You are on page 1of 21

SPE/IADC 79850

Closed Hole Circulation Drilling: Case Study of Drilling a High-Pressure Fractured


Reservoir - Tengiz Field, Tengiz, Republic of Kazakhstan
M.N. Sweep, ChevronTexaco Exploration & Production Technology Company; J.M. Bailey, ChevronTexaco Overseas
Petroleum Inc., Tengizchevroil, LLC; C.R. Stone, Signa Engineering Corp.

Copyright 2003, SPE/IADC Drilling Conference


Introduction
This paper was prepared for presentation at the SPE/IADC Drilling Conference held in
Amsterdam, The Netherlands, 1921 February 2003.
The Tengiz field is located on the south side of the 500,000-
This paper was selected for presentation by an SPE/IADC Program Committee following
review of information contained in an abstract submitted by the author(s). Contents of the km2 Caspian Basin on the northeastern edge of the Caspian
paper, as presented, have not been reviewed by the Society of Petroleum Engineers or the
International Association of Drilling Contractors and are subject to correction by the author(s).
Sea. It is one of several large carbonate formations found
The material, as presented, does not necessarily reflect any position of the SPE, IADC, their around the edge of the basin. The field is approximately 110
officers, or members. Electronic reproduction, distribution, or storage of any part of this paper
for commercial purposes without the written consent of the Society of Petroleum Engineers or km2 at the top and 400 km2 at the base. Tengizchevroil (TCO)
the International Association of Drilling Contractors is prohibited. Permission to reproduce in
print is restricted to an abstract of not more than 300 words; illustrations may not be copied.
operates the field in a joint venture with the Republic
The abstract must contain conspicuous acknowledgment of where and by whom the paper of Kazakhstan.
was presented. Write Librarian, SPE, P.O. Box 833836, Richardson, TX 75083-3836, U.S.A.,
fax 01-972-952-9435.
Field delineation and development consisted of drilling new
wells and working on existing temporarily suspended wells
Abstract that range from 4,500 5,700 m. Severe lost circulation can
be encountered while drilling the pay horizon at
The drilling of a sour, high-pressure fractured reservoir in the approximately 4,000 m in what is termed Unit 1 on the Rim
Tengiz field of Kazakhstan displayed complex and hazardous and Flank areas of the field. Please see (Fig. 1: Location Map
well control situations. While drilling the carbonate reservoir Showing T-7252) and (Fig. 2: Cross-section of Rim Region).
termed Unit 1, multiple fractures were encountered resulting Drilling fluid losses in excess of 800 bbl/hr have been
in severe lost circulation followed by hydrocarbon influx into encountered while drilling with as little as 0.3-ppg
the well-bore. overbalance. Numerous attempts to control the drilling fluid
losses with conventional means have been unsuccessful. This
Severe and uncontrollable lost circulation in the target challenging environment had prevented TCO from penetrating
reservoir prompted the use of special practices and equipment; the entire reservoir in extremely fractured areas of the Rim
thereby enhancing the safety and efficiency in the and Flank.
development drilling of the field.
Drilling of 1 7 m vertical fractures or cavities has been
A rotating control device (RCD) was employed to drill ahead observed with an associated reduction in annular fluid level
blind (no fluid returns) by pumping a sacrificial fluid (water) resulting in well control events. Due to the sour/corrosive
down the drillpipe. Simultaneously, a pressurized mud-cap on content of the reservoir, it was desirable that hydrocarbons
the annulus with weighted oil based mud OBM controlled from the reservoir not be allowed to reach the surface under
hydrocarbon influx. The overall process of pressurized mud- any drilling operations.
cap drilling will be described by the term Closed Hole
Circulation Drilling (CHCD). Drilling ahead without returns has been attempted by TCO
with OBM being pumped simultaneously down the drillpipe
The successful application of CHCD has resulted in Tengiz and annulus. This was obviously very uneconomical and
well T-7252 being the first well to completely penetrate Unit 1 could not be sustained for extended periods of time.
where lost circulation could not be controlled by conventional Drilling without returnsusing water as the drilling fluid and
methods. After all Unit 1 fractures had been penetrated, a holding a pressurized column of OBMin the annulushad not
liner was installed to isolate the fractures using the same been implemented in any of the Tengiz wells.
CHCD well control procedures employed while drilling
the interval. Historically, the challenges of drilling the objective oil
reservoir have included severe lost circulation followed by
This technical paper will describe the process used to sour gas kicks. This obviously presented a significant safety
successfully plan, develop, and implement the CHCD risk due to the high H2S content in the oil.
technique in the Tengiz field.
2 SPE/IADC 79850

Prior to the TCO Joint Venture (JV), there were 24 attempts to Devonian boundary. They are Units 1, 2, and 3; from
drill wells through Unit 1 on the Rim locations; none were youngest to oldest respectively. Unit 1 has proven to be the
successful in achieving the objective(s). Since the JV, there most challenging section of the reservoir to drill in terms of
have been only 3 complete penetrations of Unit 1. These lost circulation severity.
penetration efforts were successful because lost circulation
could be controlled by conventional methods. Lost Circulation History and Applications
To adequately appraise the full potential of the Tengiz field Lost circulation problems have plagued drilling operations in
requires successful penetration of a specific number of wells Tengiz since discovery of the field and have continued
in the Rim and Flank areas through Units 1,2, and 3. unabated until the application of CHCD. Lost circulation
challenges have ranged from relatively minor issues to
The subject well, T-7252, was predicted to have a pore catastrophic losses that were impossible to cure. Lost
pressure regression of 15.76 ppg from the top of Unit 1 at circulation is encountered more frequently on the Rim and
4,008 m (Bashkirian formation) to 14.18 ppg at the bottom of Flank regions and predominantly in Unit 1 of the Tengiz
Unit 1 at 4,700 m (Serpukhovian formation). See (Fig. 3: structure. Many remedies and techniques have been tried with
Anticipated Casing Program) and (Fig. 4: T-7252 Reservoir varying degrees of success. However, for the most severe
and Bore Hole Pressures Across the Formation). losses, none of the remedies or techniques prior to CHCD
have been completely successful. Severe lost circulation
The successful application of CHCD has resulted in T-7252 events are extremely costly due to the large amounts of lost
being the first well to penetrate Unit 1 completely where lost drilling fluids and non-productive rig time. The equipment and
circulation could not be controlled by conventional methods. materials required to mitigate these occurrences of lost
circulation varied widely and have resulted in increased costs.
This paper focuses on the verification of the application of
CHCD techniques in the Tengiz field. CHCD feasibility for Lost Circulation in the Tengiz reservoir can be mostly
the vertically fractured carbonate target may greatly impact attributed to a highly fractured carboniferous reservoir where
field rim development. See (Fig. 1: Location Map karst zones are frequently encountered. Fractures have been
Showing T-7252). encountered above and below the karst zones as well as in
non-karst zones in the Platform region. On the Rim and Flank
Geology and Reservoir Description wells, it is common to encounter significant fractures and in
some cases, large cavities in Unit 1.
In order to understand the application of the CHCD technique
it is important to summarize the geological history. The Drilling parameters, including ROP, torque and weight on bit
Reservoir Management Group (RMG) in Tengiz provided are good indicators of fractured formations. Typically, the
descriptions of the reservoir characteristics. The objective initial indicator when drilling fractures is erratic torque,
reservoir is a constructional-type carbonate build-up in size, followed by an increase in ROP and frequently, complete bit
shape, and lithofacies. The various levels are referred to as drop is experienced where cavities exist. When these events
platforms. There is a local topographic high of variable width are encountered, severe lost circulation ensues, causing well
around the entire Tengiz platform. See (Fig. 2: Cross-section control difficulties, loss of wellbore, increased costs and an
of Rim Region) inability to achieve overall well objectives.

The reservoir was formed during Devonian and Carboniferous Pre-JV Lost Circulation Applications. Lost
geological time by recurrent deposition of skeletal fragments circulation was a common occurrence in wells drilled during
along with lime mud. The top of the reservoir is at 3,850 m in the Pre-JV period prior to 1993, with 38 of 83 wells
Unit 1 with oil being found as low as 5,429 m in Unit 3. experiencing lost circulation. Of the 38 wells with lost
circulation problems, 34 of them encountered losses in Unit 1.
The reservoir is subdivided already on the basis of this local The Rim region had 25 wells drilled where 19 experienced
topographic high. The high area is referred to as the Rim lost circulation for a 76% incident rate. The Flank region had
with Platform and Flank regions to the inboard and 24 wells drilled with 12 experiencing lost circulation for a
outboard sides. These aerial regions are carried at depth using 50% incident rate. However, of the 34 wells drilled on the
the same bounds. See (Fig. 2: Cross-section of Rim Region). Platform, only 7 experienced lost circulation resulting in a
20% incident rate.
The area of focus or application for this technique is on wells
drilled in the Rim and Flank regions. It has been shown Various LCM were applied, including: mica, CaCO3, sawdust,
statistically that wells drilled in these areas have a bitumen, rubber tire particles, high viscosity OBM pills and
significantly higher probability of lost circulation in the Siloxan rubber. LCM treatments decreased losses to varying
reservoir than wells drilled in other areas. degrees depending on the severity of the fracture encountered.
Not all LCM materials were acid soluble. Siloxan rubber was
The major depositional sequences have been grouped into reported as being the most effective LCM treatment. It was
informal divisions based on the Visean volcanic layer and tested in six wells with fair success. In some cases, leak-off
SPE/IADC 79850 3

pressures were improved and allowed a continuation of aggressive formulations that were applied on Post-JV
drilling to a deeper depth below the fractured intervals. wells include:
Attempts to reduce mud rheological properties to lessen
equivalent circulation density resulted in poor hole cleaning Conventional lost circulation materials such as Kwik Seal,
and caused barite settling after contact with any oil influx into rock wool, nut plug, various fibrous products and CaCO3,
the wellbore. with a particle size distribution ranging from micron size
to 6 millimeters (mm).
Mud density adjustments while drilling were made in an Cement treatments included: cement with CaCl2,
attempt to reduce the hydrostatic pressure on the formation Nitrified cement, and Thixotropic cement. A retainer was
and avert lost circulation. Attempts to maintain mud density used to place some of these treatments in the
greater than formation pressure and less than the fracture fractured zones.
gradient did not prove successful. It was soon found that the Reverse Gunk with and without CaCO3.
mud density required to contain reservoir pressure was always DOB2C & ACDOB2C (Non-Acid soluble and Acid
in excess of what the highly fractured reservoir could support. soluble diesel oil bentonite).
Various proprietary soft plugs from a number of vendors.
Cement plugs were attempted by bull heading the slurry down Some of the pills were surface activated and some were
the drillpipe while simultaneously bull heading mud down the mixed down hole. Bridging agents in these pills ranged
annulus and placing the cement into the fractured zone. from sized salt to LCM and all contained some type of
Because the hydrostatic pressure during these cement plug cross-linked polymer.
attempts was in excess of what the fractured formation could
support, it was difficult to effectively place the cement to seal Given the extensive application of numerous lost circulation
the fractures. There was no noticeable progress in cement materials and products, all resulting in limited success, it was
slurry design or application that effectively solved the lost evident that a step change was needed to successfully drill to
circulation problem. deeper horizons on Rim and Flank region wells. Therefore,
TCO started to pursue alternatives with valuable input from
Barite plugs were applied successfully as a barrier to seal the Shareholders and industry experts.
losses prior to running casing. These plugs were set by
allowing the well to flow back to a predetermined volume,
thus mixing Tengiz crude with the mud, causing the barite to
The Technique, Closed Hole
settle and form an effective plug. This procedure normally Circulation Drilling
took several attempts to form a plug.
Closed Hole Circulation Drilling (CHCD) is formally known
as Mudcap Drilling in other parts of the world. It is a type of
Post-JV Lost Circulation Applications. The lost
Underbalanced Drilling in that the drilling fluids exert less
circulation problems experienced during Pre-JV drilling were
hydrostatic pressure than the formation pore pressure. This
also encountered during Post-JV drilling operations. This
results in a net positive pressure at the surface. There are two
complexity and drilling hazard was a major obstacle to TCO's
CHCD techniques. They are Heavy Annular (HACHCD) and
ability to appraise the Tengiz field and develop reserves. Lost
Light Annular (LACHCD). The HACHCD method controls
circulation was experienced in 8 of 9 wells drilled and
surface pressure and LACHCD controls bottom hole influx of
prevented achievement of the objectives in 5 of those wells.
sour formation fluids. For this paper, we will discuss the
Mud losses varied from seepage to massive losses.
Light Annular CHCD technique. LACHCD is best applied in
situations of natural fractures or karsts exhibiting severe loss
While drilling well T-5034, TCO realized that conventional
of circulation, high bottom hole pressure, high bottom hole
methods and materials would never accomplish the objective
temperature and H2S bearing hydrocarbons. It is possible to
of controlling severe lost circulation in the Tengiz Field.
have a fractured formation that is not a CHCD candidate. The
While drilling this well, over 27,000 bbls of OBM were lost,
ideal formation candidate for this technique is one that has low
and 20 different pills or techniques were applied without any
injectivity pressure into the formation or conversely, high
abatement of the lost circulation. Drilling was suspended on
conductivity into the formation. In other words, the imposed
the well when all available methods of lost circulation control
pressure to pump into the formation after encountering a
were tried and proved unsuccessful. Wellbore stability at this
fracture may be as little as 10 psi or a fraction of one tenth of a
point was extremely sensitive even to the extent that simply
pound per gallon equivalent mud weight (ppg emw). The
moving the drillpipe up or down would cause the well to either
Tengiz Rim and specifically well T-7252 exhibited all these
flow or go on a vacuum. Subsequently, three days were
conditions except high bottom hole temperature. The primary
required to pull the drillstring to suspend well operations.
concern with well T-7252 was avoidance of well control
situations that might precipitate an emission of sour gas at the
On Post-JV wells, the first line of defense for lost circulation
surface. It should be noted that previous attempts to attain
was acid soluble LCM. Limited success using these materials
total depth in Tengiz Rim and Flank wells had not been
caused a more aggressive approach. Many different methods
successful using conventional drilling techniques.
and materials were used in an effort to cure the lost circulation
CHCD is a form of blind drilling; no drilling fluid and/or
rather than protect the formation. Some of the rigorous and
formation cuttings are transported back to the surface. Both
4 SPE/IADC 79850

are injected into the fractures encountered during drilling. A circulation. When the loss of returns was noted, the team
specially designed fluid is placed in the drillpipe by filled the annulus with cutback fluid until the wellbore
casing/open hole annulus to allow safe control of surface remained full. The team immediately closed the annulus and
pressures. The annulus fluid is maintained in a static state by waited 5 minutes for the casing pressure to stabilize. Using
closing the return flow conduit at the surface. Some have the known mud weight in the hole at the time of the loss, plus
referred to this static fluid column as a floating mudcap. It the hydrostatic weight of the cutback fluid combined with the
is typically a weighted mud system with high viscosity and annular pressure, one can accurately calculate the
fragile gel strengths. In the LACHCD technique the annular pore pressure.
fluid is designed to be 0.1 ppg less than the formation pore
pressure in equivalent mudweight, hence the name Light Pchoke + .052*MWavg ann*TVD = PPreservoir ............................ (1)
Annular CHCD. Depending upon the depth of the uppermost
fracture, the net positive annular pressure at the surface should Note, Pchoke is the annular surface pressure and is typically a
be between 50 and 150 psi. So, the complete displacement of positive pressure, because the momentum of the falling mud
the annulus with the designated light annular mud will present column will proceed below the equilibrium point. The
a predictive positive casing pressure (pressure datum) at the cutback fluid will only fill the hole momentarily and then will
surface. The casing pressure will increase slowly begin to flow back. Closing the annulus when the cutback
corresponding to the migration rate of hydrocarbons up the fluid first fills the hole will minimize influx (unknown
annulus. Once a predetermined casing pressure/influx height density) and allow the casing pressure to give a true
is reached, the light annular mud is pumped into the annulus measurement of downhole pore pressure. Please see
until the casing pressure returns to its datum level. Nomenclature section.
Performing operations with a positive casing pressure at the
surface is uncomfortable for most conventional drillers. There Assuming vertical penetration of the target, the desired
is a tendency to want to top kill the annulus to bring the annular fluid density is simply 0.1-0.2 ppg (0.01-0.02 SG) less
surface pressure to 0 psi during tripping operations. A top kill than the EMW of the pore pressure at the top of the loss zone.
defeats the LACHCD method in that it masks the known Depending upon depth, this should present a surface casing
annular quantity and presents an unknown situation that may pressure datum between 50 and 150 psi. This low pressure
lead to an emission of sour gas in later operations. must be manageable with current rotating control device
capabilities. Gas influx and migration at the top of the loss
The CHCD technique also involves a second drilling fluid zone is the worst-case scenario for rising casing pressure.
system called Sacrificial Fluid or simply Sac fluid. This Sac Typically, the operator will pick a predetermined casing
fluid is pumped down the drillpipe to affect drilling of the pressure that represents a given column of gas influx as the
formation. It is called sacrificial fluid because it does not point at which periodic injection of annular fluid occurs. The
return to the surface, but is injected into the fracture(s) of least casing pressure chosen must be something within the working
resistance. The sacrificial fluid is also unique in that it is capability of the rotating control device, i.e., 400 psi. For
usually a lightweight, plentiful and inexpensive fluid. Since example, 100 psi may be chosen as the datum casing pressure
the Sac fluid is typically a non-native fluid to the reservoir, it and 400 psi as the upper level pressure. As drilling continues,
must be compatible with reservoir rock and associated fluids. gas migration may slowly raise the casing pressure to 400 psi.
The Sac fluid must be pumped at a rate sufficient to provide At that time, the annulus pump would begin displacing or bull
hydraulic horsepower for a mud motor (if used), to cool the bit heading light annular fluid into the hole until the casing
and to transport the drilled cuttings to the fracture(s) of least pressure gauge returns to the datum pressure of 100 psi.
resistance. If fresh water, seawater or brine is used, the lack of When the datum pressure is attained, one can be confidently
fluid viscosity may place transport of cuttings and the assured that all the influx has been forced back into the
corresponding annular velocity of the Sac fluid at the top of formation and a competent column of known mud density
these three requirement priorities. Please see (Fig. 5: exists. After the annular injection cycle, the static annular
CHCD Schematic). pressure will be the difference between the annular mud
density and the pore pressure at the top of the reservoir.
Annular Fluid Density Determination. The first
step in setting up a CHCD project is the determination of the Pchoke = .052*(MWannulus EMWPP)*TVD............................ (2)
annular fluid density. This task will determine the drillpipe
injection pressures and surface annular pressures. The fluid design for the annulus must satisfy three
Conventionally, the pore pressure of the formation being requirements. It must be of sufficient weight to assist in the
drilled must be known from offset data or determined within a containment of the formation. The fluid must mitigate
reasonable degree of accuracy. The data is used to determine hydrocarbon migration and ideally, the fluid would have gel
the mud density that will be required for a particular section of strength properties that would assist in keeping it in place in
hole. In LACHCD, the pore pressure must be precisely the annulus. The preferred fluid design would be non-
known. A proven field method of determining the pore Newtonian fluids. The thixotropic nature of the fluid will
pressure is to prepare a trip tank with cutback fluid. This mitigate hydrocarbon migration and exhibit mud column
fluid is used to chase the falling mud column when integrity for drilling and tripping of drillpipe.
encountering the type of fracture that causes complete loss of
SPE/IADC 79850 5

Estimating Drillpipe Injection Pressures. An requirements can easily be estimated for a given hole size and
LACHCD project requires knowledge of surface injection bottom hole assembly (BHA). See (Fig. 6: Drillpipe Injection
pressures and downhole volume requirements. This exercise Fluid Requirements for CHCD).
will identify standpipe pressure and volume requirements to
accomplish downhole goals. The standpipe pressure must be Estimating Annular Injection Volumes. There are
estimated for both static and dynamic conditions. The static two different methods of annular injection of fluid that assist
standpipe pressures (SPP) can be estimated using the in the control of surface pressures. The method utilized in the
following equation: Tengiz project was periodic injection. The annular fluid
represents one of two fluid systems that must be managed in a
PSPPstatic = .052 (EMWPP MWdrillpipe)*TVD ......................... (3) CHCD operation. It is imperative that we estimate the
expected daily volume so that rig site storage may be properly
Where PSPP static is the static standpipe pressure. This is the partitioned. The formulas below will assist in annular fluid
U-tube pressure differential between the annulus and the volume estimation.
drillpipe. The dynamic standpipe pressure is equal to the
static standpipe pressure plus the pressure losses down the QAnn = (SF) VHM TPI (IDHole2 ODDP2) / 1029 ...................... (5)
drillstring and into the fractures. It can be calculated by the
following equation: QADC = 24 * 60 * QAnn / TPI................................................................................ (6)

PSPPinjection = PSPP static + PDP + PDC + PMWD + PMotor + Pbit QAnn is the periodic injection rate required to prevent
+ Pfrac .................................................................................. (4) hydrocarbon migration. The rate of hydrocarbon migration is
expressed by VHM and the time between injection is
Where PSPPinjection is the dynamic or standpipe injection represented by TPI. The daily annular cumulative injection
pressure. The description of the other variables is provided in volume is QADC.
the Nomenclature section. When the CHCD technique is
properly applied, the injection pressure into the fractures is The hydrocarbon migration rate is probably the greatest
assumed to be small. If CHCD is attempted in the presence of unknown in equation (5) above. It is a function of the
small fractures, the injection pressure may increase the overall wellbore geometry, temperature, pressure and the rheology
dynamic standpipe pressures beyond the capability of and density of the annular fluid. A rule of thumb is that gas
available equipment. migrates at the rate of 1000 feet/hr. More specifically, it is
estimated that gas migrates at a rate between 7 and 15
Estimating Drillpipe Injection Rate. When feet/minute in a given fluid. Shell research found that gas will
estimating drillpipe injection rate, several considerations must migrate at the rate of 90 feet/minute with a low viscosity fluid
be studied. The cuttings generated by the bit must be in a shallow low pressured environment. Obviously, the
conveyed to the fracture of least resistance. For planning migration of a liquid hydrocarbon will be much slower than
purposes, the injection fluid should be water and the fracture the low density gas. For the purpose of estimating annular
of least resistance should be at the topmost point of the open injection volume, it may serve to assume a gas migration rate
hole. Sifferman et al. estimated that the minimum annular of 15 feet/minute.
velocity to remove cuttings from a vertical well with water is
100 ft/min. Hole conditions or the existence of multiple A simplified chart (Fig. 7: Effect of Gas Migration Rate on
injection fractures may require higher annular velocities due to Casing Pressure and Kill Volume) shows gas migration with
uneven injection of fluid along the wellbore. One hundred respect to time and its effect on casing pressure. Along with
feet per minute should be the minimum annular velocity required kill volume to force the hydrocarbon back from
anticipated for CHCD. It is wise to start with a circulation rate whence it came. The chart is a relational study only. The data
that would generate 120-140 ft/min annular velocity and assumes that hydrocarbon density and migration rate is
slowly decrease the pump rate while monitoring for drag. constant. The chart data is further simplified in that it assumes
Increasing drag on the bottom hole assembly will indicate that the migrating hydrocarbons completely displace the
inadequate hole cleaning and will require a corresponding annular fluid. The validity of this assumption decreases with
increase in pump rate. In this way, the driller can optimize the increasing depth.
volume of Sac fluid pumped away. This procedure should be
periodically repeated since new hole is generated that might Case StudyTengiz Well T-7252
change the downhole conditions.
Since the completion of T-7252, and at the time of writing of
A second consideration is the pump rate required to run a this paper, there have been 7 more successful applications of
drilling mud motor. If a motor is not used to rotate the bit, an the technique in the Tengiz Field.
adequate amount of Sac fluid must be pumped to cool and
clean the bit while still transporting the cuttings. The use of a Candidate and Rig Capability. An on-site feasibility
motor typically requires a higher pump rate to power the study concluded that the Tengiz wells were good candidates
motor. For planning purposes, 18 hrs per day is used as a for the application of CHCD. Existing equipment capabilities
typical circulating or drilling day. Daily Sac Fluid of Parker Rig 249 were adequate with modifications required
6 SPE/IADC 79850

for BOP configuration. This was due to the requirement to ground water, Plant technical water, and Plant effluent water.
install a rotating control device (RCD) on top of the BOP. For It was decided that Plant effluent water would be used and
this reason, Parker Rig 249 was chosen as the optimal rig for diverted from the injection facility to the well-site. This is
the first application. essentially wastewater produced from the plant due to the
cooling towers, steam generation, and formation water.
It was determined that T-7252 would enter Unit 1 on July 19,
2001; making this the target date for project implementation. A seven kilometer 8" (6.5" ID) polyethylene pipe was installed
Essentially, approval for the Development Team was initiated above ground with the ability to divert flow towards T-7252
on May 1st, giving the team 80 days by which to prepare all location or the injection facility. Two earth pits capable of
the required systems and design. This proved to be a holding 20,000 bbls each were constructed. The pipeline
challenge with little or no tolerance for error in the could deliver fluid to atmospheric pressure at 9,000 bbl/day
planning stage. with the pits holding a 4 day reserve in the event of a line or
facility failure.
Pressure Requirements. Parker Drilling Rig 249 has
two Continental Emsco FC 2200 HP triplex pumps and one The fluid was treated on location with caustic soda and lime
Continental Emsco FC 1600 triplex pump. Pressure rating of for pH control to assist in removal of residual H2S from the
the FC 2200 is 6,600 psi with 5.5" liners. Pressure rating of plant effluent. Additionally, H2S and O2 scavengers were
the FC 1600 is 6,000 psi with 5" liners installed. The injected into the fluid stream at the rig pumps to assist in
circulating system (standpipe, kelly, swivel, etc) is rated to corrosion prevention. The treatment schedule for 9,000
7,500 psi. Drillpipe is a 5" XD 105 (3.5" ID) heat-treated bbl/day is shown in (Table 2: Sacrificial Fluid Treatment).
string for the corrosive environment. Given these pressure
constraints, calculated surface pressures using 8.33 ppg water Annular Fluid. The existing OBM used to drill Tengiz
at 350 gpm were estimated as shown in (Table 1: T-7252 wells would be used for the annulus fluid. Design criteria are
Estimated Pressure Regimes). such that H2S effects are minimized with 3 lb/bbl of zinc oxide
and 6 lb/bbl of lime in the annular fluid. Adequate volumes
The existing circulating system was deemed adequate for the and storage of OBM was maintained by the existing
anticipated reservoir pressures. This also indicated that the infrastructure for drilling fluids.
use of water as the sacrificial fluid while drilling would be
possible. Annular velocity >150 ft/min was desirable for It was anticipated that the average daily injection rate of 450
wellbore cleaning. Although there would be no fluid returns bbl/day would be required to mitigate hydrocarbon migration.
to surface, drilled cuttings must be carried from the bottom of Actual usage was only 15 barrels over drilling of the entire
the hole to the nearest fracture(s) of least resistance. Unit 1 interval. With this observation, it was determined that
minimal hydrocarbon migration occurred in the annulus while
The Alpine rotating control device (RCD) was chosen for T- drilling T-7252.
7252. A key component of the Alpine RPM 3000 is the dual
sealing capability (see Fig. 8: Alpine RPM 3000 RCD). The Design criteria for the annulus fluid was such that a 50 psi
upper element is a passive seal or a stripper rubber energized positive pressure was left on the annulus by keeping the
by wellbore pressure. The lower element or primary seal is an annular hydrostatic pressure slightly less than
active bladder type element that is hydraulically energized formation pressure.
from a remote unit. The lower element rotates on a bearing
assembly. Maximum tool diameter that can be stripped Training. A location specific training course was
through the elements is 6.75". Another advantage is the developed and implemented by Signa Engineering Corp. All
compact dimensions required for BOP clearance. Trapped personnel both from an operational and engineering
wellbore pressure or gas between the elements can be released perspective were trained at the office facility in Tengiz. A
by a purge system. trainer was assigned to conduct the training in 2 day classes
over 8 sessions. More than 140 personnel were trained in the
Well Control Equipment Configuration. fundamentals and theory of CHCD. The training material was
Installation of the RCD required careful consideration of the modified with input/comments from TCO drilling
Class 5 BOP height. It was determined that the 13 5/8" x staff/engineers during the course of delivery. The course
10,000 psi BOP should be replaced with an 11" x 10,000 psi proved to be an effective method of communicating all the
BOP (see Fig. 9: Class 5 BOP for 11"). This facilitated the new concepts and operational changes required.
installation of the RCD without significant modifications to
the rig substructure or the wellhead configuration. Process Hazard Analysis. The Health, Environmental,
and Safety (HES) group was engaged to conduct a process
Water Supply. During the drilling phase of Unit 1, 350 hazard analysis (PHA) of well-site operations. A cross-
gpm of sacrificial fluid are required to achieve >150 ft/min functional group completed the session and identified a
annular velocity. This translates into 9,000 bbls/day of number of components that required further research. Some
continuous supply over a 4 5 day interval. A number of of the key items identified but not limited to were:
water sources were considered, such as the Caspian Sea,
SPE/IADC 79850 7

A recessed wear groove in the drillpipe tool joint required maintained through this interval. Mud density had been
smoothing to prevent excessive RCD element wear. reduced from 15.8 ppg to 15.7 ppg.
A decision protocol for converting to CHCD was written
into the Lost Circulation Contingency Plan. Transition to CHCD. Complete loss of circulation was
The rig drilling fluid storage and pumping system was encountered at 4,390 m. Rig pumps were slowed to 40
converted to handle two simultaneous fluid systems. strokes/min in an attempt to regain circulation. The rig was
A backup RCD was ordered and delivered prior able to drill ahead at 50% returns while losing 250 bbl/hr of
to implementation. OBM to formation. At 4,398 m, drilling was suspended to
Plans and procedures were developed should the loss of place a 100 bbl lost circulation pill using Halliburton pump
pressure control within the drillstring be encountered. trucks. See (Table 3: Oil Base Mud OBM). The table
Procedures for tripping of drillstring and liner were outlines the sections and volumes where significant losses
developed. occurred during drilling.

Implementation A precautionary trip into the 97/8" casing shoe was conducted
to observe the wellbore flow/loss characteristics and to
determine the next course of action.
Rig Fluid System. The drilling rig re-configured piping
and fluid supply to the pumps to allow for the distribution of A series of different mud weights were pumped into the
two different fluid types. The rig pumps had manifolds annulus in an attempt to stabilize the well. It was determined
installed such that sacrificial fluid or OBM could be delivered that reservoir pressure at 4,398 m (first fracture) was
to the drillstring. As a backup to the rig pumps, a Halliburton 15.47 ppg.
high-pressure pumping unit was positioned to deliver OBM to
the annulus via the kill line. With the well shut-in, 15.6 ppg mud was displaced into the
annulus at 2 bbl/min. Casing pressure was observed dropping
Drillstring Components. The drillstring had three float from 420 psi to 290 psi while pumping. At static conditions
subs installed, two Baker Model F type (plunger) and one the casing remained at 0 psi. Circulation or returns of 45%
Baker Model G type (flapper); all rated to 7,500 psi. This was was regained by pumping down the drillpipe at 3 bbls/min.
to provide redundant protection against the differential With the pumps off and the well shut-in, casing pressure
pressure exerted on the drillstring. This proved to be increased to 200 psi. These observations and the previously
inadequate as pumping of lost circulation material caused all agreed upon contingency criteria facilitated the decision to
three floats to fail. After this event four plunger type floats implement CHCD. Cumulative OBM lost to the formation at
were installed with no further incidents. this point was 1,874 bbls.

The final bottom-hole assembly (BHA) consisted of an 8.5" The sealing elements and bearing assembly for the Alpine
PDC bit, bit sub, 2 float subs, 1 6.75" drill collar, 1 float sub, RPM 3000 were installed on the drillpipe. At this point the
3 6.75" drill collars, pump-out sub, drilling jar, 1 6.75" well began flowing up the drillpipe. It was suspected that the
drill collar, and 21 5" heavy weight drillpipe. lost circulation material had compromised the floats.
Unsuccessful attempts were made to clear the floats with
Unit 1, Upper Section (3,994 4,398 m). The 97/8" various pump rates and fluid densities. The drillstring was
shoe was drilled out at 3994 m with 16 ppg OBM in pulled out of the well using stripping procedures with the
preparation for coring. A formation integrity test of 18 ppg RCD and periodic placement of 18.1 ppg fluid slugs in the
EMW was conducted. Two 27 m cores were cut and retrieved drillpipe. The annulus was placed on a slight vacuum to
in the Bashkirian formation of Unit 1. No lost circulation was remove the BHA.
experienced, which is not always the case in the upper section
of Unit 1. Drilling continued essentially trouble free to 4,300 It was determined that all three floats were compromised with
m with some slight tight hole sections requiring a 50,000 lb lost circulation material. An additional float sub was installed
over-pull to clean the wellbore. Mud density had been and the drillstring stripped back to bottom. The well required
reduced from 16 ppg to 15.8 ppg. Average ROP to this point that 1,400 psi injection pressure be placed on the formation to
was 4.0 m/hr. initiate the required fracture communication for CHCD. The
annulus was displaced with 675 bbls of 15.4 ppg mud to
Standard parameters for drilling with an 8.5" bit were 15,000 obtain a uniform density in the annulus.
20,000 lb WOB and 120 RPM. At 4,304 m the weight on bit
parameter went to zero and a 0.5 m bit drop was observed. During this operation the annular was closed to facilitate
Drilling continued with standpipe pressure of 3,000 psi to changing of the RCD bearing element. An equalizer line was
4,317 m where partial losses of the OBM occurred at a rate of connected to a line above the rig floor and pressures were then
40 bbl/hr. released to a Halliburton high pressure pump unit. Subsequent
removal of the RCD allowed mud in this line to drain into the
Conventional LCM pills were pumped and drilling continued. hydraulic system. This caused the hydraulic unit to be taken
The well took 150 bbls of OBM to the formation while drilling out of service and a back-up system installed. It was
ahead from 4,321 m 4,374 m. A 3.8 m/hr ROP was
8 SPE/IADC 79850

discovered that the pressure release system must be installed 25 bbls of 15.4 ppg mud and 5 bbl of 17.3 ppg mud. To
so that drilling fluids drain by gravity. retrieve the drill collars; the annulus required 10 bbls of 17.3
ppg mud and 10 bbls of 15.4 ppg mud.
Drill Unit 1 with CHCD (4,398 m 4,800 m).
Drilling resumed using plant effluent water as the sacrificial The team determined the rate of corrosion that would occur in
fluid with 250 psi on the annulus. Drilled cuttings were the drillstring due to the exposure of water. The acceptable or
assumed to be carried to the first fracture at 4,398 m. The industry standard rate of corrosion is <2.0 lb/ft2/yr. Analysis
initial design of 350 gpm flow-rate down the drillpipe was of the ring recovered from the bit sub was measured at 0.1081
reduced by 30%. Using a 245 gpm pump rate to achieve an lb/ft2/yr, well below the normal rate.
annular velocity of 120 ft/min in the open-hole section
resulted in adequate hole cleaning. Logging was conducted with a lubricator and wire-line rams
tested to 1,500 psi. Run #1 was a Gamma
No drillstring torque or over-pull was observed during drilling Ray/Caliper/Resistivity suite which only reached 4,738 m. It
or tripping of the entire section. (Table 4: CHCD Interval is unknown whether the well bridged off or a fracture caused
Pressures) groups various intervals in terms of pressure the tool to stop; subsequent trips did not indicate any fill or
management and ROP observations. Density of annular fluid debris. The well was logged from 3,994 4,738 m. A
throughout drilling of the Unit 1 fractures was maintained at periodic injection of 15.4 ppg fluid in 5 bbl increments was
15.4 ppg. required to maintain casing pressure below 250 psi.

A 20 bbl high viscosity polymer pill was pumped every 4 While logging, a weight decrease was observed with the tools
hours, or as needed, to assist in wellbore cleaning. Total at 40 m. Upon retrieval of the tools, there were only 4.7 m
chemical/treatment costs for the sacrificial fluid was $50,000 attached to the wireline, leaving 21.30 m in the wellbore. It
or $1.87/bbl. This was double the original estimate for the was determined that the tools failed due to sulfide stress
required design, but reflected the cost to treat the entire cracking. Subsequent fishing operations with a 5.75" overshot
system, including the stand-by fluid in the earthen pits. and 3.75" basket grapple were successful in retrieving the
Normalizing the costs to the actual injected volume results in logging tools from 4,714 m. Periodic injection of 15.4 ppg
treatment cost of $0.93/bbl. mud in the annulus was required to maintain casing pressure
below 600 psi.
A more detailed picture of the standpipe and casing pressure is
outlined in (Fig. 10: Actual Standpipe and Casing Pressure). Liner Running and Cementing. A 7" x 32 lb/ft liner
It can be seen that the maximum casing pressure encountered with a liner packer was run on drillpipe. The well was again
during CHCD was 600 psi with the average being in the 300 difficult to stabilize and required repeated attempts at
400 psi range. It should be noted that under static conditions stabilizing the annulus with various weights of OBM. A total
during a connection, the casing pressure would typically drop of 718 bbls were lost while running the liner through the RCD.
back to 50 psi.
While running in the hole with the liner, an attempt was made
Drilling was terminated at 4,800 m based on seismic to increase the resistance to well flow by placement of a 350
interpretation and the probability that Unit 1 had been bbl high viscosity mud at 15.4 ppg. This was not successful in
completely penetrated. stabilizing the well and continued efforts to fill the annulus
with various mud weights were required.
Tripping and Logging. At total depth of 4,800 m,
tripping procedures required that OBM be placed from the The liner stripped in the hole was run to Total Depth (TD),
bottom of the wellbore up to the first fracture at 4,398 m. This (top of packer seals at 3,842 m) and cemented with 125 bbls of
was accomplished by displacing the drillstring with 350 bbls Class G 15.8 ppg cement. A batch mix procedure was used.
of 15.6 ppg OBM. Periodic injection of 15.4 ppg fluid in the Cement was displaced with 15.4 ppg OBM while shut-in with
annulus was required to maintain casing pressure below 100 positive pressure on the annulus. A positive pressure test to
psi during tripping of the drillpipe. 17 ppg and a negative test to 13.5 ppg were
conducted successfully.
Once the BHA was reached, the ability to stabilize the annulus
became difficult. A series of attempts to balance the wellbore As the well did not have returns during the cement job, a
with various mud weights was unsuccessful. It was calculated cement top cannot be determined. Further study is
determined that the wellbore had a 0.03 ppg margin of being conducted to determine the optimum approach for
variance in terms of stability. Essentially, if the hydrostatic acquiring cement top data. Current cased hole logging
column in the annulus exceeded pore pressure by 25 psi; the techniques for obtaining a cement bond log is not applicable to
fractures would begin to take fluid and subsequent pumping of Tengiz fractured carbonates. This is due to the very high
OBM to the annulus was required. Conversely, if the velocity profile of the reservoir, making it faster in terms of
hydrostatic column in the annulus were reduced by 25 psi travel time than the cement or casing. A cased-hole
below pore pressure; the well would begin to flow. The temperature log could be run after the cement placement. This
heavyweight drillpipe was stripped from the well by pumping
SPE/IADC 79850 9

would profile the temperature gradient and assist in Application of LCM was once unsuccessful in a highly
identifying the cement top. fractured formation. Consideration should be given to
modification of the lost circulation contingency plan for
Summary conversion to CHCD.
A well engineered and detailed program must be
General. TCO was able to drill 402 m in 87.5 hrs using developed, with mitigation steps included to preserve well
CHCD methodology in the highly fractured Unit 1 formation control. The process hazard analysis was very valuable in
of the Tengiz field. A liner was successfully installed and the this regard.
well was drilled to programmed TD. This met all objectives All personnel should be trained in CHCD procedures
of the T-7252 well, including appraisal of Unit 2 and Unit 3. before attempting this technique with specific emphasis
This was the first time this objective was met where extreme placed on safety and well control.
lost circulation was encountered in Unit 1. Subsequent testing of Unit 1 in T-7252 revealed no
adverse effects from the Sac water used during the CHCD
Throughout the drilling of Unit 1, a total of 4,475 bbls of process. The production rates were above expectations.
OBM was lost to the formation. Only 15 bbls of this loss During the flow tests, no measurable Sac water was
occurred while drilling with CHCD. The remainder was used recovered.
for tripping the drillstring, logging, and running of the liner.
A total of 26,800 bbls of Sac fluid was used to drill ahead with Nomenclature
complete losses. This was essentially half the original design
estimate and reflects the operational adjustments. This was Pchoke = choke pressure, psi
mainly due to the ability to clean the wellbore effectively at MWavg ann = average mud weight in the annulus, ppg
lower than expected rates and can be used to optimize fluid TVD = true vertical depth, ft
requirements for subsequent applications. PPreservoir = pore pressure in the reservoir, psi
MWannulus = mud weight in the annulus, ppg
The planning process and implementation of CHCD was EMW pp = equivalent mud weight of pore pressure, ppg
successful in achieving the geological objectives. Penetration PSPPstatic = static stand pipe pressure, psi
rate can be improved once more experience is gained on the MWdrillpipe = mud weight inside the drillpipe, ppg
wellbore cleaning characteristics. It has been determined that PSPPinjection = dynamic or injection stand pipe pressure, psi
field development would require further use of this technique. PDP = parasitic pressure loss in the drillpipe, psi
The current systems and processes that are in place will be PDC = parasitic pressure loss in the drill collars, psi
implemented on subsequent wells where there is a potential PMWD = pressure loss through the measurement while
for lost circulation in Unit 1. drilling tool, psi
PMotor = pressure loss through the mud motor, psi
Lessons Learned and Observations. PBit = pressure loss through the bit, psi
Resource allocation was critical to achieve objectives. PFrac = parasitic pressure loss through the fractures, psi
Install RCD with gravity feed drain system for the QAnn = periodic annular injection rate, bbls
drilling fluids. SF = safety factor
Further study is required to determine logging feasibility. VHM = hydrocarbon migration rate, ft/min
Consistent delivery of water from the plant facility to the TPI = time between injection cycles, min
drilling site was critical. IDHole = diameter of the hole, inches
Hydrocarbon migration near the bottom of the hole ODDP = outside diameter of the drillpipe, inches
was minimal. QADC = annular daily cumulative injection volume,
Twelve fractures in Unit 1 were identified on the caliper bbls/day
log with some sections showing hole enlargements up to
12.8 " through the CHCD interval. Acknowledgement
The decision to implement CHCD should be driven by a
lost circulation protocol. The authors would like to thank the management of
Wellbore cleaning required a pump rate of 235 gpm in Tengizchevroil, TCO Well Construction Group, TCO
8.5" hole using freshwater Sac fluid. Reservoir Management Group, TCO Field Facilities
No hole stability problems were encountered. Construction/Engineering, and ChevronTexaco EPTC group
The CHCD technique improved the rate of penetration by in Houston for their support and contribution to the successful
more than 40%. implementation of this new technique. Also, thanks to the
Once plunger type floats are installed in the drillstring, the Joint Venture shareholders and the Republic of Kazakhstan for
use of LCM is not recommended. their permission to publish the paper.
The training modules were modified to be project or
well specific. Specific acknowledgement is given to TCO Shareholders who
Improvements to mud losses while pulling BHAs and participate in semi-annual Well Construction and Operational
running liners will be studied further and implemented. Performance Review forums conducted on-site at Tengiz. The
10 SPE/IADC 79850

authors send special thanks to ExxonMobil for sharing their 10. Sifferman, T.R., et al: Drill Cutting Transport in
expertise and encouragement of Pressurized Mud Cap Drilling Full-Scale Vertical Annuli, J. Pet. Tech.
and their support in a Tengiz application. (Nov. 1974).
11. Adams, N.: Well Control Problems and Solutions,
The authors would like to acknowledge the support work
The Petroleum Publishing Company, 1980.
provided by the following service/contractor companies:
Signa Engineering Corp., Parker Drilling International, 12. Colbert, Medley, SPE, 77352, Light Annular
Weatherford International, Schlumberger, Halliburton, MI Mudcap Drilling A Well Control Technique for
Drilling Fluids, Baker Oil Tools, and Pete Hart Drilling Fluid Naturally Fractured Formations, presented at 2002
Consultants who contributed to the success of this project. SPE Conference, San Antonio, Texas.
13. Bloys, B., Brown, J.D. and Tarr, B.A.: Drilling
References Safety and Economically in Carbonates: Collective
Experience of ARCO, BP and Mobil, presented at
1. Urselmann, R., et al: Pressured MudCap Drilling: the 1994 IADC Well Control Conference for the
Efficient Drilling of High-Pressure Fractured Asia/Pacific Region, Singapore.
Reservoirs Paper SPE/IADC 52828 presented at
the 1999 SPE/IADC Drilling Conference held
in Amsterdam. SI Metric Conversion Factors
2. Johnson, J., et al: High Efficiency Drilling A
cp x 1.0* E-03 = Pa.s
Novel Approach for Improved Horizontal and
Multi-Lateral Drilling, Paper SPE 52185 presented ft x 3.048* E-01 =m
at the 1999 Mid-Continent Operations Symposium ft2 x 9.290 304* E-02 = m2
held in Oklahoma City, Oklahoma. ft3 x 2.831 685 E-02 = m3
in. x 2.54 E+00 = cm
3. Reyna, K.: Case History of Floating MudCap lbf x 4.448 222 E+00 =N
drilling techniques - Ardalin field, Timan Pechora md x 9.869 233 E-04 = m2
Basin, Russia, Paper SPE/IADC 29423 presented psi x 6.894 757 E+00 = kPa
at the 1995 SPE/IADC Drilling Conference held
in Amsterdam. * Conversion factor is exact
4. Al-Sarraf, A. and Hazel, R.: The Drilling
Optimization Performance in Kuwaits High
Figure Captions
Pressured Wells Paper SPE/IADC 39270 presented
at the 1997 SPE/IADC Middle East Drilling Fig. 1: Location Map Showing T-7252
Conference held in Bahrain. Fig. 2: Cross-section of Rim Region
Fig. 3: Anticipated Casing Program
5. Mohd, A.: Carbonate Drilling with Mud Loss Fig. 4: T-7252 Reservoir and Bore Hole Pressures Across
Problems in Offshore Sarawak Paper IADC/SPE the Formation
36394 presented at the 1996 IADC/SPE Asia Fig. 5: Closed Hole Circulation Drilling Schematic
Pacific Drilling Technology held in Kuala Fig. 6: Drillpipe Injection Fluid Requirements for CHCD
Lumpur, Malaysia. Fig. 7: Effect of Gas Migration Rate on Casing Pressure and
Kill Volume
6. Quitzau, R., et al: System for Drilling an Offshore
Fig. 8: Alpine RPM 3000 RCD
Shallow Sour Gas Carbonate Reservoir Paper
Fig. 9: Class 5 BOP for 11"
SPE/IADC 52808 presented at the 1999 SPE/IADC
Fig. 10: Actual Standpipe and Casing Pressure
Drilling Conference held in Amsterdam.
7. Johnson, J., et al: High Efficiency Drilling A Author Biographies
Novel Approach for Improved Horizontal and
Multi-Lateral Drilling, Paper SPE 52185 presented M.N. Sweep P.Eng. Miles Sweep is a Senior Drilling
at the 1999 Mid-Continent Operations Symposium Engineer for ChevronTexaco's Exploration and Production
held in Oklahoma City, Oklahoma. Technology Company in Houston, Texas. He is currently
8. Urselmann, R., et al: Pressured MudCap Drilling: working within the Drilling Solutions business line on
Efficient Drilling of High-Pressure Fractured numerous international projects and supporting research
Reservoirs Paper SPE/IADC 52828 presented at efforts on new technology. Miles has over 20 years of
the 1999 SPE/IADC Drilling Conference held experience in oil and gas operations. He is a member of SPE
in Amsterdam. and a registered professional engineer with the Association of
Professional Engineers, Geologists, and Geophysicists of
9. McLennon/Carden/Curry/Stone/Wyman, SPE Alberta. Miles holds a Bachelor of Science Degree in
Underbalanced Drilling Manual, Gas Research Petroleum Engineering from Montana College of Mineral
Institute, 1997
SPE/IADC 79850 11

Science and Technology. He can be reached at


mnsw@chevrontexaco.com.

J.M. Bailey Jack Bailey is a Senior Drilling Superintendent


for ChevronTexaco Overseas Petroleum, Inc. He is currently
working as part of the Tengizchevroil partnership in the giant
Tengiz oilfield of Western Kazakhstan. Jack has worked in
the oil industry for 24 years, primarily in the exploration and
production drilling sector, both domestically and
internationally. He has been associated with both SPE and
IADC during his career and participated in various functions
within both organizations. Jack earned a Bachelor of Science
Degree in Civil Engineering from Utah State University. He
can be reached at email address tdril4@tengizchevroil.com.

C.R. Stone P.E. Rick Stone is the Chairman and CEO of


Signa Engineering Corp. in Houston, Texas. Rick has over 23
years of experience in oil and gas operations. A longtime
member of SPE, Rick has served the Society as a
Distinguished Lecturer. Rick will be presented the SPE
Drilling Engineering Award by SPE President Andrew Young
at the 2003 conference. He is a member of IADC and UB
AdvisorIADC Wellcap Committee. Rick holds a Bachelor
of Science degree in Mechanical Engineering from Texas
A&M University. He can be reached at rstone@signa.net.
12 SPE/IADC 79850

Fig. 1 Location Map Showing T-7252

- Proposed Location

Location Map Showing T-7252


SPE/IADC 79850 13

Fig. 2 Cross-section of Rim Region


14 SPE/IADC 79850

Fig. 3 Anticipated Casing Program


SPE/IADC 79850 15

Fig. 4 T-7252: Reservoir and Bore Hole Pressures Across the Formation

Pressure, psi
9,000 9,500 10,000 10,500 11,000 11,500 12,000 12,500 13,000
13,000
9,610 10,564
PP = 15.5 ppg emw at Top
of Reservoir
13,500
Bore Hole Pressure is balanced
14,000 at the top of the reservoir and
1156 psi overbalanced at the
Depth (TVD), ft

bottom.
14,500

Pressure Gradient in Reservoir = .389 11,400 Pressure Datum


15,000 psi / ft or 7.5 ppg emw

15,500
PP = 14.1 ppg emw at Btm of
Reservoir 11,647 12,803
16,000

PP Datum TOP - PP EMW


Static Reservoir Pressure BTM - PP EMW
16 SPE/IADC 79850

Fig. 5 Closed Hole Circulation Drilling Schematic


SPE/IADC 79850 17

Fig. 6 Drillpipe Injection Fluid Requirements for CHCD

14,000

Minimum Daily Volume - Vertical - no Motor


12,000

Maximum Daily Volume (Down Hole Motor)

10,000

8,000
BBLs / day

6,000

4,000

2,000

-
2 - 7/8" DP 3-1/2" DP 5" DP
4-1/2" Hole 6" Hole 8-1/2" Hole

Fig. 7 Effect of Gas Migration Rate on Casing Pressure


and Kill Volume

8,000 400
Assumption:
Gas Migration Rate & Density is Constant
7,000 350

6,000 300
Min. Annular Kill Volume, bls.
Casing Pressure, psi.

5,000 250

4,000 200

3,000 150

Casing Pressure - 7 ft/min


2,000 Casing Pressure - 15 ft/min 100
Casing Pressure - 90 ft/min

Minimum Annular Kill Volume, bbl - 7 ft/min


1,000 50
Minimum Annular Kill Volume, bbl - 15 ft/min

Minimum Annular Kill Volume, bbl - 90 ft/min


- 0
0 5 10 15 20 25 30
Time, hrs.
18 SPE/IADC 79850

Fig. 8: Alpine RPM 3000 RCD


SPE/IADC 79850 19

Fig. 9: Class 5 BOP for 11

Rotary beams

1.74 feet

RCD

5,000 psi annular


Annular

Top pipe rams replaced with 7 casing rams

Casing rams

CAMERON

TYPE "U"

Blind/shear rams

CAMERON
TYPE "U"

Pipe rams

CAMERON

TYPE "U"

Pipe rams
20 SPE/IADC 79850

Fig. 10: Actual Standpipe and Casing Pressure

CHCD Pressure Readings, Unit 1


6500 800
6000
700
5500
5000 600
Drill-pipe, psi

4500
4000 500

Casing, PSI
3500
400
3000
2500 300
2000
1500 200
1000
100
500
0 0
4409 4480 4580 4710 4750 4800

Drilled Depth (m)


SPE/IADC 79850 21

Table 1 T-7252 Estimated Pressure Regimes


Depth Reservoir Reservoir Standpipe Standpipe
Maximum Minimum Maximum Minimum
Unit 1 (meters) (ppg) (ppg) (psi) (psi)
Top 4,002 16.05 15.47 6,020 5,614
Datum 4,500 14.85 14.33
Bottom 4,701 14.34 13.94 5,677 5,272

Table 2: Sacrificial Fluid Treatment

Product Unit Cost Concentration Daily Cost ($)


Lime $0.15/lb 1 lb/bbl 1,350
Caustic $0.33/lb 1 lb/bbl 3,000
Oxygen $1.42/lite 0.25 liter/bbl 3,200
scavenger r
H2S scavenger $1.05/lite 0.1 liters/bbl 945
r
Total $8,495

Table 3: Oil Base Mud (OBM) Losses

Interval Volume ROP


(meters) (barrels) (m/hr)
4,317 4,327 150 3.8
4,364 4,368 27 3.6
4,390 - 4,398 813 2.7
Total 990

Table 4: CHCD Interval Pressures

Unit 1 Pump Casing Rate of Annular Sacrificial


Interval Pressur Pressure Penetratio Fluid Fluid
e n Pumped Used
(meters) (psi) (psi) (m/hr) (bbls)
4,409 4,554 5,500 270 6.04 10 6,100
4,554 4,637 5,550 350 6.14 5 2,600
4,637 4,647 5,500 240 6.66 2,600
4,647 4,680 5,550 350 4.40 2,500
4,680 4,753 5,540 300 3.10 8,000
4,753 4,800 5,550 250 3.50 5,000
Total 15 26,800

You might also like