Professional Documents
Culture Documents
24 WMP Block 8
25 Construction of outlet settling pond WMP 31 & 32
26 Road diversion Nyapa Indah A
33 Construction of WMP 46
34 Haul road diversion block 14 (Pit D2 Expansion) A
Project Design Optimization Report
Progress
Description PIC
Target Actual
Mechanical
Civil
Earth Work
- Earth work Design BOW
Electrical
Mechanical
Civil
Earth Work
- Earth work Design BOW 20/6/2016 14/6/2016
Electrical
Earth Work
- Earth work Design BOW 30/8/2016 24/8/2016
Mechanical
Civil
Earth Work
- Earth work Design BOW 15/6/2016 30/5/2016
Electrical
Mechanical
Civil
Earth Work
- Earth work Design BOW 30/9/2016 20/9/2016
Electrical
Mechanical
Civil
Earth Work
- Earth work Design BOW
Electrical
Mechanical
Civil
Earth Work
- Earth work Design BOW
Electrical
Earth Work
- Earth work Design BOW 15/2/2016 3/2/2016
Earth Work
- Earth work Design BOW 20/7/2016 19/7/2016
Earth Work
- Earth work Design BOW 10/2/2016 7/2/2016
Earth Work
- Earth work Design BOW 15/10/2016 11/10/2016
Earth Work
- Earth work Design BOW 30/1/2016 22/1/2016
Earth Work
- Earth work Design BOW 25/1/2016 21/1/2016
Earth Work
- Earth work Design BOW 30/1/2016 22/1/2016
Approved by,
Adi Supriyatna
(CHID Dept. Head)
Remark
revisi design
Approved by,
Adi Supriyatna
(CHID Dept. Head)
Contractor/Vendor Se
B
C
D
2 WMP Block 14
3 Supporting Fac. WMP Block 7 at BMO 2
4 Suaran in Loading Stage III (Additional Sykline)
5 Revitalization TLC-1 CPP BMO
6 Upgrade haul road LMO
7 Weighbridge Binungan Block 7
8 Road betterment km 0+000 to 5+200 Binungan - Suaran
9 Control system migration Suaran km. 28
10 Lati Fix Plant Optimization
11 Fuel Tank 2000 kL
12 WMP 34, 41, 42, 43, 44 & 45 at SMO
13 WMP 25 & 27
14 Culvert (pipe steel) Supply for WMP at SMO
15 Culvert (pipe steel) Supply for WMP at BMO 1
16 Culvert (pipe steel) Supply for WMP at BMO 2
17 Construction TLC-3 Binungan
18 Pile protection Jetty Suaran
19 Repair of mooring pile at Lati, Tg Perangat
20 Haul road widening KM6 Binungan - Suaran
21 Straightening km 3+000 haul road Binungan - Suaran
22 Weighbridge rectification at LMO
23 In Loading & Stockpile Suaran Expansion Stage II
24 Upgrade haul road (Block 7 CPP)
25 WMP Block 8
26 Construction of outlet settling pond WMP 31 & 32
27 Road diversion Nyapa Indah
28 Haul road diversion block 14 (Pit K12 Expansion)
29 Supporting facilities of WMP Block 56 (Pit Y)
30 Medium Voltage Line PLN BLK to Office Blok Parapatan
31 Mechanical sampler installation at TL3 CPP Binungan
32 Mobile bridge
33 Road diverison INHUTANI
34 Construction of WMP 46
35 Haul road diversion block 14 (Pit D2 Expansion)
Contractor/Vendor Selection Report
Progress
Description PIC
Target
Contractor Selection DCS/LKS
Structure & Mechanical
- Drive 75 kW dan 200 kW DCS/ISM/HHW
Civil DNK/DFA/BST
Earth Work BOW
Electrical IRF/NOP
Approved
Adi Supriya
(CHID Mana
Progress
Remark
Actual
Project Cancelled
Project Cancelled
Project Cancelled
Project Cancelled
Project Cancelled
Project Cancelled
Project Cancelled
Project Cancelled
Project Cancelled
Approved by,
Adi Supriyatna
(CHID Manager)
Project Method of Cons
B
C
D
2 WMP Block 14
3 Supporting Fac. WMP Block 7 at BMO 2
4 Suaran in Loading Stage III (Additional Sykline)
5 Revitalization TLC-1 CPP BMO
6 Upgrade haul road LMO
7 Weighbridge Binungan Block 7
8 Road betterment km 0+000 to 5+200 Binungan - Suaran
9 Control system migration Suaran km. 28
10 Lati Fix Plant Optimization
11 Fuel Tank 2000 kL
12 WMP 34, 41, 42, 43, 44 & 45 at SMO
13 WMP 25 & 27
14 Culvert (pipe steel) Supply for WMP at SMO
15 Culvert (pipe steel) Supply for WMP at BMO 1
16 Culvert (pipe steel) Supply for WMP at BMO 2
17 Construction TLC-3 Binungan
18 Pile protection Jetty Suaran
19 Repair of mooring pile at Lati, Tg Perangat
20 Haul road widening KM6 Binungan - Suaran
21 Straightening km 3+000 haul road Binungan - Suaran
22 Weighbridge rectification at LMO
23 In Loading & Stockpile Suaran Expansion Stage II
24 Upgrade haul road (Block 7 CPP)
25 WMP Block 8
26 Construction of outlet settling pond WMP 31 & 32
27 Road diversion Nyapa Indah
28 Haul road diversion block 14 (Pit K12 Expansion)
29 Supporting facilities of WMP Block 56 (Pit Y)
30 Medium Voltage Line PLN BLK to Office Blok Parapatan
31 Mechanical sampler installation at TL3 CPP Binungan
32 Mobile bridge
33 Road diverison INHUTANI
34 Construction of WMP 46
35 Haul road diversion block 14 (Pit D2 Expansion)
Project Method of Construction Report
Progress
Description PIC
Target
Structure & Mechanical
- JSA pekerjaan lifting DCS/ISM/HHW
- Schedule Construction - Structure Mechanical
Civil DNK/DFA/BST
Earth Work BOW
Electrical IRF/NOP
Approved
Adi Supriya
(CHID Mana
Progress
Remark
Actual
Project Cancelled
Project Cancelled
Project Cancelled
Project Cancelled
Project Cancelled
Project Cancelled
Project Cancelled
Project Cancelled
Project Cancelled
Approved by,
Adi Supriyatna
(CHID Manager)
Project Quality Con
B
C
D
2 WMP Block 14
3 Supporting Fac. WMP Block 7 at BMO 2
4 Suaran in Loading Stage III (Additional Sykline)
5 Revitalization TLC-1 CPP BMO
6 Upgrade haul road LMO
7 Weighbridge Binungan Block 7
8 Road betterment km 0+000 to 5+200 Binungan - Suaran
9 Control system migration Suaran km. 28
10 Lati Fix Plant Optimization
11 Fuel Tank 2000 kL
12 WMP 34, 41, 42, 43, 44 & 45 at SMO
13 WMP 25 & 27
14 Culvert (pipe steel) Supply for WMP at SMO
15 Culvert (pipe steel) Supply for WMP at BMO 1
16 Culvert (pipe steel) Supply for WMP at BMO 2
17 Construction TLC-3 Binungan
18 Pile protection Jetty Suaran
19 Repair of mooring pile at Lati, Tg Perangat
20 Haul road widening KM6 Binungan - Suaran
21 Straightening km 3+000 haul road Binungan - Suaran
22 Weighbridge rectification at LMO
23 Upgrade haul road (Block 7 CPP)
24 WMP Block 8
25 Construction of outlet settling pond WMP 31 & 32
26 Road diversion Nyapa Indah
27 Haul road diversion block 14 (Pit K12 Expansion)
28 Supporting facilities of WMP Block 56 (Pit Y)
29 Medium Voltage Line PLN BLK to Office Blok Parapatan
30 Mechanical sampler installation at TL3 CPP Binungan
31 Mobile bridge
32 Road diverison INHUTANI
33 Construction of WMP 46
34 Haul road diversion block 14 (Pit D2 Expansion)
Project Quality Control Report
Progress
Description PIC
Target
Structure & Mechanical
- Approval Drawing & BOQ DCS/ISM/HHW
- Site Inspection report
- Spesifikasi Teknis for Tender
Civil DNK/DFA/BST
Earth Work BOW
Electrical IRF/NOP
Approved
Adi Supriya
(CHID Mana
Progress
Remark
Actual
Project Cancelled
Project Cancelled
Project Cancelled
Project Cancelled
Project Cancelled
Project Cancelled
Project Cancelled
Project Cancelled
Project Cancelled
Approved by,
Adi Supriyatna
(CHID Manager)
Project Behind Budget/ Budge
Budget
Description PIC
Proposal
Structure & Mechanical
Civil
Earth Work BOW
Electrical
Overal Budget
Approved by,
Adi Supriyatna
(CHID Manager)
Budget
Remark
Actual
Project Cancelled
Project Cancelled
Project Cancelled
Project Cancelled
Project Cancelled
Project Cancelled
Project Cancelled
Project Cancelled
Project Cancelled
Approved by,
Adi Supriyatna
(CHID Manager)
Project On Tim
2 WMP Block 14
3 Supporting Fac. WMP Block 7 at BMO 2
4 Suaran in Loading Stage III (Additional Sykline) A
B
C
D
24 WMP Block 8
25 Construction of outlet settling pond WMP 31 & 32
26 Road diversion Nyapa Indah
27 Haul road diversion block 14 (Pit K12 Expansion)
28 Supporting facilities of WMP Block 56 (Pit Y)
29 Medium Voltage Line PLN BLK to Office Blok Parapatan
30 Mechanical sampler installation at TL3 CPP Binungan
31 Mobile bridge
32 Road diverison INHUTANI
33 Construction of WMP 46
34 Haul road diversion block 14 (Pit D2 Expansion)
Project On Time Report
Progress
Description PIC
Target
Structure & Mechanical
Civil
Earth Work BOW 30/4/2016
Electrical
Approved
Adi Supriya
(CHID Mana
Progress
Remark
Actual
30/4/2017
on progress
on progress
15/7/2016 finish
- on progress
30/4/2016 finish
30/06/2016 finish
31/8/2016 finish
31/8/2016 finish
Project Cancelled
Project Cancelled
Project Cancelled
Project Cancelled
Project Cancelled
Project Cancelled
Project Cancelled
Project Cancelled
Project Cancelled
Approved by,
Adi Supriyatna
(CHID Manager)
Complieence
1 HO
2 In Loading & Stockpile Suaran Expansion Stage II
3 WMP Block 14
4 Supporting Fac. WMP Block 7 at BMO 2
5 Suaran in Loading Stage III (Additional Sykline)
6 Revitalization TLC-1 CPP BMO
Progress
Description PIC
Target
DFA Hijau
ABT/DNK Hijau
- Sosialisai Procedure terkait ABT/DNK Dilaksanakan
- Record (P5M, Safet talk, Incident report, KTA TTA, inspecti ABT/DNK Dilaksanakan
- LK3 Meeting ABT/DNK Dilaksanakan
TOM Hijau
- Sosialisai Procedure terkait ABT/DNK Dilaksanakan
- Record (P5M, Safet talk, Incident report, KTA TTA, inspecti ABT/DNK Dilaksanakan
- LK3 Meeting ABT/DNK Dilaksanakan
App
Adi
(CHID
Progress
Remark
Actual
Hijau
Dilaksanakan disiapkan dokumen yg dibutuhkan
Dilaksanakan disiapkan dokumen yg dibutuhkan
Dilaksanakan disiapkan dokumen yg dibutuhkan
Project Cancelled
Project Cancelled
Project Cancelled
Project Cancelled
Project Cancelled
Project Cancelled
Project Cancelled
Project Cancelled
Project Cancelled
Approved by,
Adi Supriyatna
(CHID Manager)
Learning & Growth of even
2 Electrical 1
3 Civil 1
2
4 Other 1
Learning & Growth of event - personnel development Report
Progress
Description PIC
Target
Material handling
AUTO CAD ISM/BOW 50%
Cost control
App
Adi
(CHID
Progress
Remark
Actual
Approved by,
Adi Supriyatna
(CHID Manager)
Safety Per
No Area Description
1 HO
2 Suaran - Lati
3 Binungan - SMO
Safety Performance Report
Progress
Description PIC
Target
App
Adi
(CHID
Progress
Remark
Actual
Approved by,
Adi Supriyatna
(CHID Manager)
R
No Area Description
2 WMP Block 14
3 Supporting Fac. WMP Block 7 at BMO 2
4 Suaran in Loading Stage III (Additional Sykline)
5 Revitalization TLC-1 CPP BMO
6 Upgrade haul road LMO
7 Weighbridge Binungan Block 7
8 Road betterment km 0+000 to 5+200 Binungan - Suaran
9 Control system migration Suaran km. 28
10 Lati Fix Plant Optimization
11 Fuel Tank 2000 kL
12 WMP 34, 41, 42, 43, 44 & 45 at SMO
13 WMP 25 & 27
14 Culvert (pipe steel) Supply for WMP at SMO
15 Culvert (pipe steel) Supply for WMP at BMO 1
16 Culvert (pipe steel) Supply for WMP at BMO 2
17 Construction TLC-3 Binungan
18 Pile protection Jetty Suaran
19 Repair of mooring pile at Lati, Tg Perangat
20 Haul road widening KM6 Binungan - Suaran
21 Straightening km 3+000 haul road Binungan - Suaran
22 Weighbridge rectification at LMO
23 In Loading & Stockpile Suaran Expansion Stage II
24 Upgrade haul road (Block 7 CPP)
25 WMP Block 8
26 Construction of outlet settling pond WMP 31 & 32
27 Road diversion Nyapa Indah
28 Haul road diversion block 14 (Pit K12 Expansion)
29 Supporting facilities of WMP Block 56 (Pit Y)
30 Medium Voltage Line PLN BLK to Office Blok Parapatan
31 Mechanical sampler installation at TL3 CPP Binungan
32 Mobile bridge
33 Road diverison INHUTANI
34 Construction of WMP 46
35 Haul road diversion block 14 (Pit D2 Expansion)
Reporting
Progress
Description PIC
Target
Daily report BHO/HWY/MHR 100%
Weekly report ABT 100%
App
Adi
(CHID
Progress
Remark
Actual
100%
100%
Project Cancelled
Project Cancelled
Project Cancelled
Project Cancelled
Project Cancelled
Project Cancelled
Project Cancelled
Project Cancelled
Project Cancelled
Approved by,
Adi Supriyatna
(CHID Manager)
No KPI Description Score
-JSA
'- IK
'- Schedule/sequence pekerjaan