Menu Path -
Double click on create then select order type PM05 Calibration Order with the help of F4 or click on
radio button of possible entry & select see fig 6.1
Fig 6.1
Page 1
Press enter to go on next screen
Planner group
Above fields are shown by arrow in Fig 6.2 & the possible entries can be entered from popup list with
the help of F4 or click on radio button it found right side of block it appear after clicking in
block control key should be PM01 i.e. Plant Maintenance Order Internal
Fig 6.2
Page 2
Enter operation task list from top popup menu bar see Fig 6.3 & 6.4
Fig 6.5
Page 3
Fig 6.6
Here we enter the task list which is prepared earlier for how to create task list see general maintenance
task list --
Fig 6.7
Click on execute (F8) Button in operation selection window click on All tab in Fig 6.8
Page 4
Fig 6.8
After selecting all operation selection screen appear kept task list factor default i.e. 1
Fig 6.9
After click on all selection tab task list is being included with the order to conform this see on bottom of
screen the message displayed in Fig 6.10
Fig 6.10
Now release the order it scheduled as per activity start date entered in fig 6.2
Page 5
Fig 6.11
After release click on save button, order no appear on the screen see at bottom Fig 6.12
Fig 6.12
Order can be cross check in order list with the help of transaction code IW39 Display order list
Order type PM05 Calibration Maintenance Order & Date (Fig 6.13)
Page 6
Fig 6.13
Then execute (F8) order displayed in list with it basic start date which entered in fig 6.2
Page 7