You are on page 1of 39

Risk Assessment of

Capital Projects in Power


Industry using Stochastic
Modelling Technique
Case Study
Sadi Farooqui
Risk Consultant
25th April, 2013
Agenda

Section one : Case Study of Capital based Projects for Power


Industry

Section two : Enterprise Risk Management Solutions for Power


Industry

Section three : Stochastic Modelling Process using @Risk

Section four : Risk Assessment tool to identify key risks

Section five : Risk Management Strategy

PwC 2
Introduction

Each Section will show ....

Understanding of risk assessment tools to manage risk in Capital based


Projects for Power Industry

Application of Risk measuring tools to analyse key risks

Interpreting the results from Stochastic model to identify major risks

Enterprise Risk Management Solutions

PwC 3
Points to Note :

Due to Client Confidentiality Agreements:


No Data will be disclosed
All model outputs are based on hypothetical data

The objective is:


To explore the risk modelling technique
To understand the method of risk assessment based on current
case study
To realise the power of @ Risk software in the market

PwC 4
Section 1 :
Case Study of Capital Based Projects for Power
Industry
Power Industry
Electricity Generation
Greatly dependent on Power Stations
Energy efficiency
Meeting Power demand for current and future economy

Project Management
Define appropriate project life cycle
Managing budget vs CAPEX
Project Phases
Equipment Installation and Resource Management

Risk Management
Risk Review
Identifying, Evaluation and Analysis
Monitoring key activities
Governance and Reporting
PwC 5
Section 1 :

Power Industry : Key Objectives

Efficiency and Success of the Projects


Expand generation capacity equal to current and future electricity demand
Minimal Delays and Budget over-runs
Location of Generation Units
Accessibility of Utilities and Resources
Diversifying Energy mix to provide cleaner energy
Availability of manpower
Project Management Skills
CAPEX vs Budget
Effective Risk Management Framework
PwC 6
Section 1 : Project Phase

1-EVALUATION

2-ENGINEERING

3-CONSTRUCTION & COMMISSION

PwC
7
Section 1 : Main Components of the Project

Component Area covered


Civil Works Waterways, Powerhouse & Access
Tunnels
Hydro-Mechanical Plant Turbine & Electro Mechanical
Plant
Auxiliary Mechanical Plant Auxiliary systems
Electrical Plant Generator Transformers &
Electrical Controls

Require critical Review of each


component !

PwC
8
Section 1 : Project Planning

PwC
9
Section 2 : Risk Assessment
Identifying the risks recording all the potential risks including
political, economic, technical, project management and regulatory risks

Analysing the risks estimating the likelihood or probability of that


risk occurring and the consequence to the project if the risk were to
occur

Risk evaluation classifying the risks into probability/consequence


matrix and identifying the risk that require treatments

Risk treatment for those risks which have been identified as


requiring treatment during the risk evaluation phase, a risk mitigation
plan is developed to treat the risk

PwC 10
Section 2 : Risk Assessment Process

Stochastic
Modelling
Process

PwC 11
Section 3 : Stochastic Modelling Process

1-Collecting data on Events 2-Collecting data on Severity

Application of Convolution Technique Monte Carlo


Simulation
Event Distribution vs Severity Distribution

Obtain a Probability Distribution Curve


using @ Risk Professional
PwC 12
Section 3 : Stochastic Modelling Process

Conduct an Impact Analysis

Analyse Impact of Key Risk Events on Project

PwC 13
Section 3 : Defining Efficiency

PROJECT MANAGEMENT EFFICIENCY

Capital Expenditure % Exceeding Budget

Project Timelines Delay Period

PwC 14
Section 3 : Risk Modelling Data Input

Project Phase Number of delays Cost Over-runs Period of Delay


(Rm) (Days)
A 2 1.2 25
B 3 3 33
C 5 7 17
D 6 4.8 58
E 1 6.32 44

Cost Over-runs per phase = Cost exceeding budget


Delay Period per phase = Actual Completion date Schedule date

PwC 15
Section 3 : Risk Modelling Data Input
Frequency Chart showing the number of delays per phase
14

12

10
Frequency

6 Number of Delays

0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Number of Delays (Days)

PwC 16
Section 3 : Risk Modelling Data Input
Frequency Chart showing the cost over-runs per phase

10

6
Frequency

5
Cost Over-runs
4

0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Cost Over-runs (R'm)

PwC 17
Section 3 : Risk Modelling Data Input
Frequency Chart showing the period of delay per phase

90

80

70

60
Frequency

50

40 Period of Delay

30

20

10

0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Period of Delay (Days)

PwC 18
Section 3 : Risk Modelling Methodology

Step 1: Obtain Best fitting curve for each distribution

Curve A Curve B Curve C


Number of Delays Cost Over-runs Period of Delay

@ RISK version 6

PwC 19
Section 3 : Risk Modelling using @ Risk 6
Curve A

PwC 20
Section 3 : Risk Modelling using @ Risk 6
Curve B

PwC 21
Section 3 : Risk Modelling using @ Risk 6
Curve C

PwC 22
Section 3 : Risk Modelling using @ Risk 6

PwC 23
Section 3 : Risk Modelling using @ Risk 6

PwC 24
Section 3 : Risk Modelling using @ Risk version 6
Calibration

Monte Carlo Simulation

Mean value should approximate Calibrated !

PwC 25
Section 3 : Risk Modelling using @ Risk 6

Convolution

X Curve B
Graph from @ Risk ??

Monte Carlo Simulation Engine - @Risk 6

PwC 26
Section 3 : Risk Modelling using @ Risk 6

PwC 27
Section 3 : Model Output
Value at Risk Model

@ 99% Confidence Level = 110 Rm

PwC 28
Section 3 : Model Output
Delay at Risk Model

@ 99% Confidence Level = 101 days

PwC 29
Section 4 : Risk Assessment tool to identify Key risks

Project Events causing delays


Phase
A Landslides occurring near the construction site
B Services to construction camp not ready in time
C Construction activities causing damage to existing infrastructure
and plant
D Communicable diseases
E Ineffective working relationship between contractors and Project
Managers

Analyse the event to confirm the risk

PwC 30
Section 4 : Risk Assessment tool to identify Key risks

Project Cost Over-runs (Rm) Period of Delay (Days)


Phase

A 6.7 33

B 4.5 56

C 2.6 49

D 1.35 85

E 9.6 35

PwC 31
Section 4 : Risk Assessment tool to identify Key risks

Project Cost Over- Cost per Period of Period of Delay


Phase runs Model Delay per Model
A 6.7 0.06 33 0.33
B 4.5 0.04 56 0.55
C 2.6 0.02 49 0.49
D 1.35 0.01 85 0.84
E 9.6 0.09 35 0.35

Cost per Model = (Cost Over-runs )/ (Value at Risk Model - 99% CL)

Period of Delay per Model = (Period of Delay)/ (Delay at Risk Model - 99% CL)

PwC 32
Section 4 : Risk Assessment tool to identify Key risks

Risk Matrix
Period of Delay per Model

PROJECT @ RISK

PROJECT IN CONTROL! BUDGET CONSTRAINT

Cost per Model

PwC 33
Section 4 : Risk Assessment tool to identify Key risks

Risk Matrix

1
Period of Delay per Model

3 2

Cost per Model

PwC 34
Section 5 : Risk Management Strategy for Power Industry

Point Risk Event Risk Impact


1 Potential slip circles identified in Exceeding the budget and Damage to infrastructure
the geology further delay in the project -Loss in time
-Extensive cost & time for
repairs

2 Delays in rubble removals or Exceeding the budget and Increased volume of traffic
materials availability at site or further delay in the project
works pertaining to running the
plant.

3 Delayed approval by the Further delay in the project No accommodation for


Minister of public works increased staff levels

4 Lack of communication between Exceeding the budget Inadequate water for


project team and station construction and
management commissioning

5 Colliery not having capacity to Exceeding the budget Inadequate coal for
construct new conveyor facility commissioning and operation

PwC 35
Section 5 : Risk Management Strategy for Power Industry

Use the model to obtain the worst case loss


Board to set limits
Risk
Appetite Ensure a monitoring framework exists

Conduct scenario tests


Compare the result to current scenario
Scenario Regular back testing

Place control measures at high risk points


Emphasize regular monitoring and review
Control
Measures Update control vs economic & political cycle

PwC 36
Conclusion
This provides Project Managers in Power Industry :

An effective Risk Framework to control risks on power plant projects


To conduct impact analysis vs risk appetite
A hands on approach to understand how modelling can be used to
identify and monitor key risks
A better control on contractors assigned to complete the project
A risk mitigation solution Proactive approach vs Laid back
approach
The power of @ Risk Software tool to reach the right decision !

PwC 37
If you dont !.......Poor Risk Management !

PwC 38
Thank You !

PwC 39

You might also like