August 2000
PIP CVS02700
Underground Gravity Sewers Specification
PURPOSE AND USE OF PROCESS INDUSTRY PRACTICES
In an effort to minimize the cost of process industry facilities, this Practice has
been prepared from the technical requirements in the existing standards of major
industrial users, contractors, or standards organizations. By harmonizing these
technical requirements into a single set of Practices, administrative, application, and
engineering costs to both the purchaser and the manufacturer should be reduced. While
this Practice is expected to incorporate the majority of requirements of most users,
individual applications may involve requirements that will be appended to and take
precedence over this Practice. Determinations concerning fitness for purpose and
particular matters or application of the Practice to particular project or engineering
situations should not be made solely on information contained in these materials. The
use of trade names from time to time should not be viewed as an expression of
preference but rather recognized as normal usage in the trade. Other brands having the
same specifications are equally correct and may be substituted for those named. All
Practices or guidelines are intended to be consistent with applicable laws and
regulations including OSHA requirements. To the extent these Practices or guidelines
should conflict with OSHA or other applicable laws or regulations, such laws or
regulations must be followed. Consult an appropriate professional before applying or
acting on any material contained in or suggested by the Practice.
This Practice is subject to revision at any time by the responsible Function Team
and will be reviewed every 5 years. This Practice will be revised, reaffirmed, or
withdrawn. Information on whether this Practice has been revised may be found at
http://www.pipdocs.org.
PRINTING HISTORY
April 1995 Issued
August 2000 Complete Revision
PIP CVS02700
Underground Gravity Sewers Specification
Table of Contents
3. Definitions .................................... 4
4. General ......................................... 4
4.1 Quality Control ................................... 4
4.2 Submittals .......................................... 4
4.3 Safety................................................. 5
4.4 Environmental.................................... 5
5. Materials ....................................... 5
5.1 Pipe and Joints .................................. 5
5.2 Manholes, Inlet Structures, Frames,
and Covers ........................................ 7
5.3 Cast-in-Place Concrete...................... 7
1. Introduction
1.1 Purpose
The purpose of this Practice is to provide Contractor with underground gravity sewer
requirements. This document is a complete revision of PIP CVS02700 and, therefore,
revision markings are not provided.
1.2 Scope
This specification establishes material, installation, and testing requirements for
underground gravity sewers. Included are pipe, inlet structures, manholes, and
appurtenances for sanitary, storm, and industrial process sewers. Double-contained
and emission-controlled industrial process sewers in environmental applications are
not considered.
Any conflicts or inconsistencies between this specification, the shop drawings,
Contract Documents, or regulatory requirements shall be brought to the attention of
Owner for resolution.
2. References
Applicable requirements in the following PIP Practices, codes and standards, and
government regulations shall be considered an integral part of this Practice. The edition in
effect on the date of contract award shall be used, except as otherwise noted. Short titles will
be used herein when appropriate.
3. Definitions
Contract Documents: Any and all documents, including design drawings, that Owner has
transmitted or otherwise communicated, either by incorporation or by reference, and made
part of the legal contract or purchase order agreement between Owner and Contractor.
Contractor: The party responsible for performing excavation, backfill, and pipe installation,
including work executed through the use of sub-contractors.
Owner: The party who awards the Contract. Owner may be the owner or the owners
authorized agent.
4. General
4.2 Submittals
4.2.1 Two weeks before installation, Contractor shall submit fabrication drawings
and instructions for the installation of pipe and appurtenances furnished
under this specification to Owner.
4.2.2 Two weeks before installation, Contractor shall submit certification that an
OSHA-defined excavation-competent person (ECP) shall oversee all
excavation. All trench work requiring an ECP shall be submitted to Owner.
4.2.3 Two weeks before installation, the material supplier or Contractor (or both)
shall submit certification in writing to Owner that the materials to be used
under the contract satisfy all the requirements of the project.
4.3 Safety
4.3.1 Field construction activities on Owners property shall conform to Owners
safety requirements, including any special rules that may be in effect at a
specific site.
4.3.2 Good housekeeping practices shall be maintained in and around the work
site throughout the duration of the work.
4.3.3 Hazardous and hot work permits for chemical exposure, open flames, spark-
producing mechanical equipment, potential explosive mixtures, and any
other hazardous conditions are required in areas specified by Owner.
4.3.4 All excavation and trenching shall be in accordance with OSHA Standards
and Owners local requirements and guidelines (as applicable) for the
following:
Shoring, bracing, and/or sloping wall construction
Marking and flagging open excavations
Permitting and confined space entry requirements
4.4 Environmental
4.4.1 All sewer outfalls are required to be permitted by applicable regulations.
Contractor shall verify with Owner that the applicable permit will allow
intermittent non-storm flows into storm sewers before discharging any liquid
into drains, catch basins, or manholes in connection with trench dewatering
activities, testing, or other activities where liquids need to be disposed.
4.4.2 Excavated material shall be managed in accordance with the soil
management plan. The soil management plan will be provided by Owner as
part of these Contract Documents or shall be developed by Contractor and
accepted by Owner before the start of excavation activities.
5. Materials
6. Execution
6.3 Dewatering
6.3.1 Contractor shall provide, install, and maintain equipment such as pumps,
sumps, suction and discharge lines, and all other dewatering system
components necessary to collect and discharge water away from excavations.
Contractor shall dispose of all water encountered in such a manner that
property will not be damaged and no nuisance or health menace will result.
When required by Owner, Contractor shall provide a means of desilting the
water before disposal.
6.3.2 At any time, the length of open trench shall be limited to that which can be
dewatered with methods and equipment available.
6.3.3 Dewatering methods shall be used to minimize softening of the soil
supporting the pipe and changes in soil characteristics detrimental to
subgrade stability.
6.4 Bedding
6.4.1 Bedding material shall be granular, well graded, with all material passing 1/2
inch (12.5 mm) sieve, and at least 90 percent retained on No. 200
(75 microns) sieve as determined in accordance with ASTM D422.
6.4.2 Bedding material shall be placed under and equally along both sides of the
pipe in uniform layers not exceeding 6 inches (150 mm) loose depth to a
height of the centerline of the pipe and compacted by hand, pneumatic
tamper, or other Owner-approved means.
6.4.3 Bedding material shall be compacted to a density approximately that of the
undisturbed site soil materials or as specified on drawings. When compacted,
the pipe bed shall provide uniform bearing for the bottom of the pipe (see
trenching requirements specified herein).
6.6 Backfilling
6.6.1 Backfill and compaction shall be in accordance with PIP CVS02315 and as
specified herein.
6.6.2 The trench shall be backfilled and compacted to a density equal to that
specified on the drawings or equal to that of the adjacent in situ material.
6.6.3 As soon as possible after pipe joints are made, backfill material shall be
placed with care along the sides of the pipe to prevent movement of the line
or grade.
6.6.4 Joints shall be left exposed until completion of leak testing.
6.6.5 Backfilling of trenches shall be completed immediately after testing.
6.6.6 Backfilling shall be compacted in a manner that avoids displacement or
damage to the pipe.
6.6.7 No construction machinery or vehicles shall be allowed to pass over the
trench until the trench is backfilled and compacted sufficiently to prevent
damage to the pipe.
6.7 Testing
6.7.1 Exfiltration shall be measured at a manhole. The section of pipe to be tested
shall be plugged at the downstream end of pipe (e.g., as at a manhole). The
laterals in the section being tested shall be plugged with removable stoppers.
6.7.2 Exfiltration tests shall be conducted by filling sections of pipe, 400 feet
(122 m) maximum length at a time, with water to the top of the manhole but
not less than 5 feet (1.5 m) above the top of the pipe. If required, a standpipe
shall be used to bring the water level to 5 feet (1.5 m) above the top of the
pipe. Let water stand 4 hours. Refill manhole and measure the drop after 1
hour. Maximum exfiltration shall be as follows:
Process sewers - no measurable amount
Sanitary sewers - 0.0008 gallons/inch diameter/feet/hr
(0.00039 liters/mm diameter/m/hr)