GENERAL TECHNICAL SPECIFICATION FOR CONSTRUCTION

Sl.
Particular Detail
No.

R-APDRP is a Govt. of India initiative to renovate and modernize the electricity power
1. Introduction distribution system of urban India in order to reduce the AT&C losses and improve the
quality of power supply to the consumer.

Details of the works involved


Supply, transit storage, erection, testing, commissioning of all major and minor
equipments:

1. 33 kV sub-station
New 33/11 kV Sub Stations.
Augmentation of capacity by replacing the old or by providing additional power
transformer at existing 33/11 kV Sub Stations.
R & M of existing 33/11KV substations.
Installation of Capacitor Banks at 33/11 KV Sub Stations.

2. 33kV Line
New overhead lines and underground cables.
Bifurcation and Reconductoring of existing lines.

3. 11/0.433 kV sub-station
New 11 kV Sub Stations.
Augmentation of existing transformers.
R & M of existing 11 KV sub stations.

2. Scope of work 4. 11kV Line


New overhead lines and underground and overhead cables.
Bifurcation and Reconductoring of existing lines.

5. LT Line
New lines from distribution transformers.
Extension of existing lines.
Reconductoring and strengthening of existing lines.

6. Aerial Bunched Cable


Installation of Aerial Bunched Cables in populated areas.

7. Capacitor Banks
Installation of capacitor banks.

8. Trolley Mounted transformers.


Assembly and supply.

The scope shall cover complete installation of all equipment and accessories
covered under this contract.

All the works indicated above are to be carried out complete in all respect on Turnkey
3. Execution
basis within the specified time.

1. The quantity of material required for these works has been described separately in
the Bill of Quantity (BOQ) annexed with this tender document.
Bill of Quantity
4. 2. Quantities indicated in the BOQ are tentative. The actual quantities shall depend on
(BOQ)
the actual site conditions. Therefore the contractor shall procure the material only
after ascertaining the revised bill of quantity, approved by the CEO. The payment
shall be made accordingly.

Page | 1
Sl.
Particular Detail
No.

3. The additional quantity of items which are mentioned in BOQ shall be arranged by
the contractor at unit rates given in price schedule.

4. However some items which are not mentioned in BOQ, may be required essentially
to complete the works. These items shall also be arranged by the contractor and no
extra amount shall be made on this account.

1. It will be mandatory of the bidders to conduct pre tender survey of the sites and for
that they should visit every proposed 33/11 KV Substation and other works site &
also see the tentative line routes to assess the quantum of work.
Pre Tender Survey
5.
& Site Visit 2. To access the quantum of work before quoting the price bid, tenderer shall contact
respective Superintending Engineer/Executive Engineer of town who is designated
as Chief Executive Officer for R-APDRP.

1. The contractor has to make his own arrangements for procurement, supply and use
of materials as per requirement.

2. In procurement of these items the contractor shall follows all regulations of the
UPPCL/UP govt. / Government of India in respect of import license etc., if he
chooses to procure these from imports.
Procurement of
6. Material and
Further, the contractor shall be responsible for the payment of applicable duties
Equipment
and taxes, port clearance, inland transportation etc.

3. Manufacturers test certificate for these materials shall be submitted and got
approved by Engineer of the contract, before utilization. The materials so supplied
by the contractor shall be guaranteed as per addenda/corrigenda of Form A.

1. This being a Turnkey contract, successful installation, commissioning & integration


with existing system, of those equipment/accessories/material not specifically
mentioned in the specifications, shall be the responsibility of contractor. No extra
payment shall be made for these inherent works.

2. He shall also supply all other associated equipment/ material/accessories not


specifically mentioned in this tender specification but are required for successful
and trouble free operation of the executed work as a whole. For that no extra
payment shall be made to the contractor.
7. Accessories
3. This also includes insulators, cross arms, hardware, jumpers, cable racks, GI
strips, junction boxes, lugs, clamps, connectors, earthing rods, hardware fittings,
angles and channels and all other unforeseen items whose prices are not indicated
in the price schedule.

4. Contractor shall be supplying suitable size jumpers/ droppers/any other item,


needed for connecting equipments with existing equipments.

1. The electrical equipments and materials required during erection should be of high
standard. Technical features of these equipments and materials must conform to
the technical specification given in this bidding document. Wherever the same is
not specified, it must conform to the relevant I.S for that material.
Technical
8. 2. Materials conforming to other international standards, which ensure equal or higher
Standards
quality than the standards mentioned above, shall also be acceptable. In case the
bidders who wish to offer materials conforming to other standards, salient points of
difference between standards adopted and specific standards shall be clearly
brought out in the respective schedule. Four copies of such standards with
authentic English version shall be furnished along with the offer.

Page | 2
Sl.
Particular Detail
No.

3. Whenever a material or an article is specified or described by the name of a


particular brand, manufacturer or trade mark, the specific item shall be understood
as establishing type, function and quality desired. Products of other manufacturers
may also be considered, provided sufficient information is furnished, so as to
enable the owner to determine that the products are equivalent to those
mentioned.

4. Materials supplied/used shall conform in all respects to the relevant Indian


Standard Specification with latest amendments there to.

Title IS No.
1. Cement IS 269
2. Steel IS 6003/1970
3. Fasteners IS 6639/1972
4. Concrete mix IS 1343
5. RCC IS 456
6. Cable laying and jointing IS 1255

5. Installation work pertaining to equipment, cabling etc should be in accordance with


the applicable standards, safety codes etc.

The major equipments/material supplied by the contractor or its sub vendor has to be
got inspected and tested by the Engineers of the Corporation for its quality and quantity
before dispatch to the work site.

The contractor shall have to follow the procedures laid down with this tender
specification or any other procedure intimated later on.

Rest of the equipments/ materials shall be checked at site for dimensions, weights,
finish and quality. For this purpose the contractor shall have to provide general
measuring equipments like steel tape, vernier calipers, screw gauge, tong tester, earth
resistance tester, 2.5 KV meggar etc.

The following items shall be inspected/tested at the manufacturers premises before


dispatch:
1) Transformers
2) 33 kV Lightening Arrestors
3) 33 kV VCB
Quality Assurance, 4) 33 kV control panels
9. Inspection & 5) 11 kV VCB panels
Testing (QA&I) 6) 33 kV CT
7) 33 kV PT
8) 33 kV Isolators
9) All types of power cables
10) TPMO
11) D.O. fuse set
12) Distribution Pillar Box
13) TVMs
14) Aerial Bunched conductors
15) ST Poles
16) Conductors
17) Transformer trolley & connecting system
18) Battery & Battery Charger
19) 11 kV Capacitor Banks & panels
20) Metering Cubicles
21) 11 kV outdoor type combined CT- PT metering unit with meter box.
22) GI & GSS wire
23) Distribution Boxes/Kiosks used for tapping the connection from Aerial Bunched

Page | 3
Sl.
Particular Detail
No.
conductor.
24) LT Distribution Pillar Boxes and fuses
25) All other items required for completion of work

The approaches to site of work, if necessary, shall have to be made by the contractor at
10. Approaches his own cost so as to get easy access for both personnel and equipments.

The Contractor has to make use of the water supply if available at any of the substation
site for construction purpose. However transport of water from the source to the working
area will be contractors responsibility.
It is essential that the contractor shall prevent misuse of wastage of water at all time,
Water And Power failing which necessary charges will be collected from the contractor. In case, water is
11.
Supply not available at site, the contractor has to make his own arrangement and any extra
claim on account of this will not be entertained.
Power required for construction will be made available on demand at one point for
which payment shall be made by the contractor.

1. The contractor shall himself arrange all men & material, all constructional T & P
and any other material required for successful and speedy execution of the job
within the prescribed time
2. All tools, welding equipment, crane, scaffolding, rigging materials, ladders,
consumables, hardware etc. required for installation shall be arranged by the
Men, Material &
12. contractor.
T&P
3. The contractor shall provide experienced, technically qualified, and supervising
Engineers for supervision. The contractor shall engage only competent skilled
workers.
4. The contractor shall observe strict adherence to the existing labour laws.

1. It shall be the responsibility of the contractor to store, move/transport from


stores/storage yard etc., relevant items and accessories to the place of installation
wherever necessary he will assemble all parts of equipment. In accordance with
Site Storage/
13. the specific installation instructions as directed by Site Engineer.
Transportation
2. The stores should be dismantled and site cleared after the work is completed

1. The contractor shall be responsible for overall co-ordination with internal/external


agencies, project management, training of owners manpower etc. as required.

14. Co-ordination 2. The supplier/ contractor shall open his office in that town and shall co- ordinate with
concerned authorities of respective DISCOM for all the matters pertaining to the
works.

1. All the works covered under the scope of the tender shall be done in accordance
with the norms defined in urban construction manual of UPPCL, unless the same is
not specifically defined in the specification or with the provisions of Indian Electricity
Rules/Acts/Other Government Rules/Regulations as prevalent at the time of
execution of the job/work.

2. Installation shall be carried out strictly in accordance with the approved drawings
Erection, Testing Modifications, if any, required to suit site conditions, shall be carried out only with
15. and the prior approval of the Site Engineer. All such changes shall be incorporated in
Commissioning As built drawings to be furnished by the contractor.

3. Responsibility for successful installation of other equipment accessories,


purchased but not mentioned specifically above, and their commissioning shall be
on contractor. For all such items the contractor shall be supplying all material and
equipment required to accomplish the job complete in all respect.

Page | 4
Sl.
Particular Detail
No.
4. Installation work pertaining to equipment, cabling etc should be in accordance with
the applicable standards, safety codes etc.

5. The contractors shall themselves be responsible for timely arrangement/


procurement of all the raw materials required for the manufacture of all tendered
items by them/ their and / or by their vendors.

6. While Repairing & Replacing the equipment, if any other equipment gets damaged
due to negligent handling of the contractor the same shall be replaced by the
contractor at his cost to the owner satisfaction.

He shall be responsible for dismantling of defective equipments, there proper


handling and shifting.

Also he shall hand over the old & dismantled equipments/ material to the
purchasers local stores or other sites as per instructions of the CEO for which no
extra payment shall be made.

7. All charges on account of damages/losses/claims/thefts etc. involved under the


conditions laid down above shall be borne by the contractor. Its cost shall be
recovered from his bills /security deposits /other assets.

8. In order to avoid hazards to personnel moving around, the equipment such as


Transformer, Capacitor Banks, Switchgears etc. if required to be kept charged after
installation till their commissioning, shall be cordoned off by suitable barriers to
prevent accidental injury to personnel moving around.

9. Where the equipments/ assemblies are supplied in more than one part, the
contractor shall make all necessary mechanical and electrical connections between
the sections. The contractor shall also do necessary adjustment in the alignments
required for its proper operation.

10. Care shall be taken in handling instruments relays and other delicate devices
where instruments and relays are supplied separately they shall be mounted only
after the associated switch gear/control panels are erected and aligned.

11. Precaution: The contractor shall exercise all possible care to avoid damage to
public utilities e.g. water/ sewage pipes telephone and power lines/cable already
existing. In case of any accidental damage during the work, the contractor shall be
responsible to repair/replace the same at his own cost, and shall ensure that the
purchaser is not put to any loss.

12. The contractor shall have to provide proper lighting, barricading, signboards etc. at
the work site as a necessary precautionary arrangement to avoid accident/
damage/ losses to the public /utilities/properties.

13. Site Solution: It may be possible due to some reasons or others that it would not
be possible to work as per the procedure. In such case/cases, the solution to the
problem shall be achieved by the CEO with the consultation of contractor, and the
contractor shall work as per procedure proposed by the CEO. Such cases shall in
variably be informed to the engineer of the contract for which no extra payments
shall be made.

14. Space Constraints: While executing the job it is quite possible that some of the
specified work may not be carried out due to space/land/ other technical constraints
etc. In such case the concerned MD of DISCOM], if required, may divert this work
at some other site or cancel the left over portions of work.

15. The contractor shall ensure that the equipment under erection as well as the work

Page | 5
Sl.
Particular Detail
No.
area and the site are kept clean to the satisfaction of the Engineer. In case, the
Engineer is not satisfied about the cleanliness he will have the right to carry out the
cleaning operations and expenditure incurred in this regard will be to contractors
account. Packing cases and packing materials shall be promptly cleared from sites.

The contractor shall also be responsible for constructing all the plinths &
foundations and other switchyard structures & equipments. In case of any
16. Civil Works modification required for these at existing 33/11 kV substation, the contractor shall
carry out the necessary work. The payment for all these activities shall be governed
by the price schedule under the head ELECTRICAL WORKS.

1. The complete work mentioned in the specification shall be completed within


completion period mentioned in Special Condition of Contract from the date of
awarding the contract.

The survey of each and every site of the work shall be completed within fifteen
days time by the contractor.

2. The contractor shall estimate the actual quantities of equipments / material required
to complete the work to the full satisfaction of respective DISCOM and as per
Urban Construction manual of UPPCL and get it approved from the CEO.

3. The contractor shall submit the PERT chart for complete execution of work at the
time of signing the contract agreement as per completion schedule of contract.

Schedule of work This PERT chart shall include all the activities such as design, engineering,
17. completion/ PERT approval of drawings and vendors, procurement, manufacturing, erection, testing
Chart/Bar Chart and commissioning.

4. After placements of the orders with the manufacturer, the delivery of equipments
should be so regulated that it is received at the site nearly 15 days prior to its
erection.

5. The delivery of material/equipments being received at site, should be strictly


regulated with the schedule of its erection.

6. The payment of material shall be justified by the CEO with the physical progress of
the corresponding work.

7. Precaution should be taken, not to increase the inventory of the owner without
actually utilizing it at the site for a long time.

Sl.
Particular Detail
No.
18. 33kV Sub-station New 33/11kV Sub-station
Design, engineering, supply, transit storage, supply, erection, testing, commissioning of
18.1 Scope
all equipments of a new 33kV sub-station of specified capacity on turnkey basis.
All the equipment described, various technical specifications annexed hereafter shall
Drawings and
have to be erected as per layout plan & drawing to be submitted by the contractor and
18.2 Layout Plan
duly approved by the CEO.

Page | 6
Sl.
Particular Detail
No.
The drawing of earth mat, earthing system, the transformer plinths, the foundations of
all equipments & their support structure are to be approved by CEO and the
construction work shall be taken up by the contractor accordingly.

The layout and placement plan of equipments in switchyard and in the control room is to
be prepared by the contractor as per actual space available at site and also get it
approved by CEO.

1. Chemical Pipe earthings are generally used for earthing of equipments at 33/11 kV
substations.

2. Similar earthing will be used in station transformer.

3. All accessories associated with transformer and mounted away from the main tank
18.3 Earthing
shall be connected to the station earthing grid at minimum two points.

4. Electrode earthing shall be connected with the substation earth mat.

1. Designing the earth mat of the switchyard including diameter of the MS Rod,
spacing of the rods etc so that the specified value of the ground resistance (as per
ISS/EEE) in no case exceeds 1 ohm.

2. Laying of proper earth mat at the switchyard as per UPPCL standard, providing
pipe & electrode type earthing, connecting of these earthing to the equipment e.g.
transformer, LA, CTs, PTs etc. as per standard practice shall be the responsibility of
the contractor.

3. The earth mat & earthing work shall include laying mesh, fabrication and driving of
2500 mm. long 32 mm diameter earth electrodes, connecting the same to the earth
mat points of all the equipments installed in the outdoor as well as indoor and the
fencing. All the jointing shall be done by electric arc welding.

4. The earth mat mesh made of M.S. Bar shall be laid crisscross as per standard
practice of RESSPO applicable to the particular site and as per directives of
representative of respective DISCOM.

5. The earth mat mesh should at least be 0.75 Mtr. below the make up ground plinth
level of switchyard. The earth electrodes shall have to be fabricated and driven into
Earthing
18.4 the ground upto its full length in the manner that its top, is at least 750 mm below the
Switchyard
make up ground / plinth level. These electrodes shall be properly jointed with earth
mat mesh by way of electric arc welding.

6. All the structures of the equipments bus bar gantry and body of the
transformer shall be connected through M.S. G.I. strip and connected to the earth
mat mesh by electric arc welding.

7. This M.S./ G.I. strip shall have to be suitably shaped, bent and jointed as per
directive of site Engineer of respective DISCOM to give uniform shape above the
ground level.

8. The minimum length of contact of the earthing strip and the equipment /
structure should be 100 mm. in length.

9. The power transformer neutral shall be earthed through independent pipe in pipe
type earthing and also jointed independently with the earth mat through M.S./ G.I.
strip duly welded. These electrodes shall then be connected to independent M.S. /
G.I. strip riser over M.S. Angle Iron support duly grounded and connected to neutral
of the transformer through independent flexible copper bound of sufficient current
capacity. The angle and M.S./G.I. strip required for transformer neutral earthing shall

Page | 7
Sl.
Particular Detail
No.
also be bent / welded in proper shape as per directive of the site Engineer.

10. Transformer tank shall be earthed at two places to the station-earthing grid.

The transformer neutral terminal shall be connected to the horizontal extension of


the vertically grouted galvanized M.S. steel angle through flexible copper bound
strip of adequate cross section and size.

The vertically grouted angle frame in turn shall be solidly connected & welded to two
pipe earth electrodes in the earth pit providing adequate level of earthing i.e.
earthing resistance below prescribed level.

All accessories associated with transformer and mounted away from the main tank
shall be connected to the station earthing grid at minimum two points.

11. The fencing shall also be connected with the main earth mat mesh by means of
M.S. / G.I. strips at an interval of 10 Mtrs. (Approx.). After making joints / welding,
each joint shall be protected by coating the weld with molten bitumen.

1. All the switchyard structures shall have to be fabricated as per RESSPO manual of
drawing or firms drawing approved by respective DISCOM.

If required, modification in the structure to match with the related equipment and
ground level shall have to be carried out by the contractor.

Any special structure if required, shall also be fabricated as per directive of the site
Engineer of RESPECTIVE DISCOM.
Switchyard
18.5 The fabrication includes cutting, bending, drilling and welding as per requirement
Structure
and includes all associated incidental activities.

No extra payment shall be made for all such fabrication work.

2. The 11 KV cable joint support structure is to be fabricated by the contractor for


connecting the cable to the transformer terminals in case of 10 MVA transformers
this structure shall be designed to hold two nos. 3 X 300 Sq. mm. Size XLPE cable
with joints

1. 33kV main bus bar shall be of Panther conductor while the dropout jumper shall be
of Dog conductor.

2. The stringing and sagging of 3 Phase bus bar in the switchyard shall be done by the
18.6 33kV BUS BAR contractor as per approved drawing.

3. ACSR panther conductor, all fittings, Tee, P.G. clamps insulators; stays are to be
arranged by him without any extra payment.

1. The suitable size of aluminum connectors/ Bi-metallic connectors shall be used for
making connection to the equipment terminals.

2. The surface of the clamps shall be smooth with all edges rounded off. The Tee &
P.G. connectors shall be conventional type extra heavy-duty class tested.
Bus-Bars
18.7 Connectors and
3. The connectors shall have maximum contact surface with the conductor, extremely
Clamps
low and stable contact resistance and minimum power loss.
4. These shall maintain constant force within the connection for the life of the
connector/ clamp while compensating for thermal expansion or grip and increased
life span.

Page | 8
Sl.
Particular Detail
No.
5. An Oxidation inhibitor shall be applied to the surface thereby elimination of oxidation
of metallic surface.

6. The jumper T-clamp is required for connection of drop down type single conductor
jumpers to bus bars and equipment.

7. The normal current carrying capacity of clamp shall not be less than that specified in
the specification.

8. These connectors shall be used instead of the conventional PG and Tee clamp and
shall be installed by powder actuated tool using cartridges with valid explosive
license issued by Govt. of India /State Govt.

9. Clamps shall be corona free and shall carry an overload of at least 20% over the
rated current of 250 A.

All the steel structures shall be painted with Aluminium paint as per standard practice.
18.8 Painting
The earthing strips shall be painted with green enamel paint.

The battery and battery charger along with D.C. and A.C. distribution board are to be
Battery & Battery erected in the sub-station control room and are to be tested and commissioned.
18.9
Charger
All A.C. and D.C. wiring for the same is to be done by the contractor.

All the control and switchgear panels are to be properly grouted, erected at the
prescribed locations in the control room as per approved layout.
Control Panels and
18.10 All the A.C. and D.C. connections are to be made complete in all respect.
Switchgears
All the functions / system provided in these panels should be tested and
commissioned by the contractor.

The contractor shall be responsible to connect all protection and indicating devices of
the transformer the control / relay panel in the control room including assessment of
requirement of various size cables, supply and laying of required size standard make
copper control cables properly dressed and ferruled.
18.11 Control Cable
While carrying our settings of various protection schemes, contractor shall be
responsible for protecting cables against short circuits and earth fault etc. by suitably
designing & placing necessary protections.

The control cable trench and power cable trenches shall be constructed separately
providing proper cable racks.

Control Cable The control cable trenches shall be 300 mm. deep. It should be 150 mm. wide.
18.12
Trench These control cable trenches shall have cable-supporting racks made of M.S. strips.
These trenches shall be covered with welded frame type trench covers of 500-mm.
length. The size of control cable to be laid by the contractor shall be 2 core, 4 core and
6 core of minimum 2.5 sq. mm. cross section

Power Cable & The 33 KV and 11 KV 3 core XLPE power cable shall be governed by the detail
18.13
Termination Kits technical specification given in tender document.

Page | 9
Sl.
Particular Detail
No.
The terminations of XLPE power cable shall be properly jointed using standard make
heat shrink type termination kits which are to be supplied by the contractor himself.

Station transformer shall be supplied, erected and commissioned on the double pole
structure of 9.0 mtr. or on the plinth of 33/11 kV substation in switchyards.

The work includes supply & erection of 11/0.4 KV 63 kVA transformer, double pole,
channels, angles, GI pin with insulators, ladder frame, clamps with packing pieces,
nuts, bolts off size including all the materials and the grouting, plinthing, painting etc.
of double pole.

The transformer shall be energized through 11 kV 3x35 sq.mm. XLPE cable


Station
18.14 emanating from 11 kV station transformer panel. One outgoing cables of 3.5x70
Transformer
sq.mm. shall be used to connect to AC distribution board. Other Ckts. As required
shall be taken from there.

The cost of all the above mentioned work shall be covered under the relevant column
of the price schedule.

Installation of 11 kV TPMO & DO fuse set shall be made, as per the prices quoted for
these items in the price schedule.

The construction of main control room building is also included in the scope of work
under this tender. The control room building shall be constructed as per norm of
respective DISCOM. The land for switchyard shall be made available by respective
DISCOM. The contractor shall be responsible for carrying out civil work in respect of
Control Room
18.15 plinths, foundation & support structure related to the equipments, and construction of
Building
cable trenches, the cost of which shall be included in the cost of equipment quoted by
the contractor.

Note: What about boundary and approach road etc?

The control room and the switchyard are to be illuminated adequately to have clear
visibility at every point.
1. The switchyard and control room lighting shall be governed by detailed technical
specification given in the tender document.

2. Contractor shall be responsible for calculating the number and type of light fittings
required for achieving sufficient visibility after taking control room and switchyard
size in consideration. The number and type of fittings shall be decided based on the
switchyard area to be illuminated in consultation with Purchaser.

18.16 Lighting 3. Contractor shall be responsible for supplying light fittings and fixtures, laying and
terminating of the suitable power cable from the distribution board to the respective
light fittings.

4. In case a junction box is to be installed in the switchyard, its supply, erection


including terminal blocks shall be to contractor's account.

5. In control room, the illumination fittings and fixtures shall be so located that sufficient
illumination is available in and around C&R panels.
6. The concerned CEO has discretion to divert some of the lighting fixtures to other
substation site if so required. The contractor shall execute the work accordingly.

18.17 Substation T& P Supply of the following set of T&P (ISI marked if applicable) at each of the 33/11 KV
substations mentioned in BOQ: One sample of these T&P shall be submitted before

Page | 10
Sl.
Particular Detail
No.
supply to respective DISCOM for approval. Only after getting the approval of the
sample T&P shall be supplied.
i. Chain pulley blocks 4 Ton capable of lifting upto ten feet. -1 number
ii. Tirfur capable of pulling 5 Ton load.-1 number
iii. Hand Gloves free size- 2 sets
iv. 1 no. Tool Box carrying: pliers of different types, set of various screw drivers,
wire stripers, wire crimping tool of various sizes (4 sq. mm. to 400 sq. mm.),
slide wrench, nose plier, ratchet spanners of various sizes, power operated drill
machine, power operated grinders, box spanners, various sizes and type of
files, hexas. Also one no. each of the following instruments of standard make
Motwane/ Meco/ Riken etc.

a) Motorized cum manually operated 5 kv megger & digital multimeter


b) Tong tester capable of measuring both DC and AC voltages upto 0.5%
accuracy. It should measure A.C. upto 1400 Amps. and its loop size should
be large enough to insert 100 mm. dia cable in it comfortably.

v) Torch of three cells. 2 numbers.


vi) Set of drill bits for metal and concrete 1 set
vii) Slings of 2 meter and 6 meter sizes capable of carrying 5 ton load. 1 set.

All the equipments in the yard and control room, including oil filled equipments, are to
be protected by portable fire extinguishers. These fire extinguishers are to be put at
appropriate locations in and around control room and switchyard at specified
locations. The quantities of portable CO2 and DCP type fire extinguisher to be
Fire Fighting installed at one substation shall be governed by detailed technical specification given
18.18
System in the tender document. The payment for the same shall be made as per price
schedule. The contractor must quote the refilling charges of the extinguisher in the
schedule of spares annexed in the tender documents.

4 baskets filled with stand and all baskets filled with sand

R&M OF EXISTING 33/11 KV SUB STATION

Sl.
Particular Detail
No.
19. 33kV Sub-station R&M Of Existing 33/11 kV Sub Station
1. Design of substation and R&M of associated electrical & mechanical auxiliary
systems includes preparation / modification of single line diagrams and electrical
layouts, erection key diagrams, electrical and physical clearance diagrams, design
calculations for Earth mat and Direct Stroke Lighting Protection (DSLP), Bus Bar,
control and protection schematics, wiring and termination schedules, civil designs
and drawings of foundation, repairing and maintenance of cable trenches and
galleries etc., fire fighting, indoor and outdoor lighting/illumination and other relevant
19.1 Scope
drawings and documents required for engineering of all facilities.

2. Replacement of missing / damaged items like Circuit Breakers, Isolators, Instrument


Transformers, Lightening Arresters, associated / required foundations and support
structures, Control Panels, control cables, 11 KV VCB, 11 KV Cables, 24 volt
Battery System, Fire Fighting Equipment, Earthing, Lighting, Yard Fencing, Bus Bar
extension etc.

Page | 11
3. The erection of equipments / accessories in the existing sub-station / bays, either
supplied by the contractor or by owner/employer, with suitable modification on
existing foundation / structures, if required.

For erection of equipment involving new foundation and structure also, the payment
shall be governed as per the rates indicated in BID PROPOSAL SHEET.

The number of items and places where the equipment need to be installed are only
tentative and are given in BOQ.

4. Matching of alignment and positioning of the new equipments with the substation
layout so that they may not foul with other structure.

5. Re-orientation of Bus Bar.

6. All the connections to bare conductor bus bar, as per requirement, including
necessary clamps and connectors and their fixing / erection.
7. Supply of suitable size jumpers/droppers needed for connecting the equipment with
existing equipments in the bay.
8. Proper earthing of all the equipments and their support structure and connecting
them to the main earth mat so as to meet overall safety criterion.

CAPACITY AUGMENTATION OF 33/11 KV SUB-STATIONS

Sl.
Particular Detail
No.
20. 33kV Sub-station Capacity Augmentation of 33/11 kV Sub-stations
1. By replacing existing transformer with higher capacity transformer.

i. The new transformers are to be preferably accommodated at the same foundation


where previous transformer existed or new plinth to be constructed by the contractor
at the place having appropriate load bearing capacity.

ii. Checking of the physical dimension available, at each existing sub-station and
design the 33/11 kV transformers accordingly so that it can fit into the available
space (of older transformer). Contractor must also ensure that all statutory
20.1 Scope
clearances are met in case the design of the transformer tank is changed.

iii. Removing of existing lower capacity transformer from its foundation and
commissioning the same at another location in the circle as required.

iv. If transformer is transported without oil then assembly & erection of the transformer
including its accessories, filling of oil into the transformer which was separately
transported to site in drums after proper filtration & testing of the oil.

1. Before taking up of the Augmentation job of 33/11 kV substation, contractor shall


discuss with the engineer to finalize the sequencing of the taking up of
augmentation of capacity of 33/11 kV transformers.
Sequencing of
20.2
work
2. The preferred sequence shall be to start with the augmentation exercise at the
places where new 10 MVA, 33/11 kV transformers are to be installed.

Supply and proper laying the power cables from control room to the transformer (if
they are non-existent or damaged) either through existing cable trenches or the
20.3 Power Cable
trenches to be constructed by the contractor.

Page | 12
Sl.
Particular Detail
No.

1. To develop the design & drawing of foundation and cabinet for housing all control &
relay equipment and to obtain the approval for the same from owner.

2. To access, requirement of control cables (various sizes) its supply and laying
required for extending it from C&R panel to various equipments. For that whatever
hardware contractor envisages including terminal blocks and cable glands, shall be
in the scope of contractor.
Control Relay
3. C&R panel should use 24 Volt as control and protection auxiliary voltage. Contractor
20.4 Panel
shall be responsible for supplying, laying and commissioning of control cable from
& Control Cable
24 Volt distribution panel to C&R panel.

4. To arrange 240 volt auxiliary supply of 240 volt 50 Hz, for illumination, lighting and
heating of C&R panel from the AC distribution board including supply of cables &
connectors etc.

5. Commissioning of the C&R panel including interlocking with isolator, remote


indication, open and close operation.

1. Supply and laying of suitable sized power cable, its clamps and connectors in order
to connect battery and battery charger to DC distribution board.

2. Battery bank and battery charger of 24 Volt 200 AH capacity.


24 Volt DC Battery
20.5 and Battery 3. Supply, laying and commissioning of 1-Phase 240 volt. Power cable from AC
Charger distribution board to battery charger for Power input to the Battery charger.

4. Use of existing trench if available or else to make way of laying power cable to
battery charger.

1. Design and drawing of modules including their foundation drawings, for fixing the
modules (both I/C & O/G) in the module space, or in the space created by the
contractor.

2. Alignment of the existing bus bars and the proposed I/C and O/G modules of the
new Circuit Breakers must match the existing bus bar and switchgears.

3. Supply and laying adequate sizes of 3 phase 33kV XLPE cable, required for
extending the 11 kV supply from 33/11 kV transformer output to 11 kV switch gears
and from 11 kV switch gears to the first double pole of the feeder line. The cabling
work includes supply of heat shrink type termination kits and their jointing at either
11kV I/C and O/G
end as mentioned in BOQ/ Annexure.
20.6 Circuit Breaker
Modules
4. Contractor may use existing trench, if available, else he may have to make separate
trench for laying 11 kV power cables required for I/C and O/G modules.

5. Supply and laying of 240 Volt 50 Hz 1-Phase auxiliary supply cable which shall be
used for closing circuit of 11 kV circuit breakers. Arrangement of this supply from
AC distribution board.

6. Laying and connecting 24 Volt supply from DC distribution board to the respective
I/C and O/G modules, which shall be used for operation of the respective Circuit
breakers.

Page | 13
Sl.
Particular Detail
No.

11kV Las are to be erected on double poles of outgoing feeders. They shall be
Lighting Arrestor
20.7 preferably mounted, where the 11kV cable is connected to overhead line.
(11kV Rating)
The above LAs shall be properly earthed by pipe type earthing.

1. All the equipments in the yard and control room, including oil filled equipments, are
to be protected by portable fire extinguishers. These fire extinguishers are to be put
at appropriate locations in and around control room and switchyard.

2. Calculation of the number and type of fire extinguishers required for covering fire
hazard of control room, switch yard, oil filled equipments and cable trenches shall
be approved by CEO.
Fire Fighting
20.8 3. Supply of fire extinguisher for taking care of different category of fire hazards
System
4. Supply of the fire extinguisher shall be paid as per the provisions of the BID
PROPOSAL SHEET. For refilling the extinguishers the payment shall also be
governed as per the rates indicated in BID PROPOSAL SHEET.

The Portable CO2 and DCP type fire extinguisher shall be governed by detailed
technical specification given in the tender document.

1. The control room and the switchyard are to be illuminated adequately to have clear
visibility at every point.

2. To calculate the number and type of light fittings required for achieving sufficient
visibility after taking control room and switchyard size into consideration.

The number and type of fittings shall be decided based on the switchyard area to be
illuminated in consultation with CEO concerned.

3. In case contractor wishes to use existing mountings (if found any), in that case if
20.9 Lighting
any modification / alteration required shall be to contractors account.

4. Supply of light fittings and fixtures, laying and terminating of the suitable power
cable from the AC distribution board to the respective light fittings.

5. In case a junction box is to be installed in the switchyard, its supply, erection


including terminal blocks shall be to contractors account.
6. In control room, the illumination fittings and fixtures shall be so located that sufficient
illumination is available in and around C&R panels.

1. Designing of the earth mat of the switchyard including diameter of the MS rod,
proposed to be used, spacing of the rods etc so that the specified value of the
ground resistance (as per IS/IEEE) can be achieved. The value of earth mat
resistance in no case should exceed 1 ohm.
In case the desired results are not achieved, a new earth mat after removing older
earth mat has to be laid.
Earthing of the
sub-station
Cost for the same shall be borne by contractor.
20.10
2. Designing of the electrode earthing of the LAs, PTs Lightening Mast & Pipe
electrode for power transformer and shunt capacitor keeping in view the specified
value of the electrode earth resistance and to connect the electrode earth pits with
the switchyard earth mat.

3. On checking of the earth pit resistance of the transformer, LAs and PTs., in case the
pipe type earthing resistance comes out to be more than 4 ohm, a new pipe type

Page | 14
Sl.
Particular Detail
No.
earthing of the above mentioned equipments and its connection to station ground
mat has to be done.

4. The supply and laying of new as well as strengthening of the existing earth mat shall
be paid as per the provisions of the BID PROPOSAL SHEET.

5. To achieve the target value of the ground mat resistance.

6.. In view of the safety requirements, electrode type earthing for transformers, LAs,
PTs and shunt capacitor bank shall be done first before taking up the earth mat
work.

20.11 Sub Station T&P As given at 18.17 above

1. All civil works like foundation & support structure related to the equipments being
supplied. In case of existing civil works at 33/11 kV substation, any change /
modification felt necessary by the engineer, shall be got executed and the cost for
the same shall be included in the equipment price quoted.

20.12 Civil Work 2. The older construction including debris, wherever required has to be removed.

3. Designing of the all such civil works including construction drawings which are to be
approved by the owner.

4. RESSPO/Urban schedule for civil work will be applicable

Bus-bars,
20.13 Connectors and As given at 18.7 above
clamps

Page | 15
GENERAL SPECIFICATION FOR CONSTRUCTION OF
33Kv/11Kv/COMPOSITE/LT LINES)

Sl.
Particular Detail
No.
1. Before taking up the line construction work the contractor shall verify the
proposed line route by jointly surveying with the representative of the concerned
CEO.

2. The exact spotting of the single and multiple structures have to be finalized by
the contractor in consultation with the concerning CEO. Topographical maps of
the survey of India shall not be provided for this purpose.
Survey and Pole
1.
Spotting 3. The final schedule indicating location of poles, angle of deviation, road crossing
and other details shall be submitted for the approval to the concerned CEO/ S.E.
(D), EUDC/EDC.

4. After approval the contractor shall submit four more sets of the approved reports
along with one set of reproducible of final profile drawing to the Engineer of the
Contract for record purpose.

1. The span of the line for 33kV and 11kV shall be 50 to 60 M.

2. Span 2. Span in case of composite line (11kV and LT), shall not exceed 60 mtr.

3. Span in case of LT line shall also be 50 mtr.

Right of way and necessary way leave clearance shall be arranged by the contractor
on behalf of respective DISCOM in accordance with the work schedule. The
3. Right of Way contractor will arrange to secure way leave and Right of way in the restricted area
with the help of RESPECTIVE DISCOM. Any expenditure to be incurred shall be
borne by the contractor.

At all important road crossing the poles shall be fitted with Disc type insulator but the
ground clearance at the roads under maximum temperature and in still air shall be
4. Road Crossing such that even with conductor broken in adjacent span, ground clearance of the
conductor from the road surface will be as per IE rules1956 as amended from time to
time and proper cradle guarding to be provided across the road.

At the time of route survey, the railway crossings shall be finalized as per the
regulation laid down by the Railway Authorities. The following are the important
features of the prevailing regulations (revised in 1987):

(i) The crossing shall normally be at right angle to the railway track.

5. Railway Crossing (ii) No crossing shall be located over a booster transformer, traction switching
station, traction sub- station or a track cabin location in an electrified area.

The approval for crossing railway track shall be obtained by the Contractor from the
Railway Authority on behalf of respective DISCOM. The letter to this regard shall be
obtained by the Contractor from officer concerned of respective DISCOM and
expenditure thereof will be paid by the contractor.

Power Line Crossing Where line is to cross over another line of the same voltage or lower voltage.
6. and Tele Provisions to prevent the possibility of its coming into contact with other overhead
communication line lines shall be made in accordance with the Indian Electricity Rules, 1956 as amended

Page | 16
Sl.
Particular Detail
No.
crossing from time to time.

All the works related to the above proposal shall be deemed to be included in the
scope of the contract except in case, if modifications are required in the line below or
above, the line being crossed. In such cases, work shall be done on the conditions
agreed upon.

The angle of crossing shall be as near to 90 degree as possible. However, deviation


to the extent of 30 degree may be permitted under exceptionally difficult situations.

Also, in the crossing span, power line support will be as near the telecommunications
lines as possible, to obtain increased vertical clearance between the wires.

When the angle of crossing has to the below 60 degree the matter will referred to the
authority in charge of the telecommunication system. The contractor shall obtain the
letter from of respective DISCOM and permission of telecommunication authority shall
be obtained by the contractor on behalf of respective DISCOM.

Methods ensuring that normal services may not be interrupted nor damage caused to
property shall be used during stringing operations, where roads, channels,
telecommunication lines, power lines and railway lines have to be crossed.

However shut down shall be obtained when working at crossings of overhead power
lines.

1. While constructing the 33 & 11 kV lines on roadside having inadequate electrical


clearances between pole & buildings the feasibility of fixing projected bracket
fabricated by suitable size of M.S. Angle & Channel with its supporting bracing on
the existing poles may be explored. In case it becomes feasible, the line may be
erected on fittings & insulators to be fitted on such brackets.
The cost of these brackets shall be charged as per the prices quoted in the
relevant column of price schedule.
Clearance from
7. Ground, Building, 2. Clearance from ground, building, trees and telephone lines shall be provided in
Trees etc. conformity with the Indian Electricity Rules, 1956 as amended upto date.

3. Any way leave which may be required by the contractor shall be arranged by him
on behalf of respective DISCOM.

4. Payment of compensation if any towards the clearance etc. will be the


responsibility of the contractor.

1. The contractor is required to follow local statutory regulations stipulated in


Electricity (Supply) Act 1948, Indian Electricity Rules 1956, or as amended and
other local rules and regulations referred in this specification.

2. The codes and/ or standard referred to in the specifications shall govern. Such
codes and/ or standard, referred to shall mean the interest revisions,
Statutory Regulations
8. amendments, changes adopted and published by the relevant agencies unless
And Standards
otherwise indicated.

3. Other internationally accepted standards which ensure equal or better


performances than those specified shall also be accepted, subject to prior
approval by the CEO, respective DISCOM.

1. The pits are excavated in the direction of line as this facilitates erection of pole in
addition to giving natural stability. The depth of pit should be the 1/6 of the height
9. Erection of poles
of respective pole in all type of soil laterite / hard rock and 75 cm being in the
direction of line.

Page | 17
Sl.
Particular Detail
No.

The size of stone pad should be 300x300x75 mm.

5. The pole is to be erected in alignment with utmost care and the excavated earth
should be back filled properly by ramming and concreting in the ratio of 1:4:8
concreting is to be measured separately.

6. Concreting of the support is to done as per relevant drawing enclosed, by a


mixture of 1:4:8 (by volume). The size of the pole plinth is kept as 450x450 mm
and height 300 mm above ground level as per drawing. The top 100 mm is kept
tapered so that no rainwater gets accumulated on the top. The underground
portion of the concreting shall be 450 mm x 450 mm x depth of plantation of
support.

7. Every pole of new line is to be properly grouted by the contractor and plinth be
made around it as per as per UPPCL norms. All the fittings, cross arms,
insulators and stays are to be properly fitted/ erected by the contractor.

Pin Insulators shall be used on all poles and disc Insulator on angle and dead end
poles. Damaged insulators and fittings, if any, shall not be used. Prior to fixing, all
insulators shall be cleaned in a manner that will not spoil, injure or scratch the surface
10. Insulator Fixing
of the insulator, but in no case shall any oil be used for that purpose. Torque wrench
shall be used for fixing various line materials and components, such as suspension
clamp for conductor, whenever required.

1. Each and every pole of the new 33/11 kV line and every third pole of LT line shall
be properly earthed by the contractor by constructing electrode type earthing
using 5 mm GI wire and 2500mmx20 mm dia MS earthing rod.
Earthing
11.
2. The cost of the same shall be included in the price quoted for poles/supports as
per standard practice of UPPCL. Detailed drawing no. DD&SO-27 are enclosed.

1. Stringing and sagging of the conductor and earth wires shall be done properly by
the contractor so that all poles remain erected vertically and no insulator is tilted.
Proper binding of conductor on the insulators and proper tightening of the nut
bolts of the cross arms, bracings, guarding angle and clamps must be ensured
by the contractor.

2. It Includes spreading of conductors without any damage and stringing with proper
tension without any kinks/damage including binding of conductor at pin points,
jumpering at cut points etc.
12. Stringing
3. The stringing of the conductor shall be done by the standard stringing method.

4. The contractor will discuss with the concerned CEO/SE (D), EUDC-EDC for the
stringing methods he proposes to follow and obtain their consent to startup the
work.

5. Conductors or earth wires shall not be allowed to hang in the stringing blocks for
more than 96 hours before being pulled to the specified sag.

1. Conductor and earth wire accessories shall be installed by the contractor /


earthwire clamping. While installing the conductor as per the design requirement
Fixing of Conductors within 24 hours of the conductor and earthwire accessories.
13. and Earth Wire
Accessories 2. After installing the conductor and earthwire, its accessories shall be installed
within 24 hours.

Page | 18
Sl.
Particular Detail
No.
3. Proper care shall be taken to ensure that the surfaces are clean and smooth and
that no damage occurs to any part of the accessories or of the conductors.

1. The contractor shall be entirely responsible for any damage to the pole or
conductors during stringing. The conductors shall be run out of the drums from the
top in order to avoid damage.

2. A suitable braking device shall be provided to avoid damaging, loose running out
and kinking of the conductors. Care shall be taken that the conductors do not
touch and rub against the ground or objects, which could scratch or damage the
strands.

3. The sequence of running out shall be from the top to down. i.e. the top conductor
shall be run out first, followed in succession by the side conductors. Unbalanced
loads on poles shall be avoided as far as possible. Wherever applicable, inner
phase of line conductors shall be strung before the stringing of the outer phases is
taken up.

Handling Of Conductor 4. When lines being erected run parallel to existing energized power lines, the
14.
And Earthwire contractor shall take adequate safety precautions to protect personnel from the
potentially dangerous voltage build up due to electromagnetic and electrostatic
coupling in the pulling wire, conductors and earth wire during stringing operation.

5. The conductor shall also take adequate safety precautions to protect personnel
from potentially dangerous voltage build up due to distant electrical storms.

6. The conductor shall be continuously observed for loose or broken strands or any
other damage during the running out operations.

7. Repair to conductors, if necessary, shall be carried out with repair sleeves.

8. Repairing of the conductor surface shall be carried out only in case of minor
damage, scuff marks, etc,
9. The final conductor surface shall be clean, smooth and free from projections,
sharp points, cuts, abrasions etc.

If any replacement is to be effected after stringing and tensioning or during


Replacement of maintenance e.g. replacement of cross arms, the conductor shall be suitability tied
15.
conductor to pole at tension points or transferred to suitable roller pulleys at suspension
points.

1. When approaching the end of a drum length, at least three coils shall be left in
place when the stringing operations are stopped. These coils are to be removed
carefully, and if another length is required to be run out, a proper joint shall be
made.

2. Conductor joints shall not crack or otherwise be susceptible to damage in the


stringing operation. The Contractor shall use only such equipment /method s
during conductor stringing which ensure complete compliance in this regard.
16. Jointing
3. All the joints on the conductor and earthwire shall be of the compression type, for
which all necessary tools and equipment like compressors, dies, etc. shall be
obtained by the Contractor. Each part of the joint shall be cleaned by wire brush
till it is free of rust of dirt, etc, and be properly greased with anti corrosive
compound. If required and as recommended by the manufacture, before the final
compression is carried out with the compressors.

Page | 19
Sl.
Particular Detail
No.
4. All the joints shall be made at least 30 meters away from the pole.
No joints or splices shall be made in spans crossing over main roads, railways and
small river spans. Not more than one joint per conductor per span shall be
allowed. The compression type fittings shall be of the self-centering type, care
shall be taken to mark the conductor to indicate when the fitting is centered
properly.

During compression or splicing operation: The conductor shall be handled in such


a manner as to prevent lateral or vertical bearing against the dies. After
compressing the joint the aluminum sleeve shall have all corners rounded, burns
and sharp edges removed and smoothened.

5. During stringing of conductor to avoid any damage to the joints the contractor
shall used suitable protector for mid span compression joints in case they are to
the passed over pulley blocks aerial roller. The pulley groove size shall be such
that the joint along with protection can be passed over it smoothly.

1. The tensioning and sagging shall be done in accordance with the approved work
programme by CEO/SE (D), EUDC-EDC.

The conductors shall be pulled up to the desired sag and left in running blocks for
at least one hour after which the sag shall be rechecked and adjusted, if
necessary, before transferring the conductors from the running block to the
suspension clamps.

2. The sag will be checked in the first and the last section span for section upto eight
spans, and in one additional intermediate span for section with more than eight
Tensioning And
17. spans. The sag also be checked when the conductors have been drawn up and
Sagging Operations
transfered from running block to the insulator clamps.

3. At sharp vertical angle, conductor and earthwire sags and tensions shall be
checked for quality on both sides of the angle and running blocks. The suspension
insulators assemblies will normally assumed verticality when the conductor is
clamped.

4. Tensioning and sagging operation shall be carried out in calm weather when rapid
changes in temperature or not likely to occur.

1. Clipping of the conductor into position shall be done in accordance with the
manufacturer's recommendations.

2. Jumper at section and angle poles shall be formed to parabola shape to ensure
18. Clipping In maximum clearance requirements.

3. Fasteners in all fittings and accessories shall be secured in position. The security
clip shall be properly opened and sprung into position.

1. Guarding along the line


Two numbers parallel GI wires 6SWG (guarding wires) shall run below the
conductor and shall be supported on M.S. angle of prescribed size.

Cross lacings of GI wire 8 SWG shall be provided at every 4 M. interval


19. 33kV Guarding throughout the crossings. The cross wires/ lacings shall be bent in U shape and
their ends shall be clamped with the parallel guard wires by proper binding.

2. Guarding across the road crossing/electric lines/telecommunication line


(as Cradle guarding)

Page | 20
Sl.
Particular Detail
No.
Five numbers parallel GI wires 6SWG (guarding wires) shall run below the
conductor and shall be supported on M.S. angle of prescribed size.

Cross lacings of GI wire 8 SWG shall be provided at every 0.6 M. interval


throughout the crossings. The cross wires/ lacings shall be bent in U shape and
their ends shall be clamped with the parallel guard wires by proper binding.

1. Guarding along the line


Two parallels GI wires 6SWG (guarding wires) shall run below the conductor
and shall be supported on M.S angle of prescribed size.

Cross lacings of GI 8SWG wire shall be provided at every 1 m interval


throughout the crossing.

Guarding shall be erected with ground & line clearance as per the I.E. rules.

11kV Guarding 2. Guarding across the road crossing/electric lines/telecommunication line (as
Cradle guarding)

Five parallels G.I. wires 6SWG (guarding wires) shall run below the conductor
and shall be supported on M.S angle of prescribed size.

Cross lacings of G.I. 8SWG wire shall be provided at every 1 m interval


throughout the crossing.

Guarding shall be erected with ground & line clearance as per the I.E. rules.

After completion of the works, final checking of the line shall be carried out by the
contractor to ensure that all foundation works, pole erection and stringing have been
done strictly according to the specifications and as approved by the concerned
CEO/SE(D), EUDC-EDC.

All the works shall be thoroughly inspected in order to ensure that.


a. Sufficient backfield earth covers each foundation pit and is adequately compacted:
b. All poles are used strictly according to final approved drawing and are free of any
defect or damage whatsoever.
Final Checking, Testing c. The stringing of the conductors and earth wire has been done as per the approved
21.
and Commissioning sag and tension and desired clearance are clearly available.
d. All conductor and earth wire accessories are properly installed.
e. All other requirement for completion of works such as fixing of danger plate and
anti-climbing device (Barbed wire) have been fulfilled.
f. Wherever required, the proper revetment (erosion protection) is provided.
g. The insulation of the line as a whole is tested by the contractor through provision
of his own equipment, labour etc, to the satisfaction of the Owner;
h. All poles are properly grouted.
i. The line is tested satisfactorily for commissioning purpose.

All dismantled material e.g. conductor, insulator, poles etc. requires proper handing
and stacking. Dismantled conductor must be re-rolled on the wooden drums to avoid
any damages. All such dismantled materials may be safely transported to respective
Safe up keep and DISCOM store and handled over to the authorized representative of respective
transportation of DISCOM.
22.
dismantled material to
stores Loses, damages or theft of material during erection, transformation and landing will be
to the account of the contractor. The cost of such damages /losses/ theft will be
recovered in full from the contractors bill or in other bills.

Page | 21
DETAILS OF OVERHEAD LINE MATERIALS

Sl.
Particular Detail
No.
33kV:

1. The 33 kV line shall normally be constructed on pin insulators and 11 m long Steel
Tubular Poles (410-SP-55)/ 9m. long PCC poles using ACSR Dog conductor.

2. In some cases 33kV line shall be constructed on suspension insulators on 13 m.


STP (SP-72) using ACSR Panther conductor for which cross arms of M.S. channel
125x65 mm shall be used.
1. Poles
3. However every road crossing shall essentially be done on 13 mt. long STP (SP-72)
poles in case the line is constructed on 11 m ST poles & on 11m STP in case the
line is constructed on PCC pole

11kV:
11kV line shall normally be constructed on 11 mtr. long steel poles (410- SP-55) or
9/8.5 mtr. long PCC pole

1. Adequate number of stays shall have to be provided on the angle support, section
and terminal supports to balance the sideward pull.

2. For that stay sets or strut stays as suitable shall have to be provided by the
contractor as per standard norms of respective DISCOM.

3. The stay sets shall comprise GI stay rod, GI anchor plate, stay wire, turn buckles,
break insulators and stay clamps.
2. Stay Sets
4. Stay of size 20x1800 mm with 7/4.0 mm GSS stay wire shall be used in 33 KV
lines supports wherever required.

5. Stay of size 16x1800 mm with 7/3.15 mm GSS stay wire shall be used in 11 KV
lines supports wherever required.

6. G.S.S. wires shall comply for solid wire (as per I.S.)

1. The wire shall be drawn from mild steel rods. The general requirement relating to
G.I. wire shall be laid down in latest version.

2. The size of G.I. Wire shall be 5 mm and 3.15 mm with tolerance of 2.5% and
tensile strength of 32-55 kgf/mm2. The wires shall be galvanized with heavy
coating as per IS: 4826.
3. G.S.S Wires
3. The wire shall be circular and free from side irregularities, imperfection, flaws,
splits and other detects. The zinc coating shall conform to heavy coating as laid
down in latest version of IS: 4826 and shall be smooth, even and bright.

4. The stranded wire shall be of grade. A having minimum tensile strength of 70 Kgf/
mm2. The specific technical particulars of G.S.S. wire arc:

G.I. stay rod of size 1800 x 20 mm with stay wire 7/4 mm should be provided on 33
KV line supports whereas GI stay rod at size 1800 x 16 mm with stay wire 7/3.15
4. Stay Rod
mm should be provided on 11 KV/LT. line supports. All G.I material should conform
to IS: 226 with latest amendments.

Page | 22
Sl.
Particular Detail
No.
For installation of a stay, excavation of hole site should be so selected that the
distance of hole from support should be such that when the stay is set, it should
have the correct inclination. After digging the hole, stay rod should be placed in
position and concreting in the bottom should be carried out. The size of the
concreting is kept as 600 x 600 mm and height 300 mm. The cement concreting
should be done in the ratio of 1:4:8.
The ramming of this earth must be well done thereafter. In setting stay rod, the
whole threaded portion of the plus 12 cm should produce through the ground.

1. Turn buckle with eye bolts for 33 KV /11KV line conforming to the following.

2. One no of turn buckle made out of 22 mm dia G.I. rod and 75 x 75 x6 mm M.S
angle.

5. Turn Buckle 3. One eye bolt made of 22 mm dia G.I. rod with 40 mm inner dia. eye to eye
threaded upto 300 mm length from the other side.

4. Two nos. GI nuts suitable for the threaded portion of eye bolt material
specification IS-226/77 (tested quality).

1. Prescribed size of conductor shall be used to construct 3 phase 3 wire 33 kV


lines. in case of 33kV line, are generally ACSR Dog and Panther.

6. Conductor 2. Prescribed size of conductor shall be used to construct 3 phase 3 wire 11 kV


lines. In case of 11kV, ACSR Dog/Raccoon conductor are used for main lines and
ACSR Weasel/Rabbit conductor for the tapping lines meant for feeding the DT
substations.

1. The steel V-type cross arm of MS channel 100x50x6 mm shall be used for 33 KV
line on Dog conductor and 11 KV line on Raccoon & Dog Conductor.

Cross Arms for 2. In case of 11 KV line on Weasel & Rabbit Conductor MS angle of 65x65x6 mm
7.
various conductors shall be used to fabricate the cross arms.

3. The center-to-center hole for 33 KV & 11 KV cross arms shall be 1525 mm and
1070 mm respectively.
Steel channel / Angle capable of bearing worst loadings
Single Pole: Double Pole:

Weasel, Rabbit
65x65x6 mm M.S. 100x50X6mm, MS.
11 KV LINES AND
Angle Iron (5.8Kg/M) channel (7.9Kg/M)
11kV & L.T.
V- type cross arm, cross arm,
COMPOSIT MAINS
Raccoon, Dog
100x50x6 mm, M.S. 125x65mm, M.S.
11 KV LINES AND
channel (7.9 Kg/M) channel (10.7 Kg/M)
11kV & L.T.
V- type cross Cross arm
COMPOSIT MAINS
arm

100x50x6 mm M.S. 125x65mm, M.S.


Raccoon, Dog channel (7.9Kg/M) channel (10.7Kg/M)
33KV LINES 33KV V-type cross cross arm
arm, as per

Panther 125x65 mm M.s. Section:


33KV LINES channel (10.7xKg/M) 150x75 mm. M.S. channel (14.4

Page | 23
Sl.
Particular Detail
No.
33 KV V- type cross Kg/M) cross arm
arm, Terminal :
150x75 mm, M.S. Channel (14.4Kg/M)
cross arm

Every new support shall be provided with pole nameplate, danger plate and barbed
8. Accessories wire wrapped at prescribed height up to 900 mm length (Anti climbing device) in
accordance with the respective DISCOM drawings.

1. The D.P structure material should be after complete fabrication including drilling of
holes etc.
2. All the horizontal members of the D.P. structure material should be mounded with
suitable clamps and nut bolts with the required clearance as IE. Rule 1956.
3. D.P. Structures material also comprises of-
(a)
(i) 3KV line Double Pole: Top channel of size 125x65X6 mm (10.7kg/ Meter)
having length of 3200 mm.
9. D.P. Structure
(ii) 11KV line Double Pole: Top channel of size 100x 50X6 mm (7.9 kg/ Meter)
having length 2240 mm.
(b)
(i) 33KV Line Double Pole: Bracing two number of M.S. Angle 65x65x6mm to
be fixed by 16 mm dia bolt with suitable washer as per enclosed drawing.

(ii) 11KV Line Double Pole: Bracing two number of M.S. Angle Iron 65x65x6
mm to be fixed by 16 mm bolt with suitable washer as per enclosed drawing.

1. Both in case of 33kV and 11kV lines;


Pin insulators of appropriate strength shall be used in case of regular pole.
10. Insulators
2. Combination of Disc and Pin insulator shall be used, in case of section support.
3. Shackle insulator shall be used in case of LT lines.

11. Pins 33kV and 11kV G.I. Pins


i) For 33KV supports: Made of M.S. Flat of size 60 x 6 mm should be provided as per
drawing.
12. F bracket ii) For 11KV supports: Made of M.S. Flat of size 50x4 mm should be provided as per
drawing.

1. The danger Board shall be provided as per SMC material.

Drawing of Danger Board of 33 KV line shall be as of 11 KV line Danger Board


except displaying 33,000 volts in place of 11000 volts.
The thickness of plate for danger Boards shall be of 2 mm (14SWG). The danger
boards shall be as per IS: 2551 and duly enameled and fixed with proper clamping
13. Danger Boards arrangement.

2. The letter figures and the conventional skull and bones of danger boards shall
conform to IS: 2551 and shall be in a signal red on the front of the board.

3. The corners of the danger board shall be rounded off to remove sharp edges.

GI Barbed wire (Anti-climbing device) shall be provided and installed by the


Contractor on all poles as per drawing enclosed as Annexure - 5, 6, 7 & 8. The
14. Anti-climbing Devices barbed wire shall conform to IS- 278 (Grade A1). The barbed wires shall be given
chromating dip as per procedure laid down in IS: 1340. The Barbed Wires should
be wrapped on the poles at the specified height shown in the drawing upto length of

Page | 24
Sl.
Particular Detail
No.
900 mm.

1. The provisional quantities of required poles, concrete, excavation volume for


foundation and other items are given in Technical Specification/Price schedule.
However the work shall be executed as per approved construction drawings.

2. Cement Concreting: Cement Concrete in the ratio 1:4:8 by volume (1 parts of the
cement, 4 part of the sand and 8 parts of the concrete) is to be used for concreting
of poles & muffing - property curved.

3. The quantities of earth wire accessories indicated in BOQ are tentative and actual
quantity will depend upon final survey (check survey). Payment for contractor
supplied line materials shall be made for the quantities incorporated in the works.

4. Permitted Extra Consumption of Contractor Supplied Material: The Contractor


shall not be required to return to the respective DISCOM cable conductor drums
and shall dispose of the same at his hand.

5. All those materials required for construction & erection of the lines, whose prices
have not been asked to be quoted separately in the price schedule but have been
included with the various work activities in the price schedule, shall be
arranged/supplied by the contractor as per the technical specifications annexed
with the tender. The contractor shall take care to include their cost in the relevant
columns of the work activities, as no separate payment shall be allowed on this
head.
15. Quantities
6. The cost of GI /GSS wires and conductor required in bulk for stringing, sagging &
guarding of lines is not to be included in the activity of stringing, sagging &
guarding. The same shall be paid as per prices quoted separately in the price
schedule.

7. However the cost of GI/GSS wire required in other activities like earthing and
stays are to be included in the corresponding activities of the price schedule itself
and no separate payment shall be allowed on this head.

8. All the materials like steel sections, masonry material i.e. Cement, Sand, Coarse
Sand etc. and paints are to be arranged by the contractor and no separate
payment shall be made for these items.

9. The unit rates quoted shall include minor details which may not have been
included in these documents but are executed for satisfactory completion of the
various works.

10. All measurements for payment shall be in S.L units. Lengths shall be measured in
meters corrected to two decimal places. Areas shall be computed in square meters
& volume in cubic meters rounded off to two decimals.

11. Any other material required to complete the work/job shall be paid by respective
DISCOM

Page | 25
ERECTION & COMMISSIONING NEW 11/0.433 KV DISTRIBUTION
TRANSFORMER S/S

Sl.
Particular Detail
No.
In each town, there are number of new distribution transformers (11/0.4KV) sub-
stations required to be constructed (25/63/100/250/400 KVA). The scope includes
design, engineering, fabrication of the structure and placing of new Distribution
Transformer and its accessories on it. This shall include supply and erection of the
following items: -

1. All the equipments under scope shall be as per their respective technical
specification enclosed.

2. The main items which are to be supplied, erected and commissioned are listed
below: -
- 11 KV/0.4 KV Distribution Transformers of various capacities. (with oil) having
efficiency equivalent/better than that for three Star ratings of BEE with completely
self protective (CSP) features and guaranteed period of five years.
- 11 KV TPMO- Horizontal type
- 11 KV Drop Out fuses.
1. Scope - 11 KV LA set
- LT Distribution Box, MCCBs, neutral link etc.
- LT CT Metering Cubicle
- Pipe in Pipe earthing
- Cable lugs
- 11 KV jointing kit.
- 11 KV 3 core 70mm sq XLPE cable or construction of 11 KV overhead lines.
- Plinth/'H' structure for transformers mounting.
- LT cables (3.5 core) 240 & 400 Sq. mm XLPE
- LT XLPE cable single core 50,70,240,400,630,1000 Sq. mm.
- Capacitor bank.
- Heavy duty SFU for capacitor bank.
- FRP fencing
- 11 Meter long STP.
- ACSR Dog conductor.
- GI/ GSS Wire & other items associated with construction of overhead line.

3. Supply erection, testing and commissioning of double pole structures at DT


1.1 Double Pole
substation site for fixing of LA, TPMO- Horizontal type, DO Fuse set etc.

4. Contractor shall evolve the mounting arrangements of various equipments on DT


1.2 Mounting and shall have to get the approval of the Engineer in-charge for its detailed
engineering.

5. Contractor shall carry out BDV and DGA of the oil and submit the results to the
1.3 Oil Test
owner.

1.4 TMPO 6. TPMO shall be Horizontal type. The height of the operating handle shall be such
that a normal height operator can operate it by standing at ground level.

1.5 DO Fuse Set 7. Drop out fuse on 11KV side give protection to the DT even during dead short
circuit condition at 11 KV side.

1.6 11kV LA 8. 11KV LAs shall be pole mounted and its neutral points be earthed through G.I.
strip to the pipe in pipe earthing of DT body, LT distribution board, fencing etc.

Page | 26
Sl.
Particular Detail
No.

9. Suitable LT CT metering cubicle (as per technical spec. with


proper rating of CTs) shall be mounted on double pole for metering of all DTs.
Contractor shall be responsible for installation of DLMS type meter and Modem
(with SIM) in LT CT Metering cubicle etc., complete in all respect. The Meters shall
1.7 LT Metering
be compatible with the existing meters and system. (Supply of meter, AMR
Modem, metering cubicle & CTs etc.shall be in the scope of contractor).

(i) Conventional LT CT upto 250 KVA


(ii) Butterfly type CT for 400 KVA and above.

10. The contractor shall supply and erect pole mounted LT capacitor bank of proper
ratings. The capacitor bank shall be connected at the incoming side of the LT
distribution box through a heavy-duty switch fuse unit. The SFU shall be mounted
on double pole also or as directed by the Engineer in-charge.
1.8 LT Capacitor Bank
The capacitor on LT side shall be 10% of the capacity of transformer and 50% KVR
capacity of 10% will be installed on DT pole and 25% at 1/3 length of LT line &
rd
remaining 25% at 2/3 length of LT.

1.9 Termination Kit 11. All the LT cable shall be properly lugged at both the ends. For HT cable, the
contractor shall supply 11KV heat shrink type termination Kits of standard make.

1.10 Fencing 12. FRP fencing of DT area as per drawing including its distribution board so that
unauthorized accessing can be curtailed.

13. A suitable lockable LT distribution box (Kit Kat Rewirable Type) shall either be
placed inside the transformer sub-station fencing or between the double pole
structures on steel structure fabricated from 75 x 75 x6 mm size M.S. angle firmly
grouted in the ground with the help nut & bolts.

This distribution box shall have TPN bus bar of 500 or 800 amps capacity. The
single core cables emanating from Distribution Transformers LT side shall be
connected to bus bars and outgoing feeders shall be taken out by Single Core LT
XLPE insulated cable through Kit Kat Rewireable type fuse units. The size of bus
bar and nos. of outgoing feeders shall depend on capacity of transformer.

1.11 LT Distribution Box For 400 & 250 KVA Transformers, bus bar of 800 amps shall be used and no. of
outgoing feeder per distribution box shall be three with 300 amps fuse unit on each
outgoing feeder.

For 160 & 100 KVA Transformers, bus bar of 500 amps shall be used and no. of
outgoing feeders shall be two with 200 amps fuse unit on each outgoing feeder.

For 63 KVA Transformers, bus bar of 300 amps shall be used and no. of outgoing
feeders shall be two with 100 amps fuse unit on each outgoing feeder.

For 1000 & 630 KVA Transformers two LT distribution boxes of 800 amps shall be
placed.

14. Chemical Pipe earthing three numbers, one for transformer neutral and second for
1.12 Earthing neutral of lightening arrester and third for transformer body, LT distribution board,
fencing of distribution transformer sub-station etc. shall be done.

15. Contractor shall be responsible for carrying out commissioning of the DT and
1.13 Commissioning coordinating the protection right from 11 KV level to 0.4 KV level.

The contractor will have to construct the DTs sub-station in complete respect and

Page | 27
Sl.
Particular Detail
No.
hand over the same to the owner in ready to use condition.

If any item or items not mentioned in BOQ but required essentially for completion
of work, the same shall be arranged by the contractor without any extra payment.

Adequate number of stay shall have to be provided on the pole, double pole four
1.14 Stay Sets pole structures to balance the side wards pulls at the point of turning of the lines.
All stays had to be grouted as per drawing enclosed. Stay sets shall be as per
specification and drawing.

1.15 Painting Poles and steel structures shall be properly painted as per UPPCL norm with the
consultation of CEO.
Fabrication And
1.16 Erection Of L.T. Cable This work involves fabrication of M.S Angle 50 x 50 x 6 mm. with cable binding /
Stand clamping arrangement including its grouting and painting.
Laying of L.T. Cable shall be as per table given below: -
Capacity of For I/C of T/F For Distributors
T/F in KVA Single lead (Sq. mm.) L.T. 3x cable
(Sq. mm.)
Phase Neutral
25 4x35 4x35
63 3.5x70 70/2
1.17 Laying Of L.T. Cable 100 3.5x 120 70/2
160 3.5x240 120/2
250, 300 400 400 120/3
400, 500 400/2 400 240/3
630, 700, 750 630/2 630 240/5
800, 1000 1000/2 1000 240/8

All the incoming leads from Transformers to the LT panel are to be replaced.

The work involves construction of transformer plinth as per drawings suitable for
installation of transformer upto 1000 KVA. The size of plinth shall be 2 to 4 M long, 2M
wide and the height of the plinth shall be 1.2M with 15 Cm. thick top slabs with 2 no.
Construction of
1.18 25x65x6 mm MS channel 2M long imbedded in it.
transformer plinth
The above work includes excavation of earth, laying of brick ballast pad for foundation
brick work, RCC and plastering and proper curing. The ration of cement/course
sand/fine sand/brick ballast/stone grit shall be as per PWD schedule.
The fencing is constructed utilizing vertical post duly grouted / fitted in ground/on floor.
Horizontal rails fitted to the vertical posts, pickets (if required) fitted to rails and gate to
facilitate entry and exit within the covered area.

The vertical post shall be made out of FRP Pultruded hollow section. Such posts shall
1.19 FRP Fencing be kept preferably at a distance of 1000 mm c/c and shall be grouted in the ground
with c.c. of ratio 1:4:8. The vertical posts shall be supplied with pre-drilled holes so as
to accept rails and other accessories for fixing of gates etc. The length of vertical post
shall be sufficient to take care of grouting, depth i.e. underground and height of
fencing above the ground. Posts at corners and gate openings may be of different
size/shape so as to take care of the fencing requirements.
The hollow pipe used in the chemical pipe earthing is fitted with a G.I. strip 40x6mm and
CCM (Crystalline conducive mixture) is compressed in to the pipe and pipe is sealed at
both the end. CCM is a semi metal and the hollow pipe filled with CCM behave like a
Chemical Pipe
1.20 salt pipe and therefore the current carrying capacity increases substantially.
earthing
The CCM has a high melting temperature of 2500c and unlike coal it will not burn into
ashes under high temperatures of 1500c under high fault currents occurring due to
phase to phase or phase to earth fault
The capacitor on LT side shall be 10 % of the capacity of the transformer and 50 %
1.21 L.T. Capacitor Bank
KVAR (of 10 %) capacity will be installed on DT, 25 % KVAR (of 10 %) capacity will be

Page | 28
Sl.
Particular Detail
No.
installed on 1/3rd of length of LT line and remaining 25 % KVAR (of 10 %) capacity will
be installed on another 1/3rd of length of LT line.
The contractor shall supply and erect pole mounted LT capacitor bank of proper
ratings. The capacitor bank shall be connected at the incoming side of the LT
distribution box through a heavy-duty switch fuse unit. The SFU shall be mounted on
double pole also or as directed by the Engineer incharge.

The L.T. capacitor bank of required rating shall be placed on one of the pole of the
double pole structure. It is, therefore, essential that contractor should provide
arrangement for hanging the capacitor bank firmly on the pole from the back of
capacitor bank housing using two clamps of proper size or with any other better
arrangement. The contractor shall have to supply, erect, test and commission the
capacitor bank to the satisfaction of respective DISCOM., D.Ts capacity wise
requirement of capacitor bank shall be as follows :-
Sl. No. Capacity of DTs. Capacity of capacitor
in KVA bank in KVAR
1. 25 2+1+1
2. 63 4+2+2
3. 100 5+2+2+1
4. 250 12+4+4+3+2
5. 400 20+5+5+5+5
6. 630 30+10+10+8+5
7. 1000 50+20+10+10+10

RENOVATION & MODERNIZATION WORKS & AUGMENTATION OF 11/0.433


KV DISTRIBUTION TRANSFORMER S/S

Sl.
Particular Detail
No.
In the town under the scope of this tender, there are number of existing distribution
transformer Sub Stations (11/0.4 KV) with ratings varying from 25 KVA to 1000 KVA
scattered all over the town. Lot of its components are either missing or have become
faulty over the years. The scope of the contractor shall be to carry out reconditioning
of existing Distribution Transformers and renovation and modernization (R & M) work
of all DTs Sub Station of 25 KVA and above ratings including supply of spares,
erection, testing and commissioning. In addition to this metering system on DT sub
stations (where metering system is not installed) are also required to be installed. (LT
TVM, LT CTs & Cubicles either to be mounted on double pole structure or to be
placed in the LT distribution box without TVM cubicle). All the old Distribution
Transformers shall be made completely self protective. For self protection the
Microprocessor based MCCB shall be mounted outside the transformer tank in a
closed box and it is essentially required to meet the compatibility with Overloading
conditions of the transformer. The Internal Circuit Breaker or Microprocessor based
1. Scope MCCB must meet the overloading condition of transformer as per IS 6600. The
reconditioned transformers shall be guaranteed for three years from the date of
commission.

i) All the equipments under scope of supply shall be governed by their respective
technical specification enclosed.

ii) The main equipments which are to be supplied, erected and commissioned under
R & M work are listed below: -

- 11 KV TPMO
- 11 KV Drop Out fuse set
- 11 KV LA set
- LT distribution box, MCCBs, neutral link etc.
- Topping up of transformer oil after arresting oil leakages including maintenance of

Page | 29
Sl.
Particular Detail
No.
DTs.
- Pipe type earthing.
- Cable lugs
- Plinth for transformers.
- LT cables (3.5 core) 240 & 400 Sq. mm XLPE
- LT XLPE cable single core 50, 70, 240, 400, 630, 1000 Sq. mm.
- Heavy duty SFU for capacitor bank.
- Capacitor bank (LT).
- Fencing of sub stations
- Painting of transformer and structure.
- Replacement of faulty insulator and bushing, if any.
- Supply of new DTs in case of increasing capacity.
vi) Contractor shall be responsible for arresting oil leakages and topping up the
1.1 Transformer Oil
transformer oil (fresh) up to the required level.

vii) During the course of work, if any internal fault develops in the running DT, the
contractor shall either repair the same at site or shall transport them to the
1.2 Repair of DT workshop and repair it. Its handling and supply of spares etc shall be to
contractor's account.
Contractor will ensure continuity of supply with the help of trolley mounted DT

viii) Contractor shall ensure cleaning of the oil slippages which had taken place during
1.3 Oil Leakage oil leakage arresting.

ix) TPMO shall be gang operated and height of the operating handle shall be such
1.4 TPMO that a normal height operator can operate it by standing at ground level.

x) Drop out fuse on 11 KV side shall give protection to the DT even during dead
1.5 DO Fuse Set short circuit conditions at 11 KV side.

xi) 11KV LAs shall be pole mounted and its neutral points be earthed through G.I.
1.6 11kV LA strip to the pipe in pipe earthing of DT body, LT distribution board, fencing etc.

xii) A suitable lockable LT distribution box (Kit Kat Rewirable Type) shall either be
placed inside the transformer sub-station fencing or between the double pole
structures on steel structure fabricated from 75 x 75 x6 mm size M.S. angle firmly
grouted in the ground with the help nut & bolts.

This distribution box shall have TPN bus bar of 500 or 800 amps capacity. The
single core cables emanating from Distribution Transformers LT side shall be
connected to bus bars and outgoing feeders shall be taken out by Single Core LT
XLPE insulated cable through Kit Kat Rewireable type fuse units. The size of bus
bar and nos. of outgoing feeders shall depend on capacity of transformer.

1.7 L.T. Distribution Box For 400 & 250 KVA Transformers, bus bar of 800 amps shall be used and no. of
outgoing feeder per distribution box shall be three with 300 amps fuse unit on each
outgoing feeder.

For 160 & 100 KVA Transformers, bus bar of 500 amps shall be used and no. of
outgoing feeders shall be two with 200 amps fuse unit on each outgoing feeder.

For 63 KVA Transformers, bus bar of 300 amps shall be used and no. of outgoing
feeders shall be two with 100 amps fuse unit on each outgoing feeder.

For 1000 & 630 KVA Transformers two LT distribution boxes of 800 amps shall be
placed.
xiii) If requird suitable LT CT Metering cubicle (as per technical spec. with proper
1.8 L T Metering rating of CTs) shall be mounted on double pole for metering of all DTs. Contractor
shall be responsible for installation of LT TVM in LT CT Metering cubicle.

Page | 30
Sl.
Particular Detail
No.
xiv) Single core and 3.5 core LT cables if found damaged shall be accessed and
replaced by the contractor. For carrying out this activity, all man, material and T&
1.9 LT Cables
P shall be arranged by the contractor.

xv) Contractor shall carry out modifications, repair (in case necessary) in the plinth if
the DT is plinth mounted or the bolting arrangement of the transformer body with
2.0 Plinth
the support structure, in case DT is pole mounted.

xvii) Fencing of DT area with FRP fencing as detailed above (wherever possible)
2.1 Fencing including its distribution box so that unauthorized accessing can be curtailed.

xviii) Contractor shall be responsible for assessing the damaged bushing/insulators in


2.2 Bush/Insulators DT area and shall also be responsible for their supply and replacement.

xix) Microprocessor based MCCB of suitable rating shall be supplied and erected by
the contractor. The Microprocessor based MCCB shall be installed at
2.3 MCCB transformer's LT side. Output of this Microprocessor based MCCB shall terminate
on LT buses of LT distribution box and after buses.

xx) Contractor shall be responsible for coordinating the protection trip settings right
2.4 Protection Trip setting from 11KV level to 0.4 KV level (at DT output).

xxi) Contractor shall be responsible for painting the DT including HT and LT


2.5 Painting structures. The old paint or rust shall be cleaned first and thereafter two coats of
primer shall be applied and finally two coats of synthetic enamel shall be applied.
xxii) Contractor shall be responsible to replace the silica gel and filling them with new
2.6 Silica Gel
silica gel.

GENERAL SPECIFICATION FOR LAYING OF AERIAL BUNCHED CABLES

Sl.
Particular Detail
No.
Aerial Bunched Cable shall be laid over-head with bare messenger wire duly suspended
Aerial Bunched with the help of special clamps and hooks as per drawing enclosed. The clamps shall be
Cables on New supported on LT Poles. The maximum Sag various spans shall be as follows:
Supports
Span Sag
60 M 1.409 M
50 M 1.025 M
40 M 0.702 M
30 M 0.423 M
20 M 0.222 M

Typical arrangements of hanging from the support are shown in drawing for Straight run
1. angled and dead end locations. The clamps assembly shall provide sufficient flexibility to
allow free movements of the clamps at straight run or angled location.
The tapping arrangements shall be as shown in drawing. The tapping cable shall be
connected to the main cable with the help of L.T. insulation piercing connectors (non-
tensile). The other end of the taped cable shall be properly connected with the bus bars of
the LT Distribution boxes.
New Supports of PCC or Steel Tubular Poles shall be provided as per BID PROPOSL
SHEET and Specification. The scope covers erection, grouting and plinthing of poles
including adequate no. of stays with its nuzzling and grouting.
The pole earthing shall be done through 20 mm dia 2500 mm long earthing rod and 6 SWG
G.I. wire.

Page | 31
Sl.
Particular Detail
No.
The replacement of the L.T. bare lines by Aerial bunched conductors are to be done in
Aerial Bunched selected area of the town which are congested/densely populated and have lesser
2. Cables on clearances between lines and the houses and are prone to theft of electricity. The work
existing LT Lines may also to be done in other selected area of the town as per the decision of engineer in-
charge.

LT line shall be replaced as per load by proper size of ABC. Load on LT line shall be
measured before replacement by ABC. If required no. of LT circuit on ABC shall be
increased. Initially load on replaced ABC shall not be kept more than 70% of its continuous
current carrying capacity in air at ambient temp. 400 C. The Continuous Current Carrying
capacity in air at ambient temp. 400 C of various sizes of ABC to be used are as below:
Current Rating:
Continuous
Sl. Current Carrying Approx. weight of ABC
Size of ABC
No. capacity in air at (Kg./Km.)
0
ambient temp. 40
C (Amp.)
1 3x150+1x120+1x16 230 1909
3x120 +1x95 +1x16
2 180 1430
Sq.mm.
3 3x95 +1x70 +1x16 Sq.mm. 155 1180
4 3x70+1x50+1x16 130 890
5 3x50 +1x35 +1x16 Sq.mm. 105 640
De-energizing of L.T. system or 11 KV of the site as decided by Engineer in charge before
De-energizing of taking up the work. It shall be the sole responsibility of the contractor to ensure that the line
3.
system is de-energized and safe in all respect before start of the work.

Dismantling of existing L.T. bare conductors, old or damaged LT cable/11 KV XLPE cable,
Dismantling of consumer service lines, and other fixtures e.g. insulators, clamps, nuts & bolts etc. its
4. existing L.T. bare stacking and safe transportation to the respective DISCOM Stores as per the direction of
conductors the Engineer in charge.

Erection, stringing and sagging and commissioning of Aerial Bunched Conductors on


existing L.T. poles including fixing of necessary hardware/fittings like suspension Clamp,
Stringing and Suspension hooks, Poles clamps, Dead end Clamps, Dead end hooks etc. However, it
5.
Sagging of ABC shall be the responsibility of the Contractor to supply and erect L.T. Poles where required
and instructed by Engineer in charge of respective DISCOM.

Installation of suitable L.T. insulated piercing connectors and distribution boxes and
Installation of L.T.
reconnects the service line connections on phase and street light conductors through
6. insulated piercing
distribution boxes with the help of the power cable as per guide lines of site Engineer.
connectors
1. The distribution box (SMC as well as power coated CRCA MS Sheet by deep drawn
method) shall be suitable for mounting/fixing on round poles & rails. Number of such
distribution boxes to be mounted on one pole shall depend on the number of service
connections to be given from the pole and it may be two to three in numbers. 4 nos. 35
mm 2. Aluminium multi strand cable shall be used to connect the incoming bus bars of
the distribution box to the main Aerial Bunched conductor by using suitable L.T.
Installation of
insulation piercing connectors.
Distribution Box
The number of outgoing cable provisions shall be of approximately 10-15 service cable
7. and Release
connections from each distribution box.
Service
Connection
2. There shall be proper clamping & tightening arrangements for the outgoing service
cable.

3. The distribution box shall be of such construction that rain water does not enter into it
and there must be proper sealing arrangement of the pillar box cover.

Page | 32
Sl.
Particular Detail
No.
Alternatively at some of the sites the service connection will have to be given directly
through connectors from main phase conductors without installing distribution
box/kiosk. This decision shall be taken by the Site Engineer of respective DISCOM.

4. Installation of L.T. insulation piercing connectors for jumpering wherever required.

5. The connection to street light shall be through ON/OFF switch already existing. In case
it is not provided the same has to the provided by the contractor.

6. Dismantling of existing LT bare conductors consumer service lines, other line fixture
e.g. insulators, clamps, nuts & bolts etc. its stacking and safe transportation to the city
stores as per the decision of the Engineer in-charge.
The scope covers supply, erection, grouting & plinthing of LT poles at some places
Supply and
wherever required along with its civil work. This includes erection of adequate number of
8. erection of new
stays with its nuzzling and grouting.
poles
The pole earthing shall be done through 20 mm dia 2500 mm long earthing rod and 6 SWG
9 Earthing of poles G.I. wire.

The damaged and rusted poles which are repairable shall be identified by Engineer In-
charge. The contractor shall repair these poles at site by welding of M.S. Angle 50x50x6
mm 0.70 mm long 4 nos. to strengthen the bottom of rotten poles. The contractor shall
Repair of
10. construct adequate size plinth for such poles by concreting in the ratio of 1:3:6 of cement,
damaged poles
sand & brick ballast and curing the same. The contractor shall have to arrange welding set
and other necessary materials including M.S. Angle etc. for this work.

GENERAL SPECIFICATION FOR LAYING OF 11 KV & 33 KV XLPE CABLE

Sl.
Particular Detail
No.
1. The scope shall cover complete installation of all equipment and accessories
covered under this contract.

2. Installation work pertaining to equipment, cabling etc should be in accordance


with the applicable standards, safety codes etc.
1. General:
3. Installation shall be carried out strictly in accordance with the approved drawings
Modifications, if any, required to suit site conditions, shall be carried out only with
the prior approval of the Engineer. All such changes shall be incorporated in As
built drawings to be furnished by the contractor.

Page | 33
Sl.
Particular Detail
No.
1. It is proposed to lay underground XLPE cable(s) conforming to IS: 692 or
1S.7098 (Part-2) and any amendment thereof as per bill of quantity in various
lengths on different routs within the city.

The Engineer shall intimate the actual rout(s) to the contractor within three weeks.

2. The quantity as given in the bill of quantity are approx. and may vary on either
side as per actual requirement at site. Work should be done as per actual
distances along the route of the cable and shall be paid accordingly.

3. The scope of this specification covers loading transportation, unloading of cable


drums, digging of trenches, laying in underground trenches, jointing terminations
back filling of earth and testing & commissioning of sizes mentioned in schedule
of work conforming to relevant ISS/technical particulars enclosed herewith.

4. The following technical particulars for laying of cable shall be followed as per IS:
1255/1983 or latest amendment thereof.

S.
Item For 33 kv For 11 kv
No.
1. Depth of trench 1050 mm 900 mm
500 mm (For
2. Width of trench 750 mm
single cable)
450x600x50mm
450x600 (For 3x185sq mm
3. Size of stone slab
x50 mm or above size
Laying Of 33 KV & 11 cable)
2. KV Cables 4. No. of stone slab per meter 1.67 1.67
9x2 for 3x185
5. No. fo bricks per meter 9x2
mm2 or above
0.563 cubic 0.375
6. Local sand per meter
meter cubic meter
D.C voltage to which cable shall withstand
for 5 minutes after completion of
7. laying/jointing/termination (in kms) between 60 KV 18 KV
any conductor and metallic
sheath/screen/armour.
As per
specification
8. (HDD method)
given in Vol. II
part A

Clearance not Clearance not


necessary, necessary,
Clearances- The desired minimum
however larger however larger
Clearances are as follows.
the clearance the clearance
a) Power cable to power cable
9. better would be better would be
b) Power cable to control cable
current carrying current carrying
c) Power cable to communication cable
capacity. capacity.
d) Power cable to water line
0.2 meter 0.2 meter
0.3 meter 0.3 meter
0.3 meter 0.3 meter
Note:-
High voltage test to be conducted by contractor

Page | 34
Sl.
Particular Detail
No.
The trenchless technology shall be used with HDPE casing for the portion of the
cable route such as road, railway, nullah crossing and without HDPE casing for
major portion of the cable route. The outer diameter of the HDPE pipe shall be
suitable for insertion in an 8 diameter horizontally drilled bore. The HDPE pipe
shall be of PE 80 grade with pressure rating PN4 conforming to IS 4984/1995 and
shall have wall thickness of 6.20 to 7.10 mm. The HDPE pipes shall be joined by
using Butt welding and a 7/20 G.I wire shall be provided along the entire length of
3. each pipe duct.
The Depth of horizontal drilling shall be between 2 to 3 meters or as required. The
Cable Laying
drilling shall be with a Directional drilling unit equipped with automated pipe
handling system and all necessary accessories.

Note:-
In case of any damage of material/ equipment of 3rd party, all charges would be
borne by the contractor
1. The trenches for the cable laying shall be done as per standard practice The
trenches shall be dug in such a manner so that soil etc once excavated does not
fall back in the trench.

The cables (a) entry and exit in pipes etc should be according to relevant ISS.

2. When more than one cable shall be laid in the same trench, a horizontal inter axial
Cable Trench
4 spacing for 0.25 to 0.40 meters for 33 KV and 0.15 to 0.25 meter for 11 KV in
order to reduce the effect of mutual heating effect and also to ensure the fault
occurring on one cable shall not damage to other cable.

3. Where two cables are laid in parallel in one trench, the separation - wall shall be
provided by means of laying bricks throughout its length upto the height of top
slab/bricks.

1. In case of roads, railway tracks and water pipeline crossing, the cable shall be laid
in the cast iron/hume pipe etc as prescribed in clause 6.3.4 of IS:1255/1983.
Road and
2. In case of Railway crossing entire formality, including cost of attaining its
5. Railway crossing
permission shall have to be carried out by the contractor at its own cost. Also for
the purpose of underground Railway crossing cast iron pipe of suitable size (4"
minimum) shall be laid instead of cement hume pipe.

The contractor shall made adequate arrangement (particularly sufficient man


power & equipment) for proper handling of cables and putting the same direct on
Handling of cable rollers and ensure that no twists etc. are made in the cable and cables are not
6.
damaged in any way whatsoever. Contractor shall also ensure that during entire
working at site upto commissioning stage their responsible engineers/supervisor
with trained crew shall be continuously available

1. Necessary permissions to lay the cable in ground after cutting the road(s)
(Kuchha). Brick-pitched & Pucca. Crossing bridges railway tracks etc will be
obtained by the contractor over the request from the engineer incharge of the work
and necessary payment/charges of above shall be borne by the contractor.

Road cutting and 2. The contractor should take notice of the fact that in case of cutting of roads etc. is
7. restoration required for laying cable; the contractor shall have to take prior permission from
local authorities of PWD/ Municipalities /Nagar Nigam/Development authorities etc.
or other owner of the road.

3. The road cutting charges payable to such agencies may be substantial and shall
be borne by the contractor. The contractor shall take care of such charges while
quoting his rate for laying of cables as no extra payment shall be made to the

Page | 35
Sl.
Particular Detail
No.
contractor on this account. All necessary clearance for such work from the
respective agencies shall be responsibility of the contractor.

While the execution of work is in progress, the contractor shall have to provide
necessary lighting arrangement/signboard/ road stoppers and other precautionary
8. Warning / notices
warnings/notices so that accidents/ damages/losses to the public/manpower/
material etc are avoided.

Page | 36