Technics Offshore Engineering Pte Ltd

Fabrication Routing and Inspection Plan Revision:


Project Description : NAN CON SON Project No. : TOE-01033E Prepared by:
Customer : FISHER-ROSEMOUNT ASME No. : NA Approved by:
Equipment : PIPING Tag No. : NA Date :
INSPECTION POINT HAS BEEN INDICATED BY CUSTOMER
Serial Inspection Activities / Inspection Acceptance TOEL Q.C. FRSPL
No. Type of Inspection Criteria Type Initial Type Initial Type Initial Type Initial Type Initial
1 REVIEW OF 'AFC' DRAWING R

2 REVIEW OF PROCEDURES ASME / ANSI B31.3


a) WPS R
b) PQR R
c) Welder Qualification (WPQ) R
d) NDT Procedure R
e) Weld Repair Procedure R
f) Heat Treatment Procedure R
g) Pressure Test Procedure R
h) Painting Procedure R

3 MATERIAL VERIFICATION ASME / ANSI B31.3


a) Review of Mill Certificate R
b) Layout/Heat No. Transfer W

4 FIT-UP & WELDING OF PIPE ASME / ANSI B31.3


a) Edge Preparation & Fit up W
b) Weld size & Weld Visual Inspection V
c) Dimensional & Alignment V

5 NDE ASME B31.3 Chapter VI


Radiographic Examination for Piping 100% R
MPI for Socket Weld 10% R

6 WELD REPAIR (If Applicable) ASME / ANSI B31.3 & AWS


RT for Piping 100% R
MPI for socket weld R

7 FINAL DIMENSIONAL/VISUAL INSPECTION ANSI B31.3 H

Form FRIP_1 Rev (8/97)


Page 1 of 2
Serial Inspection Activities / Inspection Acceptance TOEL Q.C. FRSPL SEMB PTMI DNV
No. Type of Inspection Criteria Type Initial Type Initial Type Initial Type Initial Type Initial
8 POST WELD HEAT TREATMENT PWHT Procedure
for thickness over 19mm of piping 100%
a) Verify preparation of heat treatment W W R R W
b) Review of Report & Chart R R R R R

9 HYDROSTATIC TEST FOR PIPING ASME / ANSI B31.3


a) Hydro-test According to drawing requirement H H W W W
b) Review of hydrostatic test report H E W W W
c) Endorsement of hydrostatic test chart H E W W W

10 AIR LEAK TEST FOR PIPING SYSTEM Air Leak Test Procedure
Test to 6 Bar
a) Check of Pipe system W V W W W
b) Preparation check for leak test W V W W W
c) leakage inspection during test W H W W W

11 BLASTING & PAINTING INSPECTION Blasting & Painting Specification


a) Paint verification R R W W V
b) Surface preparation H V W W W
c) Coating inspection (DFT gauge) W V W W W
d) Review of painting report R R W W W

12 DOCUMENTATION (MDR) TOEPL QA/QC manual


a) Manufacturer Data Report E E R R R
b) Material & Weld Traceability E E R R R
c) Weld Map E E R R R
d) NDE reports E E R R R

Legend :
H = Hold point E = Endorsement C = Critical V = Visual Inspection
W = Witnessed point R = Review RN = Random inspection

Form FRIP_1 Rev (8/97)