Professional Documents
Culture Documents
Report
Colin A. Scholes
14 August, 2017
Housekeeping
Submission Dates
EIS/safety assessment
includes gas emissions,
utilities, water discharge.
Location
Scope whats in
All components of the CO2 utilisation process plant.
All emissions control (stack, water treatment)
All storage of chemicals
Internally generated utilities (power), if any
Scope whats out
CO2 source process.
H2 electrolysis plant
Fire water system, external utilities (substation, fresh water
supply).
Pipelines.
Project Scope
Flow sheet needs to be divided up into five/six sections (one for each
team member).
Each section will have a mass and energy balance.
Each section will have one or more equipment items
You need the overall M&E balances to balance (no discontinuities
between your flow sheets)
You need to consider heat and water integration and optimisation.
You will have to cost the entire plant so all major items must be
included.
Executive Summary
As before, 1 page summary of the PDR
What you did, how you did it and what you found
This is an interim report
Introduction
Scope of design and your main assumptions
Pay attention to the appearance especially of the PFDs
2. Process Selection and Description
Proven Technology?
Turn-down capability?
Transportation costs
Pollution generation potential
Public image and Social acceptance
Greenhouse gas impact
Information available?
Plant Preliminary Hazard Analysis
No Longer Needed
M&E Balances and Development of PFDs
For each part of the process (5 parts), show the mass and
energy balance.
Will need to do hand calculations to support the M&E
Balances and discuss your assumptions for the major and
minor equipment items.
Show equations you used for determining the energy required,
etc
You do not need to show derivations and do not teach
chemical engineering!
This is not the detailed design yet!
Hand Calculations
Work in pencil
Write out, in full, all assumptions
Set calculations out neatly and clearly
Separate calculations into sections
Take the time to set work out properly errors easily found
DONT TYPE YOUR HAND CALCULATIONS
Hand calculations go in Appendix REMEBER TO
PHOTOCOPY OR SCAN for use in your detailed design report
Write up the main assumptions and model in the body together
with results in a table
Hand Calculations
As far as possible:
Flow should be from left to right (and may be continued on several sheets)
Top section for identifiers and description
Sequence same as proposed plant (i.e. Feed treatment first, product finishing last)
Stream numbering should also be left to right
Relative sizes of main items respected (except heat exchangers, pumps, etc)
Tables of stream flows, compositions, etc, presented separately below the diagram
Border, Title Block, Revision notes
Icons for all equipment. Retain relative size as much as possible
Utilities along bottom of drawing
Vapor/vents along top of drawing
Services or Utilities (steam, cooling water, etc)
Connections to equipment items only shown
Service requirements (flowrates etc) can be included in the tabulated data
Features of PFDs
Precision of data
Stream total and component flow to appropriate significant
figures.
Flows should balance
Calculated flows of possible contaminants which are smaller
than the flowsheet precision should be marked as TRACE.
Trace components can be critical in material selection
catalyst poisoning.
Presentation of PFDs
DO
Make intelligent judgements to reduce complexity
Clearly state and justify all of your statements
Use industry standard methods (where possible, use standards)
DONT
Dont waste time on irrelevant details
Dont teach the reader chemical engineering
Dont be lazy. Cannot use justification I didnt have time
Gantt Chart
Please upload your Gantt Chart to LMS by next Monday
Gantt chart must be included as Appendix 1 of the report
All meeting minutes must be included in the Appendix of
the report
This chart will be the agreed schedule for your team in
case of disagreement refer back to it. Project leaders job
includes keeping team to the schedule.
Project Planning