You are on page 1of 2

ITP Reference

Number:AFISR/MEP/E/022

Project Title AL FORSAN HOTEL


Agreement No: Rev: 00
Inspection and Test Plan for: Installation of Auto Transfer Switch Panel
GP-213 Date: 27-MAR- 13
Location:
Legends: ITL= Independent Testing Laboratory, SUB-CON= Sub-Contractor, CONT= Contractor, Inspection Points: H= Hold Point, W= Witness Point, R= Review
ITP= Inspection and Test Plan, CI= Comments Incorporated Point, S= Surveillance, A=Approval

Inspection Points
Inspection and Test Specification
Item No. Activity Description Frequency Acceptance Criteria Verifying Document / Report
Activity Reference SUB-CON CONT ITL ENGINEER

1 Material Approval

A33 Quality
Before site Standards and
AUTO TRANSFER SWITCH Approved Material Submittal
1.1 Submit to the Engineer execution of the ENGINEER Approval Control,170.005 R R - R/A
PANEL Form
activity Standard and
Regulation

2 Drawing Submittal

Part A, A31
Before site
Ayto Transfer Switch Schematic Provision,Content Approved Shop Drawings
2.1 Submit to the Engineer execution of the Workmanlike. ENGINEER Approval R R -- R/A
Diagram and use of Submittal Form
activity
Documents

3 Method Statement

Part B, Section
V11/12/20
Before site
Method Statement for Installation Clauses Y71
3.1 Submit to the Engineer execution of the Workmanlike. ENGINEER Approval R R -- R/A Approved Method Statement
Auto Transfer Switch Panel Section V20
activity
300.275

4 Delivery & Storage

Part B, Section
V11/12/20
Visual Inspection for damages Every Delivery Proper identification, same as specification,
AUTO TRANSFER SWITCH Clauses Y71 Material Inspection Check
4.1 and appearance. Inspection and movement of finish and packing. Storage and protection as H S -- S
PANEL Section V20 sheet
for dimensions' verification material per manufacturers recommendation
300.275

Page 1 of 2
ITP Reference
Number:AFISR/MEP/E/022

Project Title AL FORSAN HOTEL


Agreement No: Rev: 00
Inspection and Test Plan for: Installation of Auto Transfer Switch Panel
GP-213 Date: 27-MAR- 13
Location:
Legends: ITL= Independent Testing Laboratory, SUB-CON= Sub-Contractor, CONT= Contractor, Inspection Points: H= Hold Point, W= Witness Point, R= Review
ITP= Inspection and Test Plan, CI= Comments Incorporated Point, S= Surveillance, A=Approval

Inspection Points
Inspection and Test Specification
Item No. Activity Description Frequency Acceptance Criteria Verifying Document / Report
Activity Reference SUB-CON CONT ITL ENGINEER

5 Installation

Part B, Section
V11/12/20
AUTO TRANSFER SWITCH Inspection for the proper For each floor Installation is as per the approved method Clauses Y71
5.1 H H - A Quality Check Sheet
PANEL installation of Earthing system level statement Section V20
300.275

Comments if any:

MEP CONTRACTOR CONTRACTOR ENGINEER

SIGN: SIGN: SIGN:

NAME: NAME: NAME:

DATE: DATE: DATE:

Page 2 of 2