03 MOVIMIENTO DE TIERRA

ID CANTIDAD BASE (m) ALTURA (m) LONGITUD (m) VOLUMEN m3


01.03.01 EXCAVACION DE ZANJAS P/ CIMIENTOS CORRIDOS H=1.4m

EJE A- TRAMO 1 AL 5 1 0.90 3.36 19.75 59.724


EJE B- TRAMO 1 AL 5 1 0.90 3.36 19.75 59.724
EJE 5- TRAMO A AL D 1 9.20 2.2 0.9 18.216

01.03.02 EXCAVACION DE ZANJAS P/ CALZADURAS H=1.4m


01.03.03 EXCAVACION MASIVA C/ MAQUINA 1 11.00 1.28 19.75 278.08

01.03.04 EXCAVAC. DE ZANJA P/ ZAPATAS


zapata 1 1 2.25 1.75 3.50 13.781
zapata 2 1 1.55 1.75 1.80 4.833
zapata 3 1 1.70 1.75 2.00 5.95
zapata 4 2 1.00 1.75 2.45 4.288
zapata 5 2 2.00 1.75 1.00 3.50

01.03.05 EXCAVACION P/CISTERNA


excavacion p/cisterna1 1 1.20 4.02 5.1 24.6
excavacion p/cisterna1 1 2.80 4.02 6.15 69.22
excavacion p/cisterna1 1 3.00 4.02 5.1 61.5

01.03.06 EXCAVACION P/ ASCENSOR 1 1.50 1.60 2.00 5.76

01.03.07 RELLENO Y COMPACTADOC/MATERIAL PROPIO EN ZANJAS


eje A tramo 1- 5 1 0.90 0.90 19.75 15.99
eje D tramo 1- 5 1 0.90 0.90 19.75 15.99
eje 5 tramo A- D 1 9.20 0.90 0.90 7.45

01.03.08 ELIMINACION DE MATERIAL EXCEDENTEC/ VOLQUETE 479.27


eje 5 - tramo A-D 1
EXCAVACION 18.216 m3 * 1.30 = 23.68 -
RELLENO 7.45 m3 * 1.30 = 12.1
11.58 m3 ELIMINACION