EQUIPMENT PREDICTIVE MAINTENANCE REPORT

No of Action Target
Dept Area Equipment PdM Technique Normal value Frequency Last Done Exceptions
Points plan date
OH Connector and
1723 Monthly Nil
EMD Switchyard clamps Thermovision Scanning <70 Deg C
H2/CH4/CO/CO2/C2
Reactor and H4/C2H6/C2H2
EMD Switchyard DGA (parameter/ppm) 70 3 years Nil
Stage-1 CT 300/30/300/2500/1
0/50/2
EMD 100 Yearly
Switchyard CT,CVT Tan Delta measurement <0.7% Nil
EMD Switchyard LA s LCM <500micro A 100 Monthly Nil
DCRM and contact DCRM pattern and
EMD 26 Yearly
Switchyard 400KV Breakers resistance CR<100microohm Nil
Surge Loading during
EMD 8 Bi annually
DC system 220V Batteries AOH Nil
EMD Main Plant HT Motors Thermovision Scanning <70 Deg C Quarterly
Quarterly
EMD Main Plant HT Motors Vibration measurement <2.0mm/sec
Yearly
EMD Main Plant St2 CW Motors Oil Wear Debris Analysis
Power
EMD Main Plant BDV measurement >60KV 21 Quarterly 25.02.2017
Transformers Nil
Power 6 Months (Netra)
EMD Main Plant Moisture measurement <20ppm 21 16.02.2017
Transformers Monthly (Local)
Nil
Power
<70 Deg c 146
EMD Main Plant Transformers Thermovision Scanning Monthly 22.02.2017 Nil
Power
<0.7% 21
EMD Main Plant Transformers Transformer Tan Delta Bi annually 06.01.2017 Nil
Service
BDV measurement >60KV and < 20ppm 159 Annually
EMD Main Plant Transformers 17.02.2017 Nil
EMD Main Plant LT Motors Thermovision Scanning <50 Deg C 72 Quarterly 04.03.2017 Nil
EMD Main Plant LT Switchgear Thermovision Scanning <50 Deg C 72 Quarterly 04.03.2017 Nil
Shaft Voltage
EMD Main Plant Generator Measurement >2 V 4 Monthly 13.02.2017 Nil
Earth Resistance
EMD Main Plant MISC Measurement <1.0 Ohm 450 Yearly 17.02.2017 Nil
EMD CHP LT Switchgear Thermovision Scanning <50 Deg C 20 Quarterly 24.01.2017 Nil
EMD CHP LT Motors Thermovision Scanning <50 Deg C 20 Quarterly 24.01.2017 Nil
EMD CHP HT Motors Thermovision Scanning <70 Deg C 15 Quarterly 13.02.2017 Nil
EMD CHP ILMS Thermovision Scanning <50 Deg C 10 Quarterly 13.02.2017 Nil
Remarks