You are on page 1of 10

Kaveri Watermarke Sewerage Treatment Plant Report

Report on
Sewerage Treatment Plant

CPG Consultants India Pvt Ltd., Page 1


Kaveri Watermarke Sewerage Treatment Plant Report

1.0 Introduction:

The objective of Sewage treatment plant is to stabilize decomposable organic


matter present in sewage so as to produce treated effluent which can be reused
for non-potable purposes or disposed off into the environment without causing
health hazard or nuisance.

A comparison chart for various types of STP is as follows:

Convention
Sl Extended
MBR al Activated Trickling
N Feature Aeration
System Sludge Filter
o Process
Process
Less(0.15- High(0.20- High(0.20-
Area
1 Least 0.20 0.25 0.30
Requirement
sqm/person) sqm/person sqm/person
Simple but
there are
Simpler than Skilled O&M operational
Operation &
2 Most Simple activated personnel is troubles like
Maintenance
sludge. required fly and
odour
nuisance
Effluent
3 Good Good Fair Fair
Quality
Removal %
i About 98 95-98 85-92 80-90
BOD5
Removal %
ii Suspended About 98 90-95 90-95 About 80
Solids
Sludge
production &
4 Less Less High High
Sludge
handling
Power
5 Very High High High Moderate
requirement
Flexible in Flexible in Sudden Has
6 Adaptability
operation operation change in flexibility in

CPG Consultants India Pvt Ltd., Page 2


Kaveri Watermarke Sewerage Treatment Plant Report

quantity and operation


quality of
sewage
produces
adverse
effects on
the process
Capital cost
High capital Cost is less
is less but
Cost of cost but less compared to
7 high High cost
Construction expense for conventional
operational
maintenance ASP
cost
Modular Not
8 Possible Not possible Not Possible
Growth Possible

Hence we recommend a MBR type Sewage Treatment Plant.

2.0 Membrane Bio-Reactor System

The units of the MBR type STP and their function is described as follows:

a) Bar Screen: The main objective of installing screens is to remove floating


matter of comparatively large size. This unit prevents problems, which are
likely to be caused in further operation of other units. Removal of these
wastes in screens prevents clogging and chocking of pumps and other
equipments.

b) Equalization Tank: Sewage generation is not uniform and maximum quantity


comes out during morning and evening hours. The flow may be zero during
afternoon and mid night. To optimize the size of the plant, the plant is
designed for continuous operation and hence there is a need to provide a
buffer tank to store sewage during its peak hour generation and supply the
same during lean or no flow hours. Hence the plant is provided with a good
capacity of buffer tank known as EQUALISATION TANK. Screened and de-
greased sewage is then passed into the equalization tank to homogenize the
sewage quality and also even out flow fluctuations and feed sewage of
uniform quality at constant rate to subsequent treatment units. Air mixing is
also provided to mix the contents of the equalization tank. A coarse bubble
aeration grid system is provided to mix the contents of the equalization tank

CPG Consultants India Pvt Ltd., Page 3


Kaveri Watermarke Sewerage Treatment Plant Report

and also to avoid septic conditions in the tank. Hydraulic retention period here
will be 8 Hrs.
c) Aeration Tank: Biological stabilization of the waste water is carried out in the
aeration tank in the presence of microorganisms. In this tank Oxygen is given
for aeration, in order to reduce BOD and COD. The aeration devices apart
from supplying the required oxygen demand shall also provide adequate
mixing or agitation in order that the entire mixed liquor suspended solids
present in the aeration tank will be available for the biological activity. The air
containing oxygen is used by the bacteria to consume the organic matter and
convert it to carbon dioxide and water. In aeration tank, MLSS (mixed liquor
suspended solids) in the range of 3000 to 6000 mg/l or more are maintained.
The high amount of bacteria gives better and complete removal of organic
matter from the raw effluent in relatively small area. Oxygen required for the
bacteria is supplied through the blower.

Aeration: fine bubble air diffusers


MLSS: 3000 -6000Mg/ Lit
Oxygen requirement: 2 kg per kg of BOD

d) MBR Tank: The waste water (mixed liquor) with the bio mass flowing out
of the aeration is taken to an MBR tank with a hopper bottom.

Module dimension (as per design): (Immersed)


ID/OD 0.8/2mm
Material PVDF
Pore size 0.1 micron
Tensile strength >25 kg/fiber
Effective area 20 m2
Flux 15 to 70 (LMH / m2 x h)
Design Flux 25 LMH
Casing Material ABS
Operating method Suction 2 way
Operating pressure 100- 300 mm Hg
Aeration External- Bottom
Max temp 40 c
Flow Mode Out to Inside

CPG Consultants India Pvt Ltd., Page 4


Kaveri Watermarke Sewerage Treatment Plant Report

Ph 2 to 10.

MBR Module:

Each module delivers (as per design) capacity cum/day of treated


water.
No of Modules: Membrane modules of design capacity.
Cassette size : As per Design
No of cassette : As per Design
The following pumps are considered:
MBR Suction pump (1W + 1S) As per Design
MBR back wash pump (1W + 1S) - As per Design
MBR chemical cleaning pump As per Design
The MBR operation is totally done by PLC based control panel which
automatically does the suction, back washing depending on the time which is set.

MBR - CHEMICAL CLEANING (CIP)

e) Final Treated Water Tank: The water sucked from the membranes is of very
high quality with respect to BOD, COD and suspended solids, and is stored in
a final treated water tank for further use. Retention period is 10-12 hrs.

CPG Consultants India Pvt Ltd., Page 5


Kaveri Watermarke Sewerage Treatment Plant Report

f) U V STERLISER or Chlorination (for disinfection): Finally the treated MBR


product water is passed through UV sterilizer/chlorination for further
disinfection if required.

The characteristic features of raw sewage and treated sewage is as


follows:-
Characteristic of Raw Sewage
pH 7.5 8.5
TSS 400 mg/lit
BOD5 350 mg/lit
COD 500 mg/lit
IN FLOW 18 Hr

Characteristic of Treated Effluent:


pH 7.0- 8.0
TSS NIL
BOD5 < 5 mg/lit
COD <20 mg/lit
TURBIDITY <2 mg/lit
COLOR <05 hazen
ODOUR un-objectionable

3.0 Sewerage Discharge-Total and Phase wise:


The Water demand calculation Table for the entire development is as given
below:

Add 10% Sewage


No. of No. of No. of
LPCD as for Total
Sl. units floors personn Water
Type per Unaccou Water Discharged
No per (ex.stilt el Required
CPHEEO nted Req'd/day ,
floor level) (No.s)
usage kld
1 Tower-1 8.00 14.00 1176.00 150.00 176400.0 17640.00 194040.00 164.93

2 Tower-2 21.00 14.00 1470.00 135.00 198450.0 19845.00 218295.00 185.55


Tower-3
3 (same 8.00 14.00 1176.00 150.00 176400.0 17640.00 194040.00 164.93
as 1)

CPG Consultants India Pvt Ltd., Page 6


Kaveri Watermarke Sewerage Treatment Plant Report

4 Tower-4 12.00 12.00 720.00 150.00 108000.0 10800.00 118800.00 100.98

5 Tower-5 12.00 12.00 720.00 150.00 108000.0 10800.00 118800.00 100.98

6 Tower-6 12.00 12.00 720.00 150.00 108000.0 10800.00 118800.00 100.98

7 Tower-7 22.00 11.00 1210.00 150.00 181500.0 18150.00 199650.00 169.70

8 Tower-8 25.00 12.00 1500.00 150.00 225000.0 22500.00 247500.00 210.38


Club
10 - 3.00 225.00 45.00 10125.00 1012.50 11137.50 9.47
House
7 Total 8917.00 1421062.5 1207.90

8 Treated Effluent from STP 1026.72

The water demand for Phase-I is as follows:

Sewage
No. of No. of Total
No. of LPCD as Water Add 10% for
Sl. units floors Water
Type Occupa per Required, Unaccounted Discharg
No per (ex. stilt Req'd/day
nts CPHEEO ltrs usage, ltrs ed,
floor level) , ltrs
kld
1 8.00 14.00 560.00 150.00 84000.00 8400.00 92400.00 78.54
Tower
-1
2 8.00 14.00 560.00 150.00 84000.00 8400.00 92400.00 78.54
Tower
3 8.00 6.00 240.00 135.00 32400.00 3240.00 35640.00 30.29
-2
Club
4 - 2.00 150.00 45.00 6750.00 675.00 7425.00 6.31
House
5 Total 1510.0 227865.00 193.69

6 STP Capacity 200.00

7 Treated Effluent from STP 164.63

Hence the initial sewage load is 200KLD and the total is 1.2MLD. Due to uncertainty in the time
duration of construction of towers, constructing and maintaining one single STP for the entire
development of 8 towers is not a good decision.

CPG Consultants India Pvt Ltd., Page 7


Kaveri Watermarke Sewerage Treatment Plant Report

Tower 1a 80
KLD

Tower 1b 80
KLD
STP Capacity
200 KLD

Tower 2a 30
KLD (6 floors)

Club house 10
KLD (2 floors)

Even the Phase-1 construction shall be done in various stages starting with Tower1A as
shown in the drawing.
The following points can be noted:
Tower 1A will be constructed first; hence we recommend a mobile STP of 100 KLD
capacity to be used for Tower 1A. This can take care of sewage during construction
stage for other tower as well and can even be shifted to other sites.

Since rate at which the tower is occupied will be slow initially we suggest that this
modular STP be used till tower 1B is fully occupied. By the time Tower-1A and 1B has
full occupancy a STP of 200 KLD can be constructed and can start operating with a load
of 160 KLD.

During such time if the phase 2 development is certain and is on the papers its
sewerage contribution can be envisaged and capacity of the STP can hence be decided.

We can design the STP and plan for the same at the beginning of phase 2 and ending of
phase 1.

CPG Consultants India Pvt Ltd., Page 8


Kaveri Watermarke Sewerage Treatment Plant Report

4.0 Area Requirement and Costing:

The cost of a mobile STP of 100KLD capacity is approximately 25, 75,000


INR.The area requirement for a 200 KLD STP is 230 sqm and the costing shall
be approximately 45, 00,000 INR.

CPG Consultants India Pvt Ltd., Page 9


Kaveri Watermarke Sewerage Treatment Plant Report

CPG Consultants India Pvt Ltd., Page 10

You might also like