You are on page 1of 49

SRI LANKAN QUANTITY SURVEYORS

Volume 4 - February 2010


SLQS Journal
The Forum of Sri Lankan Quantity Surveyors Across the Globe

Volume 4 February 2010

Editorial Committee

Ajantha Premarathna FRICS, FIQS(SL), ACIArb.

Dhammika T. Gamage
NDT(Civil Eng.), ICIOB, ACIArb, AAIQS, MIIE(SL), IEng, FACostE, FCInstCES

Lakshman Gunatilake MCInstCES, MACostE, ACIArb, MIIE(SL), IEng,

Editorial Policy

We, the editorial committee reserve the right to select, reject, edit, and excerpt articles at our sole discretion. We will
publish no article which, in the opinion of the editorial committee, can be reasonably interpreted as insulting or offensive
to any individual or group. We will not return unsolicited manuscripts. The opinions expressed in articles contained in the
SLQS Journal are the opinions of individual authors and not necessarily those of the SLQS Journal editorial committee.
Articles are provided for the general interest of the quantity surveying and contract administration community, but the
information contained therein does not constitute legal advice and should not be relied on as such. Neither the SLQS nor
the individual authors assume any responsibility for the accuracy of information reported.

The editorial committee assumes no responsibility for failure to report any matter inadvertently omitted or withheld from
it. The mode of citation utilised within the articles and for the bibliography would be the Chicago method.

Email your own creations to journal@slqs-uae.org with your passport size photograph and brief profile of yourself which
should not be more than 35 words.
February 2010
SLQS JOURNAL

CONTENTS Page

Editorial

Differences in Concepts between 1987 Red Book & 1999 Red Book
Editions of the FIDIC Forms 5
Hasaranga Fonseka BSc., MSc ACIArb, CCE

Extension of Time and Cost Reimbursement Claims 13


Lalani. C. Dodangoda Assoc.R.I.C.S, MACostE, LIMIS(U.K), ACIQS(Canada), AACE(U.S.A),
MPMI(U.S.A), MAPQSE (Sri Lanka)

How to Deal with a Delay or Default by Nominated Sub Contractor, in a


Contract under JCT 98 under JCT 98 15
Saman Jayasiri Welagedar, NCES (Civil)

Is Rent Leading Construction? 19


Wsantha Edirisinghe BSc (Hons)

Can Time Bar Clause (20.1 FIDIC 1999) Lead to Lose Contractors Rights? 23
Mahinda Ranatunga, BSc QS(Hons), MCIArb, CCE, Pg. Dip.(Arb & Const. Law)

Valuation of Variation under Lump-Sum Contracts 27


R.M Duminda Nishantha Kumara

The Relationship between Management and Personal Management Competencies 30


Punyamalie De Silva

How to Deal with an Extension of Time /Cost Claims 35


P.M. Dimuthu Niroshan Tissera B.Sc. (QS)Hons

Steps an Arbitrator should take before and during the Hearing. 38


Ananda P. Wickramasinghe. MSc(QS), ICIOB, ACIArb.

Performance of Critical Attributes in Alternative Dispute Resolution (ADR):


A Study in Sri Lankan Construction Industry 42
K.B. Dinesh Gunasena BSc (QS)Hons
February 2010
SLQS JOURNAL

Editorial

Dear Sri Lankan Quantity Surveyors

Prior to writing this editorial, I was looking back on our greatly successful commemorations of the
Silver Jubilee of the SLQS get-together, one of the most notable of which was Prof. Samaratungas
Continuing Professional Development Programme, Variations and Valuation of Variations under
the ICTAD and FIDIC Forms of Contract conducted in Colombo, followed by our recent Silver
Jubilee get-together held on December 2009. Likewise, this edition of SLQS Journal was dedicated
to commemorate the Silver Jubilee celebration of the SLQS-UAE get-togethers in the year of
2009.

We, the SLQS, are exceptionally pleased to announce our success with the publication of the SLQS
Journal as planned, an event long overdue and of significance to the Sri Lankan quantity surveying
community in the United Arab Emirates and the world at large.

We wish to thank all those of you responsible for the overwhelming response to our request; all
of those articles were a tremendous pleasure to read. Also, it was with great satisfaction that we
observed the outpouring of interest generated by the participants of the earlier workshop Sound
Contract Administration, by providing many articles which will be published in future issues. We
would like to mention that we have many more submissions of high quality than we are able to
accommodate within one volume, and the selection of the articles printed within is in no way a
rejection of other articles of equal quality.

In this edition, we found that two authors have taken a look through a different perspective at their
journey through the construction industry. The Relationship between Management and Personal
Management Competencies by Punyamalie De Silva and Is the Rent is Leading the Construction?
by Wasantha Edirisinghe are unique and noteworthy articles concerning the direct and indirect
influences on the construction industry.

Also, we consider it necessary to again discuss the appropriate length of articles. We should say
that, as we have more submissions of high quality than we may be able to accommodate within one
volume, the ideal length is around 3,000 words but should not exceed 5,000 words.

We trust that it is essential to remind you that this journal is designed to encourage interest in
all matters relating to contract administration, with an emphasis on matters of theory and on-
board issues arising from the relationship of contract administration to other disciplines in the
construction industry. The subject matter of the articles will consist mainly of, but not be limited
to contractual matters. However, it is not the purpose of this journal to concentrate solely on drily
academia-oriented matters.

We eagerly anticipate future articles from you, our readers, for our forthcoming journals.

On behalf of the editorial committee,


Dhammika T. Gamage


February 2010
SLQS JOURNAL
Differences in Concepts between 1987 Red
Book & 1999 Red Book Editions of the FIDIC
Forms
Hasaranga Fonseka BSc., MSc ACIArb, CCE
Quantity Surveyor
Mina al Arab Infrastructure Works
Halcrow International Partnership

The FIDIC form: a brief history 3.1 and 3.5 of the 1999 Red Book . In the former
The Fdration Internationale des Ingnieurs-Conseils the Engineer is required to exercise the discretion
(FIDIC) organisation was founded in 1913 as a granted to him under the contract impartially with
collaboration of France, Belgium and Switzerland. The the terms of the contract; in the latter, the Engineer
first edition of the Conditions of Contract (International) is deemed to act for the employer unless expressly
for Works of Civil Engineering Construction was stated to the contrary but, if required to agree or
published in August 1957 having been prepared on behalf determine any matter, is obliged to consult with
of FIDIC and the Fdration Internationale des Btiment the parties in any attempt to reach agreement and
et des Travaux Publics (FIBTP). failing agreement, to make a fair determination.

Both the Red and Yellow Books were revised by FIDIC Whilst all the forms of contract recognize the
and new editions were published in 1987. A key feature matrix of pure financial risk and make provision
of the 4th edition of the Red Book was the introduction for the employer to require the contractor to
of an express term which required the Engineer to act provide a performance guarantee, the wording of
impartially when giving a decision or taking any action the provision in the fourth edition of the Red
which might affect the rights and obligations of the Book differs greatly from that in the 1999 forms
parties, whereas the previous editions had assumed this of contract. Under the 1999 book the employer is
implicitly. Although this paper concentrates on the new required to return the performance security within
FIDIC forms, it should be remembered that the FIDIC 21 days of receiving a copy of the performance
4th edition (The Old Red Book) remains the contract of certificate (under sub clause 11.90), whereas by
choice throughout much of the Middle East, particularly virtue of clause 10.2 of the fourth edition of the
the UAE. Red Book the performance security is to be returned
within 14 days of issuance of the defect liability
In 1994 FIDIC established a task force to update both certificate (under sub-clauses 62.1).
the Red and the Yellow Books in the light of developments
in the international construction industry, including Under the sub clauses 2.4 of the 1999 Red Book the
the development of the Orange Book. The differences risk of inadequate employers financial arrangements
in concept between the 1987 Red book and the has been recognized and upon the contractors
1999 Red book are more important when dealing with request, if the employer fails to comply with this
Contract Administration, so the list of items below are requirement then the contractor is entitled to
the major differences of this 2 forms. suspend or reduce the rate of work and ultimately
to terminate the contract. There is no corresponding
A basic change has been made to the role of provision in respect of the employers financial
the Engineer in the 1999 Red Book . This change arrangements under the fourth edition of the Red
can be seen by comparing sub-clause 2.6 of the Book.
fourth edition of the Red Book with sub clauses


February 2010
SLQS JOURNAL
There is a new provision in the 1999 Red and employer. It would appear to derive from a similar
Yellow books expressly entitling the contractor, that concept which has been developed by the courts of
in the event of late payment by the employer, for the law of negligence.
that amount to be reimbursed as financing changes
calculated at any annual rate which is 3% above The start of time limits in relation to interim
the discount rate of central bank (in the country payments to the contractor has been altered. Under
of the currency of payment) and be compounded sub clause 14.7(b) of the 1999 Red Book, the
monthly. interim payment must be made within 56 days after
the Engineer receives the contractors statement
One of the contractors obligations in the 1999 (and supporting document) ,whereas in sub clause
forms of contract is to ensure that the works are 60.10 under the fourth edition of the Red Book
fit for the purpose for which they were intended as such payment is required to be made within 28
stated in the contract conditions. There is no such days from the date of the employers receipt of the
requirement in the fourth edition of the Red Book. interim payment certificate from the Engineer.

Whilst the concept of clause 12 of the fourth edition The employer under sub clause 15.5 of the Red
of the Red Book, in respect of the risks of Book is entitled to terminate the contract at any time
unforeseeable physical obstruction or conditions, has and for his/her convenience, by simply giving notice
been maintained in the 1999 Red Book, both the to the contractor of such termination. The only
negative and positive aspects of such risks are taken condition that applied to this provision is that the
into consideration in the latter forms. Therefore employer must not choose to terminate the contract
under the 1999 books, in making a determination in in order to execute the work him/herself or to arrange
respect of a contractors clams for adverse unforeseen for the work to be executed by another contractor.
physical obstructions/conditions, the Engineer Termination for convenience is provided for at
is entitled to review whether other physical clause 15.5 upon 28 days notice. The Contractor is
conditions encountered were more favourable than paid for work done and demobilization but receives
could reasonably have been expected at tender stage. no compensation.
In fourth edition of the Red Book there is no such
provision. Some changers have been made in relation to the
allocation of the risk between the employer and the
As an example the ground conditions claims are contractor. In particular, reference is made in the
recognized in clause 4.12 in the Red Book with the 1999 forms to sub clause 17.3, which now includes
provision that a claim may be reduced where other terrorism as one of the employer risk; and Clause
physical conditions in similar parts of the works (if 19, which now expressly defines force majeure and
any) were more favorable than could reasonably have the relief available to the parties in such an event.
been foreseen when the Contractor submitted the
Tender. Employers faced with ground conditions There is a new provision in the 1999 forms entitled
claims will no doubt be looking for reductions and limitation of liability- sub-clause 17.6 , which states
the meaning of similar parts and more favorable that neither party shall be liable to the other party
will come under close scrutiny. for loss of use of any works, loss of profit, loss of
any contract or for any indirect or consequential
The term unforeseeable is expressly defined in the loss or damage which may be suffered by the other
1999 forms of contract. This definition is a useful party in connection with the Contract, other than
attempt at bringing some certainty to the concept under Sub Clause 16.4 ( Payment on Termination
of unforeseeability. This concept relates to the ) and Sub Clause 17.1 (Indemnities). Also it limits
allocation of risks between the parties under the the contractors liability to the accepted contract
FIDIC form of contract, namely those risks which amount, or to sum stated in the particular conditions
are foreseeable and are borne by the contractor and (if any).
those which are unforeseeable and are borne by the


February 2010
SLQS JOURNAL
The insurance provision of the 1999 form of concept which has slight but potentially significant
contract, clause 18, differs greatly from the provision application in different jurisdictions, intending
under the fourth edition of the Red Book, leaving employer should follow the recommendation given
the matter to be discussed and agreed at the meeting in the Guidance for the preparation of particular
that is required to be held before the date of the Condition to the 1999 forms of contract, namely
letter of acceptance. This agreement of terms shall that before inviting tenders they should verify that
take precedence over the provisions of this clause. the wording of this clause is compatible with the
(Second paragraph of sub clause 18.1) law governing the contract. Equally important
are the consequences set out in clause 19.4, which
Under the clause 16.1 of the 1999 Red Book, if the indicate that the Contractor receives both time and
Contractor suffers delay and/or incurs Cost as a result reimbursement of costs that result from the event.
of suspending work (or reducing the rate of work)
in accordance with this Sub-Clause, the Contractor There is a new provision in the 1999 forms of
shall give notice to the Engineer and shall be subject contract requiring the employer to comply with
to Sub-Clause 20.1 [Contractors Claims] to a claims procedure for employers claims. According
payment of any such Cost plus reasonable profit, to sub-clause 2.5 this procedure is different from that
which shall be included in the Contract Price. But which is stipulated for the contractor, particularly
according to 1987 Edition the entitlement will be in respect of the time limits that apply. The notice
only for the cost. shall be given as soon as practically possible
after the employer become aware of the event or
Clause 19 of the 1999 forms entitled force majeure circumstances giving rise to the claim. This amount
replaces special risk concept of fourth edition may be included as a deduction in the Contract
of the Red Book. Since force majeure is a legal price and payment certificate.

Employers Claims and Other Deductions

Contd.

February 2010
SLQS JOURNAL

The Defects Notification Period, as it is now called, forms of contract that if a claim is to be made by
may be extended for up to 2 years if and to the the Contractor under sub-clause 20.1, a notice of
extent that the Works, Section or a major item of such a claim must be made within 28 days after the
Plant cannot be used for the purposes for which contractor become aware, or should have become
they are intended by reason of a defect or damage.- aware, of the event giving rise to the claim. Details
clause 11.3. of the claim with supporting particulars should be
given within 42 days. If a Contactor fails to give
Under the 1999 forms of contract, until the notice of a claim, the employer is discharged from
Performance Certificate has been issued, the all liabilities in connection with the claim.
Contractor shall have such right of access to the
Works as is reasonably required in order to comply Failure to provide claim notices within the 28 days as
with this clause, except as may be inconsistent with provided by clause 20.1 means,
the Employers reasonable security restrictions. In
the fourth edition of the Red Book there is no such the Time for Completion shall not be extended, the
provision. Contractor shall not be entitled to additional payment,
and the Employer shall be discharged from all liability in
Strict time limits are imposed under the 1999 connection with the claim.


February 2010
SLQS JOURNAL
Contactors claims


February 2010
SLQS JOURNAL

10
February 2010
SLQS JOURNAL
Strict time limits are imposed for other notices, ii. The Guidance for the preparation of particular
for example, the contractor must give 28 days conditions to the 1999 Red Book includes an option
notice of the intended commencement of each sub of reverting to the traditional role of the Engineer
contractors work; and employer is required not less (and gives example sub-clauses to replace /amend
than 7 days notice of the commencement date. sub-clauses 20.2 to 20.4).

The 1999 of contract has expressly introduced the As per 1987 edition, on the issue of the Taking-Over
concept of value Engineering which will if adopted, Certificate for the whole of the Works, it is found
accelerate the completion of the works; reduce the that as a result of;
cost to the employer of executing, maintaining or
operating the works; improve the efficiency or value (a) all varied work valued under Sub-Clauses 52.1 and
to the employer of the completed work or otherwise 52.2, and
be of benefit to the employer. The contractor may
make a proposal incorporating value engineering at (b) all adjustments upon measurement of the estimated
any time to the Engineer; if approved it is valued quantities set out in the Bill of Quantities, excluding
under the variation under the sub clause 13.3. Provisional Sums, day works and adjustments of price
made under Clause 70, but not from any other cause,
If this change results in a reduction in the contract value there have been additions to or deductions from the
of this part, the Engineer shall proceed in accordance with Contract Price which taken together are in excess of 15
Sub-Clause 3.5 [Determinations] to agree or determine a per cent of the Effective Contract Price then and in
fee, which shall be included in the Contract Price. This such an event, they shall be added to or deducted from
fee shall be half (50%) of the difference between the the Contract Price as such further sum may have been
following amounts: in regard to the Contractors Site and general overhead
costs of the Contract. Such sum shall be based only on
(i) such reduction in contract value, resulting from the amount by which such additions or deductions
the change, excluding adjustments under Sub- shall be in excess of 15 per cent of the Effective Contract
Clause 13.7 [Adjustments for Changes in Legislation]
Price.
and Sub-Clause 13.8 [Adjustments for Changes in
Cost],and
Under the 1999 forms of contract the above clause has
been deleted but however, a new rate or price shall be
(ii) the reduction (if any) in the value to the Employer of
appropriate for an item of work if:
the varied works, taking account of any reductions in
quality, anticipated life or operational efficiencies.
- the measured quantity of the item is changed by
more than 10% from the quantity of this item in
However, if amount (i) is less than amount (ii), there shall
the Bill of Quantities or other Schedule,
not be a fee.

A new step in the dispute settlement procedure - this change in quantity multiplied by such specified
referral of the dispute to a Dispute Adjudication rate for this item exceeds 0.01% of the Accepted
Board (DAB) similar to that introduced in the 1996 Contract Amount,
Supplement to the fourth edition of the Red Book,
has been introduced under sub-clauses 20.2 to 20.4 - this change in quantity directly changes the Cost per
of the 1999 form of contract. There are however a unit quantity of this item by more than 1%
few important aspects that differentiate the DBA
concept introduced in the 1996 supplement and the - this item is not specified in the Contract as a fixed
1999 forms. These as follows: rate item

i. The DAB in the 1999 Red Book is appointed by Under the 1999 forms of contract in Application for
the date stated in the Appendix to tender , which Interim Payment Certificates, retention will not be
proposes 28 days after the commencement date. deducted from

11
February 2010
SLQS JOURNAL

- any amounts to be added and deducted for Plant Number of words in Part I of the FIDIC forms
and Materials in accordance with Sub-Clause 14.5 Red Book 1987 Edition - 23,544 words
[Plant and Materials intended for the Works]; Red Book 1999 Edition - 29,800 words

- any other additions or deductions which may have References


become due under the Contract or otherwise, 1. FIDIC Conditions of Contract 1987 Edition, by
including those under Clause 20 [Claims, Disputes International Federation of Consulting Engineers
and Arbitration]; 2. FIDIC Conditions of Contract 1999 Edition, by
International Federation of Consulting Engineers
But as per 1987 edition retention will be deducted from 3. The FIDIC Forms of Contract 3rd Edition, by
the above two items also. Nael G Bunni

Anns and Others -v- Merton London Borough Council [1978]


The plaintiff bought her apartment, but discovered later that the foundations were defective. The
local authority had supervised the compliance with Building Regulations whilst it was being built,
but had failed to spot the fault. The authority appealed a finding that it was liable, arguing that the
claims were time barred and that it had owed no duty beyond its statutory duty.

Held: As a public body, the defendants powers and duties were defined in public not private law.
Any distinction between the powers and duties of a local authority fell to be considered in that
context. The authority should at least have considered whether to inspect the foundations, and if
it did inspect, to do so with care. The authority could not protect itself entirely, simply by failing
to carry out any inspection at all. A duty of care might exist at common law, and whether it did so
did not depend upon whether the statute imposed a duty or a power to inspect. The cause of action
arose at the time when the condition of the building suggested some fault, and time did not begin
to run until this happened. The action was not statute barred.

12
February 2010
SLQS JOURNAL
Extension of Time and Cost Reimbursement
Claims
Lalani. C. Dodangoda
Assoc.R.I.C.S, MACostE, LIMIS(U.K), ACIQS(Canada), AACE(U.S.A), MPMI(U.S.A), MAPQSE (Sri Lan-
ka) has successfully completed her National Certificate of Technology in Quantity Surveying course in the Uni-
versity of Moratuwa in 1986 & served as a senior quantity surveyor in Consultancy organization in Sri Lanka,
extended here expertise in the field of Project Management by joining to Perigon Lanka ( PVT ) Ltd and worked
as Chief Quantity Surveyor / Projects co-coordinator . She joined to Faith Ful & Gould (Middle East) in 2006,
continuing her studies in Diploma in Project Management in College of Estate Management (U.K).

Identify The Event contractor should be required to identify the contract


A delay claim of a construction project corresponds to a provisions under which claims are being made.
period of time which the project has been extended or Eg; Contract provides for time for completion to be adjusted
work has not been performed due to conditions which under FIDIC 1987 Clause 41.1 (Commencement delays &
were unforeseeable at the time the parties entered into the site conditions), 52 (Variations), 44.1 (Extension of Time).
contract. The most common cause of delay on a project
include ; Consideration of Contractual Entitlement;
a) differing site conditions Typically construction contracts contain provisions
b) changes in design requirement entitling the contractor to an extension of time on the
c) Inclement weather occurrence of a particular event provided the progress of the
d) unavailability of labour works of time for completion is delayed as a consequence.
e) market interruptions For example FIDIC 1987 provides for an entitlement
f ) defective plans & specifications for extension of time in the event of : late drawings(
g) interruption by the employer clause 6.4) ,adverse physical conditions (Clause 12.2),
discovery of fossils or antiques( Clause 27.1), suspension
Such delays often force a contractor to extend the time of work ( Clause 40.2) ,failure to give possession of site (
to complete the work required under the contract, as Clause 42.2), additional or extra work ( Clause 44.1 (a))
well as to invite additional costs to the project. Generally, , delay referred to in these conditions ( Clause 44.1 ( b)
these costs may include: the cost of sustaining an idle ), exceptional adverse climatic conditions ( Clause 44.1
workforce and equipment, unabsorbed on site and off ( c) ), any special circumstances, other than through
site expense and general conditions. However, in order the default of the contractor ( Clause 44.1 (d)), and ,
to receive an addition of time for the project completion contractors suspension of the works(Clause 69.4).
and/or to recover additional costs, the contractor must
meet a number of fundamental requirements, specified in Considerations of Contractual Compliances
the conditions of contract. Generally with an extension of a time claim, the contractor
will be obliged to submit notice(s) and detailed particulars
Liability For The Event within a specified time frame. For example, Clause 44.2
Once an event has been identified the next step is to of FIDIC 87 provides: Provided that the engineer is not
determine the liabilities of the event. If responsibility bound to make any determination unless the contactor
rests with the employer or its a neutral, such as force has a) Within 28 days after such an event has first arisen,
majeure or exceptionally adverse climatic conditions, notified the engineer with a copy to the employer b)
the contractor may be entitled to an extension of time. Noticed within 28 days, or such other reasonable time
However, this is dependent upon the terms and conditions as may be agreed by the engineer, after such notification
of the particular contract. In circumstances where the submitted to the engineer detailed particulars of any
contractor is responsible for the delayed event, then the extension of time to which may consider himself entitled
consequences remain with the contractor. Therefore the in order that such submissions may be investigated at

13
February 2010
SLQS JOURNAL
the time. Occasionally, the submission of notice and/ C) Inexcusable (Contractor culpable) Eg; Extension
or detailed particulars will be expressed to be a condition of time shall not be granted, and the contractor shall
precedent. The contractors failure to comply waives his not be relieved from the penalties. The contractor is not
entitlement to claim an extension of time and owners entitled to claim reimbursement of prolongation cost.
liability ceases. For this reason therefore, it is critical to
comply with the contract from the start of the project at Methods of delay analysis can be identified concisely as
all levels. In addition, further submissions may be required follows:
for particular events. For instance: Clause 6.3 of FIDIC As Built Vs As Planned: This method basically is a
1987 (Disruption of Progress) requires the contractor to comparison between the planned base line and up dated
give notice to the engineer, with a copy to the employer, programme.
whenever planning or execution of the works is likely to
be delayed or disrupted unless any further drawing or As Planned Vs Impacted: The impacted as planned
instructions is issued by the engineer within a reasonable technique is based on introducing the events of the
time. The notice shall include details of the drawings delay in the base line. After introducing these delays
or instructions required and of why and by when it is the programme will show a new completion date which
required and of any delay or disruption it may suffer. has resulted from these events. However in theory, the
contract should be entitled to a time extension of time
Cause & Effect A common mistake made by equivalent to the variance between the original & the
contractors when attempting to demonstrate the cause impacted dates.
and effect on the event is that they merely order the
pertinent exchanges of correspondence between the Time Impacted Analysis: In this technique the impact
parties. From my experience this is usually insufficient of delayed events are reflected on the plan updated as
to satisfy the burden of proof. To demonstrate cause and a planned programme. After completion of impacted
effect, an account should be prepared based on the facts programme for each event, the analysis has to be done to
describing the effects of the event upon the works. This establish which delays are from the contractors and which
should include detail of activities affected, referring to its may have resulted from the delayed event.
planned sequence, durations and methodology; the status
of the works in relation to the planned at the time of the Statement of Claim:
event; and description of the changes to that plan as a Every extension of time claim must contain a concise
consequence of the event. statement of what the contractor is claiming. The
claim particulars should include as a minimum a) the
Delay Analysis There are a number of delay analysis. description of the event including the timing and nature
Ultimately, the choice of delay analysis methodology
of the event b) proof of entitlement c) the impact of the
will be dependent upon such matters as level of records
contractors work programme, resources, deployment
available; the robustness of the base line programme and
of materials d) equipment & personnel e) analysis of
any updates; time available; degree of accuracy; and
measures undertaken to ease the problem f ) approved
level of proof that is required. The 1st step would be
programme g) detailed justification of the time delay
classifications of the delays, as follows.
suffered h) all other supporting documents and evidence
j) prolongation cost.
A) Excusable & compensable (Responsibility of
the Employer) Extension of time shall be granted. The
contractor is relieved from the liability of penalties and Substantiation of Claim:
the contractor is entitle to claim prolongation cost. Extract and provide documentary evidence (letters,
method statements, progress reports and photos, minutes
B) Excusable but Non compensable (Concurrent) of meeting, programme, and schedules), statements of fact
Delays are regarded as neutral. For example, extension and expert witness statements (if required). In supporting
of time shall be granted. Contractors are relieved from the assertion made within the claim submission,
the labiality of penalties. The contractor is not entitled examining this check list will give a good starting point
to claim reimbursement of prolongation cost (exceptional for evaluation of any time extension claim.
climatic conditions etc. ).
14
February 2010
SLQS JOURNAL
How to Deal with a Delay or Default by
Nominated Sub Contractor, in a Contract
under JCT 98 under JCT 98
Saman Jayasiri Welagedar, NCES (Civil)
Is a Project Quantity Surveyor attached to Cambell Reith Hill International.

A Case Study

Preamble
A contract for the construction of a new leisure centre included a PC sum for the design, fabrication and installation of
a very large sectional climbing wall, and the architect subsequently invited specialist tenders for the work. The tender
prices were closely grouped, and the architect subsequently issued an instruction to the contractor to place an order for
the work with the lowest tenderer. A nominated sub contract was subsequently signed between the main contractor
and the specialist, and a collateral warranty was put into place between the specialist and the employer under which
the specialist undertook:

to use all due skill and care in the design of the wall
to carry out the works in such a way that the main contractor would not become entitled to an extension of
time.

Installation of the wall is shown on the contractors program as lying on the critical path and the main contractor is
entitled to an extension of time for any delays by the nominated sub contractors.

The specialist company fails to commence installation on the agreed date despite a number of telephone calls from
the contractor and despite the fact that the architect has reason to believe that at least some of the wall sections have
already been fabricated. The specialist subsequently contacts the architect to say that they have discovered a serious
error in their price. They state that they are not prepared to fulfill the contract unless the contract price is increased by
some 75%.

The case study is to analyze the legal position from the point of view of all of the parties involved, citing relevant case
law as appropriate and advise the architect how he should proceed.

Introduction administrator to enter in to an agreement with the


nominated sub contractor after selecting the sub
In nominating a sub contractor for the project, the contractor. By entering to this sub contract agreement,
contract administrator has followed the formal steps in the parties; the main Contractor and the nominated sub
accordance with the main contract which has been signed Contractor have agreed to the terms and conditions fully,
between the employer and the main contractor. as related in the contract. Conditions of the main contract
Main contractor has been instructed by the contract will be included in the sub contract.

15
February 2010
SLQS JOURNAL
Under JCT 98 form, this nomination has been considered Dispute
as a nominated sub contract because in various ways it
fulfills the requirements of nominated sub contract, such The specialist nominated sub contractor was not able to
as bill of quantities showing the relevant scope as PC meet the contractual obligations due to the following:
sum , contract administrator issuing an instruction on
the expenditure of such PC sum, etc. 1. Failing to commence the works on an agreed date
2. The contractors notification of his inability to
After the completion of forming of sub contract agreement, perform the contract due to erroneous contract
the employer has entered into a collateral warranty with price.
the nominated sub contractor, in which the main terms
to read as, the nominated sub contractor should use all Failing to commence on an agreed date, nominated
due skill and care in the design of the scope specified sub contractor has created a back ground of a claim
and carry out the works in such a way that the main for extension of time from the main contractor, as the
contractor would not become entitled to an extension of particular works are on the critical path of the main
time due to any delay of nominated sub contractor. contractors program.
Accordingly, as per clause 35 of JCT 98 form this
nominated sub contract has been formed and the terms
Contractual and Legal Background
and conditions are accepted in the following order:
According to JCT 98 form of contract, the main
1. Sub contractor has tendered on form NSC/T
contractor has no liability for any delays or any other
2. Colatteral warranty has been formed as NSC/W and
damages by the nominated sub contractor. This allows
is incorporated to the sub contract agreement
the main contractor to claim an extension of time for
3. Contract administrator has formally nominated the
the delays occurred by the nominated sub contractor.
sub contractor on NSC / N
On the other hand, the main contractor is not liable
4. Completing the above (1) , (2) & (3), the main
to pay liquidated damages to the employer during the
contractor and the nominated sub contractor are
relevant period which was delayed by the nominated sub
bound by the terms of sub contract NSC / C
contractor. Similarly any damages due to the breach of
contract terms by the nominated sub contractor can not
The Contract administrator, in this case, the architect
be claimed from the main contractor.
is responsible for administration of various financial and
commercial provisions such as payments, variations and
As the nominated sub contractor has entered into a
completion of the relevant sub contract.
sub contract agreement with the main contractor, the
nominated sub contractor is liable to complete the works
With all above it is clear that the steps which have been
at the agreed price. The price which has been offered by
taken by the contract administrator and the employer
the nominated sub contractor is valid if that it is not
are according to the form of contract adopted for the
subject to a variation or omission. The main contractor
project.
is entitled to recoup any losses due to the delay of any
nominated sub contractor under the clause 4.40 of NSC/
The estimated cost of the relevant sectional climbing wall
C. The employer is not authorized to involve such claims
has been included in the bills of quantity as a PC sum. The
as this aspect does not fall under the category of relevant
main contractor is entitled for the percentage or any fixed
matters described.
amount set out in the bills of quantity against the value
of actual work done by the nominated sub contractor
Also, if the sub contract works lies on the project critical
for attendance, coordination and supervision. The
path, the nominated sub contractor gets an extension
existing general facilities such as site facilities, scaffolding,
of time for works, and such extension of time will not
temporary roads, power supply etc., will be covered by
be applicable to the main contractors time for the
the said percentage of fixed fee.
completion of the whole project. The main contractor is
unprotected in cases where the cause of delay is due to
his/her own fault.

16
February 2010
SLQS JOURNAL
By demanding an increased price for the works under the The main contractor also has responsibilities in a
sub contract, the nominated sub contractor has expressed nominated sub Contract, mainly on the quality and the
repudiation from the project. The justification which he standards of workmanship and the fitness for purpose of
has provided is not accepted as per the law of contract. As Work. Also the quality and the fitness for the purpose of
he entered into a legally binding contract, it is not possible materials supplied also should be taken into consideration
to withdraw the offer stating that there was a mistake in under the responsibilities of the main contractor.
pricing. The sub contractor is bound to complete the
scope set out in the contract at the agreed contract price As a practice the following facts are to be considered
within the contract period. before commenting on the responsibilities of the main
contractor.
Responsibility of the losses and damages due to repudiation
of a nominated sub contractor, additional costs due to 1. Terms of the main contract and the sub contract
inflation, and disruption to the main contractors program governs the project
etc. shall be borne by the employer, mainly according to 2. Type of the dispute or default
the court decisions made as follows: 3. Who is to suffer
4. Following up actions by the parties involved.
House of Lords in North West Regional Hospital Board v TA
Bickerton & Sons Ltd (1970) held that any increased cost When considering the provisions for the recovery
arisen due to the repudiation of nominated sub contractor of damages due to the delays of the nominated sub
should be borne by the employer as the nomination is a contractors, it is worthy to study the case Westminster
responsibility of employer, at the event of a withdrawal of CC v Jarvis & Sons (1970). The house of Lords held
a nominated sub contractor from the project. that the sub contractors delays (piling contractor who
has completed the job on time, but found defects at the
A nominated sub contractor has liabilities in contract and later stages which remedies have taken time causing an
in tort. This is covered by the nomination procedure of extension of time to the main contractor) shall not be
sub contractor, by adding a direct agreement between the considered for extension of time to main contractor,
employer and the nominated sub contractor. The collateral because the delays are considered only on the completion
warranty plays the role of such agreement between them, of the works. In other words, House of Lords expressed
to enable the employer to cover any damages of delays or their vision about the claim, i.e. if it is on the subject
any other due to breach of contract. With the collateral of completion of the works, the main contractor shall
agreement, a collateral contract forms and it will cover be granted the extension of time, for the delays by the
the employers rights with some established assurances nominated sub contractor.
made by the nominated sub contractor. Such assurances
are legally binding and can be presented at courts. The Also, the above has provided that the main contractor
case of Shanklin Pier Co Ltd v Detel Products Ltd (1951) shall be liable for the quality of the works and the required
which held that the sub contractor was liable for damages standards.
due to the breach of collateral contract is an example.
The current position which is in force is where a nominated
Even if any direct contractual link is not available sub contractor is in delay of practical completion, and if
between the nominated sub contractor and the employer, it is applying to a delay in the main contract, the main
a potential claim will be possible to exist in the tort of the contractor is entitled for an extension of time. Then the
negligence. Such claim shall be based on physical damages. employer can recover the liquidated damages that have
However, in the event of an employer appointing the been caused due to the delay, directly from the nominated
nominated sub contractor, it will provide an additional sub contractor, under the NSC / W clause of collateral
value of a relationship of proximity that the nominated warranty.
sub contractor has a duty of care in tort not to create pure
economic losses through negligence performance of the
sub contract. Junior Books Ltd. v Veitchi Co. Ltd (1983).

17
February 2010
SLQS JOURNAL
Main Contractors responsibility towards 1. Advise the employer regarding the procedures of
mitigation of delays and subsequent losses claims against the nominated sub contractor for his
repudiation and the subsequent delays, under the
Main contractor shall take the necessary actions for terms and conditions of the collateral warranty. The
mitigation of delays in the contract. In this particular employer may send notice to the nominated sub
case, the main contractor has placed telephone calls contractor regarding the breach of agreement of the
to nominated sub contractor to remind him about his package construction by demanding an increased
delays of the commencement of works. It is necessary to contract price under the collateral warranty. Also,
check what contractual terms are available to measure the the failure of the nominated sub contractor to
validity of such action in order to mitigate the additional avoid extension of time claims from the main
cost from any delays. As telephone calls are not accepted contractor as agreed under the collateral warranty
as recorded evidence in contracts, such action towards shall be highlighted in the notice. It is to be advised,
mitigation will be challenged against a possible claim from under the sub clause 3.3 of NSC/W, the employer
the main contractor. If the methods of notices are limited is entitled to recover the losses including liquidated
to letters, fax or other in writing systems in the contract, damages that happened due to the delay of the
the main contractor will be liable for the damages for not nominated sub contractor.
taking reasonable steps for mitigation of losses. These
measures of mitigation action by the main contractor are 2. Send a notice to the main contractor to submit
to be valued by the contract administrator. evidence of proof of the actions he has taken to
mitigate the delays by the nominated sub contractor
Following losses and damages to the employer could under the conditions of the sub contract and as
occur due to the above dispute: well as the main contract with the employer. Such
proof is analyzed by the contract administrator
1. Re-nomination and re-tendering cost , in the event to determine the level of effort taken by the main
of termination of sub contract contractor towards the mitigation of losses and
2. Cost of extension of time , if , to be granted to the the same determination shall be submitted to the
main contractor due to the delay by the nominated employer in the view of possibilities to avoid claims
sub contractor of extension of time from the main contractor.
3. Liquidated damages due to the overall delay of the
project due to the delays by the nominated sub 3. Take necessary steps towards re-nomination of
contractor. a new sub contractor for the package, according
to the conditions set out in the contract, within
In the event of the main contractor being liable for the the specified period if the current nominated sub
delays (under lack of necessary actions for mitigation), contractor does not agree with the employer and the
the following additional costs will be generated , which main contractor to continue.
are to be recovered from the nominated sub contractor.
4. The contract administrator has to organize
1. Extra costs for the required acceleration to the negotiations between the nominated sub contractor,
progress of the work to cover the delays in order to the main contractor, and the employer and instruct
avoid possible liquidated damages the nominated sub contractor to resume the works
2. Any other costs related to the breach of sub as per the collateral warranty agreement and the sub
contract. contract agreement to establish the original contract
conditions, (price and the time for completion).
Conclusion

The Contract administrator, in this case the architect shall


proceed as follows towards the mitigation of any losses
to the employer due to delays by the nominated sub
contractor;

18
February 2010
SLQS JOURNAL
Is Rent Leading Construction?

Wsantha Edirisinghe BSc (Hons)


Currently working as Senior Quantity Surveyor
ASSOCIATE MEMBER of Association of Practicing
Quantity Surveyors & Estimators Sri Lanka

Considering the current circumstance in the economy, as Above, redevelopment is the total replacement of existing
toggle of construction work force; we are continuously buildings or any other structure. This gives a broad
thinking, is there is an end of the construction industry? possible advantage in modifying land use, site coverage and
density, introducing new building techniques, standards
As a result of the higher demand for buildings, the rent of construction, and specification design layout etc. As
will increase. The reason is that the construction of a such, the redevelopment is forecast to be profitable.
building is a time consuming process and hence arrival
of new building to the market is hang fire However, the With the elapse of time, buildings tend to become
higher the rent is the more interest the developers have to increasingly unsuited for the demands placed upon them
construct the new building as it gives the impression of a by the market. This influences achievable rents. When the
better investment. With time more buildings will be added building becomes older, more expensive repairs become
to the market and eventually the rent will be reduced in necessary. As well as periodic updating such as, compiling
the market due to increase of supply. A lower rent tends with new fire regulations, installation of new heating or
to increase the demand and a higher demand again tends ventilation systems and modifying to suit with modern
to increase the rent. Thus the property development is a trends etc, become more difficult and costly.
cyclical process which changes according to the market
circumstances. Thus, when the Present Capital Value1 of the expected
flow of future net returns from the existing use of the land
Is rent leading construction? In some instances, the resources becomes less than the present capital value of
market rent is leading the re-development process of the the Cleared Site2 the redevelopment takes place.
buildings but in certain others that may be no the case. Let
us see how the market rent is leading the redevelopment (The present capital value depends on the Net Returns3
process in the private and public sector. expected in future years. Then the net return should
be estimated and discounted to the present and then
The changes in the conditions of demand and supply aggregated in order to arrive at the present capital value.
will create an impact on making some structural To arrive at the present capital value of the cleared site at
changes in the nature of buildings to compile with the any one time, the cost of demolish and clearing the site
modern activities. That will take different forms such as, and the cost of rebuilding for new use has to be deducted
modification of existing building through conversation or from the present capital value of the best alternative
refurbishment, redevelopment and new development on use.)
undeveloped land etc. Those are often seen as alternative
solutions to adapting buildings and sites to new demands The present capital value of the current use falling to
and economics use. zero, is called Physical Obsolescence. Also, when the
capitalised value of the present use falls to the level of

References:
(1) The total present value (PV) of a time series of cash flows.
(2) Cost of clearing the site and rebuilding to the new highest and best use.
(3) Ggross annual return less operating costs of

19
February 2010
SLQS JOURNAL
Diagram 1: The timing of Redevelopment

AY = Economics Obsolescent of the building (redevelopment should take place)


AZ = Physical Obsolescent of the building

the capitalised value of the redevelopment (cleared site) The capital value of property in current use.
is called Economics Obsolescence. These details are This depends on the net returns expected to be earned in
illustrated on above diagram 1. the future years. This return is estimated and discounted
building to the present and is aggregated in order to get the present
capital value. Thus, the period of years over which gross
In the private sector returns can be earned in its current use is very important.
The private development is essentially profit motivated. As well as, the appropriate rate of discount (basically
The unity of the environment and quality, externalities the interest rate) will give significant effect to the capital
and the interplay of social, political and economics value of property in current use in order to time or begin
factors thus may not be considered. Therefore, the timing redevelopment.
of redevelopment in the private sector involves the
Opportunity Costs4 of continued use. Thus, the year The net annual return in a building depends on the gross
Y in the diagram 1 takes the more important place in annual return (such as rent received) and the maintenance
relate to the timing of redevelopment. That is when the or repair (operating) cost. However, with time, the gross
distance increases between year A and Y the timing annual return will decrease, as a result of supernormal
for redevelopment tends to delay. However, being profit profit accrued by initial development which will tend
maximise motivated, the redevelopment can be started to encourage similar developments. Parallel to the time
after year X. Because in the year X, the value of cleared elapsed, the Opportunity Costs rise as a result. For
site is given a positive consideration. example, the older the buildings are the less adaptable they
are to new technical requirements (such as lifts, modern
In this condition, it is notable that the following influences air conditions systems, fire and safety, and modern office
determining the timing of redevelopment, especially in machinery etc,), and the structural, physical deterioration
the private sector. of the building.

References:
(4) the value of the next best alternative forgone as the result of making a decision.

20
February 2010
SLQS JOURNAL
Thus, considering the present capital value of current use, As per diagram- 2 above the redevelopment may occur
the timing for redevelopment would tend to delay. The in year X. However, the rise in the interest rate affects
income of the building being greater than the operating to lower the capital value of existing building (BB)
cost, indicates that the net income of the buildings is and therefore, the future net earnings are capitalised at
positive. Also, the higher interest rate which influences a higher rate. Hence, a higher interest rate is applied
to discount rate to calculate the present capital value of to fewer net annual returns from the existing building.
existing use. The redevelopment of the best alternative use will incur
higher development costs, because the higher cost of
The capital value of cleared site borrowing (as higher interest rate) will increase the capital
The value of a cleared site is determined by deducting the value of cleared site (SS) according to the timing of
cost of clearing the site, any land preparation costs and redevelopment delay from X to X years.
the cost of rebuilding a new building from the present
value of the most profitable alternative use. To calculate The cost of rebuilding of best alternative use.
the present capital value of a cleared site, the gross annual The higher cost of construction materials, labour and
return in the best alternative use and in order to operating plant, higher tax charges for the new construction, the
and maintenance cost for the same are considered. work site in congested area (such as city centre) etc, will
However, a higher value of demolishing and clearance cause to increased the construction cost. Also, that will
cost will cause to lower the value of a cleared site. The affect to decrease the capital value of a cleared site. In this
lower value of a cleared site will tend to delay the timing condition the timing of redevelopment will tend to delay.
of redevelopment. When the net annual return in the This can be illustrated in the following diagram 3
best alternative use is lower, the timing of redevelopment
tends to delay. Diagram 3: The effect of higher construction
cost
Due to the calculation of the present capital value the
interest rate takes a very important place, and it affects the
cost of borrowing. The following diagram 2 will illustrate
how the interest rate affects to delay of redevelopment.

Diagram 2: Redevelopment delayed by rise in


rate of interests (in order to cost of borrowing)

If there is no any competition, they can exercise


their monopoly power.

In this condition, the private sector can increase their net


annual income by getting a higher rent in order to delay
the timing of redevelopment

Therefore, as a result of profit maximise motivation in


the private sector, the above conditions the timing of
redevelopment will tend to delay.
21
February 2010
SLQS JOURNAL
The public sector it may fall later. Hence in this condition the timing of
redevelopment tends to delay.
The public sector development is non profit making
or is only semi commercial. They take a longer, wider Monument, prestige or architectural building.
view than the private developers. In the most economic Even the gross annual return is negligible in the this
developments, the given constraints will be those kind of building or structure, as the government giving
showing the greatest returns in aesthetics or function to permission to hold these kind of buildings considering
the community for the minimum capital invested. Also, the other external benefits, such as tourism shopping etc,
only public developers have received special privileges, and to redevelopment may tend to delay.
including extensive powers of compulsory purchase
(under legislation, such as the Community Land Act 1975 An example would be the Indian government not allowing
which abolished in 1980 in UK). clearing and redeveloping the building of Taj Mahal as
it is one of the most important places of tourism. Another
However, the development in public sector depends on would be the worlds tallest building constructed in Dubai
the historical, social or architectural or prestige views. for its prestige and improve Dubai business activities.
Thus, the public sector does not start the redevelopment However, in future even the gross annual return from this
as soon as it reaches the economics obsolescence condition building becomes zero, considering the other benefits the
in the building as private sector. redevelopment may tend to delay.

In the Economic Obsolescence situation, the value Social Benefits.
of a cleared site crosses over the current use of value (in When calculating the present capital value of the
year Y in the diagram - 1). But it can be noticed that existing buildings, the public sector is concerned about
the Physical Obsolescence will occur at in the year the external and social benefits. Hence, although the
Z. Hence, up to year Z the operating costs are not economics obsolescence in the building becomes zero,
exceeding the gross annual return (A in the diagram - 1) the public sector considers the social and welfare benefits
in the current building. If the operation cost exceeds the rather than the economics benefits.
gross annual return, it can happen in a situation such as
the physical fabric of the building being deteriorated or it As an example, if there is a school in the city centre and
becoming technologically out dated. Hence in the public that land can be utilised for any other financially profitable
sector the redevelopment can be delayed by changing construction, the government may consider the social benefits
conditions. and welfare rather than economics benefits.

Thus, in the public sector, the redevelopment may tend to Imperfect knowledge, immobility of factors,
delay in several conditions such as, imperfections of capital market, legal restrictions
and planning and regulations may cause to delay
The historical building. the timing of redevelopment.
The historical buildings are economically viable but
are under menace of redevelopment. For instance, the
Thus if the Economics Obsolescence arises the government
present capital value of historical buildings may be lower
tends to consider the other factors prior to starting
than the value of cleared site of highest best alternative
the redevelopment and in the aforesaid situations, the
use (year Y in diagram-1). However in this year, the
redevelopment may tend to delay in the public sector.
redevelopment would be economically feasible. But if
redevelopment is not contemplated in this situation, the
Therefore the current rent is not the only contributing
building will be abandoned and left to decay after year
factor that convinces the developers to invest in the
Z. Since the gross annual return of the historic building
construction industry.
may continue to rise as a result of scarcity value over time,
it is likely that the operating costs will tend to rise with
structural deterioration. But once after periodic major
expenditure the operating costs may increase and then

22
February 2010
SLQS JOURNAL
Can Time Bar Clause (20.1 FIDIC 1999)
Lead to Lose Contractors Rights?
Mahinda Ranatunga. BSc QS(Hons), MCIArb, CCE, Pg. Dip.(Arb & Const. Law)
Mahinda Ranatunga is a Member of Chartered Institute of Arbitrators, Certified Cost Engineer and a
Quantity Surveyor for the Golden Arrow Interiors, UAE. He has completed his BSc in Quantity Surveying
at the University of Moratuwa in December 2000. Further he has earned a post graduate diploma in arbitra-
tion and construction law. His Masters degree in Construction Law and Arbitration is presently underway
(final year) at Robert Gordon University, Scotland. His experience in the construction industry counts
nearly 10 years in Sri Lanka, Qatar and the United Arab Emirates.

Invariably an entitlement of extension of time (EOT) will Clause 1.3 of FIDIC 1999 has unambiguously stated that
be based on the nature of the delay event and operation notices shall be in writing. Whether site meeting minutes
of EOT mechanism. Absence of claim notification is one constitute a good delay notice will depend upon the precise
of the most common mistakes made by the Contractor wording of the Contract. In the Scottish decision of John
which can lead to lose his right to have the completion date L. Haley Ltd v. Dumfries & Galoway Regional Council
extended. Prior to FIDIC 1999, Standard Construction (1998), the court held that the minutes of meetings will
Contract Forms have not traditionally included time-bar not constitute a good notice unless the parties specially
provision. Clause 20.1 of the FIDIC 1999 standard form amend the contract in this respect. In Steria v. Sibma,
of contracts states: If the Contractor fails to give notice the Judge decided that the notice must emanate from the
of a claim within such period of 28 days, the Time for Contractor, therefore minutes of meeting recorded by a
Completion shall not be extended, the Contractor shall not third party will not suffice. And also he decided that the
be entitled to additional payment, and the Employer shall be requirement of notice, in respect of delay, did not require
discharged from all liability in connection with the claim that the notice refer to clause number and assessment of
which is unambiguously states that once the time period delay, but to achieve its purpose it did not have to give
has expired, all rights will be lost. notice that relevant circumstances had occurred and
The aims of the stringent requirements on notices of secondly that those circumstances had caused delay.
delays are;
Notice as a condition precedent is a condition which
(a) to give the employer the opportunity to take all makes the rights or duties of the parties depend upon the
reasonable steps available to minimize the effect of happening of an event the right or duty does not arise until
the delay; the condition is fulfilled 1
(b) alert the Employer to watch out for the reasonableness
of the Contractors endeavours to prevent or Situation of lack of notice was examined in case of Bremer
minimise delays in completing the works; Handelsellscaft v. Vanden Avenne-Izagem, House of Lord
(c) to alert the Employer to the effects of the delay as (1978), the Judge said; I should have expected the clause to
they occur; state the precise time within which the notice was to be served
(d) to allow the Employer to advise the Lender of likely and to have made plain by express language that unless the
delays so that the latter can re-arrange his affairs notice was served within the time the seller would lose their
accordingly or his own funds re-arranged. But even right under the clause.
though, the Employer was aware of the delay event
and recorded site minutes of meetings, it would not If the clause is treated as a condition precedent and the
constitute a good delay notice. contractor failed to take the steps specified under relevant

References
David Chappel, Derek Marshal, Vencent Powel-Smith & Simon cavender, Building Contract Dictionary, 3rd edition,
Blackwell Science.
23
February 2010
SLQS JOURNAL
clause, then unless the employer waived the requirements the previously agreed date for completion unless the contract
of the clause, the contractor would not be entitled to an states otherwise.
extension of time. Scottish case of City Inn Ltd v. Shepherd
Construction Ltd, Outer House (2001), was held by Lord Australian case, Gaymark Investment Pty Ltd v. Walter
MacFadyen and he stated; Construction Group Ltd (1999) NTSC 143, (1999) 16 BCL
449; considered that the prevention principle presented
The fact that the contractor is laid under an obligation a formidable barrier to Gaymarks claim for liquidated
to comply with clause 13.8.1, rather that merely given an damages based on delays of its own making. The arbitrator
option to do so, does not in my opinion deprive compliance expressly indicated that the employer would have been
with clause 13.8.1 of the character of a condition precedent entitled to liquidated damages but for the fact that in his
to entitlement to an extension of time. None-compliance view the prevention principle defeated the employers right.
with the condition precedent may in many situation results The employer sought leave to appeal that the concept of
in a party to a contract losing a benefit, which he would prevention had no application to this delay for which the
otherwise have gained, or incurring a liability, which he employer was responsible because the contract provides
would otherwise have gained, or incurring a liability, which mechanism for the extension of time. The Judge stated
he would otherwise have avoided. The benefit lost or the that the contract provides extension of time for delay for
liability incurred may not be in any way commensurate with which the employer directly or indirectly is responsible but
any loss inflicted on the other party by the failure to comply the right to such strict compliance is with notice. In absence
with the condition. The law does not, on that account, regard of such strict compliance there is no provision for extension
the loss or liability as a penalty for the failure to comply with of time . The prevention principle has prevailed which
the condition. In my opinion, it would be wrong to regard defeats the notice requirement as a condition precedent.
the liquidated damages to which the defendants remained No dates for an extended completion date could be set
liable because they failed to comply with clause 13.8.1, and and Walter Construction was only obliged to complete
thus lost their entitlement to an extension of time, as being a the works within a reasonable time i.e. time is at large.
penalty for that failure.
Peak Construction (Liverpool) Ltd v. McKinney Foundation
In the Australian case Turner Corporation Ltd (Receiver Ltd (1970) 1 BLR 111, CA; Lord Salmon LJ said in the
and Manager Appointed) v. Austotal Pty Ltd (1998), the Court of Appeal that the contract had contained a power
delay caused by the employer and the contractor failed to to extend time for the cause of delay, the failure to award
serve notice which is a condition precedent. They stated; an appropriate extension of time under the circumstances
if the builder, having a right to claim an extension of time would also have left the employer without an enforceable
fails to do so, it cannot claim that the act of prevention which completion date, which would have defeated the
would have entitled it to an extension of time for practical liquidated damages provisions.
completion resulted in its inability to complete by that time.
A party to a contract cannot rely on preventing conducting of In Maindenhead Electrical Services v. Johnsn Controls
the other party where it failed to exercise contractual rights (1996), pursuant to claim clause, any claim for an
which have negated the effect of that preventing conduct. extension of time had to be made within ten days of the
event has first arisen. It was held that a failure to comply
The prevention principle infers that a party can not take with the notice provisions did not render a claim invalid.
advantage of its own wrong in enforcing a contract. Gillian
Birky and Albert Point have described this principle in By considering the above, the prevention principle applies
their book of Good Practice Guide : Extension of Time, in the situation where the contract does not provide a
as; The prevention principle provides that where one remedy of extension of time and contractual mechanism
party to a contract has, by any act or omission, prevented is not adequate for act of prevention by the employer
the other party from performing a particular obligation causing delay. In order to protect the employers right
under the contract, they cannot insist upon the performance to liquidated damages, extension of time clauses need
of that obligation by the other party. Therefore, where an to provide a remedy for the expected range of act of
employer is responsible for any delay to the project (referred prevention by the employer.
to as an act of prevention) they cannot hold the contract to

24
February 2010
SLQS JOURNAL
Sub-clause 1.3 of FIDIC 1999 has unambiguously Bibliography
stated that notices shall be in writing. This sub-clause
is not amended by any other clause in the contract in Case Laws
respect of notice to intend to claim extension of time. By Gaymark Investment Pty Ltd v Walter Construction
considering court decision and phrase of this sub-clause, Group Ltd (1999) NTSC 143, (1999) 16 BCL 449
a minute of meeting would not constitute a delay notice. Peak Construction (Liverpool) Ltd v McKinney
Foundation Ltd (1970) 1 BLR 111, CA
In the case of Gaymark, the notice requirement was Maidenhead Electrical Services v Johnson Controls
unusual and it required the contractor to overcome (1996)
a threshold of burden of proof . In the case of City Bremer Handelsgesellscaft v Vanden Avenne-Izagem,
Inn, it appears to have been significant that this clause House of Lords (1978)
did not impose an excessive burden on the contractor. Turner Corporation Ltd (Receiver and Manager
There are three types of delay event (1) risk events, (2) Appointed) v Austotal Pty Ltd (1998)
instruction for extra works and (3) employers defaults City Inn Ltd v Shepherd Construction Ltd, Outer House
including breaches of contract. Risk events; in the case (2001)
of Humber Oils Terminal Ltd v. Hersent Offshore Ltd, John L. Haley Ltd v Dumfries & Gallaway, Regional
20BLR 22 (1981), a notice was necessary to allow the Council (1998)
employer to make decisions which could be of crucial Steria v Sibma
importance for the future implementation of the contract. Humber Oils Terminal Ltd v. Hersent Offshore Ltd,
Instruction for extra works; in the case of City Inn, the 20BLR 22 (1981)
notice clause required the contractor not to carry out the Alghussein Establishment v. Eton College, (1998) 1
instruction if he gave notice. The employers breaches; WLR 587
it is suggested that the prevention principle will prevail. SMK Cabinets v. Hili Modern Electrics Pty Ltd (1984)
There has been some discussion regarding whether the VR 391
prevention principle is to be considered a rule of law or
rule of contractual construction. In case of Alghussein Books and Articles
Establishment v. Eton College, (1998) 1 WLR 587, rule Roger Knowles, 150 Contractual Problems and Their
of contractual construction would take very clear words Solution, 2nd edition, Blackwell Publishing
indeed for one party to be entitled to obtain a contractual David Chappel, Derek Marshall, Vincent Powel-Smith
benefit as a result of their own contractual default. In and Simon Cavender, Building Contract Dictionary, 3rd
the case of SMK Cabinets v. Hili Modern Electrics Pty edition, Blackwell Science
Ltd (1984) VR 391, even if prevention is considered a Gillian Birkby & Albert Ponti, Oct 2008, Good Practice:
rule of law, it is one which can be modified by express Extension of Time, RIBA publication
contractual consent. In the case of Koch Hightex GmbH v. John Uff, 9th edition, Construction Law, Sweet &
New Millennium Experience Company Ltd, 1999, CA, the Maxwell
court may refuse to hold the condition precedent clause Michael Firmstone, Building Contract Casebook,
if it would be contrary to commercial sense in a special Blackwell
situation, but held that the clause was not a condition Richard Langham, 1996, Condition and Planning
precedent, even though it read. In my view, condition Obligation, CLT Professional Publication
precedent notice requirements would be commercially Anthony Speaight & Gregory Stone, 8th edition,
sensible, reasonable and fair for risk events and instruction Architects Legal Handbook: Law for Architects,
for extra works, but it would not be a commercially viable Architectural Press
clause for employers breaches. John B Molloy, Notice Provisions A Change in
Attitude?
However, the position under UAE remains to be tested. Daniel Atkinson, April 2007, Delay and Disruption
Until the law is settle in this area, both the employer and Employer Delay and the Right to Liquidated Damages
the contractor need to think very carefully to entering Keith Pickavance and Wendy Maclaughlin, October
enter into contract with clause 20.1 FIDIC 1999. 2006, A Little of Time At Large: Proof of a Reasonable
Time to Complete in the Absence of Completion Date,

25
February 2010
SLQS JOURNAL
Society of Construction Law Internet Resources
Hamish Lal, April 2002, Extension of Time: The http://www.westlaw.com
Conflict Between The Prevention Principle and http://www.info4education.com
Notice Requirement as Condition Precedent, Society of http://www.scl.org.uk
Construction Law http://sixthformlaw.inf/
Nicholas Gould, Making A Claim Under The FIDIC http://www.wikipedia.org
Form Of Contract. What is Clause 20 All About?, Fenwick http://www.contractjournal.com
Elliot Solicitors, United Kingdom, 04 December 2007. http://www.brewerconsulting.co.uk
Brodie McAdam, Apportionment and City Inn: Save it http://www.alway-associates.co.uk
for the Scots, COBRA2008, RICS Construction and http://www.mondaq.com
Building Research Conference, September 2008. http://rics.org/cobra

Caparo Industries Plc -v- Dickman and others [1990]


The plaintiffs sought damages from accountants for negligence. They had acquired shares in
a target company and, relying upon the published and audited accounts which overstated the
companys earnings, they purchased further shares.

Held: The purpose of preparing audited accounts was to assist company members to conduct
business, and not to assist those making investment decisions, whether existing or new investors
in the company. The auditors did not owe a duty of care to the plaintiffs. Liability for economic
loss for negligent mis-statement should be limited to situations where the statement was made
to a known recipient for a specific purpose of which the maker was aware, and upon which the
recipient had relied and acted upon to his detriment. The law has moved towards attaching greater
significance to the more traditional categorisation of distinct and recognisable situations as
guides to the existence, the scope and the limits of the varied duties of care which the law imposes.
The House laid down a threefold test of foreseeability, proximity and fairness and emphasised
the desirability of incremental development of the law. The test was if the court considers it
fair, just and reasonable that the law should impose a duty of a given scope upon the one party
for the benefit of the other. Lord Bridge of Harwich: What emerges is that, in addition to the
foreseeability of damage, necessary ingredients in any situation giving rise to a duty of care
are that there should exist between the party owing the duty and the party to whom it is owed
a relationship characterised by the law as one of proximity or neighbourhood and that the
situation should be one in which the court considers it fair, just and reasonable that the law should
impose a duty of a given scope upon the one party for the benefit of the other.

26
February 2010
SLQS JOURNAL
Valuation of Variation under Lump-Sum
Contracts
R.M Duminda Nishantha Kumara
Duninda is a holder of High National Diploma in Quantity Surveying & Building Economics, ICBT
Campus and also City & Guilds Higher Diploma. He is currently working as a Quantity Surveyor for Al
Jaber (ALEC) L.E.G.T Engineering & Contracting LLC.

Introduction Although the above-mentioned (1) says that the engineer


It is a common perception that variations frequently occur shall omit any such work, these omitted works shall not
and in many cases inappropriately administrated in the be carried out by the employer or by any other contractor.
Industry. This paper attempts to discuss about valuation A variation shall not in any way vitiate or invalidate the
of variations under lump-sum contract according to the contract.
FIDIC conditions of contract fourth edition 1987.
The engineer can only instruct variations. As per the sub-
Variation and Valuation of Variation clause 51.2(Instructions for variations), the contractor
The complexity of construction works means that it is shall not make any such variation without instructions
hardly possible to complete a project without changes to from the engineer. Further, it says that no instruction
the design or the construction process itself. Construction shall be required to increase or decrease the quantity of
scope of work exists in the form of drawings, and any work where such increase or decrease is not the result
specifications earmarked for a specific construction of an instruction given under this clause.
site. Changes to the scope of work are generally called
as variations initiated by the engineer on behalf of the These variations are valued in accordance with clause
employer. 52, unless the issue of an instruction to vary the work is
necessitated by some default of or breach of contract by
In FIDIC conditions of contract, these types of the contractor. If the default is with contractor, such cost
alterations, additions, and omissions are dealt by clause shall be borne by the contractor.
51(Variations). The engineer shall make any variation
according to his opinion, be necessary or appropriate as Provisions for valuing variations are stated in Sub-Clause
per Sub-Clause 51.1. As per this sub-clause engineer shall 52.1. (Valuation of Variations). It is simple to understand
have the authority to instruct the contractor to do any of when explained in four points as follows:
the following as variations;
a) As per this sub-clause, all the varied work shall be
1. Omit any such work valued at the rates and prices set out in the contract if
2. Change the character or quality or kind of any such they are applicable according to engineers opinion.
work In the contract, bill of quantities/ Schedules of rates
3. Execute additional work of any kind necessary for are the documents, which all rates and prices are
the completion of the works fixed. Hence, varied work shall be valued according
4. Increase or decrease the quantity of any work to the rates and prices in the bill of quantities. It
included in the contract is proven in the law suit, Henry Boot Constriction
5. Change the levels, lines, position and dimension of vs Alstom Combined Cycles (1999). It states that
any part of the works the rate in the contract for piles was twice than
6. Change any specified sequence or timing of what it should have been. When a variation was
construction of any part of the works instructed for more piles under similar conditions

27
February 2010
SLQS JOURNAL
to the original work, the contractor argued that the contractors risk. On completion of the works, the lump
contract rate should apply. Employer argued that a sum contract price would be paid in full to the contractor
fair valuation should be made for additional piling. subject to the approved variations. In this kind of an
Court held, that the work is of similar character instance, employer has essentially assigned all the risk
and executed under similar conditions to the work to the contractor, who in turn can be expected to ask
priced in BOQ and therefore the BOQ rates will for a higher markup in order to take care of unforeseen
apply. The fact is that BOQ rates being too high contingencies. If the actual cost of the project is
or too low is irrelevant. From this sub-clause parties underestimated, the underestimated cost will reduce the
to the contract have agreed that they will use value contractors profit by that amount. An overestimate has
variations. an opposite effect, but may reduce the chance of being a
b) If the contract does not contain such applicable low bidder for the project.
rates, the rates and prices in the contract shall be
used as the basis for valuation, the process known It is important to remind that, in both types of contracts,
as Pro-rata basis. Using appropriate mathematics or contractors obligation is to execute the Works shown
logic, new appropriate rates and prices should be in the drawings and specifications but not the BOQ or
adopted from the rates and prices contained within schedule of rates.
the contract so far as may be reasonable.
c) In case both these options fail, suitable rates or prices Variations of lump sum type contracts can be contractually
shall be agreed upon between the engineer and the agreed as follows in the construction stage, considering
contractor. the unique advantages and disadvantages in each type by
d) In case of all these options failing the engineer the engineer.
shall fix rates or prices according to his opinion
as appropriate and shall notify the contractor 1. Schedule of Rates: Quantities not present in this
accordingly, with a copy to the employer as per the type of contract. Contractors obligation is to execute
this clause. the works shown in the drawings and specifications.
Rates set out in the contact shall be applied to any
Variations shall be measured in accordance with the possible addition or omission in a variation at the
method of measurement used in the original contract, later stage according to the engineers opinion.(Refer
which may be SMM7, CESMM3, or POMI etc. Figure - 1)

It is apparent that agreeing or fixing rates or prices


would take some time. To alleviate the negative effect Item A Boundary Wall m 100.00
on contractors cash flow, the engineer shall determine Figure -1
provisional rates or prices to enable on-account payments
to be included in monthly payment applications. 2. Bill of Quantities with provision for adjustments
for tenderer to price as necessary in respect of
Lump Sum (Non Re-measurable) Contracts any missing items, errors in item descriptions,
and differences in quantities (between drawings/
Re-measurement & lump sum (Non Re-measurable) specifications and BOQ): Existing rates shall be
types are the main two types of contract pricing methods. applied to any possible addition or omission in a
In a re-measurement type contract, completed Works variation. Refer Figure 2, illustrates a segment of
would be re-measured for payment purposes. BOQ example bill page for this type.
items, quantities, descriptions are at the employers risk.
Final value of the works could either be more or less than
Item A Boundary Wall 150.00 M 100.00 5,000.00
the contract price.
Item Insert here any +5,000.00
A-1 adjustment
In a lump sum (Non Re-measurable) contract, the required due to
works shall not be re-measured for payment purposes. errors
Bill of quantity items, quantities and descriptions are at Figure -02

28
February 2010
SLQS JOURNAL
3. Figure-3 illustrates bill of quantities without even though rates are inappropriate. However, if there
provision for tenderer to price an adjustment as is no provision in the BOQ to price adjustments to the
above. The contractor does not have a place to contractor, at such instances parties can agree for new
include his/her price adjustments. Thus, contractor rates for value variations.
has to adjust rates against the given quantity until
the amount reaches the required amount. Therefore, This demonstrates complexity of valuation of variation
the contractor has provision to ask for new rates for under lump sum contract. Thus, the contactor should
additions and omissions in the contract. be more vigilant and knowledgeable to value a variation
including what he believes as entitled. The Engineer
Item A Boundary Wall 150.00 m 66.67 10,000.00 should be knowledgeable enough to assess and value a
variation according to conditions of contract.
Figure - 3
Reference
Conclusion 1. Conditions of Contract for works of Civil Engineering
Considering an early start, with less pre contract works to Construction Part 1 General Conditions 1987,
employer and less risks to the employer, employers may FIDIC, Switzerland.
tend to select lump sum type contracts for their projects 2. Procurement Guidelines 2007, Asian Development
from time to time. Bank, Manila.

When valuing a variation under lump sum contract, any


addition or omission should be valued using set out rates,

Leicester Board of Guardians v Trollope (1911)


The clerk of works altered the design of a floor and as a result dry rot broke out in the floors some
four years after completion. It was alleged that the defect arose owing to the negligence of the
architect in not seeing that the concrete was properly laid in accordance with the contract. The
architect denied that it was his duty to supervise the laying of the concrete and that this was the
duty of the clerk of works who had been appointed by the Guardians.

It was held that while it was the duty of the clerk of works to supervise the details of the work, the
laying of a floor such as this could not be regarded as a detail and that, therefore, the architect
was liable in negligence.

29
February 2010
SLQS JOURNAL
The Relationship between Management and
Personal Management Competencies
Punyamalie De Silva
Quantity Surveyor currently working with Halcrow International partnership Dubai, UAE.

People are the heart of any organization and people need nineteenth century and in the early twentieth century
to interact between each other with a good understanding. factory owners had to face problems in organizations and
(Naoum, Shamil, 2001) If the heart is not functioning in the efficiency of operating machine. Because it was very
very well, the organization will malfunction. This idea is difficult to schedule complex manufacturing operations
confirmed by the following quotation. and deal with the increasing labour dissatisfaction and the
resulting strikes in the factory system. To response to this
Managers know that people make the critical difference condition, the evolution of modern management called
between success and failure. The effectiveness with which classical perspective began. (Samson, Daft, 2003).
organizations manage, develop ,motivate, involve and
engage the willing(please check this quotation again.) to Classical perspective can be subdivided into scientific
the contribution of the people who work in them is a key management, bureaucratic organization and
determinant of how well those organizations perform administrative principles. Taylor, Frank & Lilian Gilberth
(Patterson et al.1997). and Henry Gantt are the main contributors to scientific
management. Max Weber identified the key features of
Every business or company cannot run without human Bureaucratic organization and also Henry Fayol, Mary
resources because the latest technologies also rely on Parker Follet worked on administrative principles.
it. This subject is dynamic and it always develops by
research and discoveries. Management science is changing After the Second World War, management dressed with
according to time and also according to the environment. applied mathematics, statistics, and other quantitative
Therefore, understanding of people and information techniques became a modern science. Then it was called
management theories are important to construction field Management Science Perspective.
due to the majority of usage of human resources and
rapid construction. The idea of rational man in scientific management
changed to idea of the social man in the Humanistic
This essay is divided into to three parts as: perspective. It can also be sub divided into human relation
why understanding of people and organizational movement, Human resources perspective and behavioral
management is important to the construction sciences approach.
industry ,
how it helps to meet key challenges in the twenty Famous Hawthorne studies lead to human relation
first century and movement and theory X, Y, Z and hierarchy of needs,
reflection my own experience. etc. developed in the human resources perspective.

Principles of management are concepts of both sciences System Theory and Contingency Theory are extensions of
and art. (Marino,2008). Five thousand years ago people the Humanistic perspective. Total Quality Management
started major managerial contributions to the modern too was added to the management journey in the modern
management theory. But they did not use the term world.
Management till the industrial revolution. During the

30
February 2010
SLQS JOURNAL
The latest focus on management is people and organization only commercial directors/managers are in the strategic
management. It developed since each work tends to be level. But still commercial director/manager needs to
different and the organizations need different strategies coordinate with the operational level. The prime focus
to achieve each objective. in strategy is effectiveness in the long term and the prime
focus in the operational level is the efficiency in the short
C. Handy suggested the relationship between management term. Therefore the terms effectiveness and efficiency
and organization theory by identifying the key variables describe the difference of those two levels. According
which manager needs to struggle; i.e. to Mintzbergs criticisms mechanistic view of planning
does not tell everything but it identifies the most
People important issues involved in the planning process. In our
Work and structure profession, the project is planned by using Gantt chart
System and procedures or modern software like MS Project or Primavera but
all are mechanistic when it comes to the reality because
And these variables cannot be dealt alone but within the the planning depends on other factors like recruitments,
limits of environment which Handy sees three crucial environmental, etc.
components.
Now we have a plan and we need to organize the people
The goals of the organization according to it. Therefore organising is an important
The technology available function for managers. Construction projects are varied
The culture of the organization as the nations and societies of the world. Especially in the
(its values, benefits etc.) middle east most of the people are from different nations.
The cultures are affected by the events of the past and by
To manage successfully there should be a balance the climate of the present, by the technology of the type
between the above mentioned six factors within the of work, by their aims and the kind of people that work in
particular period to reach the organization goals. Then them (Handy, 1993, p.180). Construction industry is a
contingency approach to the management is essential. very competitive market. So that people who are working
(Cole,2004,p9) in that environment should also be competitive in
knowledge and be effective in the implementation of people
Lets look at the important theories in people and and organizational management. In this part of the world
organization management which will help to improve the span of control in structures is beyond the maximum
basic functions of the managers in quantity surveying range of normal circumstances due to the squeezing of
profession. The quantity surveyor has two different employees. But according to theory the definite limit
stages in construction industry, i.e. Pre contract and Post to the span of responsibility is that the average manager
contract work. To get the job and to run the job there are can competently control. According to Mintzberg
some procedures to follows. Those procedures are almost model normally one falls to professional bureaucracy.
the same as an ordinary management function. The main Construction organizations are decentralized. When
functions are planning, organising, motivation, leadership, it comes to organization culture, Task culture (Handy,
management style, co-ordination, communication and 1993) is mostly the adapted one here. Organizations
controlling. gradually change their dominant cultures. The first signs
of organizational maturity are when time and success lead
Time is the main resource of management. Therefore to growth and to the specialization and formalization of
time can be viewed as Management of time and time activities. An individual success in one culture may not
as a competitive weapon. Hence planning becomes the always be a success in another (Handy,1993,p.204).This
first function of management to discuss. Planning can be kind of matters always appear in most of the organization
either the project, the finances or both. In QS practice, charts due to the lack of understanding of management
planning can be divided into pre and post contract stages. principles. When two cultures work together there must
In pre contract stage it appears as Strategic planning and be an integration e.g. Mercedes M-Class sport utility
in post contract stage (i.e. construction) as operational vehicle case otherwise AOL and Time Warner in 2000.
planning. Most managers are in the operational level and It is the largest annual loss in US corporate history. Here

31
February 2010
SLQS JOURNAL
most of the employees are expatriates and therefore to communication is important in the construction industry
keep them together, the government implemented tough between QS and project manager to avoid significant cost
policy in their contracts. effective incidents like claims, variations, etc.

Motivation is an essential part in the organization. If Appropriate controlling requires ensuring the system to
people are not motivated then the output will not be a achieve its objectives and to implement new objectives.
good one. Maslow identified the hierarchy of needs to Likewise the manager, who is a QS professional, needs
motivate and Herzbergs split the needs as hygiene factors to control his/her teams to produce good quality and
and motivating factors. According to Herzberg, hygiene customer satisfaction in reasonable time and value. So far
factors do not positively promote good health but only act we understand the people and organization management
to prevent ill health (Cole, 2006). The lack of motivation theory and practice in general. We may want to know
leads to unprofessionalism and irresponsibility of the how that understanding helps to overcome the twenty
work which affects the companys future. first century key challenges because we live in the early
stage of that century.
Leadership is a dynamic process which will lead to
achieve the goal/target. It can be divided into democratic In this century the construction field is facing five levels
and authoritarian processes. Nowadays most leaders are of uncertainties. First one is Industrial uncertainty. This
democratic. Trait theories are now out of way because occurs due to scarcity of resources, finance and disrupts
Handy (1993) has proved that it is an impossible task the availability of stability of the flow and price resources.
to identify strong characters. In the Middle East multi Six months ago in Dubai there was a scarcity of cement
national cultures are in one organization and therefore and steel. Due to that the construction costs increased
the leader needs to use System theory and apply the and most of the construction firms claimed extra money
contingency approach. Within each organization the from the client. But nowadays construction material as
activities can be divided roughly into four sets: Steady well as oil price is decreasing in the global market. At the
state, Innovation, Breakdown & Policy. Each of these has same time most of the reputed companies are terminating
its appropriate culture, structure and systems (Handy, their staff to response to global economic crisis. If I write
1993, p.209). So first leadership needs to understand this essay before this month my essay should address the
what it needs apply. scarcity of quantity surveyors and due to that their high
salaries. Today it is in reverse because of the recession.
Management style is the influences of all functions into There is scarcity of jobs in the market. It is the time to
one unit. According to Likerts analysis, participative implement new theories to modern management.
group style is used in most of the times in our profession.
Now in staff appraisal forms are setting targets for the Second one is the market uncertainty. A good example
employee to exercise discretion within his/her job. That is the construction boom in the Middle East. Nowadays
is called in management theory as management by the developers are not funding the projects that they have
objectives. already planned due to the uncertainty of the market.
Before the recession they invested money and they created
Flloet believed that managers would achieve goals the boom. Because of this condition the construction
partly through co-ordination and directing rather than industry is not stable.
controlling.
Third is project uncertainty. Projects can be effected by
Communication among the group is the most powerful the climatic, political and the site conditions. The people
tool in management. In Q.S. profession there are lateral, working in one project have different experience from
upward and downward communications. And also it is the people in another project, and then they will solve
open or free for all communication patterns. Because QS problems in different ways.
needs to look into technical information as well as contract
administration. Mintzbergs five categories of information Fourth one is workplace uncertainty. The construction
are used in our profession. QS needs to communicate industry is more complex and it contains macro and
with both internal and external personnel. Proper micro planning and also works in sequence. Due to the

32
February 2010
SLQS JOURNAL
complexity and differences in cultures it is very difficult contingencies that a manager can understand include
to control the work force, therefore it should lead to industry, technology, the environment and international
uncertainty. To work out those things we need to have all cultures. Management practice in QS is no longer stable
direction communication. People are moving and there because the construction industry is rapidly changing.
are thousands of memos, ad-hoc to track in document The total quality management(TQM) is most suitable for
controlling; therefore there should be a proper way to QS because the QS needs to focus on the same significant
manage documents. Thats why most of the reputed elements which TQM is focusing. Those are employee
companies are adopting Management Information involvement, focus on the customer, benchmarking and
System. It is a subfield of the Management Science continuous improvement (daft et al. 2003).
Perspective. Joan Woodward and his team concluded
establishing technology as a key role to be a major variable Employers should provide decent, safe and improved
affecting the organization structure (Cole, 2006, p.85). working environment and replace competition by clear
measurement of performance and sustained improvements
Last one is organizational uncertainty. People are the in quality and efficiency. Then employee will trust the
greatest asset in the construction companies (Carrillo et. organization and will try to protect it as on their own.
Al., 2000).Therefore, the uncertainty depends on people.
By using theories of Humanistic perspective, skilled I live in the early twenty first century and many more
people can be retained for a long time in one organization. things would die and many more things would be born
In the Middle East lots of professionals change their jobs as a result of usage of modern technology and modern
frequently due various reasons like salaries, working thinking .Handy forecasts in his writings the idea of
hours, etc. The majority of them are expatriate and their federalism, spliced careers, new pattern of planning as
retention depends on the social reasons, political reasons new challenges in future. And also he has given clues like
and the exchange rate. Also nobody has an initial plan to communication revolution, fees in replace of wages, tools
stay a long duration here because they work on contract in replace of machineries and the economic quality.
by contract basis. McGregors theory of X and Y can apply
to this situation but still it needs to be modified according Having discussed the understanding and application
to the uncertainty of the job. of theory one more thing to tell at last is that in this
changing world everything will change every second but
The above described five situations can be identified as we can feel it after some years in retrospect only. So as
Turbulent Environment in modern Management. To professionals we must implement new ideas and reflect
response to this turbulent environment, Groak (1992) on our practice.
identifies the following solutions to be used in the
organization environment. References
Belbin, R. Merdith, (1993), Teams Roles at Work
Restricting conditions like type of job, type of
contract and client requirements Belbin, R. Merdith, (1981), Management Teams:
Ignore potential problems that are uncertain like Why They Succeed or Fail
adverse climatic conditions
Restricting solutions Carrillo,P.M.,Anumba,C.J. and kamara,J.
Acquire a multi-disciplinary range of sources M.(2000),Knowledge management for
construction: key IT and contextual issues, in
In general every business group has to overcome the Gudnason , G(Ed.),proceedings of the Inter.Conf.
following critical challenges in the environment. on Construction IT, Icelandic Building Research
Those are globalization, profitability through growth, Institute, Reykjavik, Iceland, 28-30 June,pp.155-
technology and sudden changes. If I give an example 65
in Quantity Surveying, the QS in Dubai is handling
projects which are in Oman or Qatar. This market is a Cahill, D & Higgins, M (2002), People and
global market and the policies in every country affects Organizational Management in the Built
the economy. In this environment the important Environment

33
February 2010
SLQS JOURNAL

Chimay J. Anumba, Catherine Baugh, Malik M.A. Handy, C (1993), Understanding of organizations
Khalfan, Organizational structures to support
concurrent engineering in construction, Vol. 102, http://ivythesis.typepad.com/term_paper_
No. 5, 2002,pp 260-270 topics/2008/05/why-is-an-under.html

Cole G A, (2004), Management Theory and Naoum, Shamil,(2001), People and organisatonal
Practice management in construction

Colin Gray, Will Hughes (2001), Building Design Report by the comptroller and auditor general, HC
Management 87 Session 2000-2001;11 January 2001
Daft, L. Richard, Samson, Danny, (2003),
Management Construction task force in UK, (16, July 1998),
Rethinking of construction

White, Frost and others -v- Chief Constable of South Yorkshire and
others [1999]
The House considered claims by police officers who had suffered psychiatric injury after tending
the victims of the Hillsborough tragedy.

Held: An employer has a duty to protect his employees from physical but not psychiatric harm
unless there was also a physical injury. A rescuer, not himself exposed to physical risk by being
involved in a rescue was a secondary victim, and as such not entitled to claim. Primary victims are
victims who are imperilled or reasonably believe themselves to be imperilled by the defendants
negligence. Lord Steyn: (T)he law on the recovery of compensation for pure psychiatric harm
is a patchwork quilt of distinctions which are difficult to justify In my view the only sensible
general strategy for the courts is to say thus far and no further. The only prudent course is to treat
the pragmatic categories as reflected in [case law] as settled for the time being, but by and large
to leave any expansion or development in this corner of the law to Parliament. In reality there
are no refined analytical tools which will enable the courts to draw lines by way of compromise
solution in a way that is coherent and morally defensible. It must be left to Parliament to
undertake the task of radical law reform.

34
February 2010
SLQS JOURNAL
How to Deal with an Extension of Time /
Cost Claims
P. M. Dimuthu Niroshan Tissera
B.Sc. (QS)Hons
Is a Quantity Surveyor graduated from University of Moratuwa Sri Lanaka. He is currently working as
a Quantity Surveyor for Al Jaber (ALEC) L.E.G.T Engineering & Contracting LLC.

Definition The Engineer shall, after due consultation with the


Employer and the Contractor, determine the amount of
Under Clause 1.1 sub clause (c) (1) FIDIC standard form such extension and shall notify the Contractor accordingly
of contracts explains, Commencement Date and Clause with a copy to the Employer.
1.1 sub clause (c) (2) explains Time for Completion,
which means the time for completion, the execution Claim
of and passing the tests on Completion of the Works Claim can be defined as a legitimate request for additional
or any section or part thereof as stated in the Contract compensation (cost and/or time) on account of a change
(or as extended under Clause 44) calculated from the in the terms of the Contract (Wideman, 1990).
commencement date.
FIDIC fourth edition 1987, explains the procedure for
If project duration extends beyond the original date of claims under Sub Clause no 53.1. It describes that, if
completion, it is called a delay. This can happen due to the contractor intends to claim any additional payment
Employers failure, Contractors failure or for reasons pursuant to any clause of the these conditions or otherwise,
beyond the control of both parties. If it is not the the contractor shall give notice of his intention to the
Contractors failure, he is entitled to request an extension engineer, with a copy to the employer, within 28 days
of time to complete the project. Under FIDIC standard after the event giving rise to the claim has first arisen.
form of contracts 4th edition in 1987, Contractors rights
to reimburse his additional cost due to the delays of Securing a Right
projects caused by Employers failure is secured. There are four key steps in securing the right as follows.

Extension of Time 1. Identify the right


Studying the contract documents for a proper
The Contractor shall be entitled subject to Clause 44.1 understanding of the agreement is essential to deal with
to an extension of the Time for Completion of the Work claims. Acquired knowledge of the study should be
in the event of, investigated to find out the opportunities to claim for a
right.
a) the amount and the nature of extra or additional
works 2. Reserve the right
b) any cause of delay referred to in these conditions FIDIC standard form of contracts Clause 53.1 clearly
c) exceptionally adverse climatic conditions state that, if the Contractor intends to claim any
d) any delay, impediment or prevention by the additional payment, he shall give notice of his intention
Employer to the engineer within 28 days after the event giving rise
e) other special circumstances which may occur, other to the claim has first arisen. This is reserving the right of
than through a default of or breach of Contract by the contractor to compensate his additional cost, incurred
the Contractor or for which he is responsible. beyond his control.

35
February 2010
SLQS JOURNAL
Even Clause 44.2 expresses that the engineer is not bound Site equipment (scaffolding/cranes, etc.)
to make any determination unless the contractor has, Site facilities (cabins/furniture/yard, etc.)
a) Within 28 days after such event has first arisen Site utilities (power/water/phone, etc.)
notified the Engineer with a copy to the Employer,
and These detailed particulars can be categorized to substantiate
b) Within 28 days, or such other reasonable time as may a delay claim and a cost reimbursement claim. In delay
be agreed by the Engineer, after such notification, claims, the contractor has to attach contemporary records
submitted to the Engineer detailed particulars of any relevant to the event, such as;
extension of time which he may consider himself - Delay schedules
entitled. - Mitigating measures taken
- Correspondence/photographs, etc.
3. Claim the right
As general records, he has to attach,
Sub Clause 53.3 expresses that, within 28 days or such - Project progress reports including weekly/monthly
other reasonable time as may be agreed by the Engineer, programme updates
after giving notice under Sub Clause 53.1, the Contractor - Daily site diaries
shall send to the Engineer an account giving detailed - Minutes of meetings
particulars of the amount claimed and the grounds upon
which the claim is based. In cost reimbursement claim, the contractor has to
attach,
Here detailed particulars mean properly sorted Facts:- Contemporary records
contemporary records, which are the continuously Witness statements,
generated details for day to day activities. Other appropriates evidence (news releases/weather
reports etc.)
4. Prove the claim Law:- Contractual/legal provisions
Liability:- Clients liability to provide relief
Under FIDIC Sub Clause 53.2, upon the happening of Quantum:- Duration of EOT/amount of additional
the event referred to in Sub Clause 53.1, the contractor payment, etc.
shall keep such contemporary records as may reasonably
be necessary to support any claim he may subsequently Amount of the Additional Payment
wish to make. Cost of delay has to be priced demonstrating all relevant
contemporary records such as idle time of resources,
To prove the claim, the contractor must compile all abortive work/protective measures, demobilisation/
contemporary records in such a manner as detailed re-mobilisation, correspondence/photographs, etc.
particulars and demonstrate the claim step by step. Furthermore, contractor can be compensated for his
For this the contractor must comply with contemporary financing charges due to reduced revenue, loss of
records specific with the relevant event such as, productivity and subcontractors claims.
a) Idle time of resources
b) Abortive work/protective measures Prolongation cost can be apportioned as prolonged
c) Demobilisation/re-mobilisation site overheads, and head office overhead, financing the
d) Correspondence/photographs, etc. additional cost and financing charges due to late release
e) Resource utilization patterns/output. of retention.

And he has to attach general contemporary records such Here the contractor must show each event separately and
as, price the additional amounts for those events individually
a) Daily site diaries with all relevant contemporary records in proper manner
b) Minutes of meetings to claim the additional payment for the claim.
c) Site overheads during a prolongation such as; The cost which is not specific to work items and any
Site staff (Engineers/QSs/Admin staff etc.) additional costs the Contractor incurred due to extension

36
February 2010
SLQS JOURNAL
of time has to be priced under site overheads. Mainly Sub Clause 53.5 describes how to get payment of claims
these are preliminary items of the project. Head office by the contractor from the employer. The contractor is
overhead costs which are not specific to one site have entitled to include any interim payment certified by the
to be priced separately and several methods have been engineer pursuant to clause 60 as expressed by the Sub-
introduced by various experts to calculate the head office Clause 53.5. Then the engineer after due consultation
overheads component. with the employer and the contractor, may consider
the amount due to the contractor provided that the
Hudson formula is the one of such famous formulas contractor has supplied sufficient particulars to enable the
which illustrated below: engineer to determine the due amount. If such particulars
are insufficient to substantiate the whole claim, the
Head Period
contractor shall be entitled to a payment in respect of
H.O. Profit% Contract Sum such part of the claim as such particulars may substantiate
Office = X X of delay
100 Contract Period
Overheads (weeks) to the satisfaction of the engineer.
(weeks)
If the event has a continuing effect and is not practical
to submit the detailed particulars within a period of 28
This overhead claimable provision has been provided in days referred to in Sub-Clause 44.2(b), as per Sub-Clause
the Sub-Clause 1.1 (g) (i) which states that cost means 44.3, he shall nevertheless be entitled to an extension
all expenditure properly incurred or to be incurred, of time provided that he has submitted to the engineer
whether on or off the Site, including overhead and other interim particulars at intervals of not more that 28 days
charges properly allocable thereto but does not include and final particulars within 28 days at the end of the
any allowance for profit. effects resulting from the event.

Mark Alan Chapman -v- London Borough of Barking and Dagenham


[1998]
The plaintiff was severely injured when a branch was broken from a tree in a high wind, and fell
onto the van he was driving. The land-owner appealed a finding of liability in nuisance.

Held: The local authority were also the highway authority, and it was the defendants duty
regularly to inspect the tree for signs of danger, and to do what was necessary to maintain the tree
in a safe condition. The evidence was that the danger arose from earlier prunings. The appeal was
in effect an appeal on the facts, and therefore failed.

37
February 2010
SLQS JOURNAL
Steps an Arbitrator should take before and
during the Hearing.
Ananda P. Wickramasinghe. MSc(QS), ICIOB, ACIArb.
A Senior Quantity Surveyor with 30 years experience in quantity surveying in buildings, roads & infrastruc-
ture, and oil & gas projects in Sri Lanka, Qatar, Oman and UAE. Currently working with Wilbur Smith
Associates, Dubai, U.A.E.

Introduction; unless such law has already been specified in the


The purpose of this paper is to explain the steps that an arbitration agreement?
arbitrator should take before and during a full oral hearing. To determine the language or languages to be used
This paper is based on United Nations Commission on in the arbitral proceedings
International Trade Law (UNCITRAL), Modal Law on To consider whether on site inspections shall be
International Commercial Arbitration. part of the proceedings
To decide upon the powers of the arbitrator with
1.0 Steps an arbitrator should take before respect to the remedies, including interim relief and
the hearing; conservatory measures
To indicate the number of witnesses likely to be
1.1 Preliminary Meeting and Engagement Agreement produced
To estimate the length of time period the hearing
The preliminary meeting provides an opportunity for the might take
parties to arrive at vital decisions and an understanding To determine the stenographic record or other type
on various matters before meeting at the arbitral tribunal. of recording of the proceedings that should be kept
Parties can agree on including the question of the amount or if any particular services, such as interpreters,
of arbitrators fees and expenses, agreed timetable for translations, or security measures should be
some interlocutory steps such as exchange of pleadings provided
and submissions. To determine the manner in which the arbitrators
fee and the expenses of the arbitration will be
Each party shall introduce their authorized representatives calculated, secured and paid, including any deposits
to act with authority and knowledge in taking decisions to be in advance
on behalf of the relevant parties. To fix the date, time, and the place of the hearing
To make any other determinations as may be
Then the parties shall meet with the arbitrator before the necessary before the hearing
formal hearing for the purposes listed below. The meeting To decide which of the items referred above are
may take place by telephone conference call. to be covered by an engagement agreement and
to complete and sign such agreement either at the
To determine the issues in disputes meeting or prior to the formal hearing
To determine the matters, if any, on which they may
be in agreement At the preliminary meeting the arbitrator shall disclose
To determine what documents, correspondence, any personal interest in the matters in disputes and any
books or records shall be produced, when, by whom, previous relationship with any of the parties to determine
and whether experts are to be called if there is any objection to his/her continuing to act as an
To determine the law which will govern the arbitrator.
procedures and the substance of the arbitration,

38
February 2010
SLQS JOURNAL
1.1.1 Determination of rules of procedure 1.2 Pre-hearing review meeting / conference
(Article 19)
In consultation with the parties and their advisers and
According to the Article 19 of the law, the parties are free the availability of the counsel, arbitrator should fix the
to agree on the procedure to be followed by the arbitral date for the hearing. Four to six weeks before the hearing
tribunal in conducting the proceedings. If the parties fail starts, arbitrator will call a pre- hearing review meeting /
to agree on such procedure, the arbitral tribunal may conference, but it should be after witness statements and
conduct the arbitration in such a manner as considered experts reports being exchanged. Pre-hearing meeting /
appropriate according to the law. conference can save the time and costs at the hearing itself.
It is important that the parties should have comprehensive
1.1.2 Determination of the place of arbitration advance knowledge of the matters to be discussed at the
(Article 20) pre-hearing meeting/conference. The arbitral tribunal
may make an order directing the parties to appear for a
In accordance with Article 20 of the law the parties are pre-hearing meeting/ conference. The order should state
fee to agree on the place of arbitration (If the place of the matters to be discussed at the pre-hearing meeting/
arbitration is not stated in the Contract). Failing to do so, conference and the timing of the pre-hearing meeting/
the place of arbitration shall be determined by the arbitral conference.
tribunal after considering the circumstances of the case
and the convenience of the parties. The purpose of this meeting is;
To enable the arbitrator to satisfy him/herself that all
Notwithstanding the provision of the above paragraph, previous directions have been compiled.
the arbitral tribunal may unless otherwise agreed by the To consider if any further directions or discovery is
parties, meet at any place it considers appropriate for required.
consultation among its members, for hearing witnesses, To ensure that the parties have identified the issues
experts or the parties, or for inspection of goods, and and each party will come to the hearing with his/her
other property of documents. attention and concentration on the issues that really
matter.
1.1.3 Determination of language or languages to be To consider whether any issue can be tried as a
used in the arbitration. (Article 22) preliminary issue and whether any interim award
can be given before the hearing.
If the contract does not state the language or languages to To consider any issue as a preliminary issue.
be used in the arbitration, in accordance with Article 22 To understand the status of any settlement
of the law, the parties are free to agree on the language or discussions.
languages to be used in the arbitral proceedings. Failing Whether the arbitrating parties require any further
such agreement, the arbitral tribunal shall determine the written statements or any further statements are
language or language to be used in the proceedings. required by the arbitral tribunal.
To fix a schedule for submission by each party of a
1.1.4 Determination of submission of Statements summary of the documents or lists of witnesses or
of Claim and Defence Statements (Article 23) other evidence it intends to present.
To fix a schedule for submission of any documents,
In accordance with Article 23 of the law, within the exhibits or other evidence, that the arbitral tribunal
period agreed by the parties or determined by the arbitral may then require.
tribunal, opportunity to each party to submit statements To determine whether voluminous and complicated
of supporting documents or references to the evidence
data should be presented through summaries,
of his/her claim is provided. (In an exceptional case,
tabulations, charts, graphs or extracts in order to
arbitration may proceed without any such documents.)
save the time and costs.
To determine what documents are required to be
Unless otherwise not objected by the other party, any
translated and whether any party wishes to have
party can amend or supplement its claim or defend
interpreters. Any party wishing an interpreter, shall
during the course of the arbitral proceedings.
39
February 2010
SLQS JOURNAL
make all arrangements directly with the interpreter sufficient rooms for themselves and for books and
and shall notify the other parties to bear the cost of documents. In a building arbitration there are many
the services . drawings to be consulted and these drawings are to
To consider the programme of the hearing to ensure set on a separate table. (These questions will have to
that the witnesses attend on time and not attend be decided at the preliminary meeting or at an early
those parts of the hearing with which they are not stage in the proceedings.)
concerned. Fixing the dates and time for hearing
To arrange appropriate bundles of documents, Making arrangements for the transportation of the
including the list of issues to be delivered to the arbitrators, experts and the witnesses
arbitrator during the hearing giving him/her Witnesses Lists of witness who are to be presented
sufficient time enabling him/her to read them for the hearing and a time table for the witnesses and
thoroughly before the hearing begins. the oaths of the witnesses
To shorten the time of hearing by admitting to all Cross examination Prepare the lists of witnesses,
or part of the witness statements or by directing a who are to be cross- examined
further meeting between the experts. If a site visit is required, a date and time should be
To check whether a suitable venue has been arranged fixed.
and whether all the other preparations for the Photocopy machine, telephone and fax facilities
hearing are in place. should be available in the hearing room and in the
To determine the record keeping method. Any retiring rooms / accommodations.
party desiring a stenographic record shall make Record keeping arrangements should be discussed
arrangements directly with a stenographer and shall and agreed upon. A party requiring a stenographic
notify the other parties of these arrangements at least record of the proceedings or the service of a translator/
three days in advance of the hearing. The requesting interpreter the requiring party shall make necessary
party or parties shall pay the costs of the records. arrangements for and shall be responsible for the
To ensure that the hearing will start in an efficient cost. If the arbitrator calls for any such services of
manner on the scheduled date. a stenographer or an interpreter or parties agree to
the need of such services, the costs of thereof may
The above items are to be covered by an engagement be shared as agreed or may be handled as costs of
agreement and to complete and sign by the parties at the arbitration. If the transcript agreed by the parties
meeting or prior to the formal hearing. or determined by the arbitrator is to be the official
record of the proceeding, it must be provided to the
1.3 Preparation before the hearing. arbitrator and made available to the other parties for
inspection, at a date and place determined by the
Following are the important items an arbitrator must arbitrator.
consider when preparing for the hearing; At least five business days prior to the hearing, the
Venue arrangements The usual practice is for the parties shall exchange copies of all exhibits they
venue arrangements to be made by the claimant. If intend to submit at the hearing.
the claimant finds any difficulty in locating a venue, The arbitrator is authorized to resolve any disputes
the arbitrator may be of help in finding the same concerning the exchange of information.
for arbitration. The important point is the layout of The notices should be sent to the parties at least 10
the room in which the hearing is to be held and the day in advance of the hearing date unless otherwise
ancillary accommodation. agreed by the parties.
If a full formal hearing is required, there should
be a separate retiring room for the arbitrators and 2.0 Steps an arbitrator should take during
accommodation for the parties and their advisors the Hearing:
enabling them to hold private conferences.
A common way of setting the tables and chairs is in 2.1 The Hearing
a U shape or alternatively using the courtroom style
layout. Hearing is purely private and only persons entitled
The arbitrator, parties and their witnesses must have to attend are the parties themselves and those whose

40
February 2010
SLQS JOURNAL
attendance is required in order to assist the parties in i) The respondent makes their final submissions.
assisting/presenting their cases. They are advocates or j) The claimant makes their final submissions.
witnesses. If anyone else wishes to attend the hearing, the k) Prior to closing the hearing the arbitral tribunal
agreement of all other parties should be obtained first. shall inquire of all parties whether they have any
further evidence to offer or witnesses to be heard.
If any party fails to attend or be represented at the hearing Upon receiving negative replies or the parties being
of which due notice has been given, the arbitral tribunal satisfied that the records are completed, the arbitral
may continue to proceed in the absence of such party tribunal shall declare that the hearing is closed. If the
(Article 25). briefs are to be filed, the hearing shall be declared
closed as of the final date set by the tribunal for the
Smoking, drinking coffee, tea, soda etc. or eating at the receipt of briefs. If documents are to be filed and the
hearing are not allowed. Do not address the parties on date set for their receipt is later than that set for the
first name basis. Dress as you would in Court. receipt of briefs, the later date shall be the closing
date of the hearing. The time limit within which the
2.2 Procedure an arbitrator should follow at arbitral tribunal is required to make the award shall
the hearing; commence, in the absence of other agreements by
the parties upon the closing of the hearing.
a) The arbitral tribunal opens the proceedings and l) After the closing of the hearing the arbitral tribunal
announces the arrangements for the hearing. will proceed to make its award.
b) Before proceeding with the first hearing the
arbitrator may require witnesses to testify under It is important for arbitral tribunal to keep in mind that,
oath. The administration of the oath depends upon the two parties that are likely to give rise to problems
the religious beliefs of the witnesses. when the enforcement of the award is sought. Therefore
c) The claimant or their representative opens and each party should have a proper opportunity to present
presents their case. their case and that the parties must be treated equally.
d) The claimant calls their first witness and examines
them upon the evidence, which they give. References:
e) The responding party cross-examines the witness. 1) Bernstein R., Derek Wood (1993 2nd edition)
f ) The arbitral tribunal may ask questions if necessary. Handbook of Arbitration Practice.
g) The arbitral tribunal gives each party the opportunity 2) Powel V., Sims J., Dancaster C. (1998 2nd edition)
to ask questions arising out of the witnesss answers Construction Arbitration.
to the arbitrators questions. 3) Redfern A., Hunter M. (1999 3rd edition) Law and
h) The respondent outlines their case if they wish. Practice of International Commercial Arbitration

Sauter Automation Ltd v Goodman (Mechanical Services) Ltd (1840)


A sub-contractors quotation was expressed as subject to our standard terms and conditions
which included a retention of title clause. The main Contractor sent an order stating terms
and conditions in accordance with the main contract. The Sub-contractor, without further
communication, delivered the goods.

Held that this amounted to an acceptance by them of the main Contractors counter offer.

41
February 2010
SLQS JOURNAL
Performance of Critical Attributes in
Alternative Dispute Resolution (ADR):
A Study in Sri Lankan Construction Industry
K.B. Dinesh Gunasena BSc (QS)Hons
Is a Quantity Surveyor graduated from University of Moratuwa Sri Lanaka.

Abstract
Disputes are a common feature of the construction industry. As resolution methods for such disputes the usages
of Alternative Dispute Resolution (ADR) methods such as arbitration, adjudication, mediation and negotiation in
construction industry have gained great momentum during the recent years in Sri Lanka. This research is the result of a
survey that was conducted to understand the performance of critical attributes in current ADR practices in Sri Lankan
construction industry.

The findings of this research provide both practitioners and academics within the construction industry an insight
into the perception of ADR methods currently available in Sri Lanka. Further it provides information, which ensures
a better understanding of the impact of dispute resolution process upon the construction industry and this helps the
participants connected with the construction industry to identify potential problem areas in dispute resolution.

Key words: Alternative Dispute Resolution (ADR), Construction Industry, Negotiation, Mediation, Adjudication,
Arbitration.

Introduction for both parties (De Zylva, 2006). However, an amicable


solution by informal discussion is not practical when the
Disputes are a common feature of the construction complexity of dispute increases. As a result, parties who
industry (Ashworth, 2002). Construction work is a are involved in a dispute have to select the best suitable
complex process that can confound the most intricate dispute resolution method.
management systems requiring the coordinated effort
of a temporarily assembled task force. Inevitably this Litigation is the standard and conventional dispute
complexity creates disputes (Cheung et al, 2000). Not resolution mechanism used all over the world. However,
like the other manufacturing industries the output of the it is a too expensive and a time consuming method. Also,
construction industry - building and civil construction there are several disadvantages in litigation like stress,
works that have been constructed on different sites, create inflexibility and formality of court processes, restricted
their own special difficulties. Therefore, disputes can arise scope of claims and remedies as well (Astor and Chinkin,
not only because of the human nature, but also due to 1992; Ranjithkumar, 2005).
the aforesaid special circumstances (Turner and Turner,
1999). Cheung (1999) states that in present days complex The business community as well as the construction
construction projects, resolving disputes have become an industry faced the aforesaid difficulties and began to find
inevitable part of project management. alternative dispute resolution (ADR) methods. In State
of Kerala vs. Joseph Auchilose (1990) case, the court held
Earlier most disputes were settled on the job site at an that the interminable, time consuming, complex and
informal meeting between the relevant parties. It is to expensive court procedures impelled to jurists to search
the contractors advantage to resolve the disputes directly for an alternative forum less formal, more effective and
with the employer in an amicable nature. Other methods speedy for resolution of disputes avoiding procedural
of dispute resolution tend to have unpleasant side effects claptrap.
42
February 2010
SLQS JOURNAL
Wimalachandra (2007) defined ADR as any form Most of ADR methods are statutory controlled which
or procedure, whether formal or informal, whereby can be identified as a private and confidential method
parties can resolve their disputes instead of litigation with minimal outside intervention. The Parliament of
before courts of law. Justice Wimalachandra further Sri Lanka enacted several statutes to implement and
mentioned numerous advantages of ADR like flexibility, control the ADR practices (Ekanayake, 1992), such as
confidentiality, cost savings, informality, low antagonism the arbitration proceeding controlled by Arbitration Act
between the parties and time saving. No.11 of 1995, Mediation Board Act No. 72 of 1988
for mediation practices, Commercial Mediation Center
ADR methods were not new to the Sri Lankan of Sri Lanka Act No. 44 of 2000 as well as Mediation
community since the days of ancient kings, though it was Boards (special kind of disputes) Act No. 21 of 2003. The
not applied exactly in the present context. The ancient Institute for Construction Training and Development
methods of disputes resolution change their mechanisms (ICTAD) introduced the Adjudication process to the
according to the modern business requirement as well Sri Lankan construction industry as an immediate step
as international usages (Abeyaratne, 2006). Currently
towards construction dispute resolution in their first
there are several ADR methods used and adopted by
revised edition of standard bidding document in year
stakeholders in the construction industry in Sri Lanka.
2006.
Negotiation, Mediation, Adjudication and Arbitration
can be identified as widely used and recognized ADR
methods (De Zylva, 2006). Critical Attributes Affecting ADR

The practicing of ADR methods can be indicated as a ADR has been recognized as one of the key areas that
stair step way (Oreilly and Mawdesley, 1994; Cheung, requires improvement in the construction industry.
1999). According to Chung (1999) this rising steps in the Previous studies have identified several attributes which
chart intimate the escalating levels in hostility and cost critically affect the ADR practices (Cheung, 1999; Cheung
associated with the various forms of dispute resolution. and Suen, 2002). Among those attributes Cheung (1999)
Many authors (Omar, 2007; Uff, 2005) support this stair identifies twelve critical attributes which are affecting
step model, (figure 1), in construction related dispute ADR. This paper seeks to evaluate the performance of
resolution. those critical attributes along with each ADR method.
Those critical attributes can be identified as follows:

The duration of the proceedings


Increase cost and The cost involved
hostility Arbitration Preservation of relationship
Flexibility of the proceeding
Confidentiality of the process
Adjudication/ Enforceability of the decision/ settlement
Administrative Privacy of the proceeding
Decisions Obtaining fairness
Bindingness of the decision/ settlement
Mediation The parties ability to control over the proceeding
The width of remedy
Obtaining creative remedies

Negotiation By evaluating the performance of those attributes within


the Sri Lankan context, this paper try to synthesize the
ADR practices of the Sri Lankan construction industry.
Figure 1: Stair step model for Dispute Resolution
Since this paper has been compiled based upon a research
Process in Construction
Source: Ranjithkumar (2005 cited Cheung, 1999) which aimed to quantify the performance of critical

43
February 2010
SLQS JOURNAL
attributes in ADR, the outcome of the research technique Wi = ( Vij *Fi) / n
should be easy to analyze, quantify, compare and contrast. Where,
Therefore, questionnaire survey was selected as appropriate Wi - Mean Weighted Rating on i th attribute
technique to carryout the research study. In this research, Vij - Rating for i th attribute from the j th
the questionnaire was framed in to three basic sections. respondent (According to Seven scale rating)
The objective of each section can be identified as follows; Fi - Frequency of Responses in i th attribute
n - Total number of respondents
Section 01: Intended to elicit the background
information of the respondent; Severity Index

In this section, it was asked to fill the respondents The severity index computation is used to compare and
names (optional), name and the type of the organization, contrast the agreement level of the positive factors of
their profession and their working experience in the critical attributes affecting each ADR method.
construction industry as well as in dispute resolution.
S.I. i = ( Wi * Lij) / n
Section 02: Intended to evaluate the importance of the Where,
critical attributes affecting the ADR; S.I. i - Severity index value on i th attribute.
Wi - Mean Weighted Rating on i th attribute
In this section the respondent were to rate each critical Lij - Level of Agreement for the positive aspect of i th
factor which was mentioned in the research problem on a attribute from the j th respondent in each ADR
7-point scale (Not importance to very high importance). method (According to Five scale rating)-
n - Total number of responses
Section 03: Intended to scale the agreement level with
the positive aspects of the critical attributes of ADR Sample Distribution
methods;
The questionnaires were distributed equally among
In this section the level of agreement was compared clients, consultants and contracting organizations after
and contrasted with the positive aspects of the above communicating to them the aim and the objectives of
mentioned critical attributes of each ADR method by the study by the researcher. An acceptable number of
using a 5-point scale (Very low degree of agreement to responses (47) were given by the respondents (Shown in
very high degree of agreement). Table 1).

Table 1: Responses in questionnaire survey


The Purposeful selective sampling was the method of
sampling for this research as the information asked
Questionnaire
from the survey requires in depth knowledge and sound Type of
Percentage %
experiences about ADR methods. The questionnaire was Organization Distributed Responded
distributed to the respondents at their work places. The
completed questionnaires were collected by the researcher Consultant 30 17 56.7
later. Client 30 16 53.3
Contractor 30 14 46.7
Methodology Used to Analyze the Survey Results Total 90 47
Following formulas were used to analyze the data obtained Table 2: Composition of respondents
from the questionnaire survey.
Organisation type Number Percentage %
Mean Weighted Rating Consultant 17 36.2
Client 16 34.0
A mean weighted rating for each factor is computed to Contractor 14 29.8
deliver an indication of the importance of the factor, Total 47 100.0

44
February 2010
SLQS JOURNAL
It is evident that each organization type approximately This survey asked the respondents about the perception
represents one third (1/3) of respective types of and overall experiences rather than individual
respondents in the survey (Refer table 2). Therefore, the experiences. It can be assumed that respondents based
survey results are not biased towards one organization their perception on only one or several isolated incidents
type and are representative of the industry as a whole. which result in a strong belief that the ADR process is
always ineffective or, more likely effective. This would
Demographic factors of the respondents seem predictable, if there was only limited experience
of a method leading to a generalization of perception.
Table 3: Composition of respondents according to their Therefore, purposefully selected experienced personnel
profession in the construction industry and in ADR were used as
respondents. The table 4 explores the experiences of the
sample.
Number of
Profession Percentage %
Respondents
Findings and Discussions
Engineer 22 46.8
QS 18 38.3 Importance of Critical Factors in ADR
Architect 4 8.5
In section 2 of the questionnaire, scale ratings were
Lawyer 3 6.4
employed to obtain the importance of the twelve
Total 47 100.0 critical attributes to the ADR process. In this section,
the respondents rated each attribute on a 7 point scale
Table 3 shows the composition of respondents according (no importance to very high importance). The mean
to their profession. According to the tables the majority weighted ratings were calculated and were used as the
(85.1%) of the sample represents QSs (Quantity basis of priority ranking. Table 5 gives the results of the
Surveyors) and Engineers. The other professions importance ranking based on the mean weighted scores.
(Architects and Lawyers) represent 8.5% and 6.4%
respectively. This information highlighted that QSs and Table 5: Importance of critical attributes- The ranking
Engineers are the major professionals who are involved order
in ADR in the construction industry. However, the Mean
reason for the lower participation of the lawyers might Attribute Weighted Rank
be the unavailability of the in-house lawyers in day-today Rating
operations of construction organizations The duration of the proceeding 6.34 1

Table 4: Respondents working experience in the Obtaining fairness 6.32 2


industry Bindingness of the decision/
6.11 3
Settlement
Enforceability of the decision/
6.04 4
Working Percentage Cumulative Settlement
Number
Experience % percentage % Confidentiality of the process 6.00 5

Not Provided 1 2.2 2.1 Privacy of the proceeding 5.96 6


The cost involved 5.51 7
0 5 Years 3 6.5 8.5
Flexibility of the proceeding 5.47 8
6 10 Years 5 10.9 19.1
Preservation of relationship 5.38 9
11 15 Years 7 15.2 34.0
Obtaining creative remedies 5.26 10
16 20 Years 9 19.6 53.2
The parties ability to control the
5.23 11
Over 20 Years 22 47.8 100.0 proceeding

Total 47 100.0 The width of the remedy 5.02 12

45
February 2010
SLQS JOURNAL
By looking at the above ranking order, the following scales. This was done to validate and generalize the result
features can be specifically understood. and to avoid the personal interpretation of the factors.
In ADR, time duration and fairness of the decision By using those figures the severity index value of the
obtain highest ranks. However the cost involved attributes was calculated and it is shown in table 7.
obtains 7th rank. That indicates an interesting
finding. The industry does not expect less cost Table 6: Weighting given to each level of agreement.
solutions. They are willing to spend on quick, fair and Level of Agreement Weighting
binding solutions rather than low cost solutions. Very low degree of agreement 1
Parties do not highly require controlling of the Low degree of agreement 2
proceedings and their expectation in creative remedy
Average degree in agreement 3
is also of low importance.
High degree of agreement 4
The importance of preservation of relationship
obtains 9th rank. The industry does not consider Very high degree of agreement 5
the preservation of relationship as a high important
factor in dispute resolution. Table 7: Severity index Table: Agreement with positive
Binding and enforceability obtained high importance factors of the critical attributes
rankings. When evaluating the outcome of the ADR
methods, the industry considers those attributes as
(Mean Weighted

Positive factor

Adjudication
of the Critical
important.

Negotiation

Arbitration
Mediation
Importance

Attributes
Ratings)

In

In

In

In
Severity Analysis of Critical Attributes

Before deciding to use ADR methods, the practitioners Required time


should weigh the benefit of each alternative to consider 6.34 duration is low
23.01 21.87 20.29 13.95
which method is most appropriate. Section 3 of the Low cost
5.51 22.92 19.40 15.21 11.35
questionnaire was further designed to compare the involvement
weightings of such benefits. Relationship
5.38 between parties 23.78 20.39 17.32 14.15
are preserved
For the comparison of each ADR method it was required 5.47 Apply flexible
24.45 21.11 17.01 13.46
to measure the agreement level of the attributes along with procedure
Confidential
the ADR methods. Therefore, in this section respondents 6 process 24.42 22.14 22.56 22.32
were asked to state their agreement level with a positive Enforceable
factor of each attribute. The weightings are calculated by 6.04 decision/ 13.77 14.50 17.46 27.90
settlement
severity index formula. The following argument was used
Secure the
to formulate the severity index formula. 5.96 privacy of the 22.17 21.87 21.63 21.16
proceedings
Mean
X =
Level of Severity of Fairness
importance 6.32 decision/
23.64 23.38 23.64 23.26
Agreement the attributes settlement can
Weighting obtain
Parties are
Figure 2: Argument behind Severity Index Calculations 6.11 bound by the 14.36 15.34 20.47 28.23
decision
Parties can
From section 2 of the questionnaire a mean scale rating 5.23 control the 22.96 19.19 15.95 15.11
of the importance of each critical attribute was obtained. procedure
(Table 5 indicates the mean importance weightings for High width of
5.02 remedy 18.88 17.82 15.51 13.86
each attribute and their ranks.) Weightings for levels of Can obtain
agreement are given in table 6. For the calculation of 5.26 creative 21.51 18.88 15.10 11.99
remedies
severity index, the mean weighting importance of each
factor was used other than using respondents individual Average 21.32 19.66 18.51 18.06

46
February 2010
SLQS JOURNAL
The computed figures of the severity index have shown Further this research presents evidence supporting the
the severity of the attributes in dispute resolution along view of the stair-step model of ADR methods which was
with the positive aspect of critical attributes. The above discussed in the literature review. This study confirms
results further highlighted its following features. the practitioners acceptance of the stair-step model of
dispute resolution and it is understood that negotiation is
1. Highest severity index value was obtained by the best method and arbitration is the least suitable ADR
Arbitration in the attribute of Binding of the method. However, even though negotiation achieves
decision. (The industry strongly believes the outcome the highest index values in the severity index, the survey
of Arbitration as binding.) results identified the unavailability of enforceability
2. Lowest severity index was obtained by Low cost and binding of the outcome in negotiation as well as in
involvement in Arbitration. (The industry does not mediation. As ADR is not part of the mainstream legal
believe the statement of low cost involvement in system, proposed negotiated settlement arrangement
Arbitration.) can be ignored if no formal agreement is concluded to
3. Other than the sixth and ninth attributes accord the binding effect. Therefore, it cannot apply to
(Enforceability of the decision and Binding of the every dispute in the industry and the industry should take
decision) other attributes follow the stair step model necessary steps to develop the methods according to the
described above. practitioners desire.

The wisdom gained from the research is, that the industry
Conclusions
believes stair step model to be a suitable model in
Due to the fragmented and complex nature of construction
construction dispute resolution. This model starts with
projects, there is no one best way of dealing with disputes
the dispute prevention techniques such as negotiation.
as they are often different in scale, complexity and nature.
According to the stair step model, the disputes not
In deciding which dispute resolution method to apply,
resolved amicably, reach the higher steps with a third
there is a need to take into consideration various external
party involvement. The results shown by the severity
factors, such as technical, political, financial, social, index, comply with the stair step model. By analyzing
economic and legal. However, lack of experiences in these the above results further modifications to the stair step
methods has hindered the acceptance of potential users. model were introduced as follows.
Therefore, this kind of research is useful for the industry
as often practitioners are forced to resolve disputes by Decrease
the quickest, fairest, cheapest means without being fully Speedy solution
aware of the dispute resolution options available. Relationship
Flexibility
Control
This research discovers the ranking order of the important Width of Remedy
factors in dispute resolution. According to the rank Creativeness of the remedy
obtained from mean weighted scale ratings, the duration of Arbitration
the proceedings, obtaining fairness and the binding of the Increase
decision get highest ranks. Obtaining creative remedies, Bindingness
parties ability to control the proceedings and the width Enforceability
of the remedy obtain lowest mean scale ratings. It was Cost and Hostility Adjudication
understood that there is a perception in the industry that Constant
the cost of the process may not be the highest important Confidentiality
factor in ADR. Speed and fairness achieve the highest Privacy
ranks than the cost of the process. By using those results, Mediation
Fairness
the ADR system designers and practitioners can develop
and continue to enhance the proper dispute resolution
mechanism to provide better solutions for construction Negotiation
disputes.

Figure 3: Modified Stair-step model


47
February 2010
SLQS JOURNAL
References 8. Ekanayake, E.M.M.B., 1992. Methods of settling
1. Abeyaratne, S.D.B., 2006. Establishment and disputes in the construction industry of Sri Lanka
organising of Commercial/ Construction Arbitration other than litigation. Unpublished Dissertation
Tribunal. The Bar Association Law Journal, 12, 84- (B.Sc in Quantity Surveying). University of
90. Moratuwa. Sri Lanka.
2. Ashworth, A., and Hogg, E., 2002. Williss practice 9. Omar, A.M., 2007. Delay Claims Management in
and procedure for the quantity surveyor. 11th ed. Constructions. Gulf Project Management Magazine.
London: Blackwell Science. September, 20-23.
3. Astor, H., and Chinkin, C.M., 1992. Dispute 10. Oreilly, M.P., and Mawdesley, M.J., 1994. The
Resolution in Australia. Butterworth. evaluation of construction disputes: a risk approach.
4. Cheung, S.O., 1999. Critical Factors affecting Blackwell publishing.
the use of alternative dispute resolution processes 11. Ranjithkumar, S., 2005. Assessment of Alternative
in construction. International Journal of Project Dispute Resolution Methods practices in Sri Lankan
Management, 17, 189-194. construction industry. Unpublished Dissertation
5. Cheung, S.O., Tam, C.M., Ndekugri, I., and Harris, (B.Sc in Quantity Surveying). University of
F.C., 2000. Factors affecting clients project dispute Moratuwa. Sri Lanka.
resolution satisfaction in Hong Kong. Construction 12. Turner, D.F., and Turner, A., 1999. Building contract
Management and Economics, 18, 281-294. claims and disputes. 2nd ed. England: Longman.
6. Cheung, S.O., and Suen, H.C.H., 2002. A multi- 13. Uff, J., 2005. Construction Law. 9th ed. Sweet &
attribute utility model for dispute resolution Maxwell.
strategy selection. Construction Management and 14. Wimalachndra, L.K., 2007. Alternative methods of
Economics. 20, 557-568 dispute resolution. Junior Bar Law journal, vol. 2 &
7. De Zylva, E., 2006. Alternative Dispute Resolution 3, 55 - 70.
systems for construction contracts. In: K. Legal Authorities and cases
Kanagisvaran, S.S. Wijeratne; eds. Arbitration law 1. State of Kerala vs. Joseph Auchilose (1990) 101 AIR
in Sri Lanka. Colombo: ICLP, 117-138. ker 106

Gillies Ramsay Diamond v PJW Enterprices Ltd (2003)


A claim for professional negligence against Diamond, who had provided general consultancy
services in relation to a building project, was referred to adjudication.

It was found that these services included arranging construction operations for others and/or
contract administration and therefore the matter could referred to adjudication, despite the
absence of an adjudication clause in the contract.

48

You might also like