Item of Work : STRUCTURAL WORKS
Item No. : Concreting Including Formworks
Pedestal Footing
DIRECT UNIT
ITEM NO. DESCRIPTION QUANTITY UNIT AMOUNT
COST
A. MATERIAL COST Quantity
16mm Reinforcing Steel Bar 12.00 pcs. 300.00 3,600.00
G.I Tie Wire 5.00 kgs. 70.00 350.00
Cement 25.00 cu.m. 225.00 5,625.00
Sand 2.00 bags 700.00 1,400.00
Gravel 3.00 bags 850.00 2,550.00
Miscellaneous (15%) 1.00 lot 2,028.75 2,028.75
Sub-Total 15,553.75
B. LABOR COST Quantity No. of Days Cost per Day
Foreman 1.00 3.00 600.00 1,800.00
Skilled 2.00 3.00 500.00 3,000.00
Labor 2.00 3.00 350.00 2,100.00
Sub-Total 6,900.00
C. EQUIPMENT COST Quantity No. of Days Cost per Day
None - - - -
Sub-Total -
Sub-Total 11,902.50
B. LABOR COST Quantity No. of Days Cost per Day
Foreman 1.00 2.00 600.00 1,200.00
Skilled 2.00 2.00 500.00 2,000.00
Labor 2.00 2.00 350.00 1,400.00
Sub-Total 4,600.00
C. EQUIPMENT COST Quantity No. of Days Cost per Day
Concrete Vibrator 1.00 2.00 223.50 447.00
Sub-Total 447.00
Page 2 of 4
Item of Work : STRUCTURAL WORKS
Item No. : Concreting Including Formworks
Steel Column
DIRECT UNIT
ITEM NO. DESCRIPTION QUANTITY UNIT AMOUNT
COST
A. MATERIAL COST Quantity
4" GI Pipe 12.00 pcs. 3,500.00 42,000.00
2" x 4" Tubular Pipe 4.00 pcs. 6,500.00 26,000.00
Miscellaneous (15%) 1.00 lot 10,200.00 10,200.00
Sub-Total 78,200.00
B. LABOR COST Quantity No. of Days Cost per Day
30% of Material Cost 23,460.00
Sub-Total 23,460.00
C. EQUIPMENT COST Quantity No. of Days Cost per Day
Welding Machine 1.00 5.00 500.00 2,500.00
Sub-Total 2,500.00
Page 3 of 4
Item of Work : STRUCTURAL WORKS
Item No. : Roofing Works
Roofing Sheets
DIRECT UNIT
ITEM NO. DESCRIPTION QUANTITY UNIT AMOUNT
COST
A. MATERIAL COST Quantity
Roofing Sheets (Ga. 24 Pre-painted Longspan) 160.00 sq.m 380.00 60,800.00
Fascia Board 12.00 pcs 1,002.50 12,030.00
Ridge Roll 4.00 pcs 1,002.50 4,010.00
Gutter 5.00 pcs 1,002.50 5,012.50
Accessories and Miscellaneous 1.00 lot 4,092.63 4,092.63
Sub-Total 85,945.13
B. LABOR COST Quantity No. of Days Cost per Day
30% of Material Cost - - - 25,783.54
Sub-Total 25,783.54
C. EQUIPMENT COST Quantity No. of Days Cost per Day
None - - - -
Sub-Total -
Prepared by:
Page 4 of 4