Date: ______________ MOB: _______________

Agreement: Construction of Apartment Grey Structure (Labor Rate)


MR.________ Plot #:________ Sector: ________ Bahria Town Lahore.

Area 4 Kanal, Agreed Rate of covered area is Rs. 375/ Sq. Feet.

Covered Area of Ground Floor / First Floor is Approximately 17000 Square Feet.
Covered Area Includes Roof, Shade, Pergola, Roof Tank, Roof septic Tank, Under
Ground Tank. Roof Slope will be measured in slope. Measurement of Shade and
pergolas will be in half rate.

1. Following works will be included in this rate:

According to agreement Excavation will be done as per drawing. Construction of


Roof slab as per drawing. Internal and external plaster on ground and first floor.
Laying and fixing of floor tile on roof with charcoal. Kacha of ground and first floor
including brick ballast. Detail of overhead water tank will be as follow:

4.5 inch thick brick wall outer side of tank.


Thermo pole Sheet for insulation
8 inch thick RCC wall

Open floor Kacha and labor of gate is included. Complete measurements shall be
taken after construction of roof. Increase or decrease in measurement will be
compensated on the spot. Clad Stone, Face work and tile/marble also included.

2. Following works will not be included in this rate.

Sanitary and electric work, filling in plot and brick ballasting labor

Signature Contractor____________ Signature Owner____________


Date: ______________ MOB: _______________

Payment Schedule of Ground & First Floor, Bahria Town Lahore

1. Advance of total Amount (10%) __________________


2. On the completion of Foundation (10%) __________________
3. Completion of Wall till Roof (10%) __________________
4. On the day of First Floor Slab (10%) __________________
5. Second floor walls up to 7 feet (8%) __________________
6. Walls up to second floor slab (8%) __________________
7. On the day of Second Floor Slab (14%) __________________
8. Internal plaster first and second floor (10%) __________________
9. External plaster first and second floor (10%) __________________
10. After brick Ballast (8%) __________________
11. After completion of work (2%) __________________

Signature Contractor____________ Signature Owner____________


Date: ______________ MOB: _______________

Payment Schedule of First Floor, Bahria Town Lahore

1. Advance of total Amount (10%) __________________


2. On the completion of Foundation (10%) __________________
3. Completion of Wall till Roof (10%) __________________
4. On the day of First Floor Slab (10%) __________________
5. Second floor walls up to 7 feet (8%) __________________
6. Walls up to second floor slab (8%) __________________
7. On the day of Second Floor Slab (14%) __________________
8. Internal plaster first and second floor (10%) __________________
9. External plaster first and second floor (10%) __________________
10. After brick Ballast (8%) __________________
11. After completion of work (2%) __________________

Signature Contractor____________ Signature Owner____________


Date: ______________ MOB: _______________

Payment Schedule of Basement, Bahria Town Lahore

1. Advance of total Amount (20%) __________________


2. On the completion of Basement Foundation (11%) _________________
3. Completion of RCC Walls (30%) __________________
4. External plaster on RCC walls (7%) __________________
5. On the day of basement RCC Slab (14%) __________________
6. Completion of Internal plasters (9%) __________________
7. After brick Ballast (9%) __________________

Signature Contractor____________ Signature Owner____________