0
START UP (COLD START UP) - SETELAH RSH + MO 3.72 days Jan 7 12:00 AM Jan 10 5:23 PM
1 1 PREPARATION AREA WTP & AUXILIARY SYSTEM 1.08 days Jan 7 12:00 AM Jan 8 2:01 AM
2 1.1 Jockey Pump / Fire Fighting Inservice 5 mins Jan 7 12:00 AM Jan 7 12:05 AM
3 1.2 Service Water Pump Inservice 5 mins Jan 7 12:05 AM Jan 7 12:10 AM 2
4 1.3 Demin Water Pump Inservice 5 mins Jan 7 12:10 AM Jan 7 12:15 AM 3
5 1.4 Chlorine Plant Inservice (setelah CWP Start) 1 hr Jan 8 1:01 AM Jan 8 2:01 AM 15
6 1.5 H2 Plant Inservice (Setelah Air Compressor Inservice) 24 hrs Jan 7 12:00 AM Jan 8 12:00 AM
7 2 PERSIAPAN AREA TURBIN 2.6 days Jan 7 12:05 AM Jan 9 2:33 PM
8 2.1 Open Cycle Cooling Water ( CWP ) System Inservice 1.07 days Jan 7 12:05 AM Jan 8 1:48 AM
9 2.1.1 Start Lifting Pump (Filling line Condensor & CCCWHE, Oil Cooler MOT) 24 hrs Jan 7 12:05 AM Jan 8 12:05 AM 2
10 2.1.2 Screen wash pump #1 Start 2 mins Jan 8 12:15 AM Jan 8 12:17 AM 4
11 2.1.3 Travelling screen #1 Start 30 mins Jan 8 12:17 AM Jan 8 12:47 AM 10
12 2.1.4 Cooling Water Pump CWP #1 Inservice 2 mins Jan 8 12:47 AM Jan 8 12:49 AM 11
13 2.1.5 Cooling Water Pump CWP #2 Inservice 2 mins Jan 8 12:49 AM Jan 8 12:51 AM 12
14 2.1.6 Cooling Water Pump CWP #3 Stand By 2 mins Jan 8 12:51 AM Jan 8 12:53 AM 13
15 2.1.7 CWP #1 START 10 mins Jan 8 12:51 AM Jan 8 1:01 AM 13
16 2.1.8 Screen wash pump #2 Start 2 mins Jan 8 1:06 AM Jan 8 1:08 AM 20
17 2.1.9 Travelling screen #2 Start 30 mins Jan 8 1:08 AM Jan 8 1:38 AM 16
18 2.1.10 CWP #2 START 10 mins Jan 8 1:38 AM Jan 8 1:48 AM 17
19 2.2 C3WP system Inservice 0.01 days Jan 8 1:01 AM Jan 8 1:11 AM
20 2.2.1 C3W Heat Exchanger #1 Inservice 5 mins Jan 8 1:01 AM Jan 8 1:06 AM 15
21 2.2.2 C3WP #1 START 5 mins Jan 8 1:06 AM Jan 8 1:11 AM 20
22 2.3 Condensate Extraction Pump ( CEP ) Inservice 0.51 days Jan 8 1:36 AM Jan 8 1:46 PM
23 2.3.1 CEP #1 START 5 mins Jan 8 1:36 AM Jan 8 1:41 AM 59
24 2.3.2 Filling Deaerator Storage Tank (cek kualitas air) 12 hrs Jan 8 1:41 AM Jan 8 1:41 PM 23
25 2.3.3 OPEN Inlet & Outlet LPH #5,#6,#7,GSC (By Pass CLOSED) 5 mins Jan 8 1:41 PM Jan 8 1:46 PM 24
26 2.4 Generator Stator Cooling Water Pump Inservice 0 days Jan 8 1:01 AM Jan 8 1:07 AM
27 2.4.1 Filling Stator Cooling Tank 2 mins Jan 8 1:01 AM Jan 8 1:03 AM 15
28 2.4.2 Heat Exchanger Stator Cooling Inservice 2 mins Jan 8 1:03 AM Jan 8 1:05 AM 27
29 2.4.3 Stator Cooling Water pump #1 Start 2 mins Jan 8 1:05 AM Jan 8 1:07 AM 28
30 2.5 Hydrogen Generator System Inservice 0.75 days Jan 8 2:01 AM Jan 8 8:01 PM
31 2.5.1 Seal Oil Unit Inservice 0 days Jan 8 2:01 AM Jan 8 2:07 AM
32 2.5.1.1 Exhaust Fan Seal oil #1 Start 2 mins Jan 8 2:01 AM Jan 8 2:03 AM 6,5
33 2.5.1.2 AC Air Side Seal Oil System Inservice 2 mins Jan 8 2:03 AM Jan 8 2:05 AM 32
34 2.5.1.3 AC H2 Side Seal Oil System Inservice 2 mins Jan 8 2:05 AM Jan 8 2:07 AM 33
35 2.5.2 Filling H2 ke Generator (Naikkan purity H2 > 98%) 18 hrs Jan 8 2:01 AM Jan 8 8:01 PM 6,5
36 2.6 Turbine Lube Oil System Inservice 0.02 days Jan 8 1:58 AM Jan 8 2:32 AM

MENGETAHUI: MENYETUJUI: Task External Tasks Duration-only External Tasks Progress


Split External Milestone Manual Summary Rollup External Milestone Deadline
Milestone Inactive Milestone Manual Summary Critical
Summary Inactive Summary Start-only Critical Split
Project Summary Manual Task Finish-only Late

SPV. RENDAL OPERASI MANAGER OPERASI


PT. PJB UBJOM PLTU PAITON 9
JADWAL START UP SETELAH RSH NATAL , TAHUN BARU 2017 dan MAINTENANCE OUTAGE JANUARI 2017
ID AKTIFITAS DURASI TANGGAL MULAI TANGGAL SELESAI URUTAN
PEKERJAAN
SETELAH Sat Jan 7 Sun Jan 8 Mon Jan 9 Tue Jan 10
AKTIFITAS KE- 6 PM 9 PM12 AM3 AM 6 AM 9 AM12 PM3 PM 6 PM 9 PM12 AM3 AM 6 AM 9 AM12 PM3 PM 6 PM 9 PM12 AM3 AM 6 AM 9 AM12 PM3 PM 6 PM 9 PM12 AM3 AM 6 AM 9 AM12 PM3 PM 6 PM
37 2.6.1 Lube Oil Cooler #1 Inservice 2 mins Jan 8 1:58 AM Jan 8 2:00 AM 15
38 2.6.2 Fume Discharge Fan AC lube oil #1 Start 2 mins Jan 8 2:00 AM Jan 8 2:02 AM 37
39 2.6.3 AC Lube Oil Start 15 mins Jan 8 2:02 AM Jan 8 2:17 AM 38
40 2.6.4 DC Lube Oil Stand By 15 mins Jan 8 2:17 AM Jan 8 2:32 AM 38,39
41 2.7 Turning Gear Motor Inservice 0.26 days Jan 8 2:32 AM Jan 8 8:42 AM
42 2.7.1 Shaft Jacking Oil Pump #1 Start 5 mins Jan 8 2:32 AM Jan 8 2:37 AM 40
43 2.7.2 Shaft Jacking Oil Pump #2 Stand By 5 mins Jan 8 2:37 AM Jan 8 2:42 AM 40,42
44 2.7.3 TGM Start 6 hrs Jan 8 2:42 AM Jan 8 8:42 AM 43
45 2.8 EH Oil System Inservice 0 days Jan 8 8:42 AM Jan 8 8:46 AM
46 2.8.1 EH Oil Cooling & Cellulose System Inservice 2 mins Jan 8 8:42 AM Jan 8 8:44 AM 44
47 2.8.2 AC EH Oil Pump #1 Start 2 mins Jan 8 8:44 AM Jan 8 8:46 AM 46
48 2.8.3 AC EH Oil Pump #2 Stand By 2 mins Jan 8 8:44 AM Jan 8 8:46 AM 46
49 2.9 CPP Inservice (pemenuhan kualitas air) 5 hrs Jan 9 3:23 AM Jan 9 8:23 AM 71
50 2.10 Vacuum Condensor Inservice 0.13 days Jan 9 11:28 AM Jan 9 2:33 PM 88,49
51 2.10.1 Condenser Vacuum Break Valve Close 5 mins Jan 9 11:28 AM Jan 9 11:33 AM 107
52 2.10.2 Vacuum pump #1 Start 60 mins Jan 9 11:33 AM Jan 9 12:33 PM 51
53 2.10.3 Vacuum pump #2 Start 60 mins Jan 9 12:33 PM Jan 9 1:33 PM 52
54 2.10.4 Vacuum pump #3 Stand by AUTO 60 mins Jan 9 1:33 PM Jan 9 2:33 PM 53
55 3 PERSIAPAN AREA BOILER 1.57 days Jan 8 1:11 AM Jan 9 2:51 PM
56 3.1 Compressor System Inservice 0.01 days Jan 8 1:11 AM Jan 8 1:26 AM
57 3.1.1 Service Air Compressor Inservice 10 mins Jan 8 1:11 AM Jan 8 1:21 AM 21
58 3.1.2 Air Dryer Inservice 5 mins Jan 8 1:11 AM Jan 8 1:16 AM 21
59 3.1.3 Instrument Air Compressor Inservice 10 mins Jan 8 1:16 AM Jan 8 1:26 AM 58
60 3.2 Boiler Feed Water Inservice 0.57 days Jan 8 1:46 PM Jan 9 3:23 AM
61 3.2.1 OPEN Inlet & Outlet HPH #3,#2,#1 (By Pass CLOSED) 15 mins Jan 8 1:46 PM Jan 8 2:01 PM 25
62 3.2.2 Starting Oil Pump BFP - Motor 2 mins Jan 8 2:01 PM Jan 8 2:03 PM 61
63 3.2.3 BFP-Motor START 5 mins Jan 8 2:03 PM Jan 8 2:08 PM 62
64 3.2.4 Filling Steam Drum (Level > 300 mm) 12 hrs Jan 8 2:08 PM Jan 9 2:08 AM 63
65 3.2.5 Filling & Flushing line BCP (line venting keluar air dan bersih) 1 hr Jan 9 2:08 AM Jan 9 3:08 AM 64
66 3.2.6 Start BCP Cooling #1 2 mins Jan 9 3:08 AM Jan 9 3:10 AM 65
67 3.2.7 Open High Pressure cooling BWCP from CEP 5 mins Jan 9 3:10 AM Jan 9 3:15 AM 66
68 3.2.8 BWCP #1 START (Lakukan Bump Test) 2 mins Jan 9 3:15 AM Jan 9 3:17 AM 67
69 3.2.9 BWCP #3 START (Lakukan Bump Test) 2 mins Jan 9 3:17 AM Jan 9 3:19 AM 67,68
70 3.2.10 BWCP #3 (posisi Stand By) 2 mins Jan 9 3:19 AM Jan 9 3:21 AM 69
71 3.2.11 Economizer circulating OPEN (CV Feedwater CLOSED) 2 mins Jan 9 3:21 AM Jan 9 3:23 AM 70
72 3.3 Air & Gas System Inservice 0.27 days Jan 9 8:23 AM Jan 9 2:45 PM
73 3.3.1 Start Air Pre Heater Auxiliary/Main Motor #1 2 mins Jan 9 8:23 AM Jan 9 8:25 AM 49

MENGETAHUI: MENYETUJUI: Task External Tasks Duration-only External Tasks Progress


Split External Milestone Manual Summary Rollup External Milestone Deadline
Milestone Inactive Milestone Manual Summary Critical
Summary Inactive Summary Start-only Critical Split
Project Summary Manual Task Finish-only Late

SPV. RENDAL OPERASI MANAGER OPERASI


PT. PJB UBJOM PLTU PAITON 9
JADWAL START UP SETELAH RSH NATAL , TAHUN BARU 2017 dan MAINTENANCE OUTAGE JANUARI 2017
ID AKTIFITAS DURASI TANGGAL MULAI TANGGAL SELESAI URUTAN
PEKERJAAN
SETELAH Sat Jan 7 Sun Jan 8 Mon Jan 9 Tue Jan 10
AKTIFITAS KE- 6 PM 9 PM12 AM3 AM 6 AM 9 AM12 PM3 PM 6 PM 9 PM12 AM3 AM 6 AM 9 AM12 PM3 PM 6 PM 9 PM12 AM3 AM 6 AM 9 AM12 PM3 PM 6 PM 9 PM12 AM3 AM 6 AM 9 AM12 PM3 PM 6 PM
74 3.3.2 Start Air Pre Heater Auxiliary/Main Motor #2 2 mins Jan 9 8:25 AM Jan 9 8:27 AM 73
75 3.3.3 Start Lube Oil Cycle ID Fan A 2 mins Jan 9 8:27 AM Jan 9 8:29 AM 74
76 3.3.4 Start Lube Oil Cycle ID Fan B 2 mins Jan 9 8:29 AM Jan 9 8:31 AM 75
77 3.3.5 ID Fan A Cooling Fan 2 mins Jan 9 8:31 AM Jan 9 8:33 AM 76
78 3.3.6 ID Fan B Cooling Fan 2 mins Jan 9 8:33 AM Jan 9 8:35 AM 77
79 3.3.7 Start Lube Oil Cycle FD Fan A 2 mins Jan 9 8:35 AM Jan 9 8:37 AM 78
80 3.3.8 Start Lube Oil Cycle FD Fan B 2 mins Jan 9 8:37 AM Jan 9 8:39 AM 79
81 3.3.9 Start Lube Oil Hyrdaulic PA Fan A 2 mins Jan 9 8:39 AM Jan 9 8:41 AM 80
82 3.3.10 Start Lube Oil Motor PA Fan A 2 mins Jan 9 8:41 AM Jan 9 8:43 AM 81
83 3.3.11 Start Lube Oil Hyrdaulic PA Fan B 2 mins Jan 9 8:43 AM Jan 9 8:45 AM 82
84 3.3.12 Start Lube Oil Motor PA Fan B 2 mins Jan 9 8:45 AM Jan 9 8:47 AM 83
85 3.3.13 Start ID Fan #1 2 mins Jan 9 8:47 AM Jan 9 8:49 AM 84
86 3.3.14 Start FD Fan #1 2 mins Jan 9 8:49 AM Jan 9 8:51 AM 85
87 3.3.15 Start ID Fan #2 2 mins Jan 9 8:51 AM Jan 9 8:53 AM 86
88 3.3.16 Start FD Fan #2 2 mins Jan 9 8:53 AM Jan 9 8:55 AM 87
89 3.3.17 Lube Oil Mill A System Inservice 2 mins Jan 9 2:33 PM Jan 9 2:35 PM 50,88
90 3.3.18 Lube Oil Mill B System Inservice 2 mins Jan 9 2:35 PM Jan 9 2:37 PM 89
91 3.3.19 Lube Oil Mill C System Inservice 2 mins Jan 9 2:37 PM Jan 9 2:39 PM 90
92 3.3.20 Lube Oil Mill D System Inservice 2 mins Jan 9 2:39 PM Jan 9 2:41 PM 91
93 3.3.21 Lube Oil Mill E System Inservice 2 mins Jan 9 2:41 PM Jan 9 2:43 PM 92
94 3.3.22 Lube Oil Mill F System Inservice 2 mins Jan 9 2:43 PM Jan 9 2:45 PM 93
95 3.4 Furnace System Preparation 0 days Jan 9 2:45 PM Jan 9 2:51 PM
96 3.4.1 Flame Detecting Cooling Air Fan Inservice 2 mins Jan 9 2:45 PM Jan 9 2:47 PM 94
97 3.4.2 Furnace Thermperature Probe #1 Inservice 2 mins Jan 9 2:47 PM Jan 9 2:49 PM 96
98 3.4.3 Furnace Thermperature Probe #2 Inservice 2 mins Jan 9 2:49 PM Jan 9 2:51 PM 97
99 3.5 Fuel Oil system Inservice 0.09 days Jan 9 8:23 AM Jan 9 10:28 AM
100 3.5.1 LFO Pump Inservice 5 mins Jan 9 8:23 AM Jan 9 8:28 AM 49
101 3.5.2 Auxiliary Boiler Start 2 hrs Jan 9 8:28 AM Jan 9 10:28 AM 100
102 3.6 Auxiliary Steam Inservice 0.04 days Jan 9 10:28 AM Jan 9 11:28 AM
103 3.6.1 Inservice Auxiliary Steam Header 30 mins Jan 9 10:28 AM Jan 9 10:58 AM 101
104 3.6.2 Sootblower AH Inservice 30 mins Jan 9 10:58 AM Jan 9 11:28 AM 103
105 3.6.3 Warming Mini Air Heater untuk Start Mill A 30 mins Jan 9 10:58 AM Jan 9 11:28 AM 103
106 3.6.4 Warming Atomizing Steam 30 mins Jan 9 10:58 AM Jan 9 11:28 AM 103
107 3.6.5 Warming Gland Seal Steam Header 30 mins Jan 9 10:58 AM Jan 9 11:28 AM 103
108 3.6.6 Warming Deaerator 30 mins Jan 9 10:58 AM Jan 9 11:28 AM 103
109 4 PERSIAPAN AREA CHCB & FLY ASH 0.69 days Jan 9 2:51 PM Jan 10 7:21 AM
110 4.1 Coal Handling System Inservice 0.69 days Jan 9 2:51 PM Jan 10 7:21 AM

MENGETAHUI: MENYETUJUI: Task External Tasks Duration-only External Tasks Progress


Split External Milestone Manual Summary Rollup External Milestone Deadline
Milestone Inactive Milestone Manual Summary Critical
Summary Inactive Summary Start-only Critical Split
Project Summary Manual Task Finish-only Late

SPV. RENDAL OPERASI MANAGER OPERASI


PT. PJB UBJOM PLTU PAITON 9
JADWAL START UP SETELAH RSH NATAL , TAHUN BARU 2017 dan MAINTENANCE OUTAGE JANUARI 2017
ID AKTIFITAS DURASI TANGGAL MULAI TANGGAL SELESAI URUTAN
PEKERJAAN
SETELAH Sat Jan 7 Sun Jan 8 Mon Jan 9 Tue Jan 10
AKTIFITAS KE- 6 PM 9 PM12 AM3 AM 6 AM 9 AM12 PM3 PM 6 PM 9 PM12 AM3 AM 6 AM 9 AM12 PM3 PM 6 PM 9 PM12 AM3 AM 6 AM 9 AM12 PM3 PM 6 PM 9 PM12 AM3 AM 6 AM 9 AM12 PM3 PM 6 PM
111 4.1.1 Unloading System Inservice 15 mins Jan 9 2:51 PM Jan 9 3:06 PM 98
112 4.1.2 Loading System Inservice 15 mins Jan 9 3:06 PM Jan 9 3:21 PM 111
113 4.1.3 Filling Bunker Silo A B C D E 16 hrs Jan 9 3:21 PM Jan 10 7:21 AM 112
114 4.2 Fly Ash & Bottom Ash System Inservice 0.01 days Jan 9 2:51 PM Jan 9 3:06 PM
115 4.2.1 Start ESP Heater 5 mins Jan 9 2:51 PM Jan 9 2:56 PM 98
116 4.2.2 Boiler Hopper Closed 5 mins Jan 9 2:56 PM Jan 9 3:01 PM 115
117 4.2.3 SSC System Inservice 5 mins Jan 9 3:01 PM Jan 9 3:06 PM 116
118 5 BOILER FIRING 0.36 days Jan 9 11:28 AM Jan 9 8:01 PM
119 5.1 Start air pre heater tiny oil gun 30 mins Jan 9 11:28 AM Jan 9 11:58 AM 105
120 5.2 Furnace Purging 5 mins Jan 9 11:58 AM Jan 9 12:03 PM 119
121 5.3 MFT Reset 5 mins Jan 9 12:03 PM Jan 9 12:08 PM 120
122 5.4 Oil Fuel Leak Test 3 mins Jan 9 12:08 PM Jan 9 12:11 PM 121
123 5.5 OFT Reset 5 mins Jan 9 12:11 PM Jan 9 12:16 PM 122
124 5.6 ESP Inservice 5 mins Jan 9 12:16 PM Jan 9 12:21 PM 123
125 5.7 Start PA Fan #1 5 mins Jan 9 12:16 PM Jan 9 12:21 PM 123
126 5.8 Start PA Fan #2 5 mins Jan 9 12:21 PM Jan 9 12:26 PM 125
127 5.9 Start Seal Air Fan 5 mins Jan 9 12:26 PM Jan 9 12:31 PM 126
128 5.10 START TINY OIL GUN 30 mins Jan 9 12:31 PM Jan 9 1:01 PM 127
129 5.11 Pulverizer Mill #1 Inservice 45 mins Jan 9 1:01 PM Jan 9 1:46 PM 128
130 5.12 Coal Feeder #1 Inservice 6 hrs Jan 9 1:46 PM Jan 9 7:46 PM 129
131 5.13 CLOSED semua venting drum, superheater, reheater 15 mins Jan 9 7:46 PM Jan 9 8:01 PM 130
132 5.14 OPEN HP By Pass & LP By Pass 5 mins Jan 9 7:46 PM Jan 9 7:51 PM 130
133 5.15 C/O cooling BWCP from CEP to BFP 5 mins Jan 9 7:46 PM Jan 9 7:51 PM 130
134 5.16 CLOSED semua drain MOV roof tube, back pass lower header 5 mins Jan 9 7:46 PM Jan 9 7:51 PM 130
135 5.17 Economizer circulating CLOSED 5 mins Jan 9 7:46 PM Jan 9 7:51 PM 130
136 5.18 CLOSED Cooling BCP dari High Pressure Cooling 10 mins Jan 9 7:51 PM Jan 9 8:01 PM 133
137 6 ROLIING TURBIN 0.17 days Jan 9 8:01 PM Jan 10 12:05 AM 136
138 6.1 H2 Seal Oil Spare Pump Inservice 5 mins Jan 9 8:01 PM Jan 9 8:06 PM
139 6.2 START Rolling Turbine, SET POINT 400 RPM 15 mins Jan 9 8:06 PM Jan 9 8:21 PM 44,138,47,48
140 6.3 Exhaust device open 5 mins Jan 9 8:21 PM Jan 9 8:26 PM 139
141 6.4 TGM Disenganged 5 mins Jan 9 8:26 PM Jan 9 8:31 PM 140
142 6.5 Rolling Turbine SET POINT 1900 RPM 150 mins Jan 9 8:31 PM Jan 9 11:01 PM 141
143 6.6 Shaft Jacking Oil Pump Stop 10 mins Jan 9 11:01 PM Jan 9 11:11 PM 142
144 6.7 Rolling Turbine SET POINT 2850 RPM 30 mins Jan 9 11:11 PM Jan 9 11:41 PM 143
145 6.8 Transfer GV to TV 5 mins Jan 9 11:41 PM Jan 9 11:46 PM 144
146 6.9 Rolling Turbine SET POINT 3000 RPM 10 mins Jan 9 11:46 PM Jan 9 11:56 PM 145
147 6.10 Turbine Lube Oil System Outservice 2 mins Jan 9 11:56 PM Jan 9 11:58 PM 146

MENGETAHUI: MENYETUJUI: Task External Tasks Duration-only External Tasks Progress


Split External Milestone Manual Summary Rollup External Milestone Deadline
Milestone Inactive Milestone Manual Summary Critical
Summary Inactive Summary Start-only Critical Split
Project Summary Manual Task Finish-only Late

SPV. RENDAL OPERASI MANAGER OPERASI


PT. PJB UBJOM PLTU PAITON 9
JADWAL START UP SETELAH RSH NATAL , TAHUN BARU 2017 dan MAINTENANCE OUTAGE JANUARI 2017
ID AKTIFITAS DURASI TANGGAL MULAI TANGGAL SELESAI URUTAN
PEKERJAAN
SETELAH Sat Jan 7 Sun Jan 8 Mon Jan 9 Tue Jan 10
AKTIFITAS KE- 6 PM 9 PM12 AM3 AM 6 AM 9 AM12 PM3 PM 6 PM 9 PM12 AM3 AM 6 AM 9 AM12 PM3 PM 6 PM 9 PM12 AM3 AM 6 AM 9 AM12 PM3 PM 6 PM 9 PM12 AM3 AM 6 AM 9 AM12 PM3 PM 6 PM
148 6.11 H2 Seal Oil Spare Pump Outservice 2 mins Jan 9 11:58 PM Jan 10 12:00 AM 147
149 6.12 Exhaust Device Closed 5 mins Jan 10 12:00 AM Jan 10 12:05 AM 148
150 7 SINKRONISASI & LOAD UP FOLLOW P3B 0.72 days Jan 10 12:05 AM Jan 10 5:23 PM
151 7.1 Syncronize Unit + Hold Up Load 60 MW 60 mins Jan 10 12:05 AM Jan 10 1:05 AM 149
152 7.2 CLOSED Spray valve exit LP 15 mins Jan 10 1:05 AM Jan 10 1:20 AM 151
153 7.3 Pulverizer Mill #2 Inservice 45 mins Jan 10 1:05 AM Jan 10 1:50 AM 151
154 7.4 Coal Feeder #2 Inservice 10 mins Jan 10 1:50 AM Jan 10 2:00 AM 153
155 7.5 PUT DEH into MEGAWAT LOOP 5 mins Jan 10 2:00 AM Jan 10 2:05 AM 154
156 7.6 C/O supply steam ke Deaerator dari AS ke 4th ES 15 mins Jan 10 2:05 AM Jan 10 2:20 AM 155
157 7.7 C/O supply steam ke Gland Seal dari AS ke CS Steam 15 mins Jan 10 2:20 AM Jan 10 2:35 AM 156
158 7.8 C/O supply steam ke AS Header dari Aux Boiler ke CR Steam 15 mins Jan 10 2:35 AM Jan 10 2:50 AM 157
159 7.9 Exhaust Fan MOT BFPT #1 Start 5 mins Jan 10 12:05 AM Jan 10 12:10 AM 149
160 7.10 AC Lube Oil pump BFPT #1 Start 5 mins Jan 10 12:10 AM Jan 10 12:15 AM 159
161 7.11 Warming BFPT #1 2 hrs Jan 10 12:15 AM Jan 10 2:15 AM 160
162 7.12 Booster pump BFPT #1 Start 5 mins Jan 10 2:15 AM Jan 10 2:20 AM 161
163 7.13 Rolling BFPT #1 & BFPT # 1 Inservice (Load 132 MW) 2 hrs Jan 10 2:20 AM Jan 10 4:20 AM 162
164 7.14 OPEN supply steam untuk warming BFPT # 2 dari 4th ES 15 mins Jan 10 4:20 AM Jan 10 4:35 AM 163,158
165 7.15 C/O line Boiler Feedwater dari by pass ke Main Feedwater 10 mins Jan 10 4:35 AM Jan 10 4:45 AM 164
166 7.16 Paralel Boiler Feedwater antara BFP Motor dengan BFPT 30 mins Jan 10 4:45 AM Jan 10 5:15 AM 165
167 7.17 Auxiliary Boiler Stop 30 mins Jan 10 5:15 AM Jan 10 5:45 AM 166
168 7.18 Pulverizer Mill #3 Inservice 45 mins Jan 10 5:45 AM Jan 10 6:30 AM 167
169 7.19 Coal Feeder #3 Inservice (Load 330 MW) 10 mins Jan 10 6:30 AM Jan 10 6:40 AM 168
170 7.20 Open Continuous Blowdown sesuai kualitas air di drum 4 hrs Jan 10 6:40 AM Jan 10 10:40 AM 169
171 7.21 Warming BFPT #2 2 hrs Jan 10 10:40 AM Jan 10 12:40 PM 170
172 7.22 Booster pump BFPT #2 Start 5 mins Jan 10 12:40 PM Jan 10 12:45 PM 171
173 7.23 Rolling BFPT #2 & BFPT # 2 Inservice (Load 430 MW) 2 hrs Jan 10 12:45 PM Jan 10 2:45 PM 172
174 7.24 Start Oil Gun Layer DE Corner #1 2 mins Jan 10 2:45 PM Jan 10 2:47 PM 173
175 7.25 Start Oil Gun Layer DE Corner #3 2 mins Jan 10 2:47 PM Jan 10 2:49 PM 174
176 7.26 Start Oil Gun Layer DE Corner #2 2 mins Jan 10 2:49 PM Jan 10 2:51 PM 175
177 7.27 Start Oil Gun Layer DE Corner #4 2 mins Jan 10 2:51 PM Jan 10 2:53 PM 176
178 7.28 Exhaust Fan MOT BFPT #2 Start 5 mins Jan 10 4:35 AM Jan 10 4:40 AM 164
179 7.29 AC Lube Oil pump BFPT #2 Start 5 mins Jan 10 4:40 AM Jan 10 4:45 AM 178
180 7.30 Pulverizer Mill #4 Inservice 45 mins Jan 10 2:53 PM Jan 10 3:38 PM 177
181 7.31 Coal Feeder #4 Inservice (Load 530 MW) 15 mins Jan 10 3:38 PM Jan 10 3:53 PM 180
182 7.32 Cut Off HSD 30 mins Jan 10 3:53 PM Jan 10 4:23 PM 181
183 7.33 Pulverizer Mill #5 Inservice 45 mins Jan 10 4:23 PM Jan 10 5:08 PM 182
184 7.34 Coal Feeder #5 Inservice (Load 645 MW) 15 mins Jan 10 5:08 PM Jan 10 5:23 PM 183

MENGETAHUI: MENYETUJUI: Task External Tasks Duration-only External Tasks Progress


Split External Milestone Manual Summary Rollup External Milestone Deadline
Milestone Inactive Milestone Manual Summary Critical
Summary Inactive Summary Start-only Critical Split
Project Summary Manual Task Finish-only Late

SPV. RENDAL OPERASI MANAGER OPERASI

You might also like