Activity Duration Precedence ES EF LS LF Float

1 3 0 0 3 0 3 0
2 1 0 0 1 2 3 2
3 1 1,2 3 4 3 4 0
4 2 3 4 6 4 6 0
5 1 1 3 4 5 6 2
6 2 7 7 9 7 9 0
7 1 4,5 6 7 6 7 0
8 1 6 9 10 9 10 0
9 3 8 10 13 10 13 0
10 1 5 4 5 12 13 8
11 2 9,10 13 15 13 15 0
12 3 11 15 18 15 18 0
13 2 12 18 20 18 20 0
14 5 13 20 25 20 25 0
15 3 20 39 42 39 44 2
16 1 10 5 6 24 25 19
17 2 14,16 25 27 25 27 0
18 3 17 27 30 27 30 0
19 2 18 30 32 30 32 0
20 7 19 32 39 32 39 0
21 3 20 39 42 39 42 0
22 2 21 42 44 42 44 0

CRITICAL PATH: Start-1-3-4-6-7-8-9-11-12-13-14-17-18-19-20-21-22-End


PRECEDENCE CHART
GANTT CHART

Black thin lines indicate the critical path