Student Name:
Student ID:
3. To gather some more details on the customer requirement , you mailed several
stakeholders, as you needed information quickly from more than 1000 people in next
two days. Which technique is being used ?
Interviews
Delphi
Nominal group technique
survey
10. Jack, Rusty and Stacy are Project Managers working for an IT firm. In an informal
coffee session, they are discussing about a few things. Jack complains that it is very
difficult to manage a project in the company. Rusty complains that the stakeholders
make too many amendments some of which are necessary, but a few are not, Stacy
also throws some light on an uncooperative environment that exits in the company.
However, Nicole wants to understand the advantages of the Matrix organization as
compared to a Functional organization. Which of the following segments is TRUE for
Matrix organizations?
Project Managers control over resources is better with respect to Projectized
organization.
Two bosses
Smooth Communication
Project Manager has no authority
13. Lilly has been appointed as the Project Manager of an IT Project. It is a matrix
organization. So, she identified that her team
Will report to her
Will report to functional head
Will be motivated
Will report to both functional head as well as project manager
14. You are appointed as a team member in a Projectized organization. Whom would
you report to?
your project manager
functional manager
project expediter
project coordinator
15. You are appointed as a team member in a Projectized Organization. Who do you
think will give you directions?
The project manager
The functional manager
The team
The project coordinator
17. Some of your team members want to work on a flexible schedule and others want
all team members to agree on a fixed time schedule. What should you do?
Allow them for flexible time schedules
Allow them for fixed time schedules
Arrange a meeting and allow them to decide
Ask your senior management to decide
18. You are managing a project that is in the execution phase. A large and unexpected
problem occurs that will cause a delay in the schedule. What should you do?
Look for tasks in the project where there is an ability to reschedule to free
resources for this problem
Make overtime mandatory for the project team
Discuss with the stakeholders about getting additional time and budget for the
project
Reduce testing time
19. You are a project manager of Software Product company. After a person is hired,
you come to know that many of this person's ideas were developed by a competitor
company. Are you going to implement the same ideas?
Accept the new ideas
Ignore the ideas because it may be violation of the code of conduct
Ask to sign NDA
Tell the person that he should not mention that the ideas came from another
company
20. Your company policy allows accepting gifts from customer within certain limit. Your
customer is giving you a gift which is beyond limit of your company policy. You have
given a gift to the customer's representative already which has similar in value. What
should you do?
Accept it and don't tell anyone
Contact your company's senior management and ask for assistance
Ask your customer about company policy
Refuse it
B. Analyze following cases that relates to Project Planning and Project Scope
management:
Case 1: The Dirty Little Secret of Project Management: Joe Knight, Roger Thomas, and
Brad Angus, Harvard Business Review, March 10, 2013
https://www.dropbox.com/s/y76pyctez1fjto5/The%20Dirty%20Little%20Secret%20of
%20Project%20Management.pdf?dl=0
Please write 1/2 page summary based on details and points made in this case.
5) in general, product life cycles are becoming __________ and product launch
windows are becoming__________.
8) Detailed specifications, schematics, and schedules are all developed during the
__________
stage.
9) Creativity is at its zenith during the __________ stage of the project life cycle.
11) __________ are used to allow organizations to benchmark the best practices of
successful project management