Professional Documents
Culture Documents
w
x ME FEATURE
From Materials Evaluation, Vol. 70, No. 5, pp: 508519.
Copyright 2012 The American Society for Nondestructive Testing, Inc.
T
his paper details actual inspection data and extracts from reports
taken over a nine-month period of inspections of water tube boilers.
The inspections were carried out by qualified technicians and
inspectors using a combination of internal visual testing (VT) using
remote cameras, eddy current testing, ultrasonic testing (UT) and magnetic
particle testing (MT).
it is absolutely essential It is vital that photographs are taken before the appli-
cation of any dyes, contrast paints or couplants so that
a clean record of the failed area can be stored for
W Y
T
Failure site
window rupture
X Z
W, X, Y and Z
Figure 1. The failure site and surrounding area: (a) location of discontinuities; (b) rupture window; (c) end view showing
the orientation of internal cracks. Cracks W, X, Y and Z were located opposite the external weld toe, as indicated in
Figure 1c.
(a) (b)
X Y
W
(c) (d)
Figure 2. Reported cracks: (a) 30 mm (1.2 in.) external crack T; (b) 20 mm (0.8 in.) external crack U; (c) 80 mm (3.2 in.)
internal crack X and 90 mm (3.5 in.) internal crack Z; (d) 65 mm (2.6 in.) internal crack W and 95 mm (3.7 in.) internal
crack Y.
From this first inspection, the decision was taken identify all those with internal visually suspect areas.
to provide a technique that would screen the tubes This necessitated follow-up with a technique that
and identify which had the potential of having internal would give clear data for acceptance or rejection as a
discontinuities. In order to do this, a request was discontinuity. The tubes selected for phase 2 are
made to extract some full tubes and carry out shown in Figure 3.
extensive testing within a workshop environment, The first pass was carried out with the tubes intact,
utilizing test equipment and parameters that would be and various internal bore cameras were tried out to
adopted for onsite inspections. find the most convenient one that would also find all
indications. All the inspections were carried out in
Phase 2 (Follow-up Inspection and Technique workshop conditions and with good lighting of
Verification) >500 lux (46.45 fc).
Once the client granted approval, phase 2 was
initiated. To prove suitability of the techniques, it was Remote Visual Testing
first necessary to select the highest risk locations with Four camera systems (Camera A, Camera B, Camera C
the greatest stresses and then screen these tubes to and Camera D) were trialed to determine which gave
Ultrasonic Testing
The wall thickness and external radius of the tubes
narrowed the probes selection down to a 45 shear
wave with nominal frequency of 2.25 to 4 MHz. The
probe had a shoe shape to suit the curvature of the
tube and could be seated inside a metal holder
purposely built to fit the external radius and provide
stable scanning (see Figure 4).
Reference samples were made using tube
Figure 4. The ultrasonic probe curved shoe. material identical to those of the tubes to be tested.
The signal from the 1 mm (0.04 in.) deep, 20 mm recorded on the report and had a detrimental effect on
(0.79 in.) long slot was maximized, and the gain was POD.
adjusted to give a response of 80% full screen height. POD increased by the use of a complementary NDT
For scanning, 6 dB were added. This was validated as technique. Remote VT outlined within this paper fulfills
a scanning sensitivity against known cracks in the cali- these criteria and may be used as a screening
bration reference sample. technique to focus the UT and as a verification aid for
The extra 6 dB were removed for testing. All indica- indications found by UT.
tions greater than 6 mm (0.24 in.) in length had the No discontinuities were detected that did not have
length tested using the 6 dB drop; indications with a a major axis parallel to the ligature weld. Only indica-
length of less than 6 mm (0.24 in.) were not recorded. tions within 6 mm (0.24 in.) of the primary beam axis
incidence to the area designated as the suspect area
Probability of Detection were detected.
With strict adherence to the procedure, there was a
high degree of probability of detection (POD) in cracks Ultrasonic Testing Results
greater than 6 mm in length (0.24 in.) and greater During the UT, a number of discontinuities were
than 1 mm (0.04 in.) in depth, parallel to the weld observed directly opposite the tube-to-tube ligature
axis within the suspect area. Any deviation was weld zone. These were sized and recorded. The
D C AG
D C A G F E
F H
E B
B H
(a) (b)
Figure 7. Discontinuity locations in tubes 2 through 5: (a) end view; (b) side view.
TABLE 1
Detectability of each crack with each technique utilized
Crack Detectable with Detectable with Detectable with Detectable with
remote visual testing eddy current testing magnetic particle testing ultrasonic testing
A Yes Yes Yes Yes
B Yes Yes Yes Yes
C Yes Yes Yes Yes
D Yes Yes Yes Yes
E No Yes Yes No
F No Yes Yes No
G Yes Yes Yes Yes
H Yes Yes Yes Yes
Phase 2 Conclusions
The decision to adopt the following set of techniques
was based upon ASME Section V, NDT guidelines and
also the information gathered from the client regarding
their concerns at being able to screen for and detect
early stages of corrosion fatigue (ASME, 2010; ASNT,
2006; BS, 2008).
Based upon the entire set of trials and results, it
was concluded that future inspections of the boiler
tubes would be carried out as follows: tubes associ-
ated with critical high stress areas where the possi-
(a) bility of corrosion fatigue is greatest would be
selected; external eddy current testing would be
conducted at tangent welds using bridge weld probes
and sensitivity set on a 1 mm (0.04 in.) depth EDM
notch to give a signal deflection full screen height
from center. In addition, external MT would be
conducted at tangent welds using standard 110 V Y6
yokes and color contrast consumables. External UT
would be conducted at tangent weld areas using 45
shear waves with a nominal frequency between 2.25
(b) and 4 MHz, shaped to suit the tube outer radius.
Finally, internal inspections would be conducted using
Figure 9. Internal view of: (a) tube 2 showing internal an advanced video borescopes with fully articulated
indications of cracking; (b) tube 4 showing no internal fiber optic cameras.
indications or evidence of visible cracks. This set of inspections and the application of the
procedures developed would give the best chance at
early detection of crack initiation and propagation
and, if carried out on a regular frequency, could reduce
plant downtime and the possibility of further ruptures
in the future.
TABLE 2
Test technique order and reasons
Order of testing Test technique used Reason for order
1 Internal remote visual testing Initial search/screening for potential areas of thermal fatigue cracking
2 External magnetic particle testing Applied first so that the contrast aid paint would adhere
3 External eddy current testing Applied second because it could be applied on top of contrast aid paint
and was not affected by residual magnetic inks
4 External ultrasonic testing Applied last as the couplant can leave greasy film residue, which would
need extra cleaning if other techniques were to follow