You are on page 1of 5

Paiton III Expansion Project Construction Contractor : Mitsui Co.

, Ltd and TOA Corporation

WORK SCHEDULE at Unit-3 Area as of 2 Jan 2009

December-2008 January-2009
Last Week This Week Next Week
No. Item Q'ty Unit Notes
29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun
[Working Time]
Start: 7:00 7:00 7:00 7:00 7:00 7:00 7:00 0:00 0:00 0:00 0:00 0:00 0:00 0:00 0:00 00.00 00.00 00.00 00.00 00.00
Finish: 18:00 18:00 18:00 18:00 18:00 18:00 24:00 24:00 24:00 24:00 24:00 24:00 24:00 24:00 24.00 24.00 24.00 24.00 24.00 24.00

[Work Schedule]
1 Preparation Work
D/G house Construction (Fuel tank Plan
1
Foundation) Act
Plan
2 Excavation Work (Up to GL -2.5m)
Act
Temporary Drainage Construction Plan
3
(excavation work) Act
Temporary Drainage Construction (Stone Plan
4
masonry work) Act
Plan
5 Water Pipe Installation
Act
2 Test Piling Works
Plan
1 Static Load test 600-2
Act
Dismantling Main beam, cross beam and Plan
2 concrete block at loading test 1200-1
Act
Mobilize Main beam & Cross beam to Plan
3 Pcs 36
loading test 600-2 Act
Concrete block, Main & Cross beam Plan
4
arrangement for Loading test 600-2 Act
Plan
5 Rebar Fabrication
Act
Plan
6 Bentonite Plant Erection (Silo & Pipe line)
Act
Plan
7 Drilling & Concreting for Test Pilling work
Act
4 Temporary Office Work 1 ls
5 Temporary Access Road Work 1 ls
6 Soil Investigation 1 ls
Plan
1 Well pumping test (Pump Pit area)
Act
Plan
2 Soil Investigation (Turbine Area)
Act
Transportation Boring Rig to South Slope Plan
3
Area Act
Plan
3 Soil Investigation (South slope area)
Act

1/5
Paiton III Expansion Project Construction Contractor : Mitsui Co., Ltd and TOA Corporation

WORK SCHEDULE at Unit-3 Area as of 2 Jan 2009

December-2008 January-2009
Last Week This Week Next Week
No. Item Q'ty Unit Notes
29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun

2/5
Paiton III Expansion Project Construction Contractor : Mitsui Co., Ltd and TOA Corporation

WORK SCHEDULE at Unit-3 Area as of 2 Jan 2009

December-2008 January-2009
Last Week This Week Next Week
No. Item Q'ty Unit Notes
29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun
[Construction Equipment]
1 Mobile Crane(150 ton) Unit 1 1 1 1
2 Crawler Crane(35 ton) Unit 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Crawler Crane(50 ton) 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1
3 Generator Set 250kVA Unit 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
4 Excavator Unit 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
5 Drilling Machine (For Soil Investigation) Unit 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
Drilling Machine (For Bore Pile) Unit 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
6 Truck Mixer Unit 0 0 0 0 0 4 4 4 4 4 4 4 4 4 4 4 4 4
7 Dump Truck Unit 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9
8 Pick Up Truck or Trailer Unit 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
9 Light Vehicle Unit 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4

[Manpower]
1 Manager person 1 3 3 3 3 3 3 2 2 2 2 2 2 2 2 2 2 2 2 2
2 Engineer person 1 4 4 4 4 4 4 5 5 5 5 5 5 5 5 5 5 5 5 5
3 Supervisor person 1 7 7 7 7 7 7 5 5 5 5 5 5 5 5 5 5 5 5 5
4 Safety Officer person 1 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
5 Surveyor person 1 3 3 3 3 3 3 4 4 4 4 4 4 4 4 4 4 4 4 4
6 Mechanic / Electrician person 1 5 5 5 5 5 5 6 6 6 6 6 6 6 6 6 6 6 6 6
7 Foreman person 1 4 4 4 4 4 4 5 5 5 5 5 5 5 5 5 5 5 5 5
8 Skilled Worker person 5 6 6 6 6 6 6 5 5 5 5 5 5 5 5 5 5 5 5 5
9 Worker person 15 53 53 53 53 53 53 63 63 63 63 63 63 63 63 63 63 63 63 63
10 Driver/Operator person 22 22 22 22 22 22 22 27 27 27 27 27 27 28 28 28 28 27 27 27
11 Security person 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
SUBTOTAL 33 114 114 4 114 114 114 114 129 129 129 129 129 129 130 130 130 130 129 129 129

3/5
Paiton III Expansion Project Construction Contractor : Mitsui Co., Ltd and TOA Corporation

WORK SCHEDULE at Unit-3 Area ( Genset House ) as of 23 Jan 2009

January-2009 February-2009

Last Week This Week Next Week


No. Item Q'ty Unit Notes
12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1
Mon Tue Wed Wed Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun
[Working Time]
Start: 7:00 7:00 7:00 7:00 7:00 7:00 7:00 7:00 7:00 7:00 7:00 7:00 7:00 7:00 7:00 7:00 7:00 7:00 7:00 7:00 7:00
Finish: 18:00 18:00 18:00 18:00 18:00 18:00 18:00 18:00 18:00 18:00 18:00 18:00 18:00 18:00 18:00 18:00 18:00 18:00 18:00 18:00 18:00

[Work Schedule]
1 Lifting Work
Lifting Diesel Generator set (2 units) Plan
1
including oil tank (2 units) in foundation Act
Plan
2 Lifting Genset House Rafter to support
Act
Plan
3 Install Roofing
Act
2 Piping Work
Plan
1 Fuel pipe installation from Tank to DG
Act
Plan
2 Return fuel pipe installation from DG to Tank
Act
3 Grounding
Plan
1 Installation grounding
Act

4/5
Paiton III Expansion Project Construction Contractor : Mitsui Co., Ltd and TOA Corporation

WORK SCHEDULE at Unit-3 Area ( Genset House ) as of 23 Jan 2009

January-2009 February-2009

Last Week This Week Next Week


No. Item Q'ty Unit Notes
12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1
Mon Tue Wed Wed Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun
[Construction Equipment]
1 Mobile Crane(150 ton) Unit 1
2 Crawler Crane(35 ton) Unit
Crawler Crane(50 ton)
3 Generator Set 250kVA Unit
4 Excavator Unit
5 Drilling Machine (For Soil Investigation) Unit
Drilling Machine (For Bore Pile) Unit
6 Truck Mixer Unit
7 Dump Truck Unit
8 Pick Up Truck or Trailer Unit 1 1 1 1
9 Light Vehicle Unit

[Manpower]
1 Manager person 1 1 1 1
2 Engineer person
3 Supervisor person 1 1 1 1
4 Safety Officer person 1 1 1 1
5 Surveyor person
6 Mechanic / Electrician person 1 1
7 Foreman person
8 Skilled Worker person 1 1 1 1
9 Worker person 4 4 4 4
10 Driver/Operator person 1 1 1 1
11 Security person
SUBTOTAL 0 0 0 0 0 0 0 9 10 10 9 0 0 0 0 0 0 0 0 0 0