QUALITY PROCEDURAL MANUAL

QUALITY MANAGEMENT SYSTEM


DATE 11 - 03 - 2004 DOC.NO. QP.4.2.3 SHEET 1/2 VERSION 00

4.2.3 CONTROL OF DOCUMENTS


A. GENERAL
i. ISO Cell has established and maintained a procedure to
control all documents and data related to Quality Management System.
ii. All the documents are divided in three groups I, II & III as
described in chart QP 4.2.3-A depending upon the type of document.
iii. The documents of all these groups are identified by a
document numbering system as shown and described in charts QP 4.2.3-B & QP 4.2.3-C
respectively.
iv. All the master drawings of parts /sub-assemblies are kept by
QA and are arranged in files in accordance with QA catalogue system.
v. A master list of document is available with QA under File No.
QP 4.2.1.A.
B. DOCUMENT & DATA APPROVAL & ISSUES:
i. Documents are classified as controlled & uncontrolled
documents depending upon its use. All standards, drawings, system manual/procedural
manual-work instructions and test & review reports fall in controlled documents category
while general formats, dimensional & trouble reports & other fall in uncontrolled document
category. A summary master list of Controlled & uncontrolled documents are attached here
with. (Ref: QP 4.2.3-D) indicating type of Document and authorization to initiate, review
and approve for adequacy prior to issue.
ii. All the original documents are kept by ISO cell and
photocopies of controlled documents are issued to the concern shop/ department by AMR /
MR with stamp Issued by ISO cell.
iii. ISO CELL /PPC/ relevant functional heads are responsible to
ensure that the pertinent issues of controlled & uncontrolled documents are available at all
locations where operations essential to the effective functioning of the quality system are
performed. The record of issues of all documents is maintained by change history master
list QP 4.2.3.A.
iv. All departmental heads where controlled documents are
placed are responsible that unauthorized release or copy of controlled document is not
QUALITY PROCEDURAL MANUAL
QUALITY MANAGEMENT SYSTEM
DATE 11 - 03 - 2004 DOC.NO. QP.4.2.3 SHEET 2/2 VERSION 00

made. All controlled documents are identified by a mark Controlled document. These
documents can only be duplicated after the permission of ISO-CELL.
v. Permission of ISO CELL is required prior to the retention of
any obsolete document for reference/Legal purpose. Such preservations are suitably
identified by Obsolete/Not Valid stamped with Red ink in order to avoid unauthorized
use by ISO-CELL.
C. DOCUMENT & DATA CHANGES:
i. Document & data changes are controlled by ISO CELL & PPC and are reviewed
and approved by same authorities that performed the original review and approval Ref
QP4.2.3 E.
ii. Basic changes in product design/drawing information or work/operation
instructions send by Honda Motor Company, Japan and are received by PPC.
iii. For changes in standard operation procedures quality system procedures, quality
standards and local drawing change requisition form QA-GL-19 is initiated by Section
incharge / departmental head and are examined by QA or Engg. Deptt.
iv. ISO Cell issues the changed document along with change / amendment notice to
PPC, which certainly controls, distributes and publishes all document changes to the
concern locations.
v. a. The control documents are marked with stamp CD indicating Control
Documents
b. Photocopies of certain documents/formats are allowed to be used for recording quality
data, such documents are marked CD/PA, and however any changes in basic formats or basic
contents of these documents do require a formal documents change procedure.

Note: Copy of changed notice authorized by Q.A is attached Change Notice Form QA-GL-18