Give the four (4) logical relationships of activities on PDM (precedence

diagram method)?
1. Finish-to-Start
2. Finish-to-Finish
3. Start-to-Start
4. Start-to-Finish

A __________ through the network determines the earliest time of each activity can
Start and Finish. It also determines the ________ of the Project

forward pass
TOTAL DURATION

A __________ through the network determines the latest time of each activity can
Start and Finish without delaying the completion of the project. It also helps determine
the activities that can be _________ or not.

backward pass
DELAYED

In PERT/CPM, since it only uses a Finish to Start relationship, the presentation of


activity relationship shows that succeeding activity CANNOT ______until its
preceding ACTIVITY HAS BEEN _______.
START
COMPLETED