You are on page 1of 9

Robust, flexible and operational mine design

strategies
B. Groeneveld*1, E. Topal2 and B. Leenders3
Strategic planning in mining is an important value accretive process. One of the most essential
aspects during the planning phase is determining the correct system design. A traditional mine
design process develops a fixed system for one set of conditions or expected values. An
alternative is to develop a robust system that deals with variation, by handling a range of
conditions within the optimisation process. Conversely, a flexible design can be generated which
changes the system dynamically over time in response to change. It is hypothesised that a flexible
design generates more value than a robust design which in turn generates more value than a
traditional design. However, due to constant change, a fully flexible design is not practical.
Ideally, a hybrid of the two methods would be optimal. An operational design is proposed as a
manual solution to this problem. This paper compares these different new design methodologies.
Keywords: Strategic planning, Decision making, Mine design, Robust mine design, Flexible mine design

Introduction the matter worse, production needs to be maintained so


the only option is to build a new crusher. Unfortunately,
Decision making in mining operations can take many this will come at a significant capital cost and time to
years due to the period of time required to explore and build; reducing the overall value of the operation had
develop a large deposit. During the study and construc- this flexibility initially been incorporated. This upfront
tion period, many uncertainties can unfold and multiple flexibility is difficult to justify with current decision
economic cycles may occur. Making decisions based on making tools. Advances in an area broadly known as
single point estimates of the future limits flexibility, real options in projects (ROIP) are beginning to
potentially resulting in premature foreclosure of an address this gap (de Neufville et al., 2005; de Neu-
operation. By considering changing conditions (both fville, 2006; Wang and de Neufville, 2005, 2006; Cardin
upwards and downwards movements) in the decision et al., 2008; Groeneveld et al., 2009).
making process, a company is able to include flexibility Real options in projects are located midway between
in an operation allowing value to be maximised. Current financial real options analysis (which does not deal with
methodologies impair a decision makers ability to engineering system flexibility) and traditional engineering
justify this additional flexibility. approaches (which do not deal with financial flexibility).
Building flexibility into an operation provides a An analysis done using ROIP methods allows the design
company with the ability to quickly respond to change; of a system under uncertainty to be studied. Through the
however, flexibility comes at a price. For example, an analysis process, the value of each design option can be
operation of building a crusher to feed a processing tested. Having this information allows the decision maker
plant has an initial plan to produce at 6 Mtpa. An to make an informed decision on what flexibility to in-
option exists to build the allowance for a plant corporate in the final design.
expansion to 8 Mtpa (by increasing the size of the Previous papers using ROIP methods have shown the
foundations and footings to allow physical room for value of this technique (Cardin et al., 2008; Groeneveld
larger equipment). However, when the decision to build et al., 2009; Groeneveld and Topal, 2011). Cardin et al.
the plant is made, to minimise initial capital investment, (2008) implemented this technique for mining projects
this flexibility is removed. One year into the operation, with a Chilean mine in the Cluster Toki region. In the
the sale price of the product doubles and costs slightly paper, a methodology is implemented where operating
increase, while all other variables hold. In this environ- plans are varied by truck fleet capacity and crusher size
ment, it is considered favourable to expand the in response to changing prices. For each price scenario,
operation; however, due to the cost cutting decision, the optimal operational plan is selected. The application
this flexibility was removed from the plant and to make of this method resulted in y30% more project value
than current estimates. This paper provides a strong
1
basis on which to grow ROIP theory in mining. Though
Telfer Mine, Newcrest Mining Limited, Melbourne, Vic., Australia
2
Mining Engineering Department, Western Australia School of Mines, there are several deficiencies in the model. The approach
Curtin University of Technology, Kalgoorlie, WA, Australia limits the flexibility by only including a handful of static
3
Strategic Development, Rio Tinto Iron Ore, Perth, WA, Australia operational plans; it assumes that the schedule of
*Corresponding author, email benjamin.groeneveld@gmail.com material moved is fixed, fails to deal with variation in

2012 Institute of Materials, Minerals and Mining


Published by Maney on behalf of the Institute and The AusIMM
Received 20 March 2011; accepted 29 October 2011
20 DOI 10.1179/1743286311Y.0000000018 Mining Technology 2012 VOL 121 NO 1
Groeneveld et al. Robust, flexible and operational mine design strategies

ore grade and recovery and fails to consider options in physical extraction capacity that is required to move
the main value adding stages of a mining operation. material from the ground. This constraint may be an
Groeneveld et al. (2009) outlined a methodology for annual tonnage constraint or an effective flat haul
determining a flexible mine design by dynamically constraint which considers the time required to move
including design options in the optimisation in order material. Preprocessing stockpiles are stores of material
to maximise value. Multiple states of the world were after extraction from the ground, either for long term
simulated and the optimal design for each state was low grade scenarios, fluctuating demand scenarios or for
determined. A dataset of results was formed from the waste material storage. Processing plant options repre-
output of each simulated scenario. From this dataset, a sent the physical and/or chemical process that is
cumulative probability graph was produced, commonly undertaken to recover ore from the gangue material.
known as a value at risk graph. This resulting curve Capacity constraint options represent physical capacity
represents a theoretical maximum achievable value. constraints at any point in the network. These may
However, this assumes that a decision maker can make represent attributes such as port capacity, loading
perfect decisions. In reality, this is impracticable. facilities, crusher capacities or conveyor capacities.
An alternative is to produce a single fixed design which
handles optimally handles change. This is achieved by Resource representation
taking the full set of uncertainties into the optimisation The representation of the resource in the model is by
and developing a fixed design that optimally handles the parcels of material which contain multiple grade bins.
changing uncertainties. The resultant design would be a These parcels are designed to represent a physical
robust design as it would best handle variation. Since the constraint on the resource, such that they must be fully
optimisation includes high price and low price scenarios, mined before mining a parcel lower in the physical
it will attempt to produce a design that minimises any sequence. A parcel may be made up of one or more
losses and maximise any potential upside, while consider- grade bins. The average grade of a parcel is the weighted
ing that these are extreme scenarios and the main average of the grade bins. A grade bin represents a
scenarios are around the average. Note that this design quantity of material at a specified grade. The size of the
is fundamentally different to a design just generated based parcels can be determined by the modeller, but each
on the average value and this will be shown in the parcel requires a binary variable in the model for
illustrative case study. scheduling which increases the solution time of the
However, a robust design proposes that a set and model. However, the grade bins within a parcel are an
watch approach is taken by management. Therefore, it attempt to provide a level of detail that maintains the
fails to value active management of an operation. So, a selectivity of the model.
flexible model proposes constant change which is not
practicable and a robust model does not allow manage- Flow paths
ment decisions. To overcome these limitations, it is A flow path represents a route for material to travel.
proposed that an operational design be generated where Multiple processing plants/routes can be included and
the initial periods have a fixed robust design and the products can be generated at any point in the network.
later years have a flexible design where management has Different routes through the network are termed flow
the ability to have multiple options in the pipeline. paths. To explain this concept, further consider Fig. 1.
This paper compares these different design methodol- Examples of flow paths in Fig. 1 include the path
ogies. A summary of the methodology used for generat- from the resource (R) to mine 1 (M1) to stockpile 1 (S1)
ing the designs is outlined followed by the mathematical to plant 1 (P1) through circuit 1 (C1) to product A which
formulation of the robust design under uncertainty, using would be RM1S1P1C1A, the path from the resource (R)
mixed integer programming (MIP) and Monte Carlo to mine 1 (M1) to waste stockpile 1 (W1) which would
simulation (MCS) techniques. Furthermore, an opera- be RM1W1, the path from the resource (R) to mine 1
tional design is proposed as a solution to the limitations (M1) to stockpile 1 (S1) to plant 4 (P4) through circuit 2
of the robust and flexible design methodologies. Finally, (C2) to product B (B) which would be RM1S1P4C2B
the different design methodologies are compared against and the path from the resource to mine 3 (M3) to
each other and a traditional design approach, in an illu- stockpile 1 (S1) to plant 3 (P3) through circuit 1 (C1) to
strative case study. product A (A) which would be RM3S1P3C1A. This is
only a small number of the potential paths through the
network.
Methodology
It is proposed that for these different design scenarios, a Stockpiling
combination of MCS and MIP techniques be utilised. Stockpiling is used in mine operations for many reasons
Uncertainties (or stochastic parameters) are simulated including blending of material, storage of excess mine
through MCS as inputs to the MIP model. The MIP production, storage of waste material and storage of low
model allows for go or no go decisions to be grade ore for future production. When material is
modelled. An optimised MIP model therefore deter- stockpiled, the grade and tonnage of the material is
mines the optimal execution timing of design options for known. However, as the material is mixed on the
a set of uncertainties (states of the world). stockpile, the grade and the tonnage become unknown.
Since the quantity of material in the stockpile is
Design options unknown before the optimisation, this gives rise to a
Four categories of system design options are incorpo- non-linear constraint. To solve this problem, virtual
rated in the model. These are mine options, preproces- grade bins are created in the stockpile. These grade bins
sing stockpile options, processing plant options and have a maximum and minimum grade of material which
capacity constraint options. Mine options represent the can enter the bin. As material is added to a stockpile, it

Mining Technology 2012 VOL 121 NO 1 21


Groeneveld et al. Robust, flexible and operational mine design strategies

1 Example network of design options showing numerous ow paths

will be fed into a grade bin that has a suitable grade state of a project is difficult if not impossible. The
range. Many grade bins can be created without adver- proposed methodology provides information and insight
sely affecting the performance of the model which limits that can be used by the decision maker in conjunction
the averaging effect. with other tools to make timely, informed and value
adding decisions.
Stochastic parameters
The model incorporates uncertainty around the input Robust design
parameters by MCS. Each simulation of values repre- A new robust design methodology is proposed in this
sents a state of the world that is equally probable in the paper to develop a design that better handles all states
future. Various parameters can be incorporated in the of the world as opposed to just a single design. It uses
model, for example price, capital cost, operating cost, the same concepts and assumption developed in the
equipment utilisation, recovery and time to build. flexible design model but differs by considering numer-
Running a set of simulations is intended to give a ous states at once. A robust design is achieved by solving
representative sample of the future states of the world. one large MIP model that generates one design from
multiple possible options. In essence, this design is the
Models one which handles a range of conditions the best out of
all possible options.
Three different models have been proposed in order to
justify increased flexibility to determine a flexible design, Operational design
a robust design and an operational design. All models An operational design methodology is proposed as a
use MCS and MIP techniques to determine a system practical alternative to overcome the limitations of the
design. The fundamental difference between the models robust and flexible methods. Essentially, an operational
is that under a robust design, multiple states of the design is where the initial years of a fully flexible design
world are considered together, while a flexible design have been fixed by the modeller. This allows manage-
considers just one state of the world at a time. An ment to make decisions today to enable the business to
operational design is developed by determining a fixed be an ongoing concern. By not fixing future decisions,
design for the first couple of periods and having a management can maintain flexibility in order to benefit
flexible design for periods after that. The flexible design from any upside potential and minimise any downside
model has been published previously in (Groeneveld risk. As this method incorporates future flexibility into
et al., 2009; Groeneveld and Topal, 2011). The robust the analysis, the impact of the initial fixed decisions can
model is outlined in this paper and the operational plan be tested and tweaked in order to maximise value.
is a new hybrid of these two models with the main
difference that the design in the initial years is fixed. Robust model formulation
That is no binary value exits for design options in the
initial periods. The developed MIP model optimises the system design
for a risk neutral investor for all simulated states of the
Flexible design world. Each design option can impact capital commit-
Some researchers (Groeneveld et al., 2009; Groeneveld ment, revenue generated and operating expenses. The
and Topal, 2011) have previously outlined a methodol- optimisation process seeks to determine the design with
ogy for undertaking flexible mine design. The basis of the highest equally weighted net present value for all
these models was to optimise a design for a given single given financial and technical scenarios. An outline of the
state of the world. This was achieved by including mathematical formulation is provided below.
mining, plant and capacity constraint design options in
the system and allowing the MIP model to internally Notation
handle the design options. MCS was used to generate Indices
these different states of the world. b a grade bin of material within a parcel
This methodology assumes that a decision maker d product type
makes optimal decisions based on the knowledge of all e dependent options
states of the project over time (i.e. what price and costs f flow path of material through the design
occurred over time). In reality, forecasting the exact final network

22 Mining Technology 2012 VOL 121 NO 1


Groeneveld et al. Robust, flexible and operational mine design strategies

g grade element of material within a resource XOs,j,t,n the flow out from stockpile s bin j in time t
j bin of material within a stockpile: this bin for trial n
will have a maximum and minimum grade of Xp,b,f,t,n the tonnage from parcel p bin b through flow
material which can enter path f in time t for trial n
l design options Xf,t,n the tonnage mined through flow path f in
m mining options within the set of design time t for trial n
options Xp,b,t,n the tonnage mined from parcel p bin b in
n simulated state of the world time t for trial n
p parcel of material Xpzl,b,t,n the tonnage mined from the successor parcel
r required rate of return on the project pz1 bin b in time t for trial n
t time period step (periods do not need to be Ye,t  the dependent option e of Yl,t 
equal) 1, if option l is executed in time t;
Yl,t
s stockpiling options within the set of design 0, otherwise:
options ( )
1, if pushback p is fully mined in
y tolerance factor for the deviation of the Yp,t,n time t for trial n;
mining of a bin within a parcel 0, otherwise:
Capitalised indices are the maximum value or upper
limit of that index.
Formulation
Parameters Objective function
Cl,t,n the capital cost of option l in time t for trial n The objective function seeks to maximise the equally
Dd,t,n the capacity of product d in time t for trial n weighted before tax net present value (NPV) for all
Dl,t,n the disposal cost of option l in time t for trial simulated states of the world
n ( "
Xn
1 XT
1 X
D,G
DT the lag time between these relationships (i.e. Pd,g,t,n Gg,d,t,n {
N 1zr t
build option two, three periods after option n~1 t~1 d~1,g~1

one) X
P,B,F X
P,B,F
Vl,t,n Xp,b,f,t,n { Mp,b,l,t,n Xp,b,f,t,n { (1)
FDl,t,n the fixed cost saved from not operating p~1,b~1,f~1jl[f p~1,b~1,f~1jl[f jl[m
option l from time t for trial n to the end of 39
XL XL XL XL =
the project life T Cl,t,n Yl,t { Fl,t,n Yl,t { Dl,t,n IDl,t z FDl,t,n IDl,t 5
;
Fl,t,n the fixed cost of operating option l from time l~1 l~1 l~1jt=1 l~1jt=1

t for trial n to the end of the project life T


GLg,d the lower grade limit of grade g product d The constraints in the model can be divided into five
GLj the lower grade limit of bin j categories: resource, option, stockpiling, product and
GUg,d the upper grade limit of grade g product d flow balance constraints.
GUj the upper grade limit of bin j
Gp,b the grade of parcel p bin b Resource constraints
Gg,l,n the grade g through plant l for trial n X
T
Gg,s,j the calculated average, maximum or mini- Xp,b,t,n {Rp,b 0 V p,b,n (2)
mum metal units of grade g in stockpile s in t~1
bin j
Kl,t,n the capacity of option l in time t for trial n X
B,t X
B
Xp,b,tt,n Rp,b Yp,t,n V p,t,n (3)
Ks,t,n the stockpile capacity of stockpile s in time t
b~1,tt~1 b~1
for trial n
Mp,b,l,t,n the mining cost from parcel p to bin b X
t
through mine option l in time t for trial n Xpz1,b,t,n Rpz1 Yp,tt,n Vp,t,n (4)
Pg,d,t,n the sale price of grade element g for product tt~1
d in time t for trial n (in $/metal unit)
Rl the recovery of material through circuit l X
T
Rs,j the calculated average, maximum or mini- Yp,t,n 1 Vp,n (5)
mum recovery for all material in stockpile s t~1
bin j
Rp,b the available resource of parcel p bin b XB
1 1
Xp,b,t,n { Xp,b,t,n c% V p,b,t,n (6)
Rpz1 the available resource of the successor parcel R Rp,b
b~1 p,b
pz1
Vl,t,n the variable cost of option l in time t for trial n XB
1 1
Xp,b,t,n { Xp,b,t,n {c% V p,b,t,n (7)
Variables b~1
R p,b R p,b
Gg,d,t,n the metal units of grade g produced for
The resource constraints in the model limit what
product d in time t for trial n
  quantities and grades of material can be produced by
1, if option l is disposed in time t; the system. The amount of material extracted from a
IDl,t
0, otherwise: mining grade bin in a pit has an upper bound based on
XIs,j,t,n the flow in from stockpile s bin j in time t for the resource model which is constrainted by equa-
trial n tion (2). Scheduling constraints are encorporated by

Mining Technology 2012 VOL 121 NO 1 23


Groeneveld et al. Robust, flexible and operational mine design strategies

equations (3) and (4). Equation (3) ensures that a parcel Table 1 Summary of deposit
is fully mined by setting the binary value to 1 in the period
Tonnage/
that the parcel is fully mined. Equation (4) forces a parcel Parcel Bins Type Mtpa Copper/% Gold/g t21
predecessor to be fully mined before mining starting in
the sucessor. Equation (5) is a set packing constraint 1 37 Ore 73.8 1.3 0.1
which forces a parcel to only be mined once. Two fur- 1 1 Waste 118.3
ther optional constraints (equations (6) and (7)) try to 2 29 Ore 57.5 1.4 0.2
minimise grade variability by restricting the model to 2 1 Waste 244.5
3 9 Ore 14.5 1.4 0.1
mine low grade and high grade material within a parcel in 3 1 Waste 74.1
an even ratio within a given tolerance value (y%). 4 18 Ore 25.6 1.2 0.1
4 1 Waste 190.86
Option constraints
X
F X
t X
t{1
Xf,t,n{ Kl,t,n Yl,tt z Kl,t,n IDl,tt 0 V l,t,n (8) exceed the material entering the stockpile, modelled by
f~1jl[f tt~1 tt~1
equation (13). Equation (14) applies an upper limit to
the stockpiling capacity.
X
t{DT
Yl,t { Ye,tt 0 V l,t (9) Product constraints
tt~1je[l X
P,B,F
Gg,d,t,n {GUg,d Rl Xp,b,f,t,n {
X
t{1 X
t{1 p~1,b~1,f~1jd,l[fjs=
[f
IDl,t { Yl,tt { IDl,tt 0 V l,t=1 (10) (15)
tt~1 tt~2
X
F,J,S
GUg,d Rs,j XOs,j,t,n 0 V g,d,t,n
Six constraints are used to model the various design f~1,j~1,s~1jd,j,s[fjt=1
options. Each option is reflected in the model by a binary
variable. This binary variable reflects a decision about X
P,B,F
whether this option is used or not. An upper capacity Gg,d,t,n {GLg,d Rl Xp,b,f,t,n {
limit for each option is set through equation (8). Option p~1,b~1,f~1jd,l[fjs=
[f
dependence relationships can be modelled through the (16)
use of equation (9). Equation (10) introduces a disposal X
F,J,S
GLg,d Rs,j XOs,j,t,n 0 V g,d,t,n
binary variable to model disposal or closure of an option f~1,j~1,s~1jd,j,s[fjt=1
and this equation ensures that options cannot be disposed
of unless they have previously been built.
X
P,B,F

Stockpiling constraints Dd,t,n { Rl Xp,b,f,t,n {


p~1,b~1,f~1jd,l[fjs=
[f
X
P,B,F
XIs,j,t,n ~ Xp,b,f,t,n X
F,J,S

p~1,b~1,f~1js,j[f
Rs,j XOs,j,t,n 0 V d,t,n (17)
f~1,j~1,s~1jd,j,s[fjt=1
V s,j,t,njGp,b wGLj and Gp,b vGUj (11)
The system can produce multiple products allowing
different marketing strategies to be analysed. Two
X
F
XOs,j,t,n ~ Xf,t,n V s,j,t,n (12) equations handle the grade limits for the various
f~1js,j[f
products produced by equations (15) and (16).
Equation (15) determines the grade of the material
X
t{1 X
t{1 through the flow path less the upper grade limit
XOs,j,t,n XIs,j,tt,n { XOs,j,tt,n V s,j,t,n (13) multiplied by the material recovered from the plant.
tt~1 tt~2 Equation (16) handles the lower grade limit. An upper
capacity limit for the amount of product produced is
X
J,t X
J,t restricted through equation (17).
Ks,t,n XIs,j,tt,n { XOs,j,tt,n V s,t,n (14)
j~1,tt~1 j~1,tt~2 Flow balance constraints
Stockpiling is handled in the model through the use of X
F
variables for each flow path to track material flowing Xp,b,t,n ~ Xp,b,f,t,n V p,b,t,n (18)
into a grade bin within a stockpile. A grade bin defines f~1
the upper and lower grade limits of material which can
flow into a bin. The material flowing into a stockpile X
P,B

equals the tonnage from all flow paths into the stockpile, Xf,t,n ~ Xp,b,f,t,n V f ,t,njf6 [s (19)
p~1,b~1
as stated in equation (11). Each grade bin of material in
the resource has exactly one bin in the stockpile that it
can flow into based on the upper and lower grade limits X
P,B,F
Gg,d,t,n ~ Gg,l,n Rl Xp,b,f,t,n z
of the stockpile bin (this is handled preoptimisation in
p~1,b~1,f~1jd,l[fjs=
[f
the model formulation process). Likewise, the total
tonnage flowing out of a stockpile bin equals the sum of X
F,J,S
the tonnage in each flow path out of the stockpile. Gg,s,j Rs,j Xf,t,n V g,d,t,n (20)
Furthermore, the material leaving the stockpile must not f~1,j~1,s~1jd,j,s,l[fjt=1

24 Mining Technology 2012 VOL 121 NO 1


Groeneveld et al. Robust, flexible and operational mine design strategies

Several flow constraints are used in the model to equate


the amount of material entering a node (or option) with
the amount of material exiting a node. Briefly, these
constraints represent:
(i) equation (18): the tonnage from a bin equals the
tonnage through all paths from that bin
(ii) equation (19): the tonnage mined through each
flow path that does not go through a stockpile
equating to material mined from each parcel and
bin through the flow path
(iii) equation (20): the total amount of metal units
recovered to a product equates to the metal
content through all direct feed to a plant plus any
material treated after being stockpiled.

Non-negativity and integrality constraint


These constraints enforce non-negativity and integrality
of the variables, as appropriate 2 Gold price distribution over time

Gg,d,t,n ,Xp,b,f,t,n ,Xp,b,t,n ,Xf,t,n ,XIs,j,t,n ,XOs,j,t,n 0


gold and copper, capital cost, operating cost and plant
V g,d,p,b,f ,s,j,t,n (21) utilisation. No detailed analysis of the underlying nature
of the stochastic variables was undertaken, as detailed
IDl,t Integer V l,t and Yl,t , Yp,t binary V p,l,t research in this area has been undertaken in other papers
(Dowd and Xu, 1995; Godoy and Dimitrakopoulos,
2004; Dimitrakopoulos and Abdel Sabour, 2007; Topal,
2008; Shafiee and Topal, 2010).
Illustrative case study Distributions were set-up based on the parameters
This case study examines the use of several different below. An assumption of constant growth in values was
mining capacity and plant capacity options for a made and values were generated following the Markov
deposit. The deposit was divided into four parcels property. For illustrating the techniques proposed, how
generated by a single deterministic optimisation, such the variables are simulated does not have a material
as Gemcom Whittle pit shells. While this may be impact. The distributions are:
considered to be removing the optimality from the (i) gold price: starting value of $1200/oz, with a
model upfront, it was primarily used as a starting point normal growth factor of 4% with standard
for shape generation. Refinement through an iterative deviation of 20%
process could easily be undertaken to improve optim- (ii) copper price: starting value of $5000/t, with a
ality. Additionally, the purpose of this case study is to normal growth factor of 5% with standard
examine the execution of mining and plant options, deviation of 10% and a correlation of 60% to
which is not heavily reliant on schedule and/or sequence the gold price
of extraction. (iii) capital cost multiple: with a normal growth
Table 1 provides a summary of the deposit used in factor of 3% and a standard deviation 5% and a
this case study. The case study uses a single resource correlation to the gold price and copper price of
model; however, multiple stochastic models could be 10%
included. For the purposes of this case study, a physical (iv) operating cost multiple: with a normal growth
constraint exists between parcels in a sequential order, factor of 4% and a standard deviation 10% and
i.e. parcel two cannot start before parcel one is finished. a correlation to the gold price and copper price
This case study will use four mining options, four of 30% and the capital cost index of 40%
processing options and two stockpiling options to (v) plant utilisation: triangular distribution with a
undertake an analysis of the deposit. A summary of lower limit of 40%, midpoint of 85% and upper
the options included in the model is outlined in Table 2. limit of 95%.
Stochastic variables for the following items incorporate Four hundred simulations or states of the world were
the uncertainty into the model, commodity prices for used for the case study. Summaries of the ranges of

Table 2 Summary of design options

Option type Capacity/Mtpa Capital/$m Fixed cost/$/year Variable cost/$/t Disposal cost/$m

Mine A 20.0 38.5 2.60 1.22 3.5


Mine B 25.0 42.5 3.25 1.21 4.0
Mine C 30.0 45.0 3.90 1.12 4.5
Mine D 50.0 55.0 6.50 1.10 5.5
Processing A 7.5 575 13.0 1.75 5.0
Processing B 10.0 700 16.8 1.31 7.0
Processing C 12.5 850 20.0 1.05 8.5
Processing D 15.0 975 22.5 0.87 9.5
Stockpile waste 3600.0 0.20
Stockpile low grade 20.0 1.00 0.60

Mining Technology 2012 VOL 121 NO 1 25


Groeneveld et al. Robust, flexible and operational mine design strategies

4 Frequency of execution graph for exible and opera-


tional design scenarios

3 Capital cost index distribution over time mine A in period three with a net present value of
$4050m. This design was then evaluated under the
values for gold and capital cost index are shown in different simulated states of the world to test its
Figs. 2 and 3 respectively. performance under uncertainty.
A flexible design model was used to produce an
Results optimal design for each state of the world. This
Five different design scenarios were modelled based on produced a result which provided an upper bound for
the three different design methodologies. A robust, a the achievable value from the deposit, as the assumption
flexible and two operational designs, along with a is made that decision makers have perfect informa-
traditional scenario were generated. All models were tion and can therefore make perfect decision into the
processed on a Quad core Ubuntu server with 2?66 GHz future. To analyse the options used in the model, a
and 4 Gb RAM using the Gurboi 4?5?2 software. frequency of execution table and graph (Table 4 and
Solution times varied; however, for a fully flexible Fig. 4 respectively) were generated. These show how
model, the average solution time was 30 s. A summary often a particular option is used, calculated by dividing
of the results is outlined in Table 3 with a discussion the number of times that an option is used by number of
below. simulations. The available number of times that an
A traditional plan for operating a mine was generated option could be executed was 400. This showed that in
by selecting the optimal design for a single deterministic every scenario, mine D and plant D were built. Mine C
scenario. The value for the stochastic parameters was was built in most states of the world and plant C was
generated by taking the starting values and applying the built in roughly half the states of the world. It also
average growth factors only over time, i.e. no random shows that around period five, there is increased need
variation was included. This produces a value which is for mining capacity, as a handful of scenarios expand
similar to current industry practice for generating a capacity in this period.
design. For this scenario, the design generated was to Next, a robust design was generated by optimising the
build mine D, plant B and plant D in period one and design for multiple states of the world in one model. The
resulting design was to build mine option D, plants C and
Table 3 Summary of net present value results in $m D in period one and mine option C in period two. It
from different models should be noted that processing of the model with over 40
states of the world is slow. This is because the number of
Standard
Average deviation Minimum Maximum
linear variables doubles with each additional state of the
world. For the model with 40 states of the world, there
Traditional 3920 1050 1340 7640 were 22 million variables. Gurobi 4?5?2. solves this model
Flexible 4350 1140 1740 8070 in 9 h on a Quad core 2?66 GHz Ubuntu Server with
Robust 4260 1110 1560 8050 4 GB of RAM. In order to test the sensitivity of the
Operational v1 4210 1150 1530 8055 model, three scenarios were run with 25 states of the-
Operational v2 4290 1090 1670 8065
world and two scenarios with 30 states of the world.

Table 4 Frequency of execution for exible model by period

All periods 1 2 3 4 5 6 7 8 9 10

Mine A 40% 4% 3% 3% 4% 11% 7% 6% 2% 0% 0%


Mine B 42% 1% 1% 3% 7% 19% 8% 4% 1% 0% 0%
Mine C 97% 13% 7% 13% 19% 31% 11% 2% 2% 1% 0%
Mine D 100% 86% 6% 2% 1% 1% 0% 4% 1% 0% 0%
Plant A 13% 9% 1% 1% 0% 0% 0% 1% 0% 1% 0%
Plant B 33% 28% 3% 2% 0% 0% 0% 0% 0% 0% 0%
Plant C 51% 47% 2% 1% 0% 1% 0% 0% 0% 0% 0%
Plant D 100% 90% 7% 2% 0% 1% 0% 0% 0% 0% 0%

26 Mining Technology 2012 VOL 121 NO 1


Groeneveld et al. Robust, flexible and operational mine design strategies

5 Value at risk graph for design scenarios

The states were all different scenarios generated from a flexible design may be impractical in reality. However, a
the MCS; however, the all generated the same design robust design which does not incorporate any flexibility
solution. So, arguably for this model, the number of produces lower value than an operational and a flexible
states of the world included was adequate at 25; how- design as it is prohibited from reacting to change. The
ever, this may be different for other models and should be operational plan design has a lower expected value than
tested for each deposit and set of options. the fully flexible design but higher than the robust design
Based on the results of these results, two operational as it maintains flexibility in the later years and it is only
models were developed. The design was fixed for the first the initial years that flexibility is limited. A traditional
two periods. For period three onwards flexibility was design produces the lowest expected value overall since
available so the model could turn on and off design it has no flexibility and is not optimised to handle
options. The model formulation for this was the same as uncertainties.
the flexible model with the only difference being that the The differences between the expected values of each
binary values for the design options were fixed in periods design approach can be attributed to two key aspects.
one and two. Two scenarios were constructed: version First of all, actively managing the operation and
one involved mine D being built in period one, plant D allowing a flexible design (one that changes over time)
in period one and plant C in period two and version two will contribute significant additional value. The second
involved mine D in period one and mine C in period component that contributes to additional value is being
two, plant D in period one and plant C in period one. able to develop a robust fixed design which can handle a
Version one of the design has less capacity in the initial range of conditions. Refinement of the initial design
years and produces less value than version two. Version chosen for the operational plan may lead to the dis-
two produces more value as it has greater capacity in the covery of plans with a higher expected value.
initial years (just having greater capacity earlier would
not always produce greater value). Interestingly, version
two design is exactly the same in the initial years as the
Conclusions
design generated by the robust design. The difference is The paper has compared three different new design
that the operational design allows for flexibility in the methodologies: flexible, robust and operational and
later years, thus the value of the operational design is extended the application of real options in design
higher than the robust design. Also, version one under- theory to mining. It has been shown with clarity that all
performs when compared with the robust design, so this these methods outperform an approach which uses
would indicate to the modeller that there is a better average values (the current traditional design approach).
operational solution to be found. However, had the A fully flexible design approach generates the most
robust design and the flexible design not established this value; however, it has practical implementation issues
base line, this finding would have been missed. due to constant change. A robust design produces a
A value of risk graph is a cumulative probability single design that handles variation the best; however,
distribution of project value in each state of the world. the design does not change over time and therefore does
This is produced to highlight the differences between not value active management. An operational design is
the models, as shown in Fig. 5. It allows a decision proposed to overcome the limitations of the other design
maker to quickly and easily compare the different design methodologies. While it does not produce as much value
scenarios. as the flexible design (which is only a theoretical
In comparing the models, it can be seen that the flexible maximum), it does produce more value than a robust
model produces a higher expected value than any other design. Finally, the worst performing approach was the
model. This is as expected since the flexible model pro- traditional approach which does not consider flexibili-
duces an optimal design for each state of the world. Such ty and uncertainty. Flexible operations produce greater

Mining Technology 2012 VOL 121 NO 1 27


Groeneveld et al. Robust, flexible and operational mine design strategies

project value than fixed, rigid operations, thus actively Godoy, M. and Dimitrakopoulos, R. 2004. Managing risk and waste
mining in long-term production scheduling. SME Trans., 316, 4350.
managing an operation is imperative to maximising
Groeneveld, B. and Topal, E. 2011. Flexible open-pit mine design under
value. uncertainty, J. Min. Sci., 47, (2), 211226.
Groeneveld, B., Topal, E. and Leenders, B. 2009. A new methodology for
References flexible mine design, Proc. Int. Symp. on Orebody modelling and
strategic mine planning, Perth, Australia, March 2009, AusIMM,
Cardin, M. A., de Neufville, R. and Kazakidis, V. 2008. A process to 109 118.
improve expected value of mining operations, Min. Technol., 117, Shafiee, S. and Topal, E. 2010. An overview of global gold market and
(2), 6570. gold price forecasting, Resour. Policy, 35, (3), 178189.
de Neufville, R. 2006. Analysis methodology for the design of complex Topal, E. 2008. Evaluation of a mining project using discounted cash
systems in uncertain environment: application to mining industry, flow analysis, decision tree analysis, Monte Carlo simulation and
Unpublished internal report, Engineering Systems Division, real option using an example, Int. J. Min. Miner. Eng., 1, 6276.
Massachusetts Institute of Technology, Cambridge, MA, USA. Wang, T. and de Neufville, R. 2005. Real options in projects, Proc. 9th
de Neufville, R., Scholtes, S. and Wang, T. 2005. Real options by Real Options Annual Int. Conf., Paris, France, June 2005, Real
spreadsheet: parking garage case example, J. Infrastruct. Syst., 12, Options Group. Accessed online at http://www.realoptions.org/
(2), 107111. papers2005/Tao_Wang_RO_in_projects.pdf
Dimitrakopoulos, R. G. and Abdel Sabour, S. A. 2007. Evaluating Wang, T. and de Neufville, R. 2006. Identification of real options in
mine plans under uncertainty: can the real options make a projects, Proc. 16th Annual Int. Symp. of the International Council
difference? Resour. Policy, 32, (3), 116125. on Systems Engineering (INCOSE), Orlando, FL, USA, July 2006,
Dowd, P. and Xu, C. 1995. Financial evaluation of mining projects, INCOSE. Accessed online at http://ardent.mit.edu/real_options/
Proc. APCOM XXV 1995 Conf., Brisbane, Australia, July 1995, Real_opts_papers/Identification%20of%20Real%20Option%20in%
The Australasian Institute of Mining and Metallurgy, 247254. 20Projects%20INCOSE.pdf

28 Mining Technology 2012 VOL 121 NO 1

You might also like