Construction and demolition waste


The construction and demolition sectors are under increasing pressure to improve performance, reduce waste and
increase recycling in a drive towards the circular economy. Reducing waste is a priority for the European Union and
the UK Government and there are many new regulations, measures and targets to reduce waste within the
construction industry. For example, the UK Strategy for Sustainable Construction [1] included a target to reduce
construction, demolition and excavation (CD&E) waste going to landfill by 50% compared to 2008 levels by 2012.

Steel construction products and technologies are inherently low waste through all stages of the building life cycle;
production, construction and end-of-life of buildings. This article explains the measures introduced to reduce CD&E
waste and sets out steels credentials as a low waste construction material.

Waste Arisings from construction, demolition and excavation sectors (20082010)[2]

Background

1 / 17
//www.steelconstruction.info/Construction_and_demolition_waste - 17th September 2017
SteelConstruction.info
The free encyclopedia for UK steel construction information

A skip of mixed construction waste; a common sight on many construction sites

In 2011, WRAP estimated that over 100 million tonnes of inert construction, demolition and excavation (CD&E) waste
was being generated each year in England[3]. In addition, an estimated 20 million tonnes of unused waste was going to
landfill. CD&E waste is also a major component of fly-tipped waste and is estimated by the Environment Agency to be
responsible for around one third of all fly tipping incidents.

Research commissioned by WRAP suggests that 10 30% of the construction materials that end up as waste on site
have never actually been used and that the true cost of construction waste can be up to 15 times more than the waste
disposal (skip hire) costs when labour and material costs are taken into account. The construction industry therefore is
increasingly coming under pressure to improve resource efficiency and reduce waste. The revised Waste Framework
Directive (2008/98/EC)[4] came into force on 12 December 2008. Article 40 requires EU member states to bring into
force the laws, regulations and administrative provisions necessary to comply with this Directive.

The Directive requires the UK to design and implement waste prevention programmes and sets the challenging target
to reuse and recycle 70% of construction and demolition waste by 2020. Such programmes have needed to take
account of the five-step hierarchy shown.

2 / 17
//www.steelconstruction.info/Construction_and_demolition_waste - 17th September 2017
SteelConstruction.info
The free encyclopedia for UK steel construction information

UK Waste hierarchy

Reducing waste is a priority for the UK Government. The Waste Strategy for England[5] set out a number of key
objectives and targets to reduce material consumption and waste and to break the link between economic growth and
waste. In line with the above waste hierarchy, the Governments objectives in relation to construction waste are:

To provide the drivers for the construction sector to improve its economic efficiency by creating less waste at
every stage of the supply chain, from design to demolition;
To encourage the sector to treat waste as a resource, closing the loop by re-using and recycling more and
asking contractors for greater use of recovered material; and
To improve the economics of the re-use and recycling sector by increasing sector demand and securing
investment in the treatment of waste this will benefit all waste streams, including construction.

The UK Strategy for Sustainable Construction[1] was published in June 2008. The Strategy included the target to
reduce CD&E waste to landfill by 50% by 2012 compared to 2008 levels. Specific actions to help deliver this target
included:

Individual companies signing up to the Construction Waste Commitment (see the WRAP website)
Establishing sector resource efficiency plans
Setting an overall target for the diversion of demolition waste from landfill
Extending the Plasterboard Voluntary Agreement to the rest of the supply chain
Reducing construction packaging waste by 20%.

In 2013, the Government claimed that the target to reuse and recycle 70% of construction and demolition waste by
2020 had already been achieved[6].

Regulations and other drivers


To help to achieve the UKs waste reduction targets, a number of measures have been introduced to reduce and
manage waste through all stages of the design, construction and at the end-of-life of buildings. These apply to
designers and construction and demolition contractors.

Duty of Care Regulations

Construction companies have a legal duty of care[7] with respect to any waste that they generate on site. This duty
applies to anyone who produces, imports, transports, stores, treats or disposes of controlled waste from business or
industry. Commercial, industrial and household wastes (including hazardous/special wastes) are classified as
controlled waste. The duty of care also applies to anyone who acts as a waste broker. Companies must ensure that:

Their waste is stored, handled, recycled or disposed of safely and legally


Their waste is stored, handled, recycled or disposed of only by businesses which hold the correct, current
licence to do the work
They record all transfers of waste between their and another business, using a waste transfer note (WTN)
signed by both businesses
They keep all WTNs for at least two years
They record any transfer of hazardous/special waste between their business and another business, using a

3 / 17
//www.steelconstruction.info/Construction_and_demolition_waste - 17th September 2017
SteelConstruction.info
The free encyclopedia for UK steel construction information

consignment note signed by both businesses


They keep all consignment notes for at least three years.

If the company is a sub-contractor and the main contractor arranges for the recovery or disposal of waste that they
produce, the sub-contractor is still responsible for those wastes under the duty of care.

This duty of care has no time limit. It extends until the waste has either been finally disposed of or fully recovered.

If companies produce or deal with waste that has certain hazardous properties, they will also have to comply with the
hazardous/special waste regulations.

Hazardous/Special Waste Regulations

Waste that has hazardous properties which may make it harmful to human health or the environment is known as
hazardous waste[8] in England, Wales and Northern Ireland and special waste in Scotland.

The definition of hazardous/special waste is relatively wide and covers objects that contain hazardous substances
such as televisions and fluorescent light tubes. As a result, many companies are likely to produce some form of waste
that is hazardous and need to deal with it accordingly.

The European Waste Catalogue[9] (EWC) contains a list of all types of waste and each waste type is given a six-digit
code. Hazardous waste is identified in the EWC with an asterisk (*):

Some wastes, called 'absolute entries', are always classed as hazardous, for example inorganic wood
preservatives, waste paint or varnish remover and wastes from asbestos processing
Other wastes, called 'mirror entries', are classed as hazardous if they are present in amounts above certain
threshold concentrations, for example some wastes containing arsenic or mercury.

The environmental regulator, this is the Environment Agency in England and Natural Resources Wales in Wales,
tracks the movement of hazardous waste through the consignment note system. This ensures that waste is managed
responsibly from where it is produced until it reaches an authorised recovery or disposal facility. Companies must
ensure that all hazardous waste is stored and transported with the correct packaging and labelling.

Hazardous waste can only be disposed of at a landfill site that is authorised to accept it. Some landfill sites that are
classified as non-hazardous may be able to take certain stable non-reactive hazardous wastes if they have the
appropriate facilities. A landfill site authorised to accept hazardous waste may not be able to take all types of
hazardous waste.

Hazardous waste must be treated, before it can be sent to landfill, to meet the limits set by a landfill site's waste
acceptance criteria (WAC). Treatment means physical, thermal, chemical or biological processes, including sorting,
that change the characteristics of the waste in order to:

Reduce its volume


Reduce its hazardous nature
Make it safe to handle
Make it easier to recover.

For further information on current legislation with respect to construction waste see the Environment Agency
guidance.

Landfill Tax and Aggregates Levy

4 / 17
//www.steelconstruction.info/Construction_and_demolition_waste - 17th September 2017
SteelConstruction.info
The free encyclopedia for UK steel construction information

Introduced in 1996, the Landfill Tax remains the primary fiscal incentive to promote good waste management practice
in the UK. The tax rose by 8 per tonne each year from 2007 up until 2014 and the standard rate was 80 per tonne at
April 2014 for non-hazardous (and non-inert) wastes. The Government then announced that from 2015-16 it would rise
in line with inflation and in 2015 it was 82.50 per tonne. A lower rate of 2.60 per tonne applied to inactive (or inert)
waste at the same time.

Reflecting the large volume of aggregates consumed by the construction industry (over 200 Mt pa), the Aggregates
Levy was introduced in 2002 to reduce demand for primary aggregates and to encourage the use of recycled and
secondary aggregates. In 2015 the levy was 2.00 per tonne of primary aggregates.

Site Waste Management Plans Regulations (SWMP)

Effective construction site waste management is a key tool for improving efficiency and reducing waste. Introduced in
April 2008, the SWMP Regulations[10] made it compulsory to develop and implement SWMPs on construction projects
costing more than 300k. Defra guidance[11] advised that a SWMP should:

Identify the different types of waste that will be produced by the project, and note any changes in the design
and the materials specification that seek to minimise this waste
Consider how to re-use, recycle or recover the different wastes produced by the project
Require the construction company to demonstrate that it is complying with the duty of care regime
Record the quantities of waste produced.

The Regulations also required a more detailed analysis to be conducted on projects costing more than 500k.
Although the Site Waste Management Plans Regulations Act 2008 was repealed on the 1st December 2013 as part of
Governments Red Tape Challenge, SWMPs continue to be used on many construction sites and by responsible
contractors.

BREEAM
BREEAM is BREs Environmental Assessment Method for buildings. Under BREEAM, credits are awarded under a
number of environmental categories, one of which is waste, and the buildings rated according to its total score.

Under BREEAM 2014[12] the following waste issues are assessed:

Construction waste management (Wst 01 see below)


Use of recycled or secondary aggregates (Wst 02)
Operational waste - Provision of dedicated storage facilities for recyclable waste streams within new buildings
(Wst 03)
Specification and fitting of floor and ceiling finishes selected by the building occupant (Wst 04)
Adaptation to climate change - To recognise and encourage measures taken to mitigate the impact of extreme
weather conditions arising from climate change over the lifespan of the building (Wst 05)
Functional adaptability - To recognise and encourage measures taken to accommodate future changes of use
of the building over its lifespan (Wst 06).

BREEAM does not specifically address any issues in connection with demolition waste reduction or management
although credit Wst 2 does encourage the use of recycled and secondary aggregates.

The most highly weighted waste issue under BREEAM is Construction waste management (Wst 01) under which
credits are awarded according to the benchmarks shown in the table.
5 / 17
//www.steelconstruction.info/Construction_and_demolition_waste - 17th September 2017
SteelConstruction.info
The free encyclopedia for UK steel construction information

Non-hazardous construction waste (excluding demolition and excavation waste) benchmarks

BREEAM credits Amount of waste generated per 100m2 (gross internal floor area)

Volume (m3) Weight (tonnes)

One credit 13.3 11.1

Two credits 7.5 6.5

Three credits 3.4 3.2

Exemplary level 1.6 1.9

The only minimum construction waste requirement under BREEAM is that one (of 4) Wst 01 credit is required to obtain
an Outstanding rating.

Where there are existing buildings on the site being developed, it is a requirement under Wst 01 that a pre-demolition
audit be undertaken.

A further credit is available under Wst 01 where it can be demonstrated that a significant proportion of non-hazardous
C&D waste generated by the project, has been diverted from landfill.

Wst 01 requirements for diversion of C&D waste from landfill

BREEAM credits Type of waste Volume (%) Tonnage (%)

One credit Non demolition 70 80

Demolition 80 90

Exemplary level Non demolition 85 90

Demolition 85 95

BREEAM also accounts for construction waste through the assessment of materials using the Green Guide to
Specification.

Green Guide to Specification

BREEAM uses the Green Guide to Specification[13] to assess the environmental impacts of construction materials and
products. The life cycle assessment methodology used by the Building Research Establishment (Environmental
Profiles ) to derive the Green Guide ratings, takes account of waste during the production and construction stages.

Waste and Resources Action Programme (WRAP)

6 / 17
//www.steelconstruction.info/Construction_and_demolition_waste - 17th September 2017
SteelConstruction.info
The free encyclopedia for UK steel construction information

WRAP has worked to set standards for good practice in waste and resource management for the CD&E sector.
WRAP has provided free access to tools and know-how so that construction projects could make best use of materials
resource.

In 2008, WRAP launched its Halving Waste to Landfill (W2L) campaign. W2L was a voluntary agreement that
provided a framework through which industry could support and deliver against the target of halving waste to landfill
by 2012.

Initially, around 700 companies from all parts of the construction industry signed up to the campaign which required
them to:

Set a specific target for reducing waste to landfill


Embed the target in corporate policy and processes
Set corresponding requirements in project procurement and engage with their supply chain
Measure performance relative to a corporate baseline
Report annually on overall corporate performance.

In 2015, WRAP announced that over 800 companies had signed the commitment to reduce waste leading to 5 million
tonnes of waste per year diverted from landfill and 400 million cost savings per year realised by the companies
involved.

At the same time however, it announced its intention to focus its future efforts on resource management, food
sustainability and product sustainability.

ICE demolition protocol

The ICE Demolition Protocol[14] provides an overarching framework which enables the waste hierarchy to inform
approaches for managing buildings and structures at the end of their lives. First launched in 2003, the Demolition
Protocol has been adopted and implemented across a range of public and private sector projects and is included in
Supplementary Planning Guidance in a number of Local Authorities.

The Protocol describes the overarching implementation approaches for Materials Resource Efficiency (MRE)
associated with demolition and construction activities, with a decision-making framework which emphasises the need
to reuse, then recycle, with landfill as a last resort. It provides a number of overarching methodologies which include:

Providing a Deconstruction/Demolition Recovery Index (DRI) this is the percentage of building elements,
products or materials to be reused or recycled
Estimating bulk quantities through a pre-demolition audit, summarised in a Demolition Bill of Quantities (D-
BOQ)
Providing a new build recovery index (NBRI) describing the percentage of building elements, products or
materials recovered for use in the new build
Demonstrating compliance with Site Waste Management Plan requirements
Describing how carbon benefits, through avoided haulage movements, can be realised and estimated easily
Providing data for in-house and local authority monitoring of annual construction and demolition waste arisings.

7 / 17
//www.steelconstruction.info/Construction_and_demolition_waste - 17th September 2017
SteelConstruction.info
The free encyclopedia for UK steel construction information

The BRE has developed a suite of SMARTWaste tools and associated consultancy services, to measure, manage and
reduce construction and demolition waste.

Waste in steel construction


Steel construction products are inherently low waste products through all phases of the design, production,
construction and deconstruction process. Designers and specifiers can be confident that, by choosing steel
construction products and systems, material resources are optimised, waste is minimised and recycling is maximised.

Steel production

Scrap being loaded into the steel furnace

By-products from iron and steel making, including sludges, slags and dust, are beneficially used by the construction
industry in a range of products including roadstone, lightweight aggregate and as a substitute for Portland cement.
Tata Steel, the major steel producer in the UK, recycles or reuses over 90% of its process residues.

Approximately 3 million tonnes of blast furnace slag is produced in the UK annually. Of this around 75% is quenched
and this is then processed to produce ground granulated blast furnace slag (GGBS), which is used by the concrete
industry as a cement replacement material. The remainder is air-cooled and is used as an aggregate. The split
between the two uses is dictated by production choices, economics and demand.

Manufacture

8 / 17
//www.steelconstruction.info/Construction_and_demolition_waste - 17th September 2017
SteelConstruction.info
The free encyclopedia for UK steel construction information

Swarfe produced by drilling holes in structural steel members

During component manufacture, computer controlled, fully or semi-automated production lines ensure that wastage of
steel is minimised. The typical wastage rate for fabricating structural steel products is just 4% and any off-cuts,
trimmings, swarfe, etc. from the production process are 100% recycled into new steel. For steel cladding and decking
products, wastage rates are typically 1.5 2% and around 1.8% for secondary structural products such as rails,
purlins, studs, etc.

Construction

Transporting structural steel efficiently and with minimum packaging

Steel products are delivered to the construction site pre-engineered to the correct dimensions; consequently there is
no site waste. Furthermore the quality of factory produced steel construction products and the dimensional stability of
the material itself, means that there are few defects and hence little site waste. Steel products are delivered to site with
minimal packaging. Packaging comprises mainly timber pallets and bearers and plastic or metal strapping. Timber
packaging is generally reused by the haulage company making site deliveries and the strapping is either recycled or
reused.

Deconstruction

9 / 17
//www.steelconstruction.info/Construction_and_demolition_waste - 17th September 2017
SteelConstruction.info
The free encyclopedia for UK steel construction information

A steel frame being reused and extended at a distribution warehouse in Leeds

When a building is deconstructed, the ease with which steel construction products can be reclaimed, coupled with the
economic value of scrap steel, means that virtually all steel is recovered and either reused or recycled. Currently 96%
of steel from deconstructed buildings in the UK is recovered.

Designing out waste


To date the focus of C&D waste reduction has been mainly on site waste management practice. Arguably however,
the best opportunities for improving materials resource efficiency in construction projects occur during the design
stage. Implementing these opportunities can provide significant reductions in cost, waste and carbon.

There are five key principles that design teams can use during the design process to reduce waste. These principles
are based on extensive consultation, research and work carried out by WRAP[15] directly with design teams . They are
summarised below together with questions the design team should address to design out waste.

Design for reuse and recovery

Design for reuse of material components and/or entire buildings has considerable potential to reduce the
environmental burdens from construction. Much of this is common sense as, with reuse, the effective life of the
materials is extended and thus annualised burdens are spread over a greater number of years. Reuse, in the waste
hierarchy is generally preferable to recycling, where additional processes are involved, some of which will have their
own environmental burdens.

Key questions for the design team include:

On previously developed sites, can materials from demolition of the building be reused in the design?
Can reclaimed products or components be reused?
When materials are reused, can they be reused at their highest value?
Can any excavation materials be reused?
Can cut and fill balance be achieved? How can it be optimised to avoid removal of spoil from site?

In addition to considering reuse of previously developed sites, designers are encouraged to think about how their new
buildings can be designed in ways that they can be dismantled more easily for reuse and recovery in the future.

10 / 17
//www.steelconstruction.info/Construction_and_demolition_waste - 17th September 2017
SteelConstruction.info
The free encyclopedia for UK steel construction information

Design for off-site construction

The benefits of off-site factory production in the construction industry are well documented and include the potential to
considerably reduce waste especially when factory manufactured elements and components are used extensively. Its
application also has the potential to significantly change operations on site, reducing the amount of trades and site
activities and changing the construction process into one of a rapid assembly of parts that can yield many benefits
including:

Rapid construction using steel modules

Reduced construction related transport movements;


Improved health and safety on site through avoidance of accidents;
Improved workmanship quality and reducing on site errors and re-work, which themselves cause considerable
on site waste, delay and disruption; and
Reduced construction timescales and improved programmes.

Off-site construction is one of a group of approaches to more efficient construction sometimes called Modern Methods
of Construction (MMC) that also include prefabrication and improved supply chain management. Technologies used
for off site manufacture and prefabrication include light gauge steel framing systems and modular and volumetric
forms of construction which offer great potential for improvements to the efficiency and effectiveness of UK
construction. To assess the suitability of off-site construction, design teams should consider the following questions:

Can the design or any part of the design be manufactured off site?
Can site activities become a process of assembly rather than construction?

Experience shows that the choice of off-site construction can have a significant influence on initial design
considerations and therefore should be considered during the early project stages. Key considerations with respect to
the choice of off-site construction include:

Space planning, especially structural and planning grids


Structural design/system selected
Project buildability
Procurement routes
Consideration of how aesthetics are affected by off-site construction.
11 / 17
//www.steelconstruction.info/Construction_and_demolition_waste - 17th September 2017
SteelConstruction.info
The free encyclopedia for UK steel construction information

Design for materials optimisation

Resource efficient, long-span cellular beam construction

Good practice in this context means adopting a design approach that focuses on materials resource efficiency so that
less material is used in the design, i.e. lean design, and/or less waste is produced in the construction process, without
compromising the design concept.

Three main areas offer significant potential for waste reduction

Minimisation of excavation
Simplification and standardisation of materials and component choices
Dimensional coordination.

In order to assess the best project opportunities for material optimisation, the following key questions need to be
answered by the design team:

Can the design, form and layout be simplified without compromising the design concept?
Can the design be coordinated to avoid/minimise excess cutting and jointing of materials that generate waste?
Is the building designed to standard material dimensions?
Can the range of materials required be standardised to encourage reuse of offcuts?
Is there repetition & coordination of the design, to reduce the number of variables and allow for operational
refinement, e.g. reusing formwork?

Design for waste efficient procurement

12 / 17
//www.steelconstruction.info/Construction_and_demolition_waste - 17th September 2017
SteelConstruction.info
The free encyclopedia for UK steel construction information

Designers have considerable influence on the construction process itself, both through specification as well as setting
contractual targets, prior to the formal appointment of a contractor/constructor. Designers need to consider how work
sequences affect the generation of construction waste and work with the contractor and other specialist
subcontractors to understand and minimise these. Once work sequences that cause site waste are identified and
understood, they can often be designed out.

Key questions for the design team include:

Has research been carried out to identify where on site waste arises?
Can construction methods that reduce waste be devised through liaison with the contractor and specialist
subcontractors?
Have specialist contractors been consulted on how to reduce waste in the supply chain?
Have the project specifications been reviewed to select elements/components/materials and construction
processes that reduce waste?

Design for deconstruction and flexibility

Designers need to consider how materials can be recovered effectively during the life of the building when
maintenance and refurbishment is undertaken or when the building comes to the end of its life.

There are a number of barriers to large scale reuse of materials and components in the construction industry. Perhaps
the greatest difficulty in applying design for deconstruction and flexibility however, is the time frame involved, which is
very often longer than the financial and professional involvement of the client and design team. As buildings are sold
and re-sold over time, any connection between the original client and designer and the ultimate beneficiary of design
for deconstruction and flexibility can become very remote.

Nevertheless, designing for future generations is embedded in the concept of long-term sustainable development and
the circular economy. Not to design with design for deconstruction and flexibility in mind limits the future potential of
design for reuse.

To assess the best project opportunities for reducing waste at deconstruction stage, the following key questions need
to be addressed:

Is the design adaptable for a variety of purposes during its life span?
Can building elements and components be maintained, upgraded or replaced without creating waste?
Does the design incorporate reusable/recyclable components and materials?
Are the building elements/components/materials easily disassembled?
Can a Building Information Modelling (BIM) system or building handbook be used to record which and how
elements/components/materials have been designed for disassembly?

A range of alternative construction methods are likely to be suitable for design for deconstruction and flexibility.
Generally, those methods that facilitate easy disassembly at the end of the design/service life to improve the potential
for reuse and/ or recyclability should be selected in preference to the more contiguous structural systems. Reuse
should invariably be chosen as a preferred end of life scenario rather than recycling. There is an added waste
reduction benefit in the choice of such structural systems as they are likely to be fabricated using off-site construction
and assembled on site.

Steel-framed buildings are inherently reusable and flexible.

13 / 17
//www.steelconstruction.info/Construction_and_demolition_waste - 17th September 2017
SteelConstruction.info
The free encyclopedia for UK steel construction information

Long span steel beams providing flexible, column-free space, Vulcan House, Sheffield

As part of its programme to design out waste WRAP produced a series of sheets of alternative design details which
use less materials or result in less waste being created than standard details used in construction. One of these
design sheets[16] described the benefits of cellular steel beams. The table highlights the potential benefits of this form
of construction identified by WRAP.

14 / 17
//www.steelconstruction.info/Construction_and_demolition_waste - 17th September 2017
SteelConstruction.info
The free encyclopedia for UK steel construction information

Resource efficiency benefits of cellular beams

Materials/wast 25 50% reduction in steel weight in web (flanges


e unaffected).

Up to 15% reduction in M&E materials by passing


straight through the web openings.

Less material required for supporting elements


(columns, foundations etc).

Cost Average savings of 38/metre for castellated steel


beams.

Reduced savings for cellular beams due to more


complex manufacture.

Light weight can result in lower transportation costs.

Further cost savings for supporting structure.

Time Long spans and light weight allow omission of some


supporting structure leading to quicker construction.

Light weight also allows fewer deliveries and good


manoeuvrability on site.

Carbon Potential steel embodied carbon savings of 41kg


CO2e/metre compared to solid I-beams.

Other structural elements can also be lighter, reducing


embodied carbon further.

Recycling Steel is 100% recyclable.

Manufacturing waste is recycled.

Constructabili Light weight allows easy assembly.


ty
Bolted sections are easy to assemble and
disassemble.

M&E services can pass through the beams.

Replicability Bespoke for individual projects laser precision cutting


ensures efficient manufacturing process.

Particularly suitable for long spans such as stadia, car


parks and bridges

15 / 17
//www.steelconstruction.info/Construction_and_demolition_waste - 17th September 2017
SteelConstruction.info
The free encyclopedia for UK steel construction information

References
1. 1.01.1 Strategy for Sustainable Construction; Department for Business, Enterprise & Regulatory Reform. June
2008
2. CD&E WASTE: Halving Construction, Demolition and Excavation Waste to Landfill by 2012 compared to
2008
3. The Construction Commitments: Halving Waste to Landfill Signatory Report 2011, WRAP
4. Directive 2008/98/EC Of the European Parliament and of the Council of 19 November 2008 on waste and
repealing certain Directives
5. Waste Strategy for England 2007, Department for Environment, Food and Rural Affairs
6. Waste management plan for England. Published by the Department for Environment, Food and Rural Affairs,
2013
7. The Environmental Protection (Duty of Care) (England) (Amendment) Regulations 2003, Statutory
Instrument 2003 No. 63
8. The Hazardous Waste (England and Wales) Regulations 2005, Statutory Instrument 2005 No. 89
9. European Waste Catalogue. List of wastes pursuant to Article 1(a) of Directive 75/442/EEC on waste and
Article 1(4) of Directive 91/689/EEC on hazardous waste
10. The Site Waste Management Plans Regulations 2008, Statutory Instrument 2008 No. 314
11. Non-statutory guidance for Site Waste Management Plans. defra, 2008
12. BREEAM UK New Construction, Non-domestic buildings (United Kingdom), Technical Manual, SD5076: 4.1
2014. BRE Global Ltd.
13. The Green Guide to Specification, 4th ed., BRE and Oxford Brookes University, 2009
14. Demolition Protocol; The Institution of Civil Engineers, 2008
15. Designing out Waste: a design team guide for buildings, WRAP
16. Designing out Waste: design detail sheet - Castellated and cellular beams, WRAP

Resources
The whole story From cradle to grave

Further reading
Design for deconstruction. Principles of design to facilitate reuse and recycling CIRIA Report C607, 2004.
See also
Recycling and reuse
Sustainable construction legislation, regulations and drivers
BREEAM
The Case for Steel
The recycling and reuse survey
Steel and the circular economy

16 / 17
//www.steelconstruction.info/Construction_and_demolition_waste - 17th September 2017
SteelConstruction.info
The free encyclopedia for UK steel construction information

External links
WRAP website on construction waste management
BREEAM
CIRIA: construction resources and waste management

CPD
Sustainability and steel construction
Sustainable steel buildings