure,  a k a  v9a k ac cu and the passive pressure,
data or, preferably, use a simple method of design with the soil  p k p  v9p k pc cu are about equal. Therefore, for the conditions
parameters that are available (Gaba et al., 2003). Therefore, a stated, the net pressure below formation,  p   a  0, which
simple robust method is needed for temporary works design. EC7 makes the results of calculations oversensitive to small variations
allows design by calculations; adoption of prescriptive measures; in the parameter values used. This type of problem is always
experimental models; load tests; or by an observational method. present with total stress design; the inclusion in the calculation of
Numerical methods may not give realistic results and can give a MEFP, tension cracks and passive softening complicates the
false impression of accuracy; the distributed prop load method matter, but the same oversensitivity occurs for some combinations
(DPL; Twine and Roscoe, 1999) is not appropriate for excava- of circumstances. For example, a propped wall with a 5 m
tions less than 6 m deep, neither is the observational method. The retained height has been analysed using the factor on strength
remaining option, use of a limit equilibrium method, provides a method (Table 2) with allowance for passive softening, a MEFP
simple, robust design method with an established history of of 5 kN/m3 and a water-filled tension crack. The driving depth, d,
successful use. increases from 5.88 m to 12.26 m as the undrained cohesion is
decreased from 38 kPa to 36 kPa. This is due to the net pressure
Several comparisons have shown that calculation methods do below formation being close to zero when the factor of 1.4 is
not predict actual behaviour well for either limit equilibrium applied to the strength of the clay. Therefore, total stress design
methods of analysis or for numerical methods of analysis (Day must be used with caution with the factor on strength method and
and Potts, 1989; Gaba et al., 2003; Kort, 2002; Lambe and the results should be checked for sensitivity to the parameter
Turner, 1970). The comparisons also show that the high values used. This problem also occurs when using the net
factors of safety recommended by Gaba et al. (2003) in Ciria available passive resistance method as described in Ciria 104
Report C580, are necessary for a safe design; however, these (Padfield and Mair, 1984). The undue sensitivity only affects the
factors are not always used in temporary works design (see driving depth of the piles; the prop load and moment in the sheets
Section 4). are only affected in proportion to the parameter values (Table 3).

Surcharge, w

Prop
20 kN/m3
ka kp 10
50 m

kac kpc 20
cu 25 kPa
Active pressure
v 100 kPa
10 m
d

pp kp d kac cu 50 20d pa ka v k ac c u 100 20d 2 25 50 20d

Figure 5. Extreme sensitivity when using the strength factor


method

8
Geotechnical Engineering The design of temporary excavation
Volume 165 Issue GE1 support to Eurocode 7
Markham

cu : kPa Factor on strength cud : kPa Driving depth, Maximum moment: Prop load:
d: m kN m kN m

38 1.4 27.14 5.88 145 81


36 1.4 25.71 12.26 207 99

Table 2. Oversensitivity when using total stress design with the


gross pressure method of analysis

cu : kPa Factor on strength cud : kPa Driving depth, Maximum moment: Prop load:
d: m kN m kN m

56 1.4 40 1.04 36 29
49 1.4 35 1.83 48 30
45 1.4 32 4.02 44 32
43 1.4 31 6.78 46 33

Table 3. Oversensitivity when using the net available passive


resistance method of analysis as described in Ciria Report 104
(Padeld and Mair, 1984)

4. Comparison with existing methods of Using characteristic values for the soil parameters in this manner
design results in a calculated factor of safety for toe stability of 1.0 for
A comparison has been made, for a range of frictional soils, DA1-C1. In DA1-C2 the main partial factors are applied to the
between the output from a design to EC7 with the output of a material propertie (i.e. the shear strength of the soil). Therefore,
design to Ciria Report C580 for a propped wall (Figure 6). the toe depth is almost always determined from the DA1-C2
Design approach 1 (DA1) has been used for the analysis of calculation.
ultimate limit states (ULSs) to EC7. This requires the analysis of
two ULS cases, referred to as combination 1 (DA1-C1) and The water level for each design situation must be assessed by the
combination 2 (DA1-C2). In addition, the serviceability limit engineer, but for this example of temporary excavation support
state (SLS) must be considered. In DA1-C1 the main partial the highest possible water level has been taken as the character-
factors are applied to the actions (loads); this is a similar istic value. Therefore, the margin suggested by Bond and Harris
approach to that used in the other structural Eurocodes. The (2008) and discussed in Section 2.10 has been taken as zero and
engineer can choose where in the calculation to apply the partial the characteristic value of water pressure has been used in the
factors and for this comparison the calculations have been carried calculations (G 1.0). A factor of safety of 1.0 (using design
out using characteristic values and the effects factored. This values) has been used in the equilibrium calculations to determine
applies the same partial factor to active pressure, passive pressure the pile length. For both the analysis to EC7 and Ciria C580, the
and water pressure and is known as the single source principle. excavation depth has been taken as 5.4 m in the ULS load cases,
which is a 10% increase on the actual depth below the frame to
Surcharge 10 kPa allow for unplanned excavation. The serviceability load case has
10 m

been analysed using characteristic values and there is no


Prop
allowance for unplanned excavation.
50 m

19 kN/m3 The analysis shows (Figure 7) that for designs to EC7, the design
w 10 kN/m3 moment for high-friction soil (9 408) is obtained from DA1-
C1, whereas for the other three soils considered the design
Linear variation of moment is obtained from DA1-C2. This shows that it is always
hydraulic head
(BS 8002: 1994) necessary to check both load cases. The design prop load (Figure
8) for all the soils considered was obtained from DA1-C1.

Figure 6. Wall analysed for comparison of design to net pressure For design to Ciria Report C580, for the four soils considered,
method with design to EC7 the design moments and propping force are obtained from the
ULS analyses; in other words the prop forces from the ULS

9
Geotechnical Engineering The design of temporary excavation
Volume 165 Issue GE1 support to Eurocode 7
Markham

600
800 Design approach 1 combination 1
Design approach 1 combination 1

Design approach 1 combination 2 550 Design approach 1 combination 2

700 500 Ciria C580 ULS load case


Ciria C580 ULS load case
Ciria C580 SLS load case
Ciria C580 ULS moment derived from SLS 450
load case (i.e. SLS 135)
600
400

Prop load: kN
350
500
Moment: kN m

300

400
250

200
300
150

100
200
25 30 35 40
Angle of shearing resistance: deg

Figure 8. Comparison of results of design to EC7 with design to


100
net pressure method prop load
25 30 35 40
Angle of shearing resistance: deg

Figure 7. Comparison of results of design to EC7 with design to


net pressure method moment

14
analysis are greater than 1.35 times the prop force from the SLS Design approach 1 combination 1
analysis (Figure 8). However, this is not the case for all soils
13 Design approach 1 combination 2
and, as with design to EC7, it is necessary to check both load
cases. Ciria C580 ULS load case
12

The analysis to EC7 design approach 1 always produced higher


Driving depth: m

11
bending moments in the sheets than the analysis to Ciria Report
C580, by between 3% and 9% (Figure 7) and required longer
sheets (Figure 9) by between 40 mm and 690 mm (0.5% and 6%). 10
In practice, the sheets are selected from a limited range and are
sized for driveability as well as the moment produced from this 9
analysis, so this will not make much difference to the final
design. The pile length, in the EC7 calculations, was always 8
obtained from DA1-C2.
7
However, the analysis to Ciria Report C580 always produced
higher design values for the prop forces than the analysis to EC7 6
25 30 35 40
design approach 1 by between 61% and 65% (Figure 8). This is Angle of shearing resistance: deg
because of the large factors of safety (Table 4) applied at the end
of the calculation using the Ciria Report C580 method. Some Figure 9. Comparison of results of design to EC7 with design to
engineers might consider these factors of safety a model factor net pressure method driving depth
also to be applied to the output from a limit equilibrium

10
Geotechnical Engineering The design of temporary excavation
Volume 165 Issue GE1 support to Eurocode 7
Markham

Limit equilibrium calculations Soilstructure interaction calculations

SLS prop load (unfactored soil parameters) 1.85 3 calculated value 1.0 3 calculated value
ULS prop load (factored soil parameters) The greater of: The greater of:
1.35 3 Psls 1.35 3 Psls
1.85 3 calculated value 1.0 3 calculated value

Table 4. Factors of safety for the design prop loads to Ciria


Report C580 (Gaba et al., 2003)

calculation to EC7. Additionally, it is recommended in Ciria limit state and partial factor code, EC7 is a major step forward in
Report 104 (Padfield and Mair, 1984) that the prop loads from a standardisation, but the lack of prescriptive measures will lead to
limit equilibrium analysis are increased by 25% to allow for much disagreement and uncertainty among engineers.
arching. However, neither the model factor nor the 25% increase
are written into EC7, so engineers can produce a design in In the UK, only design approach 1 is permitted by the National
accordance with EC7 without using them; this means that a Annex to EC7-1 (BSI, 2004b). Even using a single method of
design to EC7 would not have the same level of reliability as design, different interpretations of EC7 can produce very differ-
existing design methods, which was one of the fundamental ent results. For example, passive earth pressure can be treated as
requirements of EC7 (Simpson and Driscoll, 1998). a resistance, a favourable action or a negative unfavourable
action, each of which produces a different result to the calcula-
However, the frames for temporary excavations are often de- tions. Water pressure can also be treated in several different ways
signed using lower factors of safety than recommended in Ciria and a consistent approach is required, such as using the single
Report C580. For routine excavation, it is common, throughout source principle, which removes some of the complexity of, and
the hire industry, to use moderately conservative soil parameter is easier to use than, applying different partial factors to the
values with a limit equilibrium method of analysis and apply a different parts of the earth and water pressure diagrams.
lumped factor of safety of 1.5 to the analysis output to calculate
the ultimate frame load. This is equivalent to the analysis of the Some of the opposition to EC7 can be explained by conserva-
serviceability loadcase and the calculations show that the ULS tism of geotechnical engineers and the unwillingness to change
prop load calculated to EC7 for these examples varies from existing practices that are known to work. Interpretation of EC7
between 1.59 and 1.60 times that calculated from the service- produces disagreement, among engineers, regarding whether
ability loadcase. Therefore, analysis of the serviceability load numerical modelling is required and interpretation of the
case and a factor of safety of 1.5 on the frame load do not individual clauses. Using EC7, it is necessary for the engineer to
produce a design with the same reliability as a design to EC7. refer to NCCI to complete the design. In the UK, Ciria Report
C580 (Gaba et al., 2003) is cited as NCCI; however, parts of
Limit equilibrium methods of analysis are not geotechnically Ciria C580 are contradictory, so a partial rewrite is required
rigorous; usually the movement of the sheets is insufficient to urgently, to ensure reliability in design and to ensure that EC7,
achieve the fully active or fully passive earth pressures on which unlike BS 8002, is widely accepted by temporary works
the methods are predicated. However, they do have the advantage engineers.
that they are simple to apply and robust in use. That is, the
factors of safety that are used with these methods are method Currently, for cohesive soils, total stress design or mixed total
dependent and have been based on much experience to produce a and effective stress design are often used for temporary excava-
safe design. Any limit equilibrium method is permitted by EC7, tions. However, whenever total stress parameters are used on the
but the factors of safety (partial factors) for use with design to passive side of the wall, the analysis can become ill-conditioned
EC7 have been predefined in the National Annex to EC7 (BSI, and a sensitivity analysis is necessary.
2004b). In the past few years, the net available passive resistance
method of design (see Padfield and Mair (1984)) has been widely The routine method of design for small temporary excavation
used. However, its use with partial factors can produce incon- support has become a hybrid method based on Ciria Reports 104
sistent results (Table 3) and it may prove necessary to develop (Padfield and Mair, 1984) and C580 (Gaba et al., 2003). When
another method that can be used with the partial factors of EC7. used with the partial factors of EC7, the overall factor of safety is
significantly less than recommended in Ciria Report C580 and
5. Conclusions the results can be sensitive to the parameter values used, which
Currently, in the UK, a variety of methods are used for the design makes it essential to check the results for sensitivity to parameter
of temporary retaining walls and, in general, design is at working values and accidental overdig, as well as checking against the
load whereas the structural codes use partial factors. In that it is a output from an existing method of design.

11
Geotechnical Engineering The design of temporary excavation
Volume 165 Issue GE1 support to Eurocode 7
Markham

REFERENCES the International Workshop held in Dublin, Ireland on 31


Bond A and Harris A (2008) Decoding Eurocode 7. Taylor and March1 April 2005. Trinity College, Dublin, Ireland.
Francis, Abingdon, Oxfordshire, UK. Padfield CJ and Mair RJ (1984) Design of Retaining Walls
BSC (British Steel Corporation) (1997) Piling Handbook, 7th edn. Embedded in Stiff Clay. Construction Industry Research and
British Steel Corporation, Scunthorpe, UK. information Association, London, UK, Ciria Report 104.
BSI (1994) BS 8002: Code of practice for earth retaining Puller M and Lee CKT (1996) A comparison between the design
structures. BSI, London, UK. methods for earth retaining structures recommended by
BSI (2002) BS EN 1990: Eurocode: Basis of structural design. BS8002:1994 and previously used methods. Proceedings of
BSI, London, UK. the Institution of Civil Engineers Geotechnical Engineering
BSI (2004a) BS EN 1997: Eurocode 7: Geotechnical design 119(1): 2934.
Part 1: General rules. BSI, London, UK. Schweiger HF (2009) Plaxis Benchmarking. Plaxis, Delft, the
BSI (2004b) NA to BS EN 1997: UK National Annex to Netherlands. See http://www.plaxis.nl/upload/benchmarks/
Eurocode 7: Geotechnical design Part 1: General rules. Benchmark%203%20-%20Embankement%201.pdf (accessed
BSI, London, UK. 27/07/2009).
BSI (2011) PD 6694, pt 1: 2011: Recommendations for the design Simpson B (2005) Retaining wall examples 57 Addendum
of structures subject to traffic loading to BS EN 1997-1: October 2005. Evaluation of Eurocode 7: Proceedings of the
2004. BSI, London, UK. International Workshop held in Dublin, Ireland on 31
Clough GW and ORourke TD (1990) Construction induced March1 April 2005 (Orr TLL (ed.)). Trinity College,
movement of in-situ walls. In Design and Performance of Dublin, Ireland.
Earth Retaining Structures (Lambe P and Hansen LA (eds)). Simpson B and Driscoll R (1998) Eurocode 7 A Commentary.
American Society of Civil Engineers, Reston, VA, USA, Building Research Establishment, Watford, UK.
Geotechnical Special Publication no. 25, pp. 439471. Twine D and Roscoe H (1999) Temporary Propping of Deep
Day RA and Potts DM (1989) A Comparison of Design Methods Excavations Guidance on Design. Construction Industry
for Propped Sheet Pile Walls. The Steel Construction Research and information Association, London, Ciria Report
Institute, Ascot, UK, SCI Publication 077. C517.
Department for Communities and Local Government (2007) A
Designers Simple Guide to BS EN 1997: 2004. Department
for Communities and Local Government, London, UK.
Driscoll R, Scott P and Powell J (2008) EC7 Implications for
UK Practice. Construction Industry Research and Information
Association, London, Ciria Report C641.
Frank R, Baudin C, Driscoll R et al. (2004) Designers Guide to
EN 1997-1 Eurocode 7: Geotechnical Design General
Rules. Thomas Telford, London, UK.
Gaba AR, Simpson B, Powrie W and Beadman DR (2003)
Embedded Retaining Walls Guidance for Economic Design.
Construction Industry Research and Information Association,
London, UK, Ciria Report C580.
Institution of Structural Engineers (1951) Earth Retaining
Structures. The Institution of Structural Engineers, London,
UK, Code of Practice No. 2, CP2.
Karlsrud K and Andresen L (2007) Design of deep excavations in
soft clay. In Geotechnical Engineering in Urban WH AT DO YO U T HI NK?

Environments: Proceedings of the 14th European Conference To discuss this paper, please email up to 500 words to the
on Soil Mechanics and Geotechnical Engineering, Madrid, editor at journals@ice.org.uk. Your contribution will be
Spain (Cuellar V, Dapena E, Alonso E et al. (eds)). IOS forwarded to the author(s) for a reply and, if considered
Press, Amsterdam, the Netherlands, vol. 1, pp. 7599. appropriate by the editorial panel, will be published as a
Kort DA (2002) Sheet Pile Walls in Soft Clay. University Press, discussion in a future issue of the journal.
Delft, the Netherlands. Proceedings journals rely entirely on contributions sent in
Lambe TW and Turner EK (1970) Braced excavations. by civil engineering professionals, academics and students.
Proceedings of the Speciality Conference on Lateral Stresses Papers should be 20005000 words long (briefing papers
in the Ground and Earth Retaining Structures, Cornell should be 10002000 words long), with adequate illustra-
University, Ithaca, New York, 2224 June 1970, pp. 149 tions and references. You can submit your paper online via
218. www.icevirtuallibrary.com/content/journals, where you
Orr TLL (ed.) (2005) Evaluation of Eurocode 7: Proceedings of will also find detailed author guidelines.

12

You might also like