Professional Documents
Culture Documents
The planning from start to finish for the proposed retaining wall in Jalan Penempatan. Period Highlight: 1 Plan Duration Actual Start
ACTIVITY PLAN START PLAN ACTUAL START ACTUAL DURATION PERCENT COMPLETE
DURATION PERIODS
1 2 3 4 5 6 7 8 9 10 11 12 13 14
100%
Group selection 1 1 1 1
100%
PBL briefing 1 1 1 1
Desk Study and Site 100%
Selection 1 1 1 1
10%
Completing Proposal 1 2 1 1
10%
Sample Recovery 2 1 1
0%
Field Test: Slope Inclination 2 1 1 1
0%
Lab Test 1: SPT test 0 0 0 0
0%
Lab Test 2: Sieve Analysis 0 0 0 0
0%
Lab Test 3: LL and PL 0 0 0 0
0%
Lab Test 4: Penetration Test 0 0 0 0
Lab Test 5: Specific Gravity 0%
Test 0 0 0 0
0%
Compile all Lab data 0 0 0 0
0%
Design Retaining wall 0 0 0 0
0%
Finalizing PBL Report 0 0 0 0
0%
Presentiationof PBL report 0 0 0 0
0%
Submission of PBL report 0 0 0 0
Page 1 of 1